3 SCHEDULE A3 – ERECTION
Name of the Bidder:…………………………………………………………………..
Require REMARK
S.N. Description Unit RATE Amount
d qty
A B C
1 Laying of 220 kV single core, 1200 sq. mm copper cable in
flat formation, tagging, fixing, pipes for drain & gate xing as
per drg & specification in trench pipes, ducts by pulling, drg km /
etc., including cables, using std cable installation equipment ckt 17.631 2,037.00 35,914.35
& as directives of Engr. In charge etc.

2 Handling & making of normal straight through joints for 220


kV S/C power cable with all consumables at site &
connection of copper bonding cables to single phase link Not in bidders
box as well as to earthing well as point, i.e. connection to Nos 30 -
scope
copper rod, including erection of single- phase link box

3 Handling & making of insulated through joints along with


three phase link boxes for 220 kV single core power cable
with all consumables& connection of copper bonding cables
to single phase link box as well as to earthing well as point, Not in bidders
i.e. connection to copper rod, including erection of three Nos 72 -
scope
phase link box

4 Handling & making of cable end in door terminations along Sets


with single phase link boxes for 220 kV single core copper (Per
cable at 220 kV SS including erection of LA, single phase link ckt
box with safety lock arrangements & connection of bonding -1 set) Not in bidders
cables, earthing etc. as per directives of Engr In charge 0 -
scope

5 Handling & making of cable out door terminations along Sets


with single phase link boxes for 220 kV single core copper (Per
cable at CTT, including erection of L.A & supporting ckt
insulators on CTT tower along with supporting structure, -1 set) Not in bidders
clamps, connection of cables to conductors etc. 24 -
scope

6 Charges for conducting pre-commissioning test from CPRI & L/S Not in bidders
successful commissioning of circuit 2 -
scope
7 Laying of Fiber Optic cable 48 fiber unarmoured cable along
with HDPE duct with MUX/Necessary constructional
equipment & with end termination to be taken up by the Km 9 150,000.00 1,350,000.00
bidder as per site requirement

8 220 KV Lightning Arrester erection Nos. 24 12,000.00 288,000.00


9 Erection of CTT towers for cable termination including
proper fixing of 220 kV cables, OPGW cables with cable MT 60 9,800.00 588,000.00
fixing clamps, tower accessories

10 Dismantling of 0.4 ACSR conductor 220 kV D/C on D/C tower KM 6.36


133,650.00 850,014.00
11 stringing of 0.4 ACSR conductor 220 kV D/C on M/C tower KM 0
(CTT tower) -
12 Destringing of OPGW E/W on 220 kV D/C & M/C tower
KM 0 -
13 Destringing of OPGW E/W on 220 kV CTT tower KM 0 -
14 Restringing of OPGW E/W on CTT tower KM 0 -
15 Dismantling of 0.4 ACSR conductor D/C on M/C conductor Km 2.50
along with OPGW E/W 123,750.00 309,375.00
16 Dismantling of D/C & M/C towers MT 719.00 9,025.00 6,488,975.00
17 Tack welding: For CTT towers(M/C) Nos. 2.00 99.00 198.00
18 Stringing of D/C on M/C 0.4 ACSR conductor km 0.038 148,500.00 5,643.00
19 Stringing of S/C on M/C 0.4 ACSR conductor km 0.33 123,750.00 40,837.50
20 FOTE system (Fibre optic terminal system) nos 5.00 6,435.00 32,175.00
21 Dismantling of CC (Infosys, H2, Pegasus) nos 16.00 3,465.00 55,440.00
22 Dismantling of wave trap (Infosys, H2, Pegasus) nos 16.00 3,465.00 55,440.00
23 Dismantling of Earth wire kms 12.00 29,700.00 356,400.00
24 Dismantling of 0.4 ACSR conductor 220 kV S/C on D/C tower kms 0.202
148,500.00 29,997.00
25 Stringing of OPGW E/W (from 28A to 220kV Pirangut S/stn
& 28A to H-1) kms 12.000 53,350.00 640,200.00

New 50x2500mm GI Rod for Joint bay earthing


Nos 102 2,375.00 242,250.00
New 150x3000mm CI earth pipe for termination and, CTT tower
LA earthing Nos 60 4,750.00 285,000.00

New 50x8mm GI flats (strip) for Grid and rigger of earthing


Mtrs 1300 71.25 92,625.00
New CTT tower fencing with civil works
Nos 3 100,000.00 300,000.00

Total estimated amount in Rs.


12,046,483.85

Terms and conditions-


1) Scope includes transportation from RCPL store to site
2 Scope includes inclusive security of laid cable upt backfilling completion
3 scope includes Joint mesurement sheet from client I,e MSETCL
S. Tende Actual Required
Description Unit RATE Counter Offer AMOUNT Toal
N. r Qty. qty

A B C E D E F G H

220 kV Laying of cable along the route: 8.82


Km
a) Excavation in all types of soil including road
cutting, dewatering, making compacted sand
1 Cum 18,894.09 - - - - -
sub base of 100 mm thick & backfilling using
excavated soil, RCC slabs, warning tape route
markers, etc. including road crossing as per
directives of Engineer in - charge.

Excavation and back filling work Cum 18,894.09 21,600.00 2,470.00 1,000.00 53,352,000.00 21,600,000.00

Crash Sand Cum 7,200.00 7,200.00 2,375.00 1,500.00 17,100,000.00 10,800,000.00

RCC tiles 350x350x100mm Sqmtrs 14,400.00 14,400.00 3,040.00 2,500.00 43,776,000.00 36,000,000.00

warning tape Mtrs 16,000.00 16,000.00 9.50 10.00 152,000.00 160,000.00

- -

For road crossing work:


2 Fixing of HDPE pipes with concreting for road Cum 263.96 264.00 7,275.00 7,500.00 1,920,600.00 1,980,000.00
crossing. Quantity of 1:1.5:3 concrete:

Concreting & Reinforcement with


epoxy/Metacam painting for RCC slabs: For
regular trench & Joint Bay:
Cum 583.89 584.00 12,610.00 13,000.00 7,364,240.00 7,592,000.00
a) Concreting with 1:1.5:3:
3 Total concrete volume of slabs excluding joint
bay

b) Reinforcement : MT 45.96 46.00 71,280.00 72,000.00 3,278,880.00 3,312,000.00

Preparing Joint Bays having dimensions 6mtr


x 2 mtr x 2mtr with brick walls & PCC at
4 Nos 44.00 34.00 321,750.00 250,000.00 10,939,500.00 8,500,000.00
bottom along with construction of link box as
per directives of engineer in charge.

Detail survey of route including section


finalisation, joint bay finalisation, tower
spotting, preparing of profiles, route
drawing in auto cad with GPS coordinates,
5 railway xing / river xing drawings, etc. showing KM - 8.00 346,500.00 350,000.00 2,772,000.00 2,800,000.00
cross section views at major points as per
directives of Engr. In charge & as per
requirement of various government authorities
etc.

Check survey : Submission of all respective


drawings with proper GPS coordinates for all
major points, such as section starts, section
end, road start , road end, railway xing, river
6 Km 8.82 8.00 - -
xing, tower spotting, Joint Bay positions etc. as
per directives of Engr. In charge & as per
requirements of various government
authorities etc.

Excavation of pits for tower footing in earth/soil


of all types including removing of excavated
material beyond tower limits up to 50 mtrs,
lead & all lifts, shoring, shuttering, dewatering,
7 - -
preparation of bed for foundation & back filling
after casting and curing of foundations, with
ramming etc. complete in all respect as per
drawing and direction of Engr. In charge.

a. Normal/Yellow/Sandy/Loose soil with lime &


Cum - - - -
clay boulders/soft murram
b. Black cotton soil / Submerged soil Cum 2,243.00 2,500.00 960.00 1,000.00 2,400,000.00 2,500,000.00
c. Soft rock / Hard murram Cum - - - -
d. Dry fissured rock Cum - - - -
e. Hard rock by chiselling Cum - - - -

Concreting of foundation : Providing & casting


in situ cement concrete of trap metal of size 20
to 40 mm as applicable including cost of
8 cement, sand, metal, water, grame work, - -
finishing, compacting, coping and curing for 21
days complete as per drawing and direction of
Engr. In charge in the following grades.

a. M30 with graded metal for foundation Cum - - - -

b. M20 (1:1.5:3) with graded metal for


Cum 996.00 996.00 6,720.00 5,000.00 6,693,120.00 4,980,000.00
foundation

c. M15 (1:2:4) with graded metal for


Cum - - - -
foundation / coping

d. M10 (1:3:6) with graded metal for


Cum 33.00 33.00 6,370.00 6,500.00 210,210.00 214,500.00
foundation / coping / bedding

e. M 7.5 (1:4:8) with graded metal for


Cum - - - -
foundation / bedding

Providing & fixing in position steel


reinforcement in concrete foundation including
supply of TMT bars with epoxy coating / Meta
cam of various diameters for RCC work like
raft, footing of column etc. as per drawing and
9 MT 88.69 88.00 70,560.00 6,209,280.00 -
direction which will be furnished by the owner
including cutting, bending, hooking the bars,
binding with binding wire or tack welding etc.
complete as directed (steel to be provided by
contractor)

Stub setting in all types of soils with the help of


template /PROB including transportation if
10 required to the desired location, fixing the - -
stubs in position as per the alignment, fixing &
levelling the template & the stub as directed.

a. 220 kV Special tower (CTT) per loc 2.00 3.00 31,850.00 25,000.00 95,550.00 75,000.00

Pipe type earthing as per approved drawing of


11 MSECL & as per directives of Engineer In Nos. 2.00 3.00 24,500.00 25,000.00 73,500.00 75,000.00
charge

12 HDD Boring mtr 800.00 800.00 1,140.00 800.00 912,000.00 640,000.00

GPR survey - Survey up to 2 mtr. Depth, Grid


Size: 20M (L) X 3M (W), Data Collection,
13 km 8.82 8.00 - -
Processing and analysis, Preparation of report
in CAD
per
14 Removal of stub 58.00 58.00 49,000.00 12,000.00 2,842,000.00 696,000.00
tower

Total estimated amount in Rs. 160,090,880.00 101,924,500.00

SCOPE-

1 Exavation scope incldes Providing barrigades as per Metro stndards


2 Work includes inclusive of all safety PPE to workers
3 Saftey officer mandatory at site
4 Work includes ROW,Existing Cable burst reapiring,Transportation,Security at site
5 Scope includes transportation from RCPL store to site
6 Scope includes inclusive security of laid cable upt backfilling completion
7 scope includes Joint mesurement sheet from client I,e MSETCL
REMARK

Not supply