Data:
Water
Ratio=¿ 0.40×2000=800
Cement
Calculation:
Discussion:
When recording the time for the concrete, the result was much less than what was expected.
The consistency of the mix was clearly seen to be lower than that predicted. This might be
due to having excess water added in the beginning of the mix. Although the workability of
concrete changes with time due to the hydration of the cement and also may be due to loss of
moisture. Tests should have been carried out on different samples at a constant time interval
if comparable results were required.
Conclusion:
This variation in the workability between the first 2 tests and the last one (VEBE
test) can be a result to losing the workability with time, the time between making
the mix and doing the VEBE time test was larger than it to the other two tests.
Other reason for that might be an error resulted from the determination of the
end of the test.