Вы находитесь на странице: 1из 1

COLUMN TIES AS PER SCHEDULE

CONSTRUCTION NOTES
LAP SPLICE LENGTH:
MAX STIRRUPS SPACING
=ø6 BARS @ 150mm 1. AT ANY LEVEL NO MORE THAN ALTERNATE

H (CLEAR HEIGHT OF COL.)


BARS SHOULD BE SPLICED.
2. MIN. DISTANCE BETWEEN TWO ADJACENT BAR
SPLICES SHALL BE 600mm.
CONFINING REINF. ZONE MAXIMUM OF
1. 1/6 CLEAR HEIGHT STRUCTURAL R.C.
2. MAX. COL. DIMENSION COLUMN
3. 450mm.
L
SUSPENDED SLAB CONSTRUCTION

HALF OF "H"
WHICHEVER IS GREATER
TOP OF FOOTING/
FOOTING TIE BEAM(FTB) JOINT DETAIL L/4
ADD'L 16mmØ CROSS TIES
SPACED @ 300 O.C. W/IN
FOOTING.
(MIN.) (MIN.)
MAIN REINFORCEMENTS
TO BE CONTINUOUS
(TOP & BOT. BARS)

CONF. REINF. TIESLAT TIES


JT. REINF.
COLUMN VERTICAL BARS
EMBEDMENT TO FOOTING DETAIL

WHERE JOINT IS AT POINT OF


STRESS, Ø12 @100 O.C.
PROVIDE SHEAR RODS SUBJECT
TO ENGINEER'S
LOCATION 28 DAYS STRENGTH MAX. SIZE AGGREGATE MAX. SLUMP APPROVAL/RECOMMENDATIONS

BEAM CONSTRUCTION COLUMN LAP SPLICE AND EXT.


1 IN. (25MM.) 4 IN. (100MM.) JOINT DETAIL GIRDER TO COL. CONNECTION DET.

3/4 IN. (19MM.) 4 IN. (100MM.) (MIN.) (MIN.)

DEPRESSION
t=FOR SLAB
CONT. FOOTING BOT. 225 mm WIDE x 6mm THK. VERIFY

PVC WATERSTOP W/ FLAT TYPE


D=FOR BEAM

BARS AS SCHEDULED
3/4 IN. (19MM.) 4 IN. (100MM.)
BLINDING CONCRETE
UNDERSIDE W/ FINS ON THE
(THICKNESS AS DETAILED) MAT FOOTING SIDE

3/4 IN. (19MM.) 4 IN. (100MM.) CONT. FTG./MAT FOOTING 2t=FOR SLAB

CONSTRUCTION JOINT DETAIL (MIN.)

CONC. REINF. Ø 16 @ 100 CONC. REINF.


Ø 16 @ 100
BEAM/SLAB CHANGE SOFFIT
(MIN.) DETAIL
SEE WALL
SCHEDULE
WALL HOR. 4-Ø16 VERT. BARS
REINFORCEMENT WALL VERT.

Ø 16 @ 100
REINFORCEMENT

LEGNTH OF COL. REINFORCEMENT


SEE TABLE OF MIN. LAP SPLICE
FOR COL. BARS SPLICES
200mm WIDE X 6mm THK.

Ø 16 @ 100 O.C.
SCHEDULE
PVC WATERSTOP,

AS PER
(TYP.)
HOOP TIES

FIN-TYPE WITH CENTER BULB.

CONC. REINF. Ø 16 @ 100 CONC. REINF.


Ø 16 @ 100
BASEMENT EXTERIOR RETAINING
WALL CONSTRUCTION WALL

Ø 16 @ 100
FILLER (BITUMINOUS MATERIAL)
SLAB REINF.
FLR. LVL. NOTES:
1. YIELD STRESS OF HOOPS = 40KSI (276 MPa).

2. D = USE MAXIMUM COLUMN DIMENSION, 1/6 CLEAR


HEIGHT OR 18" (450mm) WHICHEVER IS GREATER.

3. NUMBER OF HOOP TIES SAME AS PER COLUMN TIES


SCHEDULE.

4. ALL CONCRETE REINFORCEMENT DETAIL SHOULD BE


DONE IN ACCORDANCE WITH ACI DETAILING MANUAL
GRAVEL BASE PUB SP-66.
SUBGRADE COMPACTED TO 95% OF
VAPOR BARRIER
WHEN REQ.
MAXIMUM MOISTURE @ OPTIMUM
CONTENT (MAX. DEPTH OF
COLUMN ELEV.
COMPRESSED
FILL = 200/LAYER)
WALL CONNECTION SHOWING DOWELS
AT INTERSECTION AND TIES SPACING DETAIL
SLAB-ON-GRADE EXPANSION
JOINT DETAIL
CONSTRUCTION NOTES & STANDARD DETAILS
FILLER (BITUMINOUS MATERIAL)

SLAB REINF.

FLR. LVL. TABLE OF LAP SPLICE & ANCHORAGE LENGTH NOTES:


1. ACI SECTION 12.4 STATES THAT DEVELOPMENT LENGTH OF
INDIVIDUAL BARS W/IN A BUNDLE, IN TENSION OR COMPRESSION,
SHALL BE THAT FOR THE INDIVIDUAL BAR, INCREASED 20% FOR
THREE BAR BUNDLE, AND 33% FOR FOUR-BAR BUNDLE.

2. FOR COLUMNS, AT ANY LEVEL NO MORE THAN ALTERNATE BARS


PEJ
GRAVEL BASE SHOULD BE SPLICED. NOT MORE THAN 33 % OF THE BARS SHALL
SUBGRADE COMPACTED TO 95% OF
VAPOR BARRIER MAXIMUM DRY DENSITY @ OPTIMUM BE SPLICED W/IN THE REQUIRED LAP LENGTH. MINIMUM
WHEN REQ. MOISTURE CONTENT (MAX. DEPTH OF DISTANCE BETWEEN TWO ADJACENT BAR SPLICES SHALL BE 600
COMPRESSED MM.
FILL=(200mm PER LAYER).

SLAB-ON-GRADE CONSTRUCTION 3. TOP BARS ARE HORIZONTAL BARS W/ MORE THAN 300 MM DEPTH
OF CONCRETE CAST BELOW THE REINFORCEMENT.
JOINT DETAIL
4. AS MUCH AS POSSIBLE, SPLICES SUBJECTED TO TENSILE
STRESSES ARE DISCOURAGED, THESE SHOULD BE AVOIDED OR
PROVIDED W/ STANDARD HOOKS.

GENERAL NOTES

PROPOSED ONE STOREY RESIDENTIAL BUILDING S-1

Вам также может понравиться