PRODUCED BY
CCRCC NIG. LIMITED
SEPTEMBER, 2019
TABLE OF CONTENTS
1.0 Introduction..............................................................................................................................2
2|Page
1.0 INTRODUCTION
The new Abeokuta Dual Carriageway has been in use for over four decades, it was
constructed between 1975 and 1979. It runs through Ile – Zik (Ch. 0 + 000km to the border of
Lagos – Ogun State at Illo Awela Ch.16 + 500km). The Carriageway spans about 16.5km in
length, it is a segment under Federal road maintenance agency FERMA Lagos II West, in
Lagos State.
The population explosion and overflow of traffic from Lagos to Ogun State being the road
that links Nigeria through Ogun State to other West African Neighboring countries coupled
with numerous residential and industrial estates springing up around the area has put a great
strain on the carriageway. This has resulted in various degrees of dilapidation on the existing
pavement with level of deterioration ranging from including alligator cracks, corrugation,
rutting, fatigue distress, longitudinal cracking, striping of wearing course, stripping of
shoulders, numerous potholes, edge failures, poor drainage among others.
3|Page
2.0 CONSTRUCTION ORGANIZATION AND JOB DESCRIPTION
Project Manager:
Overall project policy and monitoring relations with consultant and clients team.
Conducting daily / weekly meetings with all staff / subcontractors to point out the
difficulties in work activities, requirement of resources, order/ direct material and
equipment at site with maximum efficiency, find solutions and taking immediate actions.
Review correspondence for proper action
Financial follow up and control the cost of project duration execution, follow up monthly
payment certificates, variation orders in co-ordination with Q.S/Planner
He will be directing the Senior Project Engineer, Architectural engineer, Planning
Engineer, Quality Control engineer, Quantity Surveyor and the Safety Officer.
Overall area activities directing, monitoring and controlling the productivity of all staff.
He will determine possible critical areas and activities have to be improved for the
successful completion of project in time
Find solutions and taking immediate action required to push the work in proper
coordination with project manager
He will be assisted by the site engineer, foreman, safety officer and services/finishing
works engineers
He will be directing the Subcontractors, Site Engineer, General foreman and Land
Surveyor and reporting to the Project Manager..
Civil Engineer
Work under the directives of the Project Engineer and will be responsible to carry out the
works as site directly, and to arrange laborers, materials, equipment, machine etc.
To supervise the work of subcontractors and arrange their responsibility.
To report for any material or other requirements well in time and report to the Project
Engineer in case of expected shortage.
To supervise the foremen and advise him to carry out the work according to drawings and
specification.
4|Page
Establish and follow up safety procedures all in accordance with the safety manual
prepared by him. He will be reporting to Project Manager, and will be coordinating with
the Senior Project Engineer to ensure safety control at site.
Review preparation of all submittals of subcontractors, supplier’s materials, samples to
provide continuous flow of procurements as per the requirement of Project program.
Supervise Quality control procedures and will follow up all types of submittals such as
Subcontractors, suppliers shop drawings, materials, etc.
1. Setting out
The right of way (R.O.W) shall be surveyed and set out before any site clearance is cleared
out. Embankment shall be constructed to the level, heights, widths and slopes shown on the
drawing.
Site clearing generally consists of the cutting and/or taking down, removal and disposal of
everything above ground level, including objects overhanging the area to be cleared such as
tree branches, except such trees, vegetation, structures or parts of structures and other things
which are designated in the contract to remain or be removed by others to which the engineer
directed to be left undisturbed. Excavate existing damaged pavement material including
subgrade, base course, binding course and wearing course to formation level using excavator
and grader and cart away to approved disposal area.
This work shall include the supply and installation of subsoil drains constructed in accordance
with the contract specification at the locations and in accordance with the lines, levels and
grades as shown on the drawings and or as directed by the Engineer. Box culverts and line
drains shall be constructed before the commencement of the construction of the sub base.
5|Page
i. Spreading, levelling and compaction sub base
The sub base layer made of crushed rock shall be placed over a well compacted subgrade and
shall be compacted to a thickness of about 200mm.
6|Page
procedures will be followed are in general conformance with those recommended in BS
1377 and ASTM. The laboratory tests will be performed included the following: -
Primary tests for subgrade soils and aggregates such as Atterberg Limits, grainsize analysis,
specific gravity and water absorption.
Strength tests for soils and aggregates including compaction tests, soaked CBR test and
abrasion test. For aggregates shape and texture flakiness and elongation tests will performed.
For bitumen, penetration, ductility, viscosity, specific gravity, etc. will be carried out.
Prime importance shall be given to safety of personnel and the public. It shall be ensured
that the personnel involved are conversant with the Company’s Safety regulations and there
shall be confirmation of the maintenance status of all machineries. Further to above, the
following key points shall be considered important.
a. Safety induction and regular training will be provided to machine operators and assistants.
b. Mechanical check and services shall be carried out on all equipment to maintain good
optimum working condition.
d. Road safety signs/diversion signs shall be installed where applicable for safe movement of
construction vehicles/equipment and public vehicles.
f. All major equipment shall be tested and certified prior to mobilization to site.
g. Services and utility company shall be engaged at preliminary stages of the project to help
in identifying underground services route. Where possible, such services shall be
relocated and shall be vividly marked and tagged where not to prevent damages to
services, machine and life.
h. When road closure is required, transport authority and public shall be informed ahead.
Training on usage of fire extinguishers and emergency action procedure shall be
provided to workers.
i. Site security shall be available to prevent intrusion by unauthorized members of the public.
7|Page
5.0 Major Items of Proposed Equipment for Carrying Out the Works
Item of Description, Make and Age (years) Condition and Number Owned,
equipment available leased, or
to be
purchased
Truck with
Crane SQ8SK3Q / 8 T Dongfeng 2015 Good 1 Owned
China
Trailer 40T Heavy Duty 2012 Good 2 Owned
Vehicle
Welding
Machine BX-500-1 Genertec 2012 Good 2 Owned
Generator 250KVA/135KVA WILSON 2015 Good 1 Owned
Level L-121c Geomteknik 2015 New 1 Owned
Fuel Tanker 5000L Dongfeng 2015 Good 1 Owned
Soil/Concrete/Asph
Laboratory alt/Bitumen USA 2014 Good 1set Owned
Laboratory
8|Page
Pick-UP
Hilux 4WD Toyota,Japan 2015 Good 2 Owned
Vechicle
Air XAVS786 / 24
Atlas 2015 Good 2 Owned
compressor M3/min
Water Tanker 5000L Dongfeng 2015 Good 2 Owned
9|Page