INSTALLATION INSTRUCTIONS

EL-G-E500 Encore Dispenser

SHEAR VALVE SUPPORT RAIL


(SEE SHEAR VALVE ARRANGEMENT BELOW)

CHANNEL SPRING NUT (4 PER RAIL)


MPK10-KIT (SUPPLIED SEPARATELY)

DISPENSER SIDE RAILS (x2)

SPREADER PLATE
(x2)
DISPENSER SUMP SUPPORT FRAME

ANCHOR BOLTS (x4)

CORBEL

CONCRETE TIE RODS x 6

SOLID BASE SUMP

FIBRELITE DOUBLE SIDED ENTRY BOOT


40FC SEALANT (x4)
(SUPPLIED SEPARATELY)

Shear Valve
Arrangement in
Plan
STANDARD
SHEAR VALVE
RAIL

WHERE 4 SHEAR VALVE


RAILS ARE USED IT WILL BE
NECESSARY TO USE 2 Nº
EL/G/500/SVR/C SHEAR VALVE
RAILS.
122
229 238 229

1-4 Issue: 12/06/2016


INSTALLATION INSTRUCTIONS
EL-G-E500 Encore Dispenser

1 2 Island Level

300 INSIDE

825 MAX.
525 INSIDE
Haunching
Permitted
Dispenser top has been supplied preassembled with
metalwork.

100
1300 x 1000
3
Dry fit the corbel on top of the sump to check level
300 and prepare a adequate support base.
NB:- Sump should be embedded into the support
base when installed.

255 4
581 Min.

281

Sump can be trimmed to reduce the height of the


system by up to 255mm , if 150mm holes will be
drilled for pipe entry kits.
If larger holes will be drilled please contact Fibrelite
for maximum trim point.

5 OUTSIDE INSIDE Mark trim point around the sump. Check position
of pipe entry sealkits before trimming with a circular
saw.
Refer to 5 and 6 for pipework positions with and
without trimming.

6
DETAIL OF DOUBLE SIDED ENTRY BOOT
OD Flange Ring 190mm
281
110

For PSB 50 to 110, PSBD 50 to 110 and PDBD pipe If sump is trimmed to minimum height centre point of
entry kit models a 150mm hole should be drilled. hole is 110mm from base internally.
Mark up hole positions as illustrated. NB: Hole size drilled is Ø150mm. OD of flange is
Ø190mm

2-4
INSTALLATION INSTRUCTIONS
EL-G-E500 Encore Dispenser

7 8

AC
ET
ON
E

Abrade internal groove of corbel and top edge of the


sump (inside & outside) with sandpaper. Degrease
Run pipework through side wall, connect to upward with acetone.
riser. Cap off pipework to allow vacuum testing in
Stage 8.
10
9

Apply a bead of sealant to the top of the sump flange.


If this has been removed during trimming, apply
sealant inside the groove of the corbel. Position the Apply sealant to BOTH the internal and external joint
corbel onto the sump and push down firmly. between the sump and corbel. Smooth off and press
into the joint with soapy water to remove trapped air.
Allow 12hours for the sealant to set.
11 OPTIONAL HYDROSTATIC TEST

12

Optional vacuum water or hydrostatic test.


Ensure pipework is capped off below the upward
riser. Tighten clips on pipe entry sealkits against the Complete pipework and secure to shear valve rails
pipe. Tighten nuts on upper support frame metalwork. with the MPK-10 mounting kit. Refer to the shear valve
Vacuum test at 0.6m depth setting only. arrangement plan detail on page 1.

3-4
INSTALLATION INSTRUCTIONS
EL-G-E500 Encore Dispenser

13 14

Backfill around the sump equally in levels to prevent


Run conduit through the locator holes in the uneven load against the sump wall.
dispenser top framework.

15 500
“A”

5-10 300

Minimum
200
Maximum
350

VERY IMPORTANT
OUTER EDGE “A” OF FRAME SET
5-10mm ABOVE GENERAL GRADE
AREA WITH CONCRETE RAMPED
AWAY OVER 300mm

Concrete island depth fixed as per architect drawing.


Allow concrete to cure

16 DISPENSER

NUT
WASHER
x4
SUMP FRAME

Remove upper nut & washer on the 4 anchor bolts


Install & connect the dispenser to the sump frame &
anchor bolt. Fit & tighten nut & washer.

4-4