Академический Документы
Профессиональный Документы
Культура Документы
2/3-1 The processes in project management have been classified into knowledge areas and
_______________.
a) Methods
b) Process Groups
c) Categories
d) Best practices
2/3-2 The application of knowledge, skills, tools and techniques to project activities to meet the
project requirements is referred to as:
a) Project initiation
b) Project coordination
c) Project administration
d) Project management
a) Organizational culture
b) Political climate
c) Performance measurement criteria
d) Existing facilities and infrastructure
2/3-4 The person or organization that provides the funding or financial resources for the project is
referred to as the:
a) Customer
b) Sponsor
c) Steering committee
d) Project Management Office
2/3-7 Which of the following statements about the project life cycle is false?
a) Cost and staffing are at the highest levels during the start of the project
b) Risk is at the highest level of uncertainty at the start of the project
c) The control needs of the organization will determine how many phases will be included in the
project life cycle
d) Project phases are typically completed sequentially but can be overlapped to accelerate
completion of a project
2/3-8 You are defining the project in more detail and moving through the phases of the project. You
are engaged in:
a) Progressive elaboration
b) Project selection
c) Monitoring and Controlling
d) Decomposition
a) Unique undertaking
b) A temporary endeavor with specific starting and ending dates
c) Ongoing and continually supporting organizational operations
d) Completed when all objectives are achieved or terminated when the project objectives are no
longer viable
2/3-10 Your company is introducing a new product to be available in the first quarter of the next
business cycle. The product will support an existing product as an add-on optional feature.
Which of the following is true?
a) This is an ongoing operation because the previous product is already in use by customers
b) This is a project because it involves a new product that has not been previously developed
c) This is an operation because it adds a feature that will be part of an ongoing sales effort
d) This is a program that supports the operations of the company
a) All employees are grouped by expertise and assigned to one clear manager
b) Communication between the elements of each functional group is fast and efficient
c) Project work is considered to be priority work in all functional groups
d) Resources are easily shared across functional groups
2/3-13 You have been assigned as project manager in a balanced matrix organizational structure. This
presents a challenge to you in obtaining and assigning project resources because:
a) Stakeholder identification
b) Business case development and review
c) A contract or statement of work
d) Project scope statement
2/3-15 Which of the following process groups is specifically targeted to complete the project work and
to satisfy project requirements?
2/3-16 The project manager should communicate the need for a change control process mainly
because:
a) Project execution
b) Inputs, Tools and Techniques, Outputs
c) Project Integration Management
d) Project Monitoring and Control
4-2 The document that assigns a project manager and officially authorizes a project to use
organizational resources for the purpose of planning, executing, and controlling a project is
the:
a) Project Charter
b) Project Plan
c) Scope Statement
d) Work Authorization Form
4-3 A project manager schedules meetings for many different reasons. Status review meetings are
typically held:
4-5 A _________________ consists of the data sources and tools and techniques used to gather,
integrate, analyze, and disseminate the results of the combined outputs of the project
management processes.
4-6 Assumptions are factors used for planning purposes and may be communicated to a project
team by several different stakeholders. These factors, when stated, are generally considered to
be true, real, or certain and are:
a) Provide project inputs, tools and techniques, and outputs to be used on the project for the
purpose of managing the product of the project
b) Guide project execution, document project planning assumptions, and facilitate
communication among stakeholders
c) Provide general management, product quality, and project management information, which is
communicated to all stakeholders
d) Create organized policies using stakeholders’ skills and knowledge, which is then itemized and
catalogued in the corporate knowledge base
4-8 ______________ are usually included to support the overall project management plan and are
developed to provide more detailed information, guidelines, and control processes for
specifically defined project elements or planning components.
4-9 During the planning process, the project manager should be aware that assumptions generally
involve:
a) A degree of risk
b) Direction from the Sponsor
c) Financial controls
d) Detailed, factual information
4-10 _________________ are applicable restrictions that will affect project performance
a) Organizational policies
b) Performance guidelines
4-11 __________________ is a formal, approved document that includes the collection of outputs of
the planning process and is used to manage and control project execution.
4-12 Risk plans, quality plans, and change control plans are all ______________ to the project plan.
a) Constraints
b) Appendixes
c) Additions
d) Subsidiaries
4-13 _________________ is the primary process for carrying out the project plan.
a) Configuration management
b) Direct and Manage Project Work
c) Administrative management
d) Monitor and Control Project Work
4-14 As a project manager, you must ensure that changes are coordinated across the entire project
life cycle, from conception to completion. Which process focuses on this requirement?
4-15 A project is being executed and is progressing through its life cycle. You notice that a
significantly large percentage of project changes occurring on the project have been initiated
by the research department. What should you do?
4-16 You are managing an information technology project. A technical specialist on your team, after
having an informal meeting with a low-ranking customer representative working on the
project, determines that a simple alteration would be a great addition to the project. You and
the project sponsor have already signed off on the scope, and a change control process is in
place. The technical specialist installs the change with no negative effect to the project
schedule and at no additional cost. What management action should be taken?
a) The technical specialist should be recognized for exceeding customer expectations without
affecting project cost or schedule
b) The project manager should add a task to the project plan with no additional scheduled time
and note that there was no increased budget
c) The technical specialist should be informed that the actions were not authorized and were
inconsistent with the change management plan
d) The project manager should create a change control form and get the customer sign-off since
the change has already been made
4-17 Two months into a design project, the customer requested a modification to the product
specifications. The change was immediately implemented by the project team without
notifying the project manager. During the final testing phase, results were different from what
was planned. This scenario is an example of:
a) Project Charter
b) Project Scope Statement
c) Statement of Work
d) Project Plan
5-3 As a project manager, you should become familiar with the description of the product that will
be delivered to ensure that:
5-4 The process of planning in increments and adding detail as the plan is developed is known as:
a) Scope definition
b) Decomposition
c) Progressive elaboration
d) Rolling Wave Planning
5-6 You and your team are working together to divide the major deliverables of the project into
smaller components. You are involved in the process of:
a) Scope Planning
b) Decomposition
c) Initiation
d) Scope statement development
5-7 ________ process will help to improve the reliability of cost, duration, and resource estimates
is.
a) Define scope
5-8 The document that describes the objectives, project work, deliverables, and product of a
project in detail is the:
a) Scope statement
b) Project Charter
c) Work breakdown structure
d) Work breakdown structure dictionary
a) Product requirements
b) Project requirements
c) Project objectives
d) Scope statement
structure is a deliverable-oriented grouping of components, but the work package is the lowest
level deli
5-11 You receive a verbal change request from your client that will impact the agreed upon scope of
work. You should:
a) Accept the change, document the request, and then assign someone to oversee it
b) Advise the customer that changes to the scope are not acceptable
c) Review the change control process with the client
d) Accept the change only after ensuring you are not held accountable for additional work.
a) Re-planning
b) Feasibility analysis
c) Scope creep
d) Performance measurement
a) Formal acceptance
b) Inspection
c) Additional planning
d) Internal failure
5-15 _____________ aids in creating a more detailed definition of the scope of the project and can
be used to validate the work of the project.
a) Scope baseline
b) Work breakdown structure
c) Project charter
d) Alternatives identification
a) Project Scope statement, work breakdown structure, and work breakdown structure
Dictionary
b) Approved project scope statement and charter
c) Approved project scope, schedule, and budget
d) Validated measurements and approved changes
5-19 A stakeholder wants to make a change to the work breakdown structure that does not affect
the time or cost of the project. What is the BEST thing to do?
a) Tell the stakeholder that the change cannot be made without revising the project plan
b) Make the change since it does not affect the schedule or the project budget
c) Meet with management to discuss the change control processes
d) Have a change request initiated and look for other impacts on the project
6-2 Which of the following is NOT an input to the “define activities” process?
a) Scope baseline
b) Organizational process assets
c) Enterprise environmental factors
d) Decomposition
6-3 The software cannot be tested until coding is completed. This is an example of:
a) Discretionary dependency
b) Soft logic
c) Preferential logic
d) Mandatory dependency
6-4 You have been asked to reduce the schedule duration of a major project. Your team suggests
overlapping several project activities to reduce the overall duration. This process is known as:
a) Crashing
b) Fast tracking
c) Leveling
d) Monte Carlo technique
6-5 A functional manager for the engineering team has provided you with this information: A work
package for engineering activities will most likely require 12 weeks to complete. If everything
goes well, it could take 8 weeks, but there have been times when this work has taken 24 weeks
to be completed. Based on this information, what is the expected duration of the work
package?
a) 13.33
b) 14.27
c) 44
d) 12
6-6 A work package is behind schedule. You decide to add more resources to the activities and use
overtime to correct the schedule slippage. This is an example of the technique known as:
a) Resource leveling
b) Heuristics
c) Crashing
d) CPM
6-7 The start of an activity must be delayed until 5 days after the finish of its preceding activity.
The correct term for this modification of the logical relationship is:
a) Lead
b) Lag
c) Slack
d) Float
6-8 The most common type of relationship in the precedence diagramming method (PDM) is the:
a) Start to Finish
b) Finish to Finish
c) Finish to Start
d) Start to Start
6-9 Which of the following is not a tool or technique in the Control Schedule process?
a) Schedule compression
b) Performance review
c) Resource optimization technique
d) Change request
6-10 The technique used to modify the project schedule to account for limited resources or to
develop a “resource-limited” schedule is known as:
a) Finish to Start
b) Start to Finish
c) Start to Start
d) Finish to Finish
6-12 You are in the process of calculating the early and late start and finish dates for your project
activities. This form of mathematical analysis is known as:
6-13 Your sponsor has informed you that a major project activity must be scheduled to start no
earlier than June 1. This is an example of:
a) A major milestone
b) A lag
c) A constraint
d) An activity duration estimate
6-14 Your project sponsor contacts you and asks you to provide an estimate of the total duration of
a newly approved project. He wants the estimate to be available for a meeting with project
stakeholders that has been scheduled for later in the afternoon. The most appropriate
estimating technique to meet this need would be:
a) A bottom-up estimate
b) A definitive estimate
c) A PERT estimate
d) An analogous estimate
a) Mandatory dependency
b) External dependency
c) Internal dependency
d) Discretionary dependency
6-17 Which of the following is not a tool and technique of the “Define Activities” process?
a) Decomposition
b) Rolling wave planning
c) Scope baseline
d) Expert judgment
6-18 You have been asked to develop a schematic display of the logical relationships of your
project’s activities. The result of your efforts is the:
a) 12
b) 13
c) 14
d) 15
a) ABCDEH
b) ACDEGH
c) ABDEGH
d) ABDEFH
a) 9
b) 10
c) 13
d) 15
6-22 Typically, during the project planning process, a detailed project network schedule can be
created after:
6-23 Generally, projects are planned by developing phases that are performed sequentially. In some
cases, it is necessary to accelerate the project life cycle by overlapping project phases. Which of
the following best describes this technique?
a) The technique of overlapping requires the elimination of minor project activities, which results
in higher quality
b) Overlapping project phases will compress the schedule but will not generally have an effect on
project risk
c) This technique is known as fast tracking and the risk level should be acceptable before it is
implemented
d) This technique is known as crashing and can increase the cost of the project but will not affect
project risk
7-1 Which of the following is NOT an input to the Determine Budget process?
a) Scope Baseline
b) Project Schedule
c) Activity cost estimates
d) Human Resource Plan
7-2 Your project’s earned value (EV) = 350, its actual cost (AC) = 400, and its planned value (PV) =
325. What is the cost variance (CV)?
a) +350
b) -75
c) +400
d) -50
7-3 Measuring the square footage of a building and then multiplying that figure by a set cost factor
for construction is an example of:
a) Analogous estimating
b) Parametric estimating
c) SWAG
d) Bottom-up estimating
7-4 Your team is in the process of finalizing and producing the cost baseline for the project you are
working on. Your team is involved in:
a) Cost Estimating
b) Determining Budget
c) Resource leveling
d) Bottom-up estimating
7-5 You are involved in the process of developing an assessment of the likely quantitative amount
of funding that will be required to complete the project. You are involved in:
a) Pricing/Costing
b) Alternatives analysis
c) Estimating costs
d) Risk assessment
a) Materials
b) Subcontractor expenses
c) Employee benefits
d) Project manager salary
7-7 Your project’s actual cost has been reported at $200.000. This is equal to the Earned Value. The
Budget at completion for your project is $400.000. It is assumed that all future work will be
accomplished at the budgeted rate. The EAC (Estimate At Completion) is:
a) $200,000
b) $600,000
c) $400,000
d) Cannot be determined with the information provided
7-8 You are requested to produce the estimated cost of the project as closely and as accurately as
possible. Which of the following techniques would you use?
a) Bottom-up estimating
b) Order of Magnitude
c) Parametric
d) Analogous
7-9 Doubling the number of resources will not necessarily halve the time taken on a project. This is
an example of:
a) Marginal analysis
b) Pareto rule
c) Parkinson's law
d) Law of diminishing returns
a) Project schedule
b) Cost control plan
c) Time-phased budget
d) Estimate At Completion
7-12 Earned value management is a tool and technique that can be used in:
7-13 You are reviewing an earned value report and observe that the CPI is 1.2 and the SPI is 1. You
will report to your sponsor that the project is:
7-14 Your earned value analysis report is due. Project information indicates the following: EV =
150,000, PV = 140,000, AC = 160,000. You will report to your project sponsor that the project is:
7-15 As projects progress through their lifecycles, a graph of project cost expenditures will follow a
characteristic “S” shape. Typically, the information provided in this type of graph indicates
that:
7-16 If the cumulative CPI falls below the baseline plan, all future work must be performed at:
7-17 The average cost of a 6-year project is estimated to be $6 million per year and the estimated
total profit is expected to be $12 million. The annual ROI for this project is:
a) 33%
b) 0%
c) 50%
d) 25%
7-18 Generally, Earned Value Management is a technique used for measuring variance on:
a) Inaccurate
b) Imprecise
c) Low grade
d) Non-conforming
8-2 Quality planning involves documenting how the project will demonstrate compliance in
meeting requirements. It should be performed:
8-3 To ensure that a product has been properly prepared for safe use, which of the following
should be used by the inspector operating the product?
a) Checklist
b) Quality control plan
c) Cause and effect process
d) Work breakdown structure
8-4 Your team is analyzing defects and attempting to isolate the root cause of a problem. Two
variables have been isolated through analysis of the data that is available. There is a concern
that one of the two variables is compounding the problem by causing an effect on the other.
Which of the following tools or techniques will assist in identifying the relationship between
variables?
a) Flow chart
b) Pareto diagram
c) Scatter diagram
d) Run chart
8-5 According to technical characteristics, a classification for items that have the same functional
use is:
a) Grade
b) Quality
c) Accuracy
8-6 Which of the following is not a tool and technique used in Control Quality?
a) Pareto diagram
b) Quality metrics
c) Control charts
d) Scatter diagram
8-7 You are managing a project and have discovered during a walkthrough inspection that a large
amount of scrap material has been generated by a team of newly hired workers. The scrap
material is an example of:
a) Internal failure
b) External failure
c) Cost of conformance
d) Appraisal costs
8-8 You have been asked to identify the primary reasons for the high percentage of product
returns your company is experiencing. Which of the following tools will most effectively assist
you in further identifying the reasons for the failures?
a) Pareto chart
b) Fishbone or Ishikawa diagram
c) Scatter Diagram
d) Attribute sampling
8-9 The total cost of all efforts, including prevention, appraisal, and defect repair, to achieve
product or service quality is known as:
a) Quality Plan
b) Cost of quality
c) Cost baseline
d) Total Quality Management
8-10 A project team is inspecting specific outputs based on defined criteria and rejecting the
defective outputs. Which process group is the team working on?
a) Execution
b) Planning
c) Monitoring and Controlling
d) Closing
a) Statistical sampling
b) Brainstorming
c) Nominal group technique
d) Design of experiments
8-12 You have developed a graphical display of process results gathered over time and have used
the information to determine that the process is not performing within expected parameters.
You have identified eight consecutive data points that are above the process average. This is an
indication of ________________.
a) A trend
b) Process out of control
c) A random cause
d) An alpha risk
8-13 Inspections are utilized by the project manager to assess the quality of deliverables produced
during the project life cycle. The costs incurred during the inspection process are associated
with:
a) Prevention cost
b) Cost of non-conformance
c) Cost benefit analysis
d) Appraisal costs
8-14 The process of monitoring specific project results to determine if they comply with relevant
quality standards is referred to as:
a) Quality control
b) Quality assurance
c) Quality planning
d) Earned Value Management
8-15 Fitness for use and the legal aspects of quality are key items emphasized by:
a) Crosby
b) Juran
c) Kerzner
d) Heerkens
a) Pareto diagram
b) Run chart
c) Control chart
d) Scatter diagram
8-17 You are performing root cause analysis to figure out the reason behind a problem that was
discovered during testing. Which process are you performing?
8-18 Which of the following is NOT a tool and technique in the Control Quality process?
8-19 As the project manager for a product, you contract with a subject matter expert to determine if
the project activities comply with organizational and project policies and procedures. The SME
is specifically interested in identifying gaps and shortcomings in your processes. You have
initiated:
8-20 Comparing actual or planned project practices to those of other projects to generate ideas for
improvement is known as:
a) Benchmarking
b) Benefit/cost analysis
c) Flowcharting
a) Matrix
b) Strong Matrix
c) Projectized
d) Functional
9-3 Project managers must develop skills to ensure that work is completed and deliverables are
produced. This means developing an understanding of formal and informal structures of all
organizations involved in the project, plus an understanding of power and politics.
Understanding all of these elements will assist in improving the project manager’s:
9-4 A project manager realizes that more IT system administrators are urgently needed to manage
the IT systems on a project. Who is responsible for providing these resources?
9-5 In the balanced organization matrix, the project manager generally shares authority with or
has relatively the same authority as the:
a) Sponsor
b) Customer
c) Functional manager
d) Executive staff
a) Projectized
b) Strong matrix
c) Weak matrix
d) Balanced matrix
9-7 You have just completed negotiations to acquire additional resources for your project. During
the negotiations, there was considerable conflict about which resources would be provided by
the functional group. A solution was reached in which you were able to obtain most of the
resources you needed, but you had to agree to give up some of those resources at an earlier
date than you had planned. This conflict was resolved using which type of conflict handling?
a) Forcing
b) Collaboration
c) Compromise
d) Smoothing
9-8 You have just joined an informal group of people who meet to discuss new trends and issues in
project management. The satisfaction that you gain from associating with that group is most
closely aligned with:
9-9 Which tool is used to specify the roles played by the team members on various activities of a
project?
9-10 The project manager is likely to be most successful in developing a strong and supportive high-
performing team in _______ structure.
a) Projectized
b) Strong matrix
c) Balanced matrix
d) Functional
a) Assumption
b) Constraint
c) Pre-determined project team selection
d) Expected staff assignment
9-12 You have decided that your best approach to keep your team working effectively is to monitor
team members’ performance very closely and to carefully analyze their work output. This style
of management is referred to as:
a) Theory Y
b) Hygienic motivation
c) Theory Z
d) Theory X
9-13 Which of the following is NOT a tool and technique for team development?
9-14 According to the Tuckman Ladder, the greatest level of conflict in team building is most likely
to appear in the____________ phase.
a) Forming
b) Adjourning
c) Mourning
d) Storming
9-15 You are reviewing previous work experience, personal interests, and personal characteristics of
a potentially available group of people and preparing to negotiate for the resources you need.
You are engaged in the process of:
a) Organizational Planning
b) Acquiring Project Team
c) Team development
d) Pre-assignment
a) Strong Matrix
b) Projectized
c) Functional
d) Departmentalized
9-17 The project manager and the functional manager cannot reach agreement about the
assignment of resources for a project. The functional manager insists that the resources are not
available due to other priorities. In this case, the conflict will require the assistance of
the___________ to reach a solution.
a) Customer
b) Project Sponsor
c) A new project manager
d) Contractor
9-18 The motivational theory in which the manager thinks he/she needs to watch the employees
every minute is called:
a) Theory X
b) Theory Y
c) Theory Z
d) Hygiene Theory
9-19 The project manager of a project remains distant from his team and often places one of his
team members in charge for days at a time. This style of management is generally considered
to be:
a) Motivational
b) Participatory
c) Laissez Faire
d) Conciliatory
9-20 A project manager relies on personal charisma and charm to get the project work done. What
form of authority is being used?
a) Coercive
b) Referent
c) Formal
d) Penalty
10-2 You have been asked to provide a report about the cost and schedule variances. The report
must also indicate forecast for actuals at the end of the project. Which report will help you to
get this information?
a) Progress report
b) Earned Value Analysis report
c) Jeopardy report
d) Status report
10-3 There are 15 people in a team. An addition of one person was made. How many
communication channels are present in the team now?
a) 16
b) 105
c) 120
d) 56
10-4 As a project manager for a new and highly complex project, when is it important for you to
develop your communications plan?
a) During execution
b) At the earliest stages of the project
c) Upon completion of the project plan
d) Evenly throughout each project phase
a) Servant Leader
b) Integrator
c) Single point of contact
d) Customer management
10-7 The collecting, storing, analysis, and distribution of project information is accomplished most
effectively using:
10-8 During project execution, the project manager is required to submit several reports that will
communicate information about the project. Which of the following describes the project
conditions at the present moment in relationship to schedule and other metrics?
a) Status report
b) Progress report
c) Project Forecast
d) Quality report
10-9 A project team has 10 members. An eleventh member has just been added. How many
communication channels does the team have?
a) 11
b) 55
c) 45
d) 355
a) 13
b) 45
c) 33
d) 78
10-12 In the communications model, the sender transmits information to the receiver.
Communication is most effective between sender and receiver when the _________ between
the sender and receiver overlaps.
a) Area of responsibility
b) Personality screen
c) Region of experience
d) Perception screen
10-13 Which of the following is NOT a best practice for project meetings?
10-14 In the communication process, which of the following is NOT included in the basic
communications model?
a) Noise
b) Medium
c) Urgency
d) Message
10-15 Which of the following is NOT an output of the Manage communications process?
a) Communication technology
b) Project communications
c) Project management plan updates
d) Project document updates
10-17 Which of the following is most closely linked to the Plan Communications Management
process?
a) Project Charter
b) Project Management Plan
c) Organizational Process Assets
d) Risk Register
a) Change requests
b) Project documents
c) Risk register
d) Organizational process assets updates
11-3 You are managing a project and have a major decision to make about a change in the plan. You
decide to contact several subject matter experts to obtain their opinions before making a
decision. Each expert is unaware of the participation of the other experts you have contacted.
The process being used is:
11-4 You have just completed an analysis of project risks and have prioritized them using a
probability and impact matrix. The approach you used to prioritize the risks is:
a) Qualitative analysis
b) Quantitative analysis
c) Sensitivity analysis
d) Earned value analysis
11-5 Defining _____________ will provide a structure for systematically identifying risks to a
consistent level of detail during the project planning process. The areas defined in this process
should reflect common sources of risk for the industry or application area.
a) Assumptions
b) Constraints
c) The product description
d) Risk categories
11-6 Which of the following is NOT a tool and technique of risk identification process?
a) Risk events
b) Risk triggers
c) Primary risks
d) Residual risks
a) System flows
b) Predecessor and successor tasks
c) Causes and effects
d) Casual influences and relationships between activities
11-9 Which of the following is NOT an enterprise environmental factor that can influence the
“Identify Risk process”?
a) Assumptions analysis
b) Risk attitudes
c) Industry studies
d) Commercial data bases
11-10 Your team is using a probability impact matrix. The scales on each axis of the matrix are labeled
Very High, High, Moderate, Low, and Very Low. Which process is your team performing?
a) A cardinal scale
b) An ordinal scale
c) SWOT analysis
d) Quantitative risk analysis
11-11 The two dimensions of risk used to determine expected value are:
11-12 Your team is using a model that translates the uncertainties specified at a detailed level into
their potential impact on project objectives at the level of the whole project. The technique
being used is:
11-13 You believe the project’s product design effort would be a major challenge to the team’s
abilities and you do not have the tools or material to manage it effectively. You decide to seek
a supplier who specializes in the specific technical area. You sign a fixed-price contract to
execute this piece of the project work. This is an example of:
a) Risk avoidance
b) Risk transfer
c) Risk mitigation
d) Risk acceptance
11-14 Your team has utilized all of the appropriate tools and techniques for responding to identified
project risks and has discovered that some risks have been reduced in impact but remain a
potential threat. These risks require further monitoring and are referred to as:
a) Secondary risks
b) Primary risks
c) Cumulative risks
d) Residual risks
11-15 Which of the following is NOT a tool and technique of the Monitor Risks process?
a) Reserve Analysis
b) Project risk audit
c) Technical performance measurement
d) Exploitation
a) Mitigation
b) Transfer
11-18 You are the project manager assigned to a critical project, which requires that you handle
project risk intentionally and methodically. You have assembled only the project team. They
have identified 32 potential project risks, determined what would trigger the risks, and rated
and ranked each risk using a risk rating matrix. You have also reviewed and verified all
documented assumptions from the project team and verified the sources of data used in the
process of identifying and rating the risks. You are continuing to move through the risk
management process. What have you forgotten to do?
11-19 A project manager is faced with a product design risk issue. It has been determined that a
critical component of the product may face significant corrosion as a result of exposure to the
typical work environment. The project team decides to modify the design of this component
using very expensive corrosion-resistant materials, which will basically eliminate the risk. The
technique used by the team is:
a) Risk avoidance
b) Risk acceptance
c) Risk transference
d) Risk deflection
11-20 Using the following information and a normal distribution curve, what is the probability that
the project will be completed in 64 days?
Optimistic time is 48 days. Pessimistic time is 72 days. Most likely time is 60 days
a) 16%
b) 84%
c) 50%
d) 100%
Answer: B – To Determine the probability of completing in 64 days, the following steps are required:
1. Determine the weighted average using the formula {Optimistic + 4(Most Likely) + Pessimistic}/6.
12-2 Which of the following is NOT a tool and technique of the Control Procurements process?
a) Performance reporting
b) Payment systems
c) Inspections and audits
d) Change requests
12-3 The ________ process ensures that each party meets their contractual obligations and that
their legal rights are protected.
a) Control procurements
b) Contract payment systems
c) Claims administration
d) Contract change control
12-4 Ending a contract before all contractual objectives have been reached due to a buyer’s decision
to change business direction is an example of:
a) Breach of contract
b) Contract close out
c) Termination for convenience
d) Letter of intent
12-5 As the buyer during the contract negotiation process, you are interested in a contract that
would have the least amount of risk to your organization. Which of the following contracts
would meet your risk-averse needs?
a) $56,000
b) $104,000
c) $30,000
d) $24,000
12-7 You are involved in finalizing contract negotiations. The definitive contract has not yet been
signed and may take an additional two weeks, but it is critical to start several work packages
within three days to avoid schedule problems later. You should utilize a:
12-9 Buyers may wish to review the qualifications of potential sellers before they actually meet with
them. This process is known as:
12-10 As the project manager for a new project, you have been given the responsibility to provide all
potential contractors with the information they need to determine if they would like to
continue with the contracting process. To accomplish this, you may want to schedule a:
a) Buyer
b) Seller
c) Project team
d) Functional managers
12-13 The seller is protected from liabilities and penalties when a project is impacted by a natural
disaster through the:
12-14 A high-level description of the scope issued by the buyer that specifies the work expected to be
completed by the seller is called:
a) Statements of work
b) Acceptance criteria
c) Considerations
d) Teaming agreements
12-15 The legal contractual relationship that exists between a buyer and a seller after the contract is
signed is known as:
a) Privity
b) Obligation
c) Bilateral agreement
d) Legally bonded relationship
12-16 In a cost reimbursable contract, the risk of cost escalation is borne by the:
a) $31,000
b) $19,000
c) $15,000
d) None of the above
12-18 Under which type of contract does the seller accept all liability for poor workmanship,
engineering errors, and consequential damages?
a) Incentive fee
b) Fixed price
c) Cost plus
d) Cost plus fixed fee
12-19 Contractual language does not preclude the possibility of misunderstandings and situations
that could adversely affect project progress. Therefore, it is considered a best practice to have
a ______ committee established as a means of removing the obstacles and managing conflicts.
a) Top management
b) Disputes resolution
c) Steering
d) Engagement
12-20 Which of the following contract types does not encourage the seller to control costs and places
the greatest risk on the buyer?
a) Cost exclusive
b) Cost Plus Fixed Fee
c) Cost Plus Incentive Fee
d) Cost Plus Percentage of Cost
a) Inform the stakeholder of the date when the change was approved
b) Review the communications plan with the stakeholder and explain his responsibility
c) Review the communications plan and make revisions if necessary
d) Address the situation in the next steering committee meeting so others do not miss publish
changes
Answer: C – In this case, the communications plan and the communications requirements analysis may
not have included all Key stakeholders. Informing the stakeholder of the date of the change does not
13-2 During stakeholder analysis, the project manager and team may use many different models to
classify stakeholders. The model that helps to analyze a stakeholder’s ability to impose his or
her power and influence the need for immediate attention from the project team, along with
the legitimacy of the stakeholder’s involvement, is the:
a) Power/interest grid
b) RAM
c) Salience model
d) Stakeholder register
a) Project Manager
b) Project Team
c) Everybody in the customer organization
d) Suppliers to the project
13-5 Which of the following should you be most concerned about during stakeholder analysis?
13-6 What is the best way to manage stakeholders who are low on power and interest?
a) Monitor them
b) Ignore them
c) Treat all stakeholders as equal
d) Keep them informed
13-7 Which of the following is a tool to assess the current and desired state of engagement of a
stakeholder on the project?
a) Stakeholder register
b) Stakeholder management plan
c) Stakeholder engagement assessment matrix
d) Stakeholder issue log
13-8 Which of the following is an input to the plan stakeholder management process?
a) Stakeholder register
b) Stakeholder management plan
c) Stakeholder engagement assessment matrix
d) Impact/Power grid
13-9 Which conflict resolution technique is most likely to result in a permanent resolution?
a) Compromise
b) Negotiation
c) Confrontation
d) Smoothing
n
13-10 Which of the following is NOT true about critical path activities?
13-11 An important stakeholder in a project is at an “unaware” state at present, i.e., he does not
know what is going on in the project. You know that his support could be very important.
Which of the following is the BEST way to get him to a “supportive” state?
13-12 Which of the following is a tool and technique used in manage stakeholder
engagements process?
13-14 One of the important inputs to the Control stakeholder engagements is:
a) Change request
b) Issue log
c) Information management system
d) Work performance information
13-15 During the execution of a construction project, excavation activities unearth some artifacts
that seem to have some archaeological importance. What should the project manager do?