MTM DESIGN AND TECHNICAL REVIEW PROCEDURE
Table of Contents
1 Purpose................................................................................................................................ 3
2 Scope ...................................................................................................................................3
3 References........................................................................................................................... 3
5 Approach ............................................................................................................................. 6
7 Responsibilities................................................................................................................... 8
7.1 Design Consultants.............................................................................................................. 8
7.2 MTM Projects..................................................................................................................... 11
7.3 MTM Network Asset Management...................................................................................... 12
7.4 MTM Infrastructure Delivery ............................................................................................... 12
7.5 MTM Engineering Design Review Group............................................................................ 13
7.5.1 Registration of Technical Design Review................................................................ 14
7.5.2 Technical Review Form.......................................................................................... 15
Approving Manager: Head of Network Asset Management Approval Date: 12/06/2013 Next Review Date: 12/06/2016
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 2 of 27
MTM DESIGN AND TECHNICAL REVIEW PROCEDURE
1 Purpose
MTM is an accredited Rail Operator and under the Rail Safety Act (2006) must ensure the
safe operation, construction and maintenance of all of the railway infrastructure and assets.
This includes the engagement of a design consultant to provide an engineering design, (or
the review of a design) required for the delivery of a project or asset renewal to be
incorporated as part of the operating railway.
The purpose of this procedure is to define the process and responsibilities required for
Metro Trains Melbourne (MTM) to undertake a Technical/Engineering review (including
design reviews) for all infrastructure projects (to be delivered under the Projects Agreement
with the Department of Transport (DoT)) and Network Asset Management configuration
changes that require design input. The design reviews are intended to establish design
control against agreed standards and defined operational requirements, while also
considering the impact on MTM maintenance practices. The review is not intended as a
“design check”.
2 Scope
This document applies to the design management and technical review of designs
prepared on behalf of MTM Projects or other stakeholders. This procedure also applies to
the design review for State, Franchise, Third Party and MTM Asset Management works
proposed on the MTM rail network covering all disciplines such as:
Track and Civil
Bridges, structures, buildings and facilities
Signalling systems and power
Overhead power and traction
Substations
Operational Control Systems
The design review must follow the Terms of Reference specified by MTM and shall provide
assurance that all the requirements of the Accredited Rail Operator’s (ARO’s) Safety
Management System, including operational and functional requirements and the
appropriate standards, have been met.
3 References
L1-SQE-PRO-001 - Management of Change Process
L1-ASY-PRO-001 - Engineering Change Control Procedure
L1-NAM-PRO-001 - Signalling Design Technical Review Procedure
Approving Manager: Head of Network Asset Management Approval Date: 12/06/2013 Next Review Date: 12/06/2016
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 3 of 27
MTM DESIGN AND TECHNICAL REVIEW PROCEDURE
Review Staff available from MTM Engineering Design Review Group (EDRG)
Team (containing various disciplines) and/or suitably qualified and
experienced consultants supporting the MTM Engineering Design
Review Group.
Design A plan submitted by the designer detailing how the design process will
Management be managed and drawings submitted to EDR for review, comment and
Plan feedback.
Drawing A plan submitted by the designer detailing how the documents and
Management drawings for each design stage will be managed and submitted for
Plan (DwMP) review and incorporate DMS requirements. The DwMP is required to
incorporate a schedule for the delivery of drawings and reports
identifying timing for issue of design packages to the ARO for review.
Interface A plan submitted by the designers detailing how the design consultant
Management will manage the interface between design disciplines, design
Plan consultants, stakeholders and adjacent work packages as part of the
overall project and other projects including the optimisation of
occupations and impact on the current MTM Maintenance & Renewal
program [Incorporated into the DMP when the design is of a single
discipline or involving minimal interfaces] .
M&R Program The annual Maintenance and Renewal Program managed by MTM
Infrastructure Delivery.
MTM MTM Division responsible for the management and operation of the
Operations metropolitan train system.
Approving Manager: Head of Network Asset Management Approval Date: 12/06/2013 Next Review Date: 12/06/2016
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 4 of 27
MTM DESIGN AND TECHNICAL REVIEW PROCEDURE
Network Asset Network Asset Management is responsible for the Asset Management
Management of all infrastructure assets within Metro’s lease.
(NAM)
Project Brief The Project Brief is a document containing the Project Objectives, the
Functional Operational Requirements and establishes the design basis
to be adopted by the project.
FIS The Final Impact Statement is a report detailing the preferred option for
the project and confirms that it meets the Operational Requirement of
Metro and stakeholders.
SID Register The Safety In Design Register detailing the safety related items raised
and considered during the design development and design review
process.
Approving Manager: Head of Network Asset Management Approval Date: 12/06/2013 Next Review Date: 12/06/2016
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 5 of 27
MTM DESIGN AND TECHNICAL REVIEW PROCEDURE
5 Approach
The technical review undertaken by the EDR group must consider the design from the
Network Asset Management perspective, in particular the impact on the existing inspection
and maintenance regime and future maintenance access requirements.
The technical review is not a substitute for the checking and independent review processes
that form part of the preparation of engineering drawings.
The aim of the review is to assist the designer to resolve any design deficiencies, errors or
omissions and non-compliances in relation to the functional and operational requirements
and any deviation or non-compliance to current standards and maintenance practices.
It is essential that the reviewer assesses the impact of the design on the maintenance of
the assets for the duration of their life cycle including any potential interface issues and the
impact on existing or related assets.
The technical review should be conducted using the appropriate MTM Engineering Review
Form. The review must follow the RAMS principle to ensure these are considered during
the technical review.
Aspects of the review should include but not be limited to:
1. Documents – List the project documents provided by MTM for review.
2. Design - including compliance with relevant specifications and standards.
3. Type Approval/Engineering Change Approval - what is the status of such
application.
4. Identify changes that will have an impact on operational safety and rail accreditation,
in particular:
Description of the area of non-compliance including the exact variation from
the standard
Comment on the reason that the standard can not be complied with
Comment on what would have to be done (regardless of practicability) to
comply with the standard, ideally including an estimate of time and cost
Comment on proposed mitigations, if any, for the area of non-compliance
These above points would form the basis for the risk assessment of areas of non-
compliance to determine whether they can be accepted and what controls need to be put
in place to reduce the risk to SFAIRP in accordance with the MTM Engineering Change
process.
5. Reliability - proposed design must consider the enhancement of performance and
reliability of the rail assets.
6. Availability - downtime required for maintenance and renewal.
7. Maintainability - including the required competencies of technicians attending the
failure of an asset and on the access for maintenance and renewal activities and
ongoing OEM support and supply of spares.
8. Supportability - ongoing availability/technical support for asset life cycle.
9. Form, Fit, Function - configuration management parameters relating to asset
maintenance and renewal activities.
10. Occupational Health & Safety and Environment - list any OH&S and/or
environmental hazards/impacts. The review shall consider any personal safety risks
to personnel and maintenance staff that may need to access the installed
infrastructure.
Approving Manager: Head of Network Asset Management Approval Date: 12/06/2013 Next Review Date: 12/06/2016
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 6 of 27
MTM DESIGN AND TECHNICAL REVIEW PROCEDURE
11. Risk Assessment - list any risks of the design including rail safety criticalities.
12. Provide any other comments for consideration in the design.
13. Verify compliance with the MTM Functional and Operational requirements.
The Final Design Report, incorporating verification and validation of safety functions during
design, confirmation that MTM design standards and operational requirements have been
met, close out of all design issues raised by the EDR group and any approved non-
conformances accepted during the design, must be submitted to MTM EDR to confirm that
the design has been completed in accordance with the requirements as specified by MTM.
MTM EDR is to endorse that the design provided is appropriate and the engineering
review has been completed satisfactorily and all the issues have been closed out
and/or referred to the next stage of design for further consideration.
Approving Manager: Head of Network Asset Management Approval Date: 12/06/2013 Next Review Date: 12/06/2016
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 7 of 27
MTM DESIGN AND TECHNICAL REVIEW PROCEDURE
7 Responsibilities
MTM has a primary responsibility as the Accredited Rail Operator under the Rail Safety Act
(2006) for the safe construction, operation and maintenance of the railway infrastructure.
This includes the engagement of a design consultant to provide an engineering design for
the delivery of a project or significant maintenance and renewal works to be incorporated
as part of the operating railway.
MTM remain responsible for the safe conduct of their rail operations irrespective of whether
or not activities are contracted to other parties. MTM cannot contract out responsibility for
safety, and retains responsibility to the extent that they can exercise control irrespective of
the details of the design contract entered into.
As the ARO, MTM must take all reasonably practicable steps to ensure that design
services provided are of an appropriate standard and specification to ensure the continued
safety of the railway operations. Design consultants are subject to the safety duty of the rail
transport operator (MTM) for whom they undertake the work and must ensure that the work
undertaken satisfies the, so far as reasonably practicable principles and must comply with
MTM’s safety management system to the extent that it applies to the design task
undertaken.
Approving Manager: Head of Network Asset Management Approval Date: 12/06/2013 Next Review Date: 12/06/2016
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 8 of 27
MTM DESIGN AND TECHNICAL REVIEW PROCEDURE
Approving Manager: Head of Network Asset Management Approval Date: 12/06/2013 Next Review Date: 12/06/2016
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 9 of 27
MTM DESIGN AND TECHNICAL REVIEW PROCEDURE
Approving Manager: Head of Network Asset Management Approval Date: 12/06/2013 Next Review Date: 12/06/2016
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 10 of 27
MTM DESIGN AND TECHNICAL REVIEW PROCEDURE
After submission and review of the initial design, the design consultant must prepare
progressive design package submissions to cover the stages as the design
progresses from preliminary design through to the final design stage. It is essential
that the designer considers all the comments and issues raised by the technical review
team for each stage of the design and ensures that these comments are incorporated,
where possible, into the next stage of the design.
The designer must demonstrate how the comments and issues have been closed out
and incorporated into the updated designs, or provide reasons why this has not been
done, as part of the subsequent design submission stages.
The final design package must be submitted and shall incorporate the following:
Final design report including a table listing the variance to standards, SID
registers and associated report
Final drawings
Evidence of closed out items
Evidence of design checks by independent third party where appropriate
Consolidated comments sheet for final review by technical group
Updated risk register (to be part of Management of Change process)
Approving Manager: Head of Network Asset Management Approval Date: 12/06/2013 Next Review Date: 12/06/2016
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 11 of 27
MTM DESIGN AND TECHNICAL REVIEW PROCEDURE
Ensure the preparation of documentation that will facilitate the design and
construction process, in accordance with the MTM Standards, Operational
Requirement, Functional Specification, Project Brief and Scope of Work documents
Arrange and manage the necessary preliminary, detailed and final designs and
associated plans and technical documents for review
Provide details of occupation schedules for proposed project works to enable EDRG
to plan the timing of documents to be submitted for review and ensure sufficient
resources are available to complete “each stage of the review” within the agreed
timeframes
Liaise with MTM EDR to ensure technical review of all documents relating to the
project are undertaken
Facilitate the preparation of the DMP, DwMP and IMP
Liaise with MTM EDR to identify suitable consultant/s to assist in the review process
Liaise with MTM EDR to manage resources required to meet project response
deadlines
Ensure the relevant Testing and Commissioning Plans and relevant drawings, for
each stage of the project works, are prepared and submitted for review by EDR and
MTM Infrastructure
Ensure the Project Handover responsibilities are achieved, incorporating the close
out of contract issues, provision of As-in-Service drawings for incorporation into the
DoT DMS
Other responsibilities as outlined in the MTM Project management plan
Approving Manager: Head of Network Asset Management Approval Date: 12/06/2013 Next Review Date: 12/06/2016
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 12 of 27
MTM DESIGN AND TECHNICAL REVIEW PROCEDURE
Approving Manager: Head of Network Asset Management Approval Date: 12/06/2013 Next Review Date: 12/06/2016
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 13 of 27
MTM DESIGN AND TECHNICAL REVIEW PROCEDURE
Approving Manager: Head of Network Asset Management Approval Date: 12/06/2013 Next Review Date: 12/06/2016
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 14 of 27
MTM DESIGN AND TECHNICAL REVIEW PROCEDURE
Approving Manager: Head of Network Asset Management Approval Date: 12/06/2013 Next Review Date: 12/06/2016
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 15 of 27
MTM DESIGN AND TECHNICAL REVIEW PROCEDURE
Yes No
1.3 Request, receive and check all additional information for completeness
1.5 Ensure the relevant Rail Industry design standards have been
provided/are available.
2.2 Confirm that the design specification properly captures the scope and
intent of the design
2.3 Confirm that the design has addressed all the interface issues relevant to
all disciplines relating to the Project
2.4 Confirm that the operational and functional requirements have been
addressed as part of the design.
4.1 Confirm that the concept design review comments and recommended
changes have been considered and incorporated where deemed
beneficial, and that all stipulated changes have been incorporated
Approving Manager: Head of Network Asset Management Approval Date: 12/06/2013 Next Review Date: 12/06/2016
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 16 of 27
MTM DESIGN AND TECHNICAL REVIEW PROCEDURE
Yes No
4.2 Identify the changes that will have an impact on operational safety and
rail accreditation and ensure the changes have been referred for
processing in accordance with the MTM Management of Change
Process
4.3 Identify the need for the submission of Engineering Change for the
introduction of a new type of asset, changes to operating software or
dispensations required for changes to standards.
5.1 Confirm that all approvals required from regulatory authorities have been
identified
5.2 Confirm that all external interfaces have been verified and validated
5.3 Confirm that the implications of all design changes have been analysed
and the impacts have been resolved and that specifications and interface
documentation have been updated accordingly
5.4 Confirm that the design has been independently reviewed and formally
signed off by the independent third party where mandated
5.5 Confirm that the required level of design checking and verification has
been carried out for all critical or safety related elements in the design.
5.6 Undertake Safety in Design reviews and prepare the relevant SID
registers and reports for consideration by the responsible ARO.
Approving Manager: Head of Network Asset Management Approval Date: 12/06/2013 Next Review Date: 12/06/2016
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 17 of 27
MTM DESIGN AND TECHNICAL REVIEW PROCEDURE
Yes No
6.5 Ensure that final specialist engineering reports are completed and
recommendations incorporated in the design
6.6 Ensure that third party services for overhead and underground services
have been identified and the impact of the proposed design on these
services has been considered
7.2 When performing a detailed / follow-up review, ensure that all issues
identified as part of the earlier review have been addressed and resolved
or considered during the final stages of the design
7.3 Record the details and findings of the review undertaken for ‘each stage’
of the design review on the relevant Technical Review Forms and submit
to MTM Projects or Infrastructure for endorsement as applicable.
Approving Manager: Head of Network Asset Management Approval Date: 12/06/2013 Next Review Date: 12/06/2016
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 18 of 27
MTM DESIGN AND TECHNICAL REVIEW
PROCEDURE
L1-NAM-PRO-002 Version: 2 Effective from: 12th June 2013
Approving Manager: Head of Network Asset Management Approval Date: 12/06/2013 Next Review Date: 12/06/2016
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 19 of 27
MTM DESIGN AND TECHNICAL REVIEW PROCEDURE
Project Title
Project Package No:
MTM Package No: TS1.16. Engineering Manager:
Package Title: Date Distributed:
Drawings sent by: Date Compiled:
MTM Project Manager:
Review
Item Document Reference Cat. Comp/ Engineering Team Directions Designer Response
Comment
Initial
1
Approving Manager: Head of Network Asset Management Approval Date: 12/06/2013 Next Review Date: 12/06/2016
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 20 of 27
MTM DESIGN AND TECHNICAL REVIEW PROCEDURE
Approving Manager: Head of Network Asset Management Approval Date: 12/06/2013 Next Review Date: 12/06/2016
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 21 of 27
MTM DESIGN AND TECHNICAL REVIEW PROCEDURE
Approving Manager: Head of Network Asset Management Approval Date: 12/06/2013 Next Review Date: 12/06/2016
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 22 of 27
MTM DESIGN AND TECHNICAL REVIEW PROCEDURE
A Proof Engineering Report shall be submitted in respect of each Design Package. The Proof
Engineering Report shall be an independent review report.
The Proof Engineering Reports must be structured in the following format (as a minimum):
a) introduction
b) key design inputs provided by the Designer
c) design assumptions and criteria adopted for proof engineering
d) key standards used in proof engineering
e) analytical methodology used in proof engineering
f) any non-conformances with standards and design brief
g) Attachment A - Proof Engineering Certificates
h) Attachment B – Certified Drawings
i) Attachment C – Relevant Correspondence; and
j) Attachment D – Other Related Information.
Approving Manager: Head of Network Asset Management Approval Date: 12/06/2013 Next Review Date: 12/06/2016
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 23 of 27
MTM DESIGN AND TECHNICAL REVIEW PROCEDURE
Name
(please print)
On behalf of (Company)
Date
Approving Manager: Head of Network Asset Management Approval Date: 12/06/2013 Next Review Date: 12/06/2016
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 24 of 27
MTM DESIGN AND TECHNICAL REVIEW PROCEDURE
Appendix 6 Cont’d
CONTRACTOR’S ENGINEER
I ............................................................................................................................., the undersigned
am responsible for supervising the construction of temporary works detailed on the following listed
final drawings and specifications certified by the Proof Engineer. Using due skill, care and diligence, I
have reviewed the relevant geometric surveys and test reports and made inspections during the
construction of the temporary works and certify that the completed temporary works complies with the
certified drawings and specifications.
Signed ...................................................................................................................
Date ....................................................................
DESIGN ENGINEER
Signed ...................................................................................................................
Date ....................................................................
Contractor to Schedule all Drawings and Specifications of temporary works certified by the Proof
Engineer, applicable to this joint Certificate of Compliance.
Approving Manager: Head of Network Asset Management Approval Date: 12/06/2013 Next Review Date: 12/06/2016
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 25 of 27
MTM DESIGN AND TECHNICAL REVIEW PROCEDURE
1. Introduction
3. Definitions
4. Abbreviations
5. Project Definition
5.1 Background
5.2 Work Package - Project Scope
5.3 Locations and Limit of Work
5.4 Contractors and Consultants for Project
7. Stakeholders
9. Detail Design
9.1 MTM Design Management Role
9.2 Design Handover
9.3 Value Engineering
9.4 Constructability and Occupational Planning
9.5 Safety in Design
9.6 Detail Design Review
12. Construction
12.1 Design Queries – DTQs
12.2 Design Changes and Variations
12.3 Construction Inspections
Approving Manager: Head of Network Asset Management Approval Date: 12/06/2013 Next Review Date: 12/06/2016
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 26 of 27
MTM DESIGN AND TECHNICAL REVIEW PROCEDURE
Approving Manager: Head of Network Asset Management Approval Date: 12/06/2013 Next Review Date: 12/06/2016
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 27 of 27