The document reports on the daily physical and financial performance of the Yabelo Bypass Road Construction Project in Ethiopia. It includes tables showing the project's progress against plans in terms of kilometers completed for different construction components and budgets spent against allocated funds. Overall, the report indicates that construction is ongoing but facing challenges including right-of-way issues, design review problems, and labor and equipment shortages.
The document reports on the daily physical and financial performance of the Yabelo Bypass Road Construction Project in Ethiopia. It includes tables showing the project's progress against plans in terms of kilometers completed for different construction components and budgets spent against allocated funds. Overall, the report indicates that construction is ongoing but facing challenges including right-of-way issues, design review problems, and labor and equipment shortages.
The document reports on the daily physical and financial performance of the Yabelo Bypass Road Construction Project in Ethiopia. It includes tables showing the project's progress against plans in terms of kilometers completed for different construction components and budgets spent against allocated funds. Overall, the report indicates that construction is ongoing but facing challenges including right-of-way issues, design review problems, and labor and equipment shortages.
Table 1: project Physical performance Project Name :Yabelo Bypass Road Construction Project Main contract Amount= 296,853,599.16 ETB Reporting date 27/11/2020 Length 7.44 km
Plan (km) Performance (km) Remark
S. No Main component Unit Weight(km)
Plan for the budget This date plan To this date Plan This date To this date Performance(km) year(km) (km) (km) performance (km)
Construction, repair & maintenance of temporary diversions and
1 km 0.02 0.014 - - - 0.00348 accommodating traffic 2 In situ treatment by ripping m3 0.01 0.011 - - - 0.00102 3 Road bed preparation m3 0.03 0.023 0.0010 0.06777 0.00017 0.01041 4 Cement- Mortared Stone Masonry Walls Class B ( Ditch) m3 0.98 0.938 0.0027 0.33186 0.00171 0.04174 Excavating material irrespective of classification of material and 5 m3 0.02 0.003 0.0003 0.03700 - 0.01705 depth ranges Cut and borrow to fill compacted in 200mm layers to 95% 6 m3 0.50 0.335 0.003 0.01055 0.00305 0.16801 AASHTO T-180 7 Cut to spoil irrespective of type of excavated material m3 0.02 0.024 - 0.00042 0.00246 0.03053 8 (a) Cast insitue Concrete lining (Class-C) m3 0.03 0.0274 - 0.00042 0.00305 0.00060 9 (i) 1.55x0.3x0.12 m concrete cover, Class 'A' Pedestrian crossing No 0.88 0.750 0.0031 0.00930 0.00008 0.00033 11 Dayworks birr 0.14 0.1399 - - - 0.00150 12 Clearing and Grubbing ha 0.01 0.0125 0.0004 0.00125 - 0.00861 13 Improved Sub grade m3 0.07 0.0671 - - - 0.00054 Excavation of materials regardless of classification of materials 14 m3 0.01 0.0066 - - - - and irrespective of depth Total
Table 2: Project Financial performance
Reporting date 27/11/2020 Project Name :Yabelo Bypass Road Construction Project
Plan (ETB) Performance ( ETB)
S. No Contract Amount Plan for this budget year Remark This date Performance to Plan for this date Plan to this date performance this date To this 1 616,709.20 565,316.77 - - 138,759.57 no need currently
Right off way problem,Design
2 430,440.00 430,440.00 - - 40,604.84 review problem
3 1,328,943.00 913,515.73 39,636.79 2,704,040.32 6,673.48 415,427.27 Right of way problem
Right off way problem,Design 4 39,103,713.50 37,438,103.43 107,400.00 13,241,255.87 68,378.00 1,665,610.07 review problem & Shortage of mason on the site 5 781,178.35 100,885.39 12762.10 1,476,442.78 680,292.96 Design review problem
Right off way problem,Design
6 20,082,870.00 13,379,220.42 134,816.33 421,112.29 121,526.29 6,703,649.58 review problem ,shortage of dump truck
Right of way problem & no
7 960,234.34 960,234.34 16,663.32 98,342.40 1,218,110.10 reccommendation Shortage of mason and laborer on the 8 1,286,428.71 1,093,464.41 16,663.32 23,755.76 site shortage of bar bender & OPC 9 35,227,500.00 29943375 123,750.00 371,250.00 3,300.00 13,200.00 cement 11 5,581,359.45 5,581,359.45 - - 60,000.00 no reccommendtaion 12 497,042.97 497,042.97 16,663.32 49,989.95 343,550.01 Right of way problem 13 2,677,714.20 2,677,714.20 - - 21,600.00 no reccommendtaion 14 261,357.84 261,357.84 - - - Design review problem 15 Total Contract 108,835,491.55 93,842,029.93 435,028.53 18,297,417.86 298,220.17 11,324,560.16 Amount Production & preparation Works Ø3/4 M3 Rock Productionfor Masonry 113.4M3 Ø3/8 M3 Borrow material Production=m3 Concerete Aggregate production fine m3 Rock material production for crusher Rock hauling for masonry 40M3 Stone hauling for crusher 250M3 Sub base Material Production 498.43M3