CONSTRUCTION NOTES
LAP SPLICE LENGTH:
MAX STIRRUPS SPACING
=ø6 BARS @ 150mm 1. AT ANY LEVEL NO MORE THAN ALTERNATE
HALF OF "H"
WHICHEVER IS GREATER
TOP OF FOOTING/
FOOTING TIE BEAM(FTB) JOINT DETAIL L/4
ADD'L 16mmØ CROSS TIES
SPACED @ 300 O.C. W/IN
FOOTING.
(MIN.) (MIN.)
MAIN REINFORCEMENTS
TO BE CONTINUOUS
(TOP & BOT. BARS)
DEPRESSION
t=FOR SLAB
CONT. FOOTING BOT. 225 mm WIDE x 6mm THK. VERIFY
BARS AS SCHEDULED
3/4 IN. (19MM.) 4 IN. (100MM.)
BLINDING CONCRETE
UNDERSIDE W/ FINS ON THE
(THICKNESS AS DETAILED) MAT FOOTING SIDE
3/4 IN. (19MM.) 4 IN. (100MM.) CONT. FTG./MAT FOOTING 2t=FOR SLAB
Ø 16 @ 100
REINFORCEMENT
Ø 16 @ 100 O.C.
SCHEDULE
PVC WATERSTOP,
AS PER
(TYP.)
HOOP TIES
Ø 16 @ 100
FILLER (BITUMINOUS MATERIAL)
SLAB REINF.
FLR. LVL. NOTES:
1. YIELD STRESS OF HOOPS = 40KSI (276 MPa).
SLAB REINF.
SLAB-ON-GRADE CONSTRUCTION 3. TOP BARS ARE HORIZONTAL BARS W/ MORE THAN 300 MM DEPTH
OF CONCRETE CAST BELOW THE REINFORCEMENT.
JOINT DETAIL
4. AS MUCH AS POSSIBLE, SPLICES SUBJECTED TO TENSILE
STRESSES ARE DISCOURAGED, THESE SHOULD BE AVOIDED OR
PROVIDED W/ STANDARD HOOKS.
GENERAL NOTES