Вы находитесь на странице: 1из 45

MONTHLY REPORT

Project : CAMBODIA CHINA POLYTECHNIC UNIVERSITY


Report : No 003
Period : 24th December To 24th January, 2019
Owner : OCIC

To : Director of Mega Asset Management


CC : ………………………………………….

Phnom Penh, Date: 24th January 2019


Approved by Checked by Prepared by: MAM

Meas Daramony Tep Kosal Chhem Sophea


CONTENT

Page
I. Monthly Construction Activities 1-8

II. Master Schedule and Summary Of Bill Of Quantity 9 - 17

III. Manpower Record

IV. Weather Record 18 - 19

V. Site Progress Photos Report 20 - 28

VI. Summary of Monthly CPM Record 29 - 33

VII. Zoning & Schedule Plan 34 - 36


I. MONTHLY CONSTRUCTION ACTIVITIES
MONTHLY CONSTRUCTION ACTIVITIES

DATE DESCRIPTION MANPOWER


PRELIMINARY
1 Roof zince sheet installing for warehouse
2
3
STRUCTURAL WORK
1 Removing formwork after lean concreting around bored piles

December 24, 2018


2
3
MEP WORK

None

ARCHITURAL WORK

None

PRELIMINARY
1 Steel yard preparation
2 Warehouse installation
3
STRUCTURAL WORK
1 Soil excavation for pile's heads cut off
December 25, 2018

2
3
MEP WORK

None

ARCHITURAL WORK

None

PRELIMINARY
1 Steel yard preparation
2 Warehouse installation
3
STRUCTURAL WORK
1 Soil preparation for pile's heads cut off
December 26, 2018

2
3
MEP WORK

None

ARCHITURAL WORK

None
PRELIMINARY
1 Warehouse installation
2
3
STRUCTURAL WORK
1 Pile's head cutting/breaking

December 27, 2018


2
3
MEP WORK

None

ARCHITURAL WORK

None

PRELIMINARY
1 Temporary access road setting out
2
3
STRUCTURAL WORK
1 Pile's head cutting/breaking
December 28, 2018

2
3
MEP WORK

None

ARCHITURAL WORK

None

PRELIMINARY
1
2
3
STRUCTURAL WORK
1 Pile's head cutting/breaking
December 29, 2018

2
3
MEP WORK

None

ARCHITURAL WORK

None

PRELIMINARY
1 Steel yard preparation
2
3
STRUCTURAL WORK
1 Pile's head cutting/breaking
December 31, 2018

2 Soil compaction before lean concreting


3
MEP WORK

None

ARCHITURAL WORK

None
PRELIMINARY
1 Steel yard preparation
2
3
STRUCTURAL WORK
1

January 1, 2019
2
3
MEP WORK

None

ARCHITURAL WORK

None

PRELIMINARY
1 Warehouse installation
2
3
STRUCTURAL WORK
1
January 2, 2019

2
3
MEP WORK

None

ARCHITURAL WORK

None

PRELIMINARY
1 Soil preparation for site office and parking lot
2
3
STRUCTURAL WORK
1 Levelling pile's cut off level
January 3, 2019

2
3
MEP WORK

None

ARCHITURAL WORK

None

PRELIMINARY
1 Lean concreting for site office and parking lot
2 Warehouse installation
3
STRUCTURAL WORK
1 Lean concreting for pile cap work
January 4, 2019

2
3
MEP WORK

None

ARCHITURAL WORK

None
PRELIMINARY
1
2
3
STRUCTURAL WORK
1 Pile's head cutting/breaking

January 5, 2019
2
3
MEP WORK

None

ARCHITURAL WORK

None

PRELIMINARY
1 Steel yard preparation
2
3
STRUCTURAL WORK
1
January 7, 2019

2
3
MEP WORK

None

ARCHITURAL WORK

None

PRELIMINARY
1
2
3
STRUCTURAL WORK
1 Lean concreting for pile cap work
January 8, 2019

2
3
MEP WORK

None

ARCHITURAL WORK

None

PRELIMINARY
1
2
3
STRUCTURAL WORK
1 Rebar bending/arrangment for pile cap work
January 9, 2019

2 PIT test for bored piles


3
MEP WORK

None

ARCHITURAL WORK

None
PRELIMINARY
1
2
3
STRUCTURAL WORK
1 Rebar bending/arrangment for pile cap work

January 10, 2019


2
3
MEP WORK

None

ARCHITURAL WORK

None

PRELIMINARY
1 Warehouse installation
2
3
STRUCTURAL WORK
1 Rebar bending/arrangment for pile cap work
January 11, 2019

2 Preparing formwork for pile cap work


3
MEP WORK

None

ARCHITURAL WORK

None

PRELIMINARY
1
2
3
STRUCTURAL WORK
1 Preparing pile's head for PDA testing
January 12, 2019

2 Pile's head breaking


3 Rebar bending/arrangment for pile cap work
MEP WORK

None

ARCHITURAL WORK

None

PRELIMINARY
1
2
3
STRUCTURAL WORK
1 Pile cap setting dimension setting out
January 14, 2019

2 Rebar cage of pile cap placing


3
MEP WORK

None

ARCHITURAL WORK

None
PRELIMINARY
1
2
3
STRUCTURAL WORK
1 Pile cap setting dimension setting out

January 15, 2019


2 Rebar cage of pile cap placing
3
MEP WORK

None

ARCHITURAL WORK

None

PRELIMINARY
1
2
3
STRUCTURAL WORK
1 Rebar installation for pile cap work
January 16, 2019

2 Formwork enclosing for pile cap


3
MEP WORK

None

ARCHITURAL WORK

None

PRELIMINARY
1
2
3
STRUCTURAL WORK
1 Pile cap concrete casting
January 17, 2019

2 Pile's head preparation for pile cap work


3
MEP WORK

None

ARCHITURAL WORK

None

PRELIMINARY
1 Safety barrier installation near excavated zone
2
3
STRUCTURAL WORK
1 Formwork dismantle of pile cap
January 18, 2019

2 Curing concrete pile cap after casting


3
MEP WORK

None

ARCHITURAL WORK

None
PRELIMINARY
1 Safety barrier installation near excavated zone
2 Temporary access road paving
3
STRUCTURAL WORK
1 Curing concrete pile cap after casting

January 19, 2019


2 Rebar installation for pile cap work
3 Formwork enclosing for pile cap
MEP WORK

None

ARCHITURAL WORK

None

PRELIMINARY
1
2
3
STRUCTURAL WORK
1 Pile's heads cutting
January 20, 2019

2
3
MEP WORK

None

ARCHITURAL WORK

None

PRELIMINARY
1 Temporary access road paving
2
3
STRUCTURAL WORK
1 Pile's heads cutting
January 21, 2019

2 Formwork enclosing for pile cap


3
MEP WORK

None

ARCHITURAL WORK

None

PRELIMINARY
1 Temporary access road paving
2
3
STRUCTURAL WORK
1 Pile's head cutting/breaking
January 22, 2019

2 Formwork enclosing for pile cap


3 Pile cap concrete casting
4 PIT test for bored piles
MEP WORK

None

ARCHITURAL WORK

None
PRELIMINARY
1 Temporary access road paving
2
3
STRUCTURAL WORK
1 Pile's head cutting/breaking

January 23, 2019


2 Rebar installation for pile cap work
3 Formwork enclosing for pile cap
MEP WORK

None

ARCHITURAL WORK

None

PRELIMINARY
1 Temporary access road paving
2
3
STRUCTURAL WORK
1 Pile's head cutting/breaking
January 24, 2019

2 Rebar installation for pile cap work


3 Formwork enclosing for pile cap
MEP WORK

None

ARCHITURAL WORK

None
II. MASTER SCHEDULE & BOQ SUMMARY
BILL OF QUANTITY AND COST ESTIMATION
PROJECT: CAMBODIA-CHINESE POLYTECNIC Project No:
SECTION: STRUCTURAL,ARCHITECTURAL & MEP WORKS Job No:
File No:
ADDRESS: PHNOM PENH,CAMBODIA
Issued Date 02-10-18

Floor Area Material Cost (USD) Labour Cost (USD) Total Cost Unit Rate
No Description of Work
(Sq.m) Total Total (USD) $/m2

I PRELIMINARIES 8,000.00 109,000.00 117,000.00 17.22


II STRUCTURAL WORKS 680,353.88 197,879.36 878,233.24 129.27
6,794.00
III ARCHITECTURAL WORKS 530,284.70 249,081.58 779,366.28 114.71
IV MEP WORKS 221,951.73 43,756.19 265,707.92 39.11
TOTAL= $ 1,440,590.31 $ 599,717.12 $ 2,040,307.43 $ 300.31
GRAND TOTAL PLUS 15% OF BENEFIT AND WASTAGE $ 1,656,678.85 $ 689,674.69 $ 2,346,353.55 $ 345.36

**If in doubt please contact us for more detail


Date: ______/______/2018 Phnom Penh , Date: ______/______/2018
Approved by: Prepared by:
PERCENTAGE OF COMPLETION
PROJECT: CAMBODIA-CHINESE POLYTECNIC
SECTION: STRUCTURAL,ARCHITECTURAL & MEP WORKS
ADDRESS: CHROY CHANGVA

Item Description of Work Unit Quantity Material Cost (USD) Labor.Cost (USD) Total Cost Actual Work Done (December) Actual Work Done (January)
Unit Rate $/m2
Unit Cost Total Unit Cost Total (USD) % (USD) % (USD)

A PRELIMINARIES
A-01 Site Clearing & Setting Out Ls 1.00 0.00 - 1000.00 1,000.00 1,000.00 50.00% 500.00
A-02 1 Tower Crane Rental for 6 Months Mth. 6.00 0.00 - 4500.00 27,000.00 27,000.00
A-03 Tower Crane Operator Mth. 6.00 0.00 - 1000.00 6,000.00 6,000.00
A-04 Foundation for Tower Crane Ls 1.00 6000.00 6,000.00 3000.00 3,000.00 9,000.00 30.00% 2,700.00 30.00% 2,700.00
A-05 Scaffoldings Ls 1.00 2000.00 2,000.00 2000.00 2,000.00 4,000.00
A-06 Hoarding Ls 1.00 0.00 - 2000.00 2,000.00 2,000.00 100.00% 2,000.00 100.00% 2,000.00
A-07 Security Services Ls 1.00 0.00 - 4000.00 4,000.00 4,000.00 5.00% 200.00 8.33% 333.33
A-08 Site Warehouse Ls 1.00 0.00 - 2000.00 2,000.00 2,000.00 50.00% 1,000.00 80.00% 1,600.00
A-09 Temporary Elevator Mth. 6.00 0.00 - 9000.00 54,000.00 54,000.00
A-10 Staff Admin & Management Ls 1.00 0.00 - 6000.00 6,000.00 6,000.00 5.00% 300.00 8.33% 500.00
A-11 Site Safety Ls 1.00 0.00 - 2000.00 2,000.00 2,000.00 5.00% 100.00 8.33% 166.67
Sub Total- A 8,000.00 109,000.00 117,000.00 5.38% 6,300.00 6.67% 7,800.00 17.22
B STRUCTURAL WORKS
B-I-PILLING WORKS
B-I-01 Pile Diametre 800mm m 1512.00 88.00 133,056.00 0.00 - 133,056.00 100.00% 133,056.00 100.00% 133,056.00
B-I-02 Pile Diametre 600mm m 1128.00 62.00 69,936.00 0.00 - 69,936.00 100.00% 69,936.00 100.00% 69,936.00
B-I-03 Breaking Head for Pilling Nos 66.00 0.00 - 100.00 6,600.00 6,600.00 75.76% 5,000.00
B-I-04 PDA Test Nos 2.00 0.00 - 2000.00 4,000.00 4,000.00
B-I-05 PIT Test Nos 66.00 0.00 - 35.00 2,310.00 2,310.00 54.55% 1,260.00
Sub Total- B-I 202,992.00 12,910.00 215,902.00 94.02% 202,992.00 96.92% 209,252.00 31.78
B-II PILECAP
B-II-01 Soil Excavation Work for Pilecap m3 1000.00 0.00 - 5.00 5,000.00 5,000.00 65.00% 3,250.00
B-II-02 Soil Filling Work for Pilecap m3 775.00 0.00 - 2.00 1,550.00 1,550.00
B-II-03 Lean Concrete for Pilecap m3 68.50 65.00 4,452.50 10.00 685.00 5,137.50 40.91% 2,101.70
B-II-04 Concrete for Pilecap m3 225.00 75.00 16,875.00 10.00 2,250.00 19,125.00 22.73% 4,346.59
B-II-05 Deformed Bar SD390 for Pilecap Ton 33.75 700.00 23,625.00 150.00 5,062.50 28,687.50 22.73% 6,519.89
B-II-06 Formworks for Pilecap m2 225.00 6.00 1,350.00 6.00 1,350.00 2,700.00 22.73% 613.64
B-II-07 Wire Tie kg 675.00 0.00 - 1.50 1,012.50 1,012.50 22.73% 230.11
Sub Total- B-II 46,302.50 16,910.00 63,212.50 26.99% 17,061.93 9.30
B-III GROUND FLOOR
B-III-01 Formwork for Ground Floor Beams m2 1025.00 6.00 6,150.00 6.00 6,150.00 12,300.00
B-III-02 Deformed Bar SD390 for Ground Floor Beams Ton 14.31 680.00 9,730.80 150.00 2,146.50 11,877.30
B-III-03 Concrete C30 for Ground Floor Beams m3 106.00 75.00 7,950.00 10.00 1,060.00 9,010.00
B-III-04 Formwork for Ground Floor Slabs m2 1250.00 6.00 7,500.00 6.00 7,500.00 15,000.00
B-III-05 Deformed Bar SD390 for Ground Floor Slabs Ton 14.25 680.00 9,690.00 150.00 2,137.50 11,827.50
B-III-06 Concrete C30 for Ground Floor Slabs m3 150.00 75.00 11,250.00 10.00 1,500.00 12,750.00

1 of 14
Item Description of Work Unit Quantity Material Cost (USD) Labor.Cost (USD) Total Cost Actual Work Done (December) Actual Work Done (January)
Unit Rate $/m2
Unit Cost Total Unit Cost Total (USD) % (USD) % (USD)
B-III-07 Formwork for Columns m2 150.00 6.00 900.00 6.00 900.00 1,800.00
B-III-08 Deformed Bar SD390 for Columns Ton 3.40 680.00 2,312.00 150.00 510.00 2,822.00
B-III-09 Concrete C30 for Columns m3 17.00 75.00 1,275.00 10.00 170.00 1,445.00
B-III-10 Formwork for Core Walls m2 20.00 6.00 120.00 6.00 120.00 240.00
B-III-11 Deformed Bar SD390 for Core Walls Ton 0.72 680.00 489.60 150.00 108.00 597.60
B-III-12 Concrete C30 for Core Walls m3 6.00 75.00 450.00 10.00 60.00 510.00
B-III-13 Formwork for Ramp m2 100.00 6.00 600.00 6.00 600.00 1,200.00
B-III-14 Deformed Bar SD390 for Ramp Ton 3.60 680.00 2,448.00 150.00 540.00 2,988.00
B-III-15 Concrete C30 for Ramp m3 30.00 75.00 2,250.00 10.00 300.00 2,550.00
B-III-16 Wire Tie kg 725.60 0.00 - 1.50 1,088.40 1,088.40
Sub Total- B-III 63,115.40 24,890.40 88,005.80 68.86
B-IV 1ST FLOOR
B-IV-01 Formwork for First Floor Beams m2 955.00 6.00 5,730.00 6.00 5,730.00 11,460.00
B-IV-02 Deformed Bar SD390 for First Floor Beams Ton 13.50 680.00 9,180.00 150.00 2,025.00 11,205.00
B-IV-03 Concrete C30 for First Floor Beams m3 100.00 75.00 7,500.00 10.00 1,000.00 8,500.00
B-IV-04 Formwork for First Floor Slabs m2 1041.67 6.00 6,250.00 6.00 6,250.00 12,500.00
B-IV-05 Deformed Bar SD390 for First Floor Slabs Ton 13.75 680.00 9,350.00 150.00 2,062.50 11,412.50
B-IV-06 Concrete C30 for First Floor Slabs m3 125.00 75.00 9,375.00 10.00 1,250.00 10,625.00
B-IV-07 Formwork for Columns m2 430.00 6.00 2,580.00 6.00 2,580.00 5,160.00
B-IV-08 Deformed Bar SD390 for Columns Ton 10.00 680.00 6,800.00 150.00 1,500.00 8,300.00
B-IV-09 Concrete C30 for Columns m3 50.00 75.00 3,750.00 10.00 500.00 4,250.00
B-IV-10 Formwork for Core Walls m2 40.00 6.00 240.00 6.00 240.00 480.00
B-IV-11 Deformed Bar SD390 for Core Walls Ton 2.04 680.00 1,387.20 150.00 306.00 1,693.20
B-IV-12 Concrete C30 for Core Walls m3 17.00 75.00 1,275.00 10.00 170.00 1,445.00
B-IV-13 Formwork for Staircases m2 40.00 6.00 240.00 6.00 240.00 480.00
B-IV-14 Deformed Bar SD390 for Staircases Ton 2.03 680.00 1,377.00 150.00 303.75 1,680.75
B-IV-15 Concrete C30 for Staircases m3 15.00 75.00 1,125.00 10.00 150.00 1,275.00
B-IV-16 Wire Tie kg 826.30 0.00 - 1.50 1,239.45 1,239.45
Sub Total- B-IV 66,159.20 25,546.70 91,705.90 83.14
B-V 2ND FLOOR
B-V-01 Formwork for Second Floor Beams m2 1000.00 6.00 6,000.00 6.00 6,000.00 12,000.00
B-V-02 Deformed Bar SD390 for Second Floor Beams Ton 14.18 680.00 9,639.00 150.00 2,126.25 11,765.25
B-V-03 Concrete C30 for Second Floor Beams m3 105.00 75.00 7,875.00 10.00 1,050.00 8,925.00
B-V-04 Formwork for Second Floor Slabs m2 1208.33 6.00 7,250.00 6.00 7,250.00 14,500.00
B-V-05 Deformed Bar SD390 for Second Floor Slabs Ton 15.95 680.00 10,846.00 150.00 2,392.50 13,238.50
B-V-06 Concrete C30 for Second Floor Slabs m3 145.00 75.00 10,875.00 10.00 1,450.00 12,325.00
B-V-07 Formwork for Columns m2 430.00 6.00 2,580.00 6.00 2,580.00 5,160.00
B-V-08 Deformed Bar SD390 for Columns Ton 10.00 680.00 6,800.00 150.00 1,500.00 8,300.00
B-V-09 Concrete C30 for Columns m3 50.00 75.00 3,750.00 10.00 500.00 4,250.00
B-V-10 Formwork for Core Walls m2 40.00 6.00 240.00 6.00 240.00 480.00
B-V-11 Deformed Bar SD390 for Core Walls Ton 2.04 680.00 1,387.20 150.00 306.00 1,693.20
B-V-12 Concrete C30 for Core Walls m3 17.00 75.00 1,275.00 10.00 170.00 1,445.00
B-V-13 Formwork for Staircases m2 40.00 6.00 240.00 6.00 240.00 480.00
B-V-14 Deformed Bar SD390 for Staircases Ton 2.03 680.00 1,377.00 150.00 303.75 1,680.75

2 of 14
Item Description of Work Unit Quantity Material Cost (USD) Labor.Cost (USD) Total Cost Actual Work Done (December) Actual Work Done (January)
Unit Rate $/m2
Unit Cost Total Unit Cost Total (USD) % (USD) % (USD)
B-V-15 Concrete C30 for Staircases m3 15.00 75.00 1,125.00 10.00 150.00 1,275.00
B-V-16 Wire Tie kg 883.80 0.00 - 1.50 1,325.70 1,325.70
Sub Total- B-V 71,259.20 27,584.20 98,843.40 76.98
B-VI 3RD FLOOR
B-VI-01 Formwork for Third Floor Beams m2 1000.00 6.00 6,000.00 6.00 6,000.00 12,000.00
B-VI-02 Deformed Bar SD390 for Third Floor Beams Ton 14.18 680.00 9,639.00 150.00 2,126.25 11,765.25
B-VI-03 Concrete C30 for Third Floor Beams m3 105.00 75.00 7,875.00 10.00 1,050.00 8,925.00
B-VI-04 Formwork for Third Floor Slabs m2 1208.33 6.00 7,250.00 6.00 7,250.00 14,500.00
B-VI-05 Deformed Bar SD390 for Third Floor Slabs Ton 15.95 680.00 10,846.00 150.00 2,392.50 13,238.50
B-VI-06 Concrete C30 for Third Floor Slabs m3 145.00 75.00 10,875.00 10.00 1,450.00 12,325.00
B-VI-07 Formwork for Columns m2 430.00 6.00 2,580.00 6.00 2,580.00 5,160.00
B-VI-08 Deformed Bar SD390 for Columns Ton 10.00 680.00 6,800.00 150.00 1,500.00 8,300.00
B-VI-09 Concrete C30 for Columns m3 50.00 75.00 3,750.00 10.00 500.00 4,250.00
B-VI-10 Formwork for Core Walls m2 40.00 6.00 240.00 6.00 240.00 480.00
B-VI-11 Deformed Bar SD390 for Core Walls Ton 2.04 680.00 1,387.20 150.00 306.00 1,693.20
B-VI-12 Concrete C30 for Core Walls m3 17.00 75.00 1,275.00 10.00 170.00 1,445.00
B-VI-13 Formwork for Staircases m2 40.00 6.00 240.00 6.00 240.00 480.00
B-VI-14 Deformed Bar SD390 for Saircases Ton 2.03 680.00 1,377.00 150.00 303.75 1,680.75
B-VI-15 Concrete C30 for Staircases m3 15.00 75.00 1,125.00 10.00 150.00 1,275.00
B-VI-16 Wire Tie kg 883.80 0.00 - 1.50 1,325.70 1,325.70
Sub Total- B-VI 71,259.20 27,584.20 98,843.40 76.98
B-VII 4TH FLOOR
B-VII-01 Formwork for Fourth Floor Beams m2 1000.00 6.00 6,000.00 6.00 6,000.00 12,000.00
B-VII-02 Deformed Bar SD390 for Fourth Floor Beams Ton 14.18 680.00 9,639.00 150.00 2,126.25 11,765.25
B-VII-03 Concrete C30 for Fourth Floor Beams m3 105.00 75.00 7,875.00 10.00 1,050.00 8,925.00
B-VII-04 Formwork for Fourth Floor Slabs m2 1365.00 6.00 8,190.00 6.00 8,190.00 16,380.00
B-VII-05 Deformed Bar SD390 for Fourth Floor Slabs Ton 18.018 680.00 12,252.24 150.00 2,702.70 14,954.94
B-VII-06 Concrete C30 for Fourth Floor Slabs m3 163.80 75.00 12,285.00 10.00 1,638.00 13,923.00
B-VII-07 Formwork for Columns m2 430.00 6.00 2,580.00 6.00 2,580.00 5,160.00
B-VII-08 Deformed Bar SD390 for Columns Ton 10.00 680.00 6,800.00 150.00 1,500.00 8,300.00
B-VII-09 Concrete C30 for Columns m3 50.00 75.00 3,750.00 10.00 500.00 4,250.00
B-VII-10 Formwork for Core Walls m2 40.00 6.00 240.00 6.00 240.00 480.00
B-VII-11 Deformed Bar SD390 for Core Walls Ton 2.04 680.00 1,387.20 150.00 306.00 1,693.20
B-VII-12 Concrete C30 for Core Walls m3 17.00 75.00 1,275.00 10.00 170.00 1,445.00
B-VII-13 Formwork for Staircases m2 40.00 6.00 240.00 6.00 240.00 480.00
B-VII-14 Deformed Bar SD390 for Saircases Ton 2.03 680.00 1,377.00 150.00 303.75 1,680.75
B-VII-15 Concrete C30 for Staircases m3 15.00 75.00 1,125.00 10.00 150.00 1,275.00
B-VII-16 Wire Tie kg 925.16 0.00 - 1.50 1,387.74 1,387.74
Sub Total- B-VII 75,015.44 29,084.44 104,099.88 76.26
B-VIII ROOF FLOOR
B-VIII-01 Formwork for Roof Floor Beams m2 700.00 6.00 4,200.00 6.00 4,200.00 8,400.00
B-VIII-02 Deformed Bar SD390 for Roof Floor Beams Ton 10.13 680.00 6,885.00 150.00 1,518.75 8,403.75
B-VIII-03 Concrete C30 for Roof Floor Beams m3 75.00 75.00 5,625.00 10.00 750.00 6,375.00
B-VIII-04 Formwork for Roof Floor Slabs m2 373.40 6.00 2,240.40 6.00 2,240.40 4,480.80

3 of 14
Item Description of Work Unit Quantity Material Cost (USD) Labor.Cost (USD) Total Cost Actual Work Done (December) Actual Work Done (January)
Unit Rate $/m2
Unit Cost Total Unit Cost Total (USD) % (USD) % (USD)
B-VIII-05 Deformed Bar SD390 for Roof Floor Slabs Ton 4.93 680.00 3,351.64 150.00 739.33 4,090.97
B-VIII-06 Concrete C30 for Roof Floor Slabs m3 44.81 75.00 3,360.60 10.00 448.08 3,808.68
B-VIII-07 Formwork for Columns m2 200.00 6.00 1,200.00 6.00 1,200.00 2,400.00
B-VIII-08 Deformed Bar SD390 for Columns Ton 3.00 680.00 2,040.00 150.00 450.00 2,490.00
B-VIII-09 Concrete C30 for Columns m3 20.00 75.00 1,500.00 10.00 200.00 1,700.00
B-VIII-10 Structural Steel Roof m2 965.00 35.00 33,775.00 15.00 14,475.00 48,250.00
Sub Total- B-VIII 64,177.64 26,221.56 90,399.20 70.40
B-IX STRUCTURAL WORKS FOR MAIN GATE
B-IX-01 Excavation for Footings & Ground Beams m3 36.00 0.00 - 5.00 180.00 180.00
B-IX-02 Stone 4-6 under Footings m3 10.80 20.00 216.00 4.00 43.20 259.20
B-IX-03 Lean Concrete under Footings m3 1.80 65.00 117.00 10.00 18.00 135.00
B-IX-04 Formwork for Footings m2 64.00 6.00 384.00 6.00 384.00 768.00
B-IX-05 Deformed Bar SD390 for Footings ton 4.80 680.00 3,264.00 150.00 720.00 3,984.00
B-IX-06 Concrete C30 for Footings m3 24.00 75.00 1,800.00 10.00 240.00 2,040.00
B-IX-07 Soil Backfill and Compaction for Footings m3 12.00 0.00 - 4.00 48.00 48.00
B-IX-08 Stone 4-6 under Ground Beams m3 0.64 25.00 16.00 4.00 2.56 18.56
B-IX-09 Lean Concrete under Ground Beams m3 1.20 65.00 78.00 10.00 12.00 90.00
B-IX-10 Formwork for Ground Beams m2 80.00 6.00 480.00 6.00 480.00 960.00
B-IX-11 Deformed Bar SD390 for Ground Beams ton 0.86 680.00 587.52 150.00 129.60 717.12
B-IX-12 Concrete C30 for Ground Beams m3 6.40 75.00 480.00 20.00 128.00 608.00
B-IX-13 Ground Compaction under Ground Slabs m2 225.00 0.00 - 1.00 225.00 225.00
B-IX-14 Deformed Bar SD390 for Ground Slabs ton 2.25 680.00 1,530.00 150.00 337.50 1,867.50
B-IX-15 Concrete C30 for Ground Slab m3 22.50 75.00 1,687.50 10.00 225.00 1,912.50
B-IX-16 Wire Tie kg 158.28 1.00 158.28 0.00 - 158.28
B-IX-17 Structural Steel Roof m2 265.00 35.00 9,275.00 15.00 3,975.00 13,250.00
Sub Total- B-IX 20,073.30 7,147.86 27,221.16

C ARCHITECTURAL WORKS
C-I GROUND FLOOR
C-I-01 Column Plastering Work m2 459.00 1.50 688.50 3.25 1,491.75 2,180.25
C-I-02 Column Painting Work m2 459.00 2.50 1,147.50 2.00 918.00 2,065.50
C-I-03 Exterior Plastering Work m2 775.00 1.50 1,162.50 3.25 2,518.75 3,681.25
C-I-04 Interior Plastering Work m2 1,955.00 1.50 2,932.50 2.75 5,376.25 8,308.75
C-I-05 Brick Wall 10cm thk m2 35.00 6.00 210.00 3.75 131.25 341.25
C-I-06 Brick Wall 20cm thk m2 1,335.00 11.50 15,352.50 5.50 7,342.50 22,695.00
C-I-07 Moulding Decoration Around m 110.00 2.50 275.00 2.50 275.00 550.00
C-I-08 Painting for Moulding Decoration Around m2 110.00 2.50 275.00 2.50 275.00 550.00
C-I-09 Floor Hardener m2 315.00 3.00 945.00 2.50 787.50 1,732.50
C-I-10 External Column and Wall Groving Ls 1.00 - - 5,000.00 5,000.00 5,000.00
C-I-11 Interior Painting Work m2 1,955.00 2.50 4,887.50 2.00 3,910.00 8,797.50
C-I-12 Exterior Painting Work m2 775.00 2.50 1,937.50 2.50 1,937.50 3,875.00
C-I-13 Floor Tile (60x60)mm m2 1,147.00 12.00 13,764.00 4.50 5,161.50 18,925.50
C-I-14 Bathroom Floor Tile m2 58.00 15.00 870.00 5.00 290.00 1,160.00
C-I-15 Waterproof for Bathroom m2 58.00 3.50 203.00 1.50 87.00 290.00
C-I-16 Ceiling for Bathroom (Moisture Resistant) m2 58.00 9.50 551.00 5.00 290.00 841.00

4 of 14
Item Description of Work Unit Quantity Material Cost (USD) Labor.Cost (USD) Total Cost Actual Work Done (December) Actual Work Done (January)
Unit Rate $/m2
Unit Cost Total Unit Cost Total (USD) % (USD) % (USD)
C-I-17 Natural Granite for Stair m2 68.00 30.00 2,040.00 15.00 1,020.00 3,060.00
C-I-18 Ceiling m2 1,147.00 7.50 8,602.50 2.50 2,867.50 11,470.00
C-I-19 Glass Handrail m2 20.00 180.00 3,600.00 20.00 400.00 4,000.00
C-I-20 Glass Window m2 261.00 70.00 18,270.00 10.00 2,610.00 20,880.00
C-I-21 Glass Door for Entrance Ls 4.00 470.00 1,880.00 40.00 160.00 2,040.00
C-I-22 Wooden Door 1500x2200mm Ls 10.00 330.00 3,300.00 20.00 200.00 3,500.00
C-I-23 Wooden Door 1000x2200mm Ls 4.00 220.00 880.00 20.00 80.00 960.00
C-I-24 Partition for Toilet Ls 8.00 250.00 2,000.00 50.00 400.00 2,400.00
Sub Total- C-I 85,774.00 43,529.50 129,303.50
C-II 1ST FLOOR
C-II-01 Column Plastering Work m2 459.00 1.50 688.50 3.25 1,491.75 2,180.25
C-II-02 Column Painting Work m2 459.00 2.50 1,147.50 2.00 918.00 2,065.50
C-II-03 Exterior Plastering Work m2 784.70 1.50 1,177.05 3.25 2,550.28 3,727.33
C-II-04 Interior Plastering Work m2 2,016.00 1.50 3,024.00 2.75 5,544.00 8,568.00
C-II-05 Brick Wall 10cm thk m2 56.00 6.00 336.00 3.75 210.00 546.00
C-II-06 Brick Wall 20cm thk m2 1,335.00 11.50 15,352.50 5.50 7,342.50 22,695.00
C-II-07 Moulding Decoration Around m 110.00 2.50 275.00 2.50 275.00 550.00
C-II-08 Painting for Moulding Decoration Around m2 110.00 2.50 275.00 2.50 275.00 550.00
C-II-09 External Column and Wall Groving Ls 1.00 - - 5,000.00 5,000.00 5,000.00
C-II-10 Interior Painting Work m2 2,016.00 2.50 5,040.00 2.00 4,032.00 9,072.00
C-II-11 Exterior Painting Work m2 784.70 2.50 1,961.75 2.50 1,961.75 3,923.50
C-II-12 Floor Tile (60x60)mm m2 989.00 12.00 11,868.00 4.50 4,450.50 16,318.50
C-II-13 Bathroom Floor Tile m2 58.00 15.00 870.00 5.00 290.00 1,160.00
C-II-14 Waterproof for Bathroom m2 58.00 3.50 203.00 1.50 87.00 290.00
C-II-15 Ceiling for Bathroom (Moisture Resistant) m2 58.00 9.50 551.00 5.00 290.00 841.00
C-II-16 Natural Granite for Stair m2 68.00 30.00 2,040.00 15.00 1,020.00 3,060.00
C-II-17 Ceiling m2 989.00 7.50 7,417.50 2.50 2,472.50 9,890.00
C-II-18 Glass Window m2 261.00 70.00 18,270.00 10.00 2,610.00 20,880.00
C-II-19 Wooden Door 1500x2200mm Ls 11.00 330.00 3,630.00 20.00 220.00 3,850.00
C-II-20 Glass Handrail m2 44.00 180.00 7,920.00 20.00 880.00 8,800.00
C-II-21 Wooden Door 1000x2200mm Ls 4.00 220.00 880.00 20.00 80.00 960.00
C-II-22 Partition for Toilet Ls 8.00 250.00 2,000.00 50.00 400.00 2,400.00
Sub Total- C-II 84,926.80 42,400.28 127,327.08
C-III 2ND & 3RD FLOOR
C-III-01 Column Plastering Work m2 459.00 1.50 688.50 3.25 1,491.75 2,180.25
C-III-02 Column Painting Work m2 459.00 2.50 1,147.50 2.00 918.00 2,065.50
C-III-03 Exterior Plastering Work m2 784.70 1.50 1,177.05 3.25 2,550.28 3,727.33
C-III-04 Interior Plastering Work m2 2,434.00 1.50 3,651.00 2.75 6,693.50 10,344.50
C-III-05 Brick Wall 10cm thk m2 56.00 6.00 336.00 3.75 210.00 546.00
C-III-06 Brick Wall 20cm thk m2 1,552.70 11.50 17,856.05 5.50 8,539.85 26,395.90
C-III-07 Moulding Decoration Around m 110.00 2.50 275.00 2.50 275.00 550.00
C-III-08 Painting for Moulding Decoration Around m2 110.00 2.50 275.00 2.50 275.00 550.00
C-III-09 External Column and Wall Groving Ls 1.00 - - 5,000.00 5,000.00 5,000.00
C-III-10 Interior Painting Work m2 2,434.00 2.50 6,085.00 2.00 4,868.00 10,953.00

5 of 14
Item Description of Work Unit Quantity Material Cost (USD) Labor.Cost (USD) Total Cost Actual Work Done (December) Actual Work Done (January)
Unit Rate $/m2
Unit Cost Total Unit Cost Total (USD) % (USD) % (USD)
C-III-11 Exterior Painting Work m2 784.70 2.50 1,961.75 2.50 1,961.75 3,923.50
C-III-12 Floor Tile (60x60)mm m2 1,147.00 12.00 13,764.00 4.50 5,161.50 18,925.50
C-III-13 Bathroom Floor Tile m2 58.00 15.00 870.00 5.00 290.00 1,160.00
C-III-14 Waterproof for Bathroom m2 58.00 3.50 203.00 1.50 87.00 290.00
C-III-15 Ceiling for Bathroom (Moisture Resistant) m2 58.00 9.50 551.00 5.00 290.00 841.00
C-III-16 Ceiling m2 1,147.00 7.50 8,602.50 2.50 2,867.50 11,470.00
C-III-17 Natural Granite for Stair m2 68.00 30.00 2,040.00 15.00 1,020.00 3,060.00
C-III-18 Glass Window m2 327.00 70.00 22,890.00 10.00 3,270.00 26,160.00
C-III-19 Wooden Door 1500x2200mm Ls 14.00 330.00 4,620.00 20.00 280.00 4,900.00
C-III-20 Wooden Door 1000x2200mm Ls 4.00 220.00 880.00 20.00 80.00 960.00
C-III-21 Glass Handrail m2 20.00 180.00 3,600.00 20.00 400.00 4,000.00
C-III-22 Partition for Toilet Ls 8.00 250.00 2,000.00 50.00 400.00 2,400.00
Sub Total- C-III 186,946.70 93,858.25 280,804.95
C-IV 4TH FLOOR
C-IV-01 Column Plastering Work m2 459.00 1.50 688.50 3.25 1,491.75 2,180.25
C-IV-02 Column Painting Work m2 459.00 2.50 1,147.50 2.00 918.00 2,065.50
C-IV-03 Exterior Plastering Work m2 650.00 1.50 975.00 3.25 2,112.50 3,087.50
C-IV-04 Interior Plastering Work m2 1,314.00 1.50 1,971.00 2.75 3,613.50 5,584.50
C-IV-05 Brick Wall 10cm thk m2 46.00 6.00 276.00 3.75 172.50 448.50
C-IV-06 Brick Wall 20cm thk m2 1,142.00 11.50 13,133.00 5.50 6,281.00 19,414.00
C-IV-07 Moulding Decoration Around m 110.00 2.50 275.00 2.50 275.00 550.00
C-IV-08 Painting for Moulding Decoration Around m2 110.00 2.50 275.00 2.50 275.00 550.00
C-IV-09 External Column and Wall Groving Ls 1.00 - - 5,000.00 5,000.00 5,000.00
C-IV-10 Interior Painting Work m2 1,314.00 2.50 3,285.00 2.00 2,628.00 5,913.00
C-IV-11 Exterior Painting Work m2 650.00 2.50 1,625.00 2.50 1,625.00 3,250.00
C-IV-12 Floor Tile (60x60)mm m2 1,149.00 12.00 13,788.00 4.50 5,170.50 18,958.50
C-IV-13 Bathroom Floor Tile m2 58.00 15.00 870.00 5.00 290.00 1,160.00
C-IV-14 Waterproof for Bathroom m2 58.00 3.50 203.00 1.50 87.00 290.00
C-IV-15 Natural Granite for Stair m2 68.00 30.00 2,040.00 15.00 1,020.00 3,060.00
C-IV-16 Ceiling for Bathroom (Moisture Resistant) m2 58.00 9.50 551.00 5.00 290.00 841.00
C-IV-17 Ceiling m2 1,149.00 7.50 8,617.50 2.50 2,872.50 11,490.00
C-IV-18 Glass Window m2 400.00 70.00 28,000.00 10.00 4,000.00 32,000.00
C-IV-19 Wooden Door 1500x2200mm Ls 9.00 330.00 2,970.00 20.00 180.00 3,150.00
C-IV-20 Wooden Door 1000x2200mm Ls 5.00 220.00 1,100.00 20.00 100.00 1,200.00
C-IV-21 Glass Handrail m2 20.00 180.00 3,600.00 20.00 400.00 4,000.00
C-IV-22 Partition for Toilet Ls 8.00 250.00 2,000.00 50.00 400.00 2,400.00
Sub Total- C-IV 87,390.50 39,202.25 126,592.75
C-V ROOF FLOOR
C-V-01 Waterproof for Rooftop m2 590.00 3.50 2,065.00 1.50 885.00 2,950.00
C-V-02 Moulding for Roof m3 79.72 200.00 15,944.00 100.00 7,972.00 23,916.00
C-V-03 Painting for Roof Moulding m2 335.00 2.50 837.50 2.50 837.50 1,675.00
C-V-04 Roof Tiles m2 2,000.00 18.00 36,000.00 7.00 14,000.00 50,000.00
C-V-05 Glass Window m2 195.50 70.00 13,685.00 10.00 1,955.00 15,640.00
C-V-06 Exterior Plastering Work m2 54.00 1.50 81.00 3.25 175.50 256.50

6 of 14
Item Description of Work Unit Quantity Material Cost (USD) Labor.Cost (USD) Total Cost Actual Work Done (December) Actual Work Done (January)
Unit Rate $/m2
Unit Cost Total Unit Cost Total (USD) % (USD) % (USD)
C-V-07 Interior Plastering Work m2 54.00 1.50 81.00 2.75 148.50 229.50
C-V-08 Brick Wall 20cm thk. m2 54.00 11.50 621.00 5.50 297.00 918.00
C-V-09 Exterior Painting Work m2 54.00 2.50 135.00 2.50 135.00 270.00
C-V-10 Interior Painting Work m2 54.00 2.50 135.00 2.00 108.00 243.00
Sub Total- C-V 69,584.50 26,513.50 96,098.00
D MAIN GATE
D-01 Column Decoration Ls 16.00 180.00 2,880.00 20.00 320.00 3,200.00
D-02 Glass Window m2 95.00 70.00 6,650.00 10.00 950.00 7,600.00
D-03 Glass Door 1000x2200mm Ls 2.00 280.00 560.00 80.00 160.00 720.00
D-04 Floor Tile m2 23.00 15.00 345.00 5.00 115.00 460.00
D-05 Roof Tiles m2 290.40 18.00 5,227.20 7.00 2,032.80 7,260.00
Sub Total- D 15,662.20 3,577.80 19,240.00
E LANDSCAPE
E-1 Hard Scape Ls 1.00 0.00 - 0.00 - - BY OWNER
E-2 Soft Scape Ls 1.00 0.00 - 0.00 - - BY OWNER
Sub Total- E - - -
F MEP WORKS
F-0 GENERAL REQUIREMENTS
F-0-1 Water and Electrical Consumption Cost Item 1.00 0.00 - 0.00 - - BY OWNER
F-1 ELECTRICAL WORKS

Lighting, Power, Sockets, Lightning, Earthing System,MDB, Power Cable for LV MV Cable is
F-1-1 Lot 1.00 72,397.56 72,397.56 12,776.04 12,776.04 85,173.60
System Only, Conduits Cable Tray, Fitting & Accessories Excluded

F-1-2 Transformer 1600KVA, MV & LV DB Lot 1.00 62,400.00 62,400.00 15,600.00 15,600.00 78,000.00
F-1-3 Generator 1600KVA Lot 1.00 68,000.00 68,000.00 17,000.00 17,000.00 85,000.00 OPTION
F-1-4 Fire Alarm & CCTV System Lot 1.00 61,015.04 61,015.04 10,767.36 10,767.36 71,782.40 OPTION
F-2 AC SYSTEM
Copper Pipe with Insulation, Drain Pipe, Power Cable, Cable Tray,
F-2-1 Lot 1.00 43,368.19 43,368.19 7,653.21 7,653.21 51,021.40
Conduite,Support, Fitting & Accessories
F-2-2 AC Split, Support & DB Lot 1.00 141,255.00 141,255.00 15,695.00 15,695.00 156,950.00 OPTION
F-3 PLUMBING SYSTEM
Outside Main
PPR, PVC Pipe, Water Storage Tank, Septic Tank, Transfer Pump, Rain Water
F-3-1 Lot 1.00 43,785.98 43,785.98 7,726.94 7,726.94 51,512.92 Drain System is
Pump & Booster Pump System
Excluded
F-3-2 Fire Fighting System Lot 1.00 112,592.52 112,592.52 19,869.27 19,869.27 132,461.78 OPTION
F-4 LIFT SYSTEM Lot 1.00 98,448.00 98,448.00 14,767.20 14,767.20 113,215.20 OPTION
Lift, Power cable & Cable Tray, Conduite,Support, Fitting & Accessories
CCVP-1 PRELIMINARIES Ls 1.00 8,000.00 109,000.00 $ 117,000.00 $ 6,300.00 6.67% $ 7,800.00 $ 17.22
CCVP-2 STRUCTURAL WORKS FOR BUILDING Ls 1.00 680,353.88 197,879.36 $ 878,233.24 23.11% $ 202,992.00 25.77% $ 226,313.93 $ 129.27
CCVP-3 ARCHITECTURAL WORKS FOR BUILDING Ls 1.00 530,284.70 249,081.58 $ 779,366.28 $ 114.71
CCVP-4 MEP WORKS FOR BUILDING Ls 1.00 221,951.73 43,756.19 $ 265,707.92 $ 39.11
CCVP-5 TOTAL COST OF BUILDING Ls 1.00 1,440,590.31 599,717.12 $ 2,040,307.43 10.26% $ 209,292.00 11.47% $ 234,113.93 $ 300.31
CCVP-6 PROFIT+WASTAGE 15% Ls 1.00 216,088.55 89,957.57 $ 306,046.11 10.26% $ 31,393.80 11.47% $ 35,117.09 $ 45.05
CCVP-7 GRAND TOTAL COST OF BUILDING Ls 1.00 1,656,678.85 689,674.69 $ 2,346,353.55 10.26% $ 240,685.80 11.47% $ 269,231.02 $ 345.36

7 of 14
COMPARISION of TOTAL ESTIMATED COST and WORK DONE COMPLETED COST
PROJECT: CAMBODIA CHINA POLYTECHNICH UNIVERSITY
by 24th January 2019

Estimated Cost and Actual Cost


N Description Total Amount Work Percentage (%)
I-0 Preliminaries $ 117,000.00 4.99%
I-0 Preliminaries Wastage and Profit $ 17,550.00 0.75%
I-1 Total: Structural Work for Building $ 878,233.24 37.43%
I-2 Structural Wastage and Profit $ 131,734.99 5.61%
II-1 Total: Architectural Work for Building $ 779,366.28 33.22%
II-2 Architectural Wastage and Profit $ 116,904.94 4.98%
III-1 Total: MEP Work for Building $ 265,707.92 11.32%
III-2 MEP Wastage and Profit $ 39,856.19 1.70%
Grand Total: $ 2,346,353.55 100.00%
Total Area : 6794.00 m2
1m2= $ 345.36

Actual Work
% of Completed by
N Description Evaluation Cost
January
I-0 Preliminaries $ 7,800.00
6.67%
I-0 Preliminaries Wastage and Profit $ 1,170.00
I-1 Total: Structural Work for Building $ 226,313.93
25.77%
I-2 Structural Wastage and Profit $ 33,947.09
II-1 Total: Architectural Work for Building
II-2 Architectural Wastage and Profit
III-1 Total: MEP Work for Building
III-2 MEP Wastage and Profit
GRAND TOTAL OF COMPLETED WORK 11.47% $ 269,231.02

Project Summary
% of Completed by Previous Month (December) % of Completed by This Month (January) % Increase

10.26% 11.47% 1.21%


III. MANPOWER RECORD
IV. MONTHLY WEATHER RECORD
MONTHLY WEATHER RECORD
PROJECT : Cambodia China Polytechnic University
CONTRACTOR : KPCC
MONTH : December 2018
WEATHER : Sunny Cloudy Rainy Heavy Rain

Sunday

1-Dec-18 2-Dec-18 3-Dec-18 4-Dec-18 5-Dec-18 6-Dec-18

Sunday Sunday

7-Dec-18 8-Dec-18 9-Dec-18 10-Dec-18 11-Dec-18 12-Dec-18

Sunday

13-Dec-18 14-Dec-18 15-Dec-18 16-Dec-18 17-Dec-18 18-Dec-18

Sunday

19-Dec-18 20-Dec-18 21-Dec-18 22-Dec-18 23-Dec-18 24-Dec-18

Sunday

25-Dec-18 26-Dec-18 27-Dec-18 28-Dec-18 29-Dec-18 30-Dec-18

Weather record Total Rain Hours: (None) Inspected by :


12
31-Dec-18

………………………..
9 15 Name : Chhem Sophea
Date : 24, December 2018
Position: Independent Inspector

18
MONTHLY WEATHER RECORD
PROJECT : Cambodia China Polytechnic University
CONTRACTOR : KPCC
MONTH : January 2019
WEATHER : Sunny Cloudy Rainy Heavy Rain

Sunday

1-Jan-19 2-Jan-19 3-Jan-19 4-Jan-19 5-Jan-19 6-Jan-19

Sunday

7-Jan-19 8-Jan-19 9-Jan-19 10-Jan-19 11-Jan-19 12-Jan-19

Sunday

13-Jan-19 14-Jan-19 15-Jan-19 16-Jan-19 17-Jan-19 18-Jan-19

Sunday

19-Jan-19 20-Jan-19 21-Jan-19 22-Jan-19 23-Jan-19 24-Jan-19

25-Jan-19 26-Jan-19 27-Jan-19 28-Jan-19 29-Jan-19 30-Jan-19

Weather record Total Rain Hours: _ Inspected by :


12
31-Jan-19

………………………..
9 15 Name :: Nhoek Ren
Date : 24, January 2019
Position: Independent Inspector

18
V. SITE PROGRESS PHOTOS REPORT
Site Progress Photos from 25th December to 24th January 2019
1 Soil excavation for pile cap work

25-Dec-18

2 Warehouse's wall enclosing

26-Dec-18

3 Pile's head cutting

27-Dec-18
4 Pile's head breaking

28-Dec-18

5 Pile's heads breaking

29-Dec-18

6 Preparation for lean concreting of pile cap

31-Dec-18
7 Installation of steel yard

1-Jan-19

8 Warehouse's wall enclosing

2-Jan-19

9 Leveling on bored pile for cut off level

3-Jan-19
10 Soil preparation and lean concreting for site office and parking lot

4-Jan-19

11 Pile's head cutting

5-Jan-19

12 Steel yard installation

7-Jan-19
13 Lean concreting for pile cap

8-Jan-19

14 PIT test for bored piles

9-Jan-19

15 Rebar pre-arrangement for pile cap

10-Jan-19
16 Warehouse's shelf installation

11-Jan-19

17 Pile's head preparation for PDA test

12-Jan-19

18 Pile cap rebar installation

14-Jan-19
19 Pile cap rebar and starter bar for column installation

15-Jan-19

20 Rebar pre-arrangement & formwork enclosing for pile cap

16-Jan-19

21 Pile cap concrete casting

17-Jan-19
22 Pile cap concrete casting

18-Jan-19

23 Pile cap concrete casting

19-Jan-19

24 Formwork preparation for pile cap

21-Jan-19
25 Pile cap concrete casting

22-Jan-19

26 Pile's head breaking

23-Jan-19

27 Rebar pre-arrangement & formwork enclosing for pile cap

24-Jan-19
VI. SUMMARY OF MONTHLY CPM RECORD
MONTHLY INSPECTION RECORD
STRUCTURE WORK
PILING WORK INSPECTION
INSPECTION
No PILE CODE DESCRIPTION STATUS
DATE
1 P12E 23-Oct-18 No inspection form submission Disapproved

2 P10F 27-Oct-18 No inspection form submission Disapproved

3 P6BF 30-Oct-18 No inspection form submission Disapproved


Approved with
4 P5BE 01-Nov-18 Error depth
comment
Approved with
5 P9D 01-Nov-18 Bored pile concrete casting
comment
Approved with
6 P9F 02-Nov-18 Bored pile concrete casting
comment
Approved with
7 P6DF 02-Nov-18 Bored pile concrete casting
comment
Approved with
8 P5F 03-Nov-18 Bored pile concrete casting
comment
Approved with
9 P11B 04-Nov-18 Bored pile concrete casting
comment
Approved with
10 P11E 05-Nov-18 Bored pile concrete casting
comment
11 P5D 05-Nov-18 Error depth Disapproved

12 P5A 06-Nov-18 Over time casting & removing tremie error Disapproved

13 P9A 07-Nov-18 Rebar cage broken after removing casing Disapproved


Approved with
14 P11A 08-Nov-18 Bored pile concrete casting
comment
Approved with
15 P4F 09-Nov-18 Bored pile concrete casting
comment
16 P8F 09-Nov-18 Casting concrete without site engineer Disapproved
Approved with
17 P10DA 10-Nov-18 Bored pile concrete casting
comment
Approved with
18 P2D 10-Nov-18 Bored pile concrete casting
comment
Approved with
19 P11D 11-Nov-18 Bored pile concrete casting
comment
Approved with
20 P2B 14-Nov-18 Bored pile concrete casting
comment
Approved with
21 P8D 15-Nov-18 Bored pile concrete casting
comment
Approved with
22 P3DA 16-Nov-18 Bored pile concrete casting
comment
Approved with
23 P10DB 17-Nov-18 Bored pile concrete casting
comment
Approved with
24 P2E 17-Nov-18 Bored pile concrete casting
comment
Approved with
25 P7DA 17-Nov-18 Bored pile concrete casting
comment
Approved with
26 P2A 18-Nov-18 Bored pile concrete casting
comment
Approved with
27 P3DB 18-Nov-18 Bored pile concrete casting
comment
Approved with
28 P7DB 19-Nov-18 Bored pile concrete casting
comment
Approved with
29 P4A 26-Nov-18 Bored pile concrete casting
comment
Approved with
30 P4D 27-Nov-18 Bored pile concrete casting
comment
31 P6DA 27-Nov-18 Concrete mixture contain foreign material Disapproved
Approved with
32 P8A 28-Nov-18 Bored pile concrete casting
comment
Approved with
33 P6AF 29-Nov-18 Bored pile concrete casting
comment
Approved with
34 P8B 29-Nov-18 Bored pile concrete casting
comment
35 P5B 29-Nov-18 Error depth Disapproved
Approved with
36 P10A 30-Nov-18 Bored pile concrete casting
comment
Approved with
37 P12B 30-Nov-18 Bored pile concrete casting
comment
Approved with
38 P10B 30-Nov-18 Bored pile concrete casting
comment
Approved with
39 P9B 01-Dec-18 Bored pile concrete casting
comment
Approved with
40 P6DB 01-Dec-18 Bored pile concrete casting
comment
Approved with
41 P4B 01-Dec-18 Bored pile concrete casting
comment
Approved with
42 P6CF 01-Dec-18 Bored pile concrete casting
comment
Approved with
43 P7A 02-Dec-18 Bored pile concrete casting
comment
Approved with
44 PR4 02-Dec-18 Bored pile concrete casting
comment
Approved with
45 P6F 03-Dec-18 Bored pile concrete casting
comment
Approved with
46 P7B 03-Dec-18 Bored pile concrete casting
comment
Approved with
47 P6B 03-Dec-18 Bored pile concrete casting
comment
Approved with
48 P7F 04-Dec-18 Bored pile concrete casting
comment
Approved with
49 P6A 04-Dec-18 Bored pile concrete casting
comment
Approved with
50 PZ3 05-Dec-18 Bored pile concrete casting
comment
Approved with
51 PR3 05-Dec-18 Bored pile concrete casting
comment
Approved with
52 PZ4 05-Dec-18 Bored pile concrete casting
comment
Approved with
53 P11F 06-Dec-18 Bored pile concrete casting
comment
54 P8BE 06-Dec-18 Additional water in concrete Disapproved

55 P3F 06-Dec-18 Concrete mixture contain foreign material Disapproved


Approved with
56 P5AE 07-Dec-18 Bored pile concrete casting
comment
Casting concrete new pile next to old one
57 P5CE 07-Dec-18 Disapproved
before it setting time
58 P8DE 07-Dec-18 Concrete mixture contain dried block Disapproved
Approved with
59 PR8 09-Dec-18 Bored pile concrete casting
comment
Approved with
60 P8AE 10-Dec-18 Cleaning bored hole's base
comment
Cleaning bored hole's base; 35.5m change Approved with
61 PR7 10-Dec-18
36.3m comment
Casting concrete new pile next to old one
62 P5DE 10-Dec-18 Disapproved
before it setting time
Approved with
63 PZ2 10-Dec-18 Bored pile concrete casting
comment
Concrete mixture contain foreign material &
64 P8CE 11-Dec-18 Disapproved
concrete contain dried block
65 PR1 12-Dec-18 Concrete mixture contain dried block Disapproved
Approved with
66 P2F 12-Dec-18 Bored pile concrete casting
comment
Approved with
67 PR5 13-Dec-18 Bored pile concrete casting
comment
Approved with
68 PR2 13-Dec-18 Bored pile concrete casting
comment
Approved with
69 P3A 13-Dec-18 Bored pile concrete casting
comment
70 P1B 14-Dec-18 Concrete mixture contain foreign material Disapproved
Approved with
71 P1E 14-Dec-18 Bored pile concrete casting
comment
Approved with
72 P3B 15-Dec-18 Bored pile concrete casting
comment
Casting concrete finished later than setting
73 PR6 15-Dec-18 Disapproved
time
Approved with
74 PZ1 15-Dec-18 Bored pile concrete casting
comment

Noted: P2F/ Status "Disapproved" is changed to "Approved with Comment"


"P6BF" cast concrete on 03-Dec-18 is changed to "P6B"
MONTHLY INSPECTION RECORD
STRUCTURE WORK
Request for Inspection (RFI)
INSPECTION
No RFI Code DESCRIPTION STATUS
DATE
1 N/A 17-Jan-19 No RFI submission
Casting 3 pile caps (forgot starter bar of BF
2 RFI-001 22-Jan-19 Replied
wall)
3

Reinforcing Steel Inspection (RSI)


INSPECTION
No RSI Code DESCRIPTION STATUS
DATE
Casting 12 pile caps at 1:25 - 4:30 without
1 N/A 17-Jan-19 Disapproved
request for inspection and no site engineer
Casting 3 pile caps (forgot starter bar of BF Approved with
2 RSI-001 22-Jan-19
wall) comment
3

Concrete Work Inspection (CWI)


INSPECTION
No CWI Code DESCRIPTION STATUS
DATE
Casting 12 pile caps at 1:25 - 4:30 without
1 N/A 17-Jan-19 Disapproved
request for inspection and no site engineer
Casting 3 pile caps (forgot starter bar of BF Approved with
2 CWI-001 22-Jan-19
wall) comment
3

5
VII. ZONING & SCHEDULE PLAN
1. STRUCTUAL WORK
2. ARCHITECTURAL WORK
Mega Asset Management Co., Ltd.
Canadia Tower, 10F, No.315, Ang Duong Street
(corner of Monivong Blvd), Phnom Penh, Cambodia

1. STRUCTURAL WORK
1.1. Piling Work

Block Name Progress rate (%)

Main Building 100%

TOTAL

1.2. Pile Cap Work

Block Name Progress rate (%)

Main Building 26.99%

TOTAL

LEGEND: Task completed Task on progress Task pending


Mega Asset Management Co., Ltd.
Canadia Tower, 10F, No.315, Ang Duong Street
(corner of Monivong Blvd), Phnom Penh, Cambodia

1.3. Basement Floor Work


1.4. Ground Floor Work
1.5. Mezzanine Floor Work
1.6. 2nd Floor Work
1.7. 3rd Floor Work
1.8. 4th Floor Work
1.9. 5th Floor work
1.10. Roof Floor Work

LEGEND: Task completed Task on progress Task pending


Mega Asset Management Co., Ltd.
Canadia Tower, 10F, No.315, Ang Duong Street
(corner of Monivong Blvd), Phnom Penh, Cambodia

ARCHITECTURAL WORK
1.11. Basement Floor Work

1.12. Ground Floor Work


1.13. Mezzanine Floor Work
1.14. 2nd Floor Work
1.15. 3rd Floor Work
1.16. 4th Floor Work
1.17. 5th Floor work

LEGEND: Task completed Task on progress Task pending

Вам также может понравиться