Page 1/2 DAILY DRILLING REPORT

8-Mar-20 No: 26

GENERAL DATAINFORMATION:
Rig Name: ADM-6 DRLG SUPV. MOHAMED HASHEM Water Depth: 77 ONHIRE DAYS: 25.52
Well Name: AMAL-18 STA Night DRLG. MOHAMED SABER RKB-MSL: 95.3 MOVING: 1.52
Location: Gulf Of Suez DRLG ENG ISLAM BADR RKB-THF: 57.5 FT PLANNED DAYS: 48
Field: AMAL FIELD PET. ENG PLANNED TD: 10242 FT TODAY NPT, HR:
PLATFORM: AMAL-B SPUD DATE 29/02/2020 Cumulative NPT, hrs: 6

06:00 Status: RIH W/ 8 1/2" RSS BHA (BHA #7) F/ 3400' T/5650' Daily Cost, USD: $ 102,523

24Hs Summary: till CONT'D DRLG OF 8 1/2" HOLE FROM 5990' TO 6150' (BASE OF S.GHARIB), SWEEP HOLE WITH TANDEM PILL, SPOT 50 BBL HI-VIS PILL ON
Cum. Cost, USD: $ 1,664,709
00:00 BTM, POOH INSIDE CASING,

24Hs plan: CONT'D RIH W/ 8 1/2" RSS BHA (BHA #7) T/6150 FT, DISPLACE HOLE TO OBM AND CONTINUE DRLG TO 10246 FT. A.F.E: MM $6.00

HSE:
Trip Drill: Sour Gas: Fire Drill: 16/02/2020 Days Free Since LTA
Kick Drill: Rig Evac: M O B: LAST BOP TEST 20/02/2020
Drills run Today: STOP CARDS First aid Cases: H2S Drill 21/02/2020

BHA
BHA Number: 7 Length (ft): BHA Wt: 48.00 Wt. below jar IN MUD: 12 KLBS JAR S/N: DJ 10-650-90
Jar in hole (hrs) 20
Components
** BHA #7 : ( 8 1/2" PDC BIT + ATK STEERABLE + 6 3/8" FLEX SUB + 6 3/4" ON-TRACK-STOP + 6 3/4" BCPM + 6 3/4" NM STOP-SUB + 6 3/4" STAB. + 6 CIRC. SUB S/N: 81
3/2" FLOAT-SUB + 6 3/8" BPL+ 6 X 6 1/2" DC + 6 1/2" JAR + 3 X 6 1/2" DC + 24/5" HWDP).
CIRC. SUB HR: 44.5
BIT INFORMATION MUD Information WellControl: Drilling Information
Bit Number: 2 TEST TIME: Last Csg Depth MD(ft): 3456.5 Motor AKO

Run Number: 3 Mud sys: OBM Last Csg TVD (ft): Motor RPG
Type: PDC Mud type: OBM FIT/LOT (EMW): P/U - S/O- ROT WT.S (klbs):
IADC Code: M223 FLOW LINE TEMP, F 90 current mud wt. Motor RPM
Manufacturer: BAKER HUGHES DEPTH 6150 MAASP (psi): 0 Wt on Bit (klbs):
Size (in.): 8 1/2" MUD WT - PPG 10.50 Last BOP Test: Surface RPM:
Serial No: 5300526 F. VIS.- SEC/Q 65 SCR Pump Information:
Nozzles: 6 * 13 RPM 6 13 DEPTH: Pump PumpLiner Strokes Circ. Rate
TFA : RPM 3 11 time: Number bore(in) Ln(in) SPM (gpm)
BIT FOOTAGE PV - CP 20 SPM: 1
Last Run date: 2/3/2020 YP - lb/100ft2 26 Pump1 -psi 2
total on-btm(hrs) 57.42 GEL 10S - lb/100ft2 12 Pump2 -psi Stand-Pipe (psi):
TOTAL FOTAGE: 1538.0 GEL 10M - lb/100ft2 15 Pump3 -psi Flowrate (gpm):
current run depth: 3900 API FILTRATE HPHT 6 Directional Survey Information:
Today on-btm hrs: 3.68 CAKE API/HTHP- 1/32 1 MD Angle AZI TVD Vertical Coordinates DLS
Today footage: 160.0 RETORT WATER 17% 4983.00 32.02 37.79 4780.89 714.69 867964.61 599154.56 0.84
Today ROP (on btm) 45.0 RETORT BASE FLUID 69% 5080.00 32.55 38.41 4862.89 766.05 867974.36 599167.00 0.64
RETORT SOLIDS 14% 5176.00 32.61 38.13 4943.78 817.42 867984.13 599179.38 0.17
OIL % 5272.00 32.51 37.84 5024.69 868.73 867993.83 599191.80 0.19
ALKALINITY 4 5366.00 32.76 37.61 5103.85 919.05 868003.29 599204.03 0.30
DULL GRADING WATER % 5461.00 32.77 37.90 5183.74 970.09 868012.89 599216.43 0.17
Inner Rows: MP-CCs H2SO4 5555.00 32.74 37.87 5262.79 1020.59 868022.42 599228.68 0.04
Outer Rows: O/W % 5651.00 32.71 37.65 5343.55 1072.11 868032.11 599241.19 0.13
Dull Charac.: EXCESS LIME 5 5747.00 32.72 38.76 5424.33 1123.66 868041.90 599253.63 0.62
Location: CL-Mg/L 32,000 5842.00 32.58 39.92 5504.32 1174.69 868051.81 599265.72 0.68
Bearing Seals: CACL2 - %/WT 22.8 5938.00 32.52 38.74 5585.24 1226.11 868061.80 599277.91 0.66
Gauge: ELECT. Stability - Volts 600 6035.00 32.41 39.21 5667.08 1277.92 868071.79 599290.25 0.28
Other Dull: KCL %
Reason Pulled:
CONSUMABLES
PRODUCT PREV. BBLS RCVD. BBLS USED BBLS TODAY BBLS USABLE REQUIRED
P/ WATER, BBL 490 80 80 490 0
D/ WATER, BBL 176 0 0 176
DIESEL, BBL 626 0 41 585 365
BULK MATERIAL
PRODUCT PREV. RCVD. USED TODAY (CU.FT) TODAY (SACKS) TODAY (MT)
CEMENT G-NEAT #1 800 442 358 358.00
CEMENT G-NEAT #2 0 0 0 0.00
CEMENT G-NEAT #3 0 0 0 0.00
BARITE #1, CU.FT 56 0 7 49 66.22
BARITE #2, CU.FT 0 0 0 0.00
BARITE #3, CU.FT 0 0 0 0.00

1of2
Allowed Loads

Page 2/2 DAILY DRILLING REPORT


8/Mar/20 No: 26

### Geology Information:


Formation Top in program Actual Formation Top in program Actual
Lithology Lithology
Name: MD/TVDSS MD/TVDSS Name: MD/TVDSS MD/TVDSS
S.Gharib ANHYDRITE, SALT & SHALE BELAYIM 6150/-5675
KAREEM RUDIES
PERSONNEL ON BOARD
Company No. of people Company No. of people
Amapetco 5 Mud logging Petro-service 4
ENVIRONMENTAL SOLUTION 4 ADES Service 1
Amapetco Field 6 SLB W/L 0
EVACO 2 SLB Downhole 0
RIG ADM-6 47 Gharib S/L 0
Catering 14 Baker Fishing 0
Baker Mud 1 WELL SERVICE GYRO 0
DIRECTIONAL & MWD BAKER 4 TOTAL ON BOARD 88
TIME (HH:MM)
OPERATIONS
From To Hrs
0:00 4:30 4.5 CONT'D DRLG OF 8 1/2" HOLE FROM 5990' TO 6150' (BASE OF S.GHARIB)
** WASH UP & REAM DOWN EVERY STAND
** SWEEP HOLE W/ TANDOM PILL EVERY STAND.
** SEND DOWNLINK EVERY STAND.
** RECORD MWD SURVEY EVERY STAND.
4:30 6:00 1.5 SWEEP HOLE WITH TANDEM PILL (50 BBL LOW VIS + 50 HIGH VIS), CIRCULATE TILL HAD SHAKER CLEAN.SPOT 50 BBL HI-VIS PILL ON BTM.
6:00 9:00 3.0 POOH INSIDE CASING, INSTALL FULL OPENING SAFETY VALVE & MONITOR THE WELL THROUGH TRIP TANK
** HOLE IN GOOD CONDITION (MAX DRAG WHILE POOH : 25 KLBS)
** NO LOSSES WHILE RIH.
9:00 0:00 15.0 RIG IS ZERO RATE FOR PREPARING OBM & HANDLING OF BOAT OPERATIONS INCLUDING BACKLOAD (DUE TO RIG LIMITED VARIABLE LOADS)
** RECEIVED 310 BBL PREMIXED OBM FROM BOAT ( WT: 9.5 PPG , ES: 400 & OWR: 70:30)
** OFFLOAD CHEMICALS TO BUILD FRESH OBM.

BOAT MD-519 OPERATIONS :


OFF-LOAD BACKLOAD
11 MUD CHEMICAL BALLETS 118 JTS 5" DP (BOAT DECK STORAGE)
39 BIG BAG CACO3 10 JTS JUNK 5" DP
5 FIRE EX. BOXES 5 BIG BAG KCL
BAKER EMPTY LONG BASKET BAKER LONG BASKET (MODULAR MOTOR)
10 CUTTING BOX MUD CHEMICAL XANPLEX BALLET
ADES OPEN TOP CONTAINER 48 JTS 7" CSG (BOAT DECK STORAGE)
PETROSERVICE TOOLBOX
2 2 DRUMS OF OIL DISPERSENT
310 BBL PRE-MIXED OBM

TOTAL 24.0
OPERATION AFTER MIDNIGHT
0:00 4:00 4.0 RIG IS ZERO RATE FOR PREPARING OBM. (DUE TO LIMITED VARIABLE LOADS).
4:00 6:00 2.0 RIH W/ 8 1/2" RSS BHA (BHA #7) F/ 3400' T/5650 FT.
** PERFORMED VERIFICATION ELECTRONIC TEST FOR BAKER MWD & DIRECTIONAL EQUIP.
** HOLE IN GOOD CONDITION

TOTAL 6.0

Rental Equipments Tracker


No. COMPANY Description Arrival date Departure date Remarks
1 E.S. SOLID REMOVAL 3/Mar/20
10 Bakerhuges Directional drilling 26/Feb/20
11 POSS Drilling Jars 26/Feb/20
12 WEATHERFORD Multi Circulation ByPass Sub PBL 26/Feb/20
13 PETROSERVICE Mud Logging Unit 20/Feb/20
14 Well Service Gyro Survey 24/Feb/20 03/March/2020.
UNIT PRICE, $
DESCRIPTION 12-Feb-20 13-Feb-20
OPERATING/S.BY

7" P-110, 29, BTC 800 /Jt


Wellhead and Manifold
3 1/2" tbg 900/Jt
Tubing-Completion Equipment
Down Hole Equipment (B-PLUG)
MATERIAL TANGIBLE
Casing Cementing Accessories
Mud and Chemicals
Completion Fluid (Incase of Diesel)
Cement and Additives
Bits and coreheads 20000 / Bits
Fuel (85$/bbl) including boats consumpsion 6000/DAY 1275 3825
Water Supply 500/Truck
Other Material (transportaion,inspection,
material)
DRILLING RIG
Drilling Rig rates (RIG Adm-VI) 31000 14854 31000
Catering 60/Person/Day 420 420
Extra Rig Equipment
MATERIAL INTANGIBLE
Csg.,CP & Tbg Services 1000 / Day
Fishing Operator 1200/Day
Fishing Equipmet 2000 /Day
Whipstock (Total Five Days) 67,000 /Job
Mud Logging 500/DAY
Mud Engineering 400/DAY
Cement Operator 1200/DAY

Drlg eng (450$/one Eng) + MWD(Eng. 546 $/day) 1446 /Day

RSS (AUTOTRAK ONLY) (Stby $ 4155/Day) 7850/DAY


MWD 900 / Day
Drilling MOTOR ( Stby $ 195 /Day) 136 /Cir. Hrs
LWD Tripple Combo (Stby $ 1746 /Day ) 4000 / Day
Electric Logs / Wireline Operations 100,000/Job
PBL Multi Activation Bypass Sub 350/Day
Drilling Jars 200/Day
Solid Removal Equipment & OPERATOR 1000/DAY
Casing Circulating Packer & OPERATOR 600/DAY
Well Completion ENGINEER 1200/DAY
Casing Perforations 420000
CONSULTANT (supervision) 500/DAY
COIL TUBE & LIFTING 50,000/Job
Rig Inspection 30000/Job
DOwn Hole ENGINEER (B.P. Ops) 500/day
RCT Job (RCT + EMA) 36000/Job
RCT Job (RCT + PTC) 51000 / Job
Gharib S/L 500 /Day
Other Services
AUXILIARY SERVICES
BOATS (Tug Boats & Mooring Buoy AHTS) 15000/DAY 57188 15000
Dp1 AHTS 4750/DAY 4750 4750
RIG MOVE (towing) & POSITIONING 40000/DAY 40000
SEA BED SURVEY (ROV) 15000 15000
Jetty Rental 1000/DAY 1000 1000
12000/DAY (Crew
HELLICOPTER
Change)

LOGISTIC SERVICES $

TOTAL WELL COST/ DAY $ $ 134,487 $ 55,995

CUM. WELL COST : $ $ 134,487 $ 190,482


14-Feb-20 15-Feb-20 16-Feb-20 17-Feb-20 18-Feb-20 19-Feb-20 20-Feb-20 21-Feb-20

1034

2720 2975 2295 2125 2040 2500 5100 5950


500 500

0 0 0 0 0 13562.5 31000 31000


420 1440 1440 1440 1440 1440 1300 660

1000 1000 1000 1000 1000 1000 1000 1000


1200 1200 1200 1200 1200 1200 1200 1200
2000 2000 2000 2000 2000 2000 2000 2000

400 400 400 400 400 400 400

500 500 500 500 500 500 500


30000 15000

275 275 275 275 275 275 275 275


7648
500 500 500 500 500 270 270

15000
4750 4750 4750 4750 4750 4750 4750 4750

1000 1000 1000 1000 1000 1000 1000 1000

8000 12000

$ 36,365 $ 16,040 $ 15,860 $ 15,190 $ 57,105 $ 44,128 $ 57,977 $ 49,005


$ 226,847 $ 242,887 $ 258,747 $ 273,937 $ 331,042 $ 375,169 $ 433,146 $ 482,151
22-Feb-20 23-Feb-20 24-Feb-20 25-Feb-20 26-Feb-20 27-Feb-20 28-Feb-20 29-Feb-20

8750

1174 0 492 13996 582 1630 1492

40000
32000
5950 6630 2805 2805 5100 4675 4675 4675

31000 31000 31000 31000 31000 31000 31000 31000


600 660 660 660 660 1200 1000 1000

1000
1200 1200 1200
2000 2000 2000 2000 2000

500 500 500 500 500


400 400 400 400 400 400 400 400
1200 1200 1200 1200 1200 1200 1200

1466 1466

4155 4155
900 900
195 195

40000
350 350
200 200

500 500 500 500 500 500 500 500


500 500 500 500 500 500 500 500

270 270 270 270 270 270

4750 4750 4750 4750 4750 4750 4750 4750

1000 1000 1000 1000 1000 1000 1000 1000

12000

$ 51,544 $ 48,910 $ 45,577 $ 46,785 $ 115,076 $ 95,327 $ 86,421 $ 53,083


$ 533,695 $ 582,605 $ 628,182 $ 674,967 $ 790,043 $ 885,370 $ 971,791 $ 1,024,874
1-Mar-20 2-Mar-20 3-Mar-20 4-Mar-20 5-Mar-20 6-Mar-20

1364 266 7000 1730 2295 0

4845 4675 6205 6205 6800 6800

31000 31000 31000 31000 31000 31000


1000 1000 1200 1200 1000 1000

67000
500 500 500 500 500 500
400 400 400 400 400 400

1466 1466 1466 1466 1466 1466

4155 4155 7850 7850 7850 7850


900 900 900 900 900 900
2877.76 1020 190 190 190 190
1750 1460 4000 4000 4000 4000

350 350 350 350 350 350


200 200 200 200 200 200
1000 1000 1000 1000

500 500 500 500 500 500


500 500 500 500 500 500

4750 4750 4750 4750 4750 4750

1000 1000 1000 1000 1000 1000

12000

$ 124,558 $ 54,142 $ 81,011 $ 63,741 $ 64,701 $ 62,406


$ 1,149,432 $ 1,203,574 $ 1,284,585 $ 1,348,326 $ 1,413,027 $ 1,475,433
7-Mar-20 8-Mar-20 9-Mar-20 10-Mar-20 11-Mar-20 12-Mar-20 13-Mar-20 14-Mar-20

1397 29917

29750 17000

31000 31000
1000 1000

500 500
400 400

1466 1466

7850 7850
900 900
190 190
4000 4000

350 350
200 200
1000 1000

500 500
500 500

4750 4750

1000 1000

$ 86,753 $ 102,523 $ - $ - $ - $ - $ - $ -
$ 1,562,186 $ 1,664,709 ### ### ### ### ### ###
15-Mar-20 16-Mar-20 17-Mar-20 18-Mar-20 19-Mar-20 20-Mar-20 21-Mar-20 22-Mar-20
$ - $ - $ - $ - $ - $ - $ - $ -
### ### ### ### ### ### ### ###
23-Mar-20 24-Mar-20 25-Mar-20 26-Mar-20 27-Mar-20 28-Mar-20 29-Mar-20 30-Mar-20
$ - $ - $ - $ - $ - $ - $ - $ -
### ### ### ### ### ### ### ###
31-Mar-20 1-Apr-20 2-Apr-20 3-Apr-20 4-Apr-20 5-Apr-20 6-Apr-20 7-Apr-20
$ - $ - $ - $ - $ - $ - $ - $ -
### ### ### ### ### ### ### ###
8-Apr-20 9-Apr-20 10-Apr-20 11-Apr-20 12-Apr-20 13-Apr-20 14-Apr-20 15-Apr-20
$ - $ - $ - $ - $ - $ - $ - $ -
### ### ### ### ### ### ### ###
16-Apr-20 17-Apr-20 18-Apr-20 19-Apr-20 20-Apr-20 21-Apr-20 22-Apr-20 23-Apr-20
$ - $ - $ - $ - $ - $ - $ - $ -
### ### ### ### ### ### ### ###
24-Apr-20 25-Apr-20 26-Apr-20 27-Apr-20 28-Apr-20 29-Apr-20 30-Apr-20 1-May-20
$ - $ - $ - $ - $ - $ - $ - $ -
### ### ### ### ### ### ### ###
2-May-20 3-May-20 4-May-20 5-May-20 6-May-20 7-May-20 8-May-20 9-May-20
$ - $ - $ - $ - $ - $ - $ - $ -
### ### ### ### ### ### ### ###
10-May-20 11-May-20 12-May-20 13-May-20 14-May-20 15-May-20 16-May-20 17-May-20
$ - $ - $ - $ - $ - $ - $ - $ -
### ### ### ### ### ### ### ###
18-May-20 19-May-20 20-May-20 21-May-20 22-May-20
$ - $ - $ - $ - $ -
### ### ### ### ###

Вам также может понравиться