Вы находитесь на странице: 1из 12

c c

 

 c c 

 
 
V   c„ 
u

 „

 
„ 
 
u
It is a requirement of the Electricity (Licensing) Regulations 1991 that all
electrical installing work carried out in Western Australia complies with the
relevant standards, including Australian/New Zealand Standard AS/NZS
3000:2000 (known as the Wiring Rules) and the WA Electrical Requirements.
The application of minimum electrical requirements and standards is essential for
the safety of persons, livestock and property.
A clear understanding of these requirements is essential for those involved with
electrical installing work carried out in Western Australia.
All completed electrical work must be checked and tested by a licensed
electrician before the electrical contractor certifies the work to the relevant
network operator.
This booklet has been produced as a guide to meet the checking and testing
requirements for electrical installing work, as specified in the Wiring Rules. Whilst
the details are focussed on domestic electrical installations, the principles apply
to all electrical installing work.
The testing methods in this booklet are not exclusive. Other test methods may be
used provided that they meet the minimum requirements of the Wiring Rules.
More detailed testing information is contained in the Australian/New Zealand
Standard AS/NZS 3017 Electrical installations - Testing and inspection
guidelines.

 „

 
„ 
 

 „

 
„ 
 
u c
checking, Testing and certification of Electrical Installing Work 1
Installation Test certificate 2
checking and Testing 4
checking and Testing Procedure 5
1. Visual Inspection 5
2. Earth Resistance and continuity Tests 5
Test Equipment 6
Test Procedure 7
3. Insulation Resistance Test 8
Test Equipment 8
Test Procedure 8
4. Polarity/Functional Test 10
Test Equipment 10
Test Procedure 10
5. correct circuit connections 11
6. Fault-loop Impedance Test 11
Test Equipment 11
Test Procedure 11
7. Verification of Rc Operation 12
Testing Alterations and Additions 12
Test Equipment 13
Table 1 - Maximum resistance values of final subcircuit 14
protective earthing conductor
Table 2 - comparison of voltage drop and fault-loop 15
impedance to determine circuit maximum distance
Further Information 16

 „

 
„ 
 

 „

 
„ 
 
½
c !" ucu
uu !
All completed electrical installing work must be checked and tested to confirm
that it complies with the Wiring Rules and is safe for connection to the electricity
supply. The required steps to comply with the current regulatory requirements are
as follows:
1. When the electrical installing work has been completed, a licensed electrician
(which may be the contractor or an employee) is required to carry out checks
and tests of the installation, to ensure the electrical work meets the
requirements of the Wiring Rules. The checking and testing should be carried
out in accordance with a formalised checking and testing procedure.
2. Once these checks and tests have been completed, the electrician confirms
on the relevant section of the Notice of completion or Notice of completion-
Minor Work, that the checking and testing has been carried out.
3. For electrical installing work that requires the network operator to attend
(eg. for electricity supply connection or alteration to the supply service
apparatus), the electrician then completes an Installation Test certificate and
fixes it inside the meter enclosure of the installation.
4. Then, in the usual manner, the electrical contractor (or nominee) completes
the Notice of completion, thereby certifying the work, and submits the Notice
to the network operator.
5. When the Notice of completion is received, the network operator will
determine if an inspection of the installing work will be carried out, to ensure
that the standards of electrical safety of t he installation are being maintained.
The network operator will also arrange for the connection of the electricity
supply if necessary.

1. Minor work, ie. alterations and additions to existing electrical installations, is
also subject to a similar system except that the work is connected to the
electricity supply by the electrician.
2. Western Power¶s contractor connect Scheme permits accredited electrical
contractors and authorised electrical workers to connect the electricity supply
to the installation and to then submit the Notice of completion following
connection.

 „

 
„ 
 
uu cu
When a Notice of completion is to be submitted for completed electrical installing
work that may require the network operator to attend (eg. new connection or
upgrade of supply), the electrician carrying out the checking and testing must
complete an Installation Test certificate.
An Installation Test certificate is an adhesive label (included in books of
Preliminary Notices / Notices of completion and also available from network
operators) that must be filled in by the electrician who performed the checking
and testing of the completed electrical installing work.
An Installation Test certificate is to be fixed by the electrician to the inside of the
meter enclosure to indicate to the network operator and the customer that the
installation is completed, has been checked and tested and is safe to be
connected to the electricity supply.
The electrician is requested to record the following key installation test results
and the underground consumer¶s mains cable route on a self adhesive label
which is also to be placed inside the meter enclosure:
‡ main earth conductor resistance;
‡ either the earth continuity or fault-loop impedance values for each sub circuit;
and
‡ insulation resistance values for each sub circuit.
The information will benefit subsequent electrical work and inspection, as well as
assist in preventing electric shocks and accidents.
º
#

 „

 
„ 
 

  

 

     
          
                
       
     !     
V "    
 #        
   $       
     %       
      
  
&  
     '  
         
$ %    c c &'
 &
(
 c
 c c c c  

 „

 
„ 
 
)
c !u 
On completion of the electrical work and before the electricity supply is
connected and energised, the electrical contractor is responsible to ensure that:
‡ the electrical work has been carried out in accordance with the Electricity
(Licensing) Regulations 1991; and
‡ the installation has been checked and tested and is safe for connection to
the electricity supply.
To achieve this, the following minimum checks and tests should be carried out by
the electrician:
1. Visual Inspection - should be carried out whilst referring to a plan (to ensure
a systematic check to pick up any omissions and to verify that the work
complies with the requirements of the applicable standards).
2. Earth Resistance and continuity Tests - this test is to include the main
earthing conductor, protective earth conductor and bonding conductor.
3. Insulation Resistance Test - this test is necessary to ensure that the
insulation resistance between live parts/conductors and earth is adequate.
4. Polarity Test - used to ensure correct connection of active, neutral and
earthing conductors.
5. correct circuit connections - this test checks earthing conductors do not
carry current during normal operation and no short circuit exists.
6. Fault Loop Impedance - measures the fault loop impedance of each circuit to
verify the protective device will operate.
7. Verification of Rc (residual current device) Operation - testing of Rc s is
carried out to ensure that the Rc operates.

 „

 
„ 
 
c !u 
 !! "
# "$" """  $"
" %"&'     
# ""$ 

" "  ""% ""


"()* 
  
'  "+"  && " 
 " )""  & "%" ' 
%"  "  '%" 
""% !$
½ *u 
A visual inspection is carried out to ensure that all work has been correctly
completed, by checking that:
‡ all cables and equipment have been correctly installed and terminated, and
‡ the installation complies with the relevant parts of the Wiring Rules and the
WA Electrical Requirements.
º u  uuc  
Earth resistance tests are required to confirm the installed earthing system will
cause circuit protective devices to operate and maintain cable integrity if there is
a fault between live parts and exposed conductive parts.
u 
u
The resistance from any point of the electrical installation required to be earthed,
to the point where the main earthing conductor is connected to the neutral
conductor (MEN connection) of the supply system, shall be low enough to permit
the passage of current necessary to operate the circuit protective devices. To
confirm this value (which is dependent upon the type and rating of the protective
device and the fault-loop impedance of the associated conductors) requires the
following test to be performed:
Test 1: Obtain the resistance value of the protective earthing conductor using a
quality ohm meter (see next page for procedure) and compare this value
with the maximum allowable resistance as tabulated in Table 1, page 14
of this booklet.
r

 „

 
„ 
 
"+  
,
Test 2: Obtain the fault-loop impedance of each sub circuit using a quality faultloop
impedance meter (refer to manufacturer¶s instructions and page 15
of this booklet for procedure). compare the measured fault-loop
impedance value with the maximum value provided at Appendix B,
Table B4.1 of the Wiring Rules.
,
1 If the application of a fault-loop impedance test onto an Rc
protected sub circuit results in the Rc operating, then:
‡ the earth resistance and continuity test requirements are
considered to be satisfied; and
‡ the fault-loop impedance value need not be considered further.
2 If the value measured is GREATER than the allowable maximum,
then the following steps must be performed:
Test 2.1 check the MEN connection, active, neutral and earth
conductor/equipment connections are all solidly made.
Repeat the fault-loop impedance Test 2, above.
If the fault-loop impedance values exceed the requirements
of Table B4.1, then perform Test 2.2
Test 2.2 Perform the earth continuity measurement, Test 1 and
confirm results.
Repeat the fault-loop impedance Test 2, above.  u'
u-uu . u /) ½
 u +!uu-   
u 
%uu c 
The resistance from the earthing electrode to the point where the main earthing
conductor is connected to the neutral conductor of the supply system shall not
exceed 0.5 ohms.
.
‡ A multimeter set to ohms.
‡ Insulated copper conductor of suitable length (long lead).
0

 „

 
„ 
 

uu,
1. Ensure that the electricity supply has been disconnected.
2. connect an insulated copper conductor of suitable length (long lead) to one
terminal of the ohm meter.
3. connect a standard length test lead to the other terminal of the ohm meter
(short lead).
4. connect the two leads together, and
‡ zero the multimeter or, if this is not possible,
‡ record the resistance of the test leads.
5. isconnect the water pipe equipotential bonding conductor and the water
heater earthing conductor (if applicable).
  "% !      "
""&$ ""  "% 
  ""$
6. isconnect the MEN link from the main neutral link and connect it to the long
lead (ie. long lead now connected to the earth bar).
,%uu c 
‡ connect the short lead to the earth electrode and measure the earth
resistance of the main earthing conductor.
‡ The resistance shall not exceed 0.5 ohms for the main earthing conductor.
/,u c  
‡ Using the long lead and zeroed multimeter, measure, for each circuit, the
earth conductor resistance from the circuit extremity to the switchboard.
‡ confirm the measured values are LESS THAN those values as provided at
Table 1, page 14 of this booklet for each sub circuit.
‡ This test is applicable to all circuits, including socket outlet circuits, lighting
circuits and fixed equipment (eg. water heater supply) circuits.
7. Re-connect the MEN link to the main neutral link.
8. Re-connect the water pipe equipotential bonding conductor.
-

 „

 
„ 
 
# u u 
An insulation resistance test is performed to ensure that the resistance between
all live conductors and earth, or as the case maybe, all live parts and earth, is
adequate to prevent electric shock hazards, fire hazards and equipment damage.
It is a requirement of clause 6.3.3.3.1 of th e Wiring Rules that the insulation
resistance between all live conductors (including the neutral) connected together,
and earth, measured with all protective devices in circuit and all switches on, is
not less than 1 Megohm (see Note below). This applies to the complete
installation and all parts of the installation.
This does not preclude the use of appliances incorporating heating elements
provided that, when tested with all elements in circuit, the insulation resistance
between live parts and the earthing terminal or earthing contact of the appliance
is not less than 0.01 Megohm (10,000 ohms).
: Whilst the minimum reading is 1 Megohm, the ideal reading is infinity.
This indicates a sound installation.
.
Where the supply voltage does not exceed 250 volts between conductors and
earth, a 500 volt insulation tester should be used to perform this test.

1. Ensure that all protective devices are in circuit and that all switches are on. If
there are two way lighting circuits in the installation, tests must be carried out
with the two way switches in all positions, so all circuit conductors are tested.
2. Set the insulation tester (eg. Megger) to Megohms.
3. connect one lead of the insulation tester to the main earthing bar (MEN Link
disconnected) and the other lead to the actives and neutrals connected
together.  +u-uu 
4. Measure the insulation resistance of the total installation (including the
consumers mains).
 uu½% - re-connect the MEN
Link and return the installation to normal.
1

 „

 
„ 
 
 uu u½%  - test all circuits
individually, starting with circuits supplying appliances incorporating heating
elements.
Where a circuit is less than 1 Megohm, disconnect the appliance or
appliances. Then test the circuit and appliance (separately) to ensure that the
insulation resistance of both the circuit and the appliance complies with the
following:
‡ not containing a heating element - is not less than 1 Megohm, or
‡ containing a heating element - is not less than 0.01 Megohm
,Where the insulation resistance of an appliance containing heating
elements is found to be less than 0.01 Megohm and the defect cannot be
rectified at the time of checking and testing, the electrical contractor must
make arrangements for correction of the defect prior to submission of the
Notice of completion. Alternatively, the following procedure may be used:
a) Isolate the defective circuit, including the neutral conductor, by
disconnecting at the appropriate switchboard.
b) Attach an ³out of service´ tag to the circuit protection device, advising that
the circuit has been disconnected due to low insulation resistance.
c) check that the earth conductor has been reconnected at the MEN point.
d) Then submit the Notice of completion.
"  " ,   -
"" $
Ô

 „

 
„ 
 
) u 
Polarity tests are carried out to ensure the correct connection of active, neutral
and earth conductors to electrical equipment and to ensure that switches are not
installed in neutral conductors. clause 6.3.3.4 ³Polarity´ of the Wiring Rules
specifies the testing requirements for this mandatory test.
.
To carry out these tests, a continuity tester such as a multimeter (set to ohms)
should be used.

To ensure that the installation circuits/equipment will function as intended, it is
necessary that the following tests be performed:
‡ Isolate the active conductors by turning the main switch OFF and tagging.
‡ confirm consumer and sub mains cables/connections by simply testing from
the point of supply or distribution board to the main switchboard using an
ohm meter and long test loads. Test result 0 0 .
‡ confirm active conductor switching by using an ohm meter with the long lead
connected to the active conductor at the switchboard and the short lead
connected to the switch terminals (one at a time) in the following manner:
i) Switch ON 0 0  for both terminals
ii) Switch OFF 0 0  for one terminal and µinfinity¶ for the other terminal
‡ With the MEN link in place, confirm the polarity of socket outlets using a 10
resistor and an ohm meter. connect the 10 resistor between the circuit
active conductor and the neutral bar then at each socket outlet connect one
lead of the multimeter to the earth terminal and the second lead to the active
terminal. Test the resistance value for:
i) socket outlet switch OFF 0 µinfinity¶
ii) socket outlet switch ON 0 10.
½

 „

 
„ 
 
r ccc
These tests are required to ensure the following:
1. that protective earthing conductors do not carry current;
2. to prove there are no µshort circuits¶ within the installation; and
3. for the circuit continuity test, to prove each circuit for electrical continuity and
that all switches operate in the active conductors.
0 2u'u 
This test is carried out to confirm the fault-loop impedance value of each circuit
will be low enough to ensure the operation of the protective device during a fault.
.
To perform the fault-loop impedance test, a fault-loop impedance meter is
required.

‡ Energise all circuits
‡ Using the fault-loop impedance meter, proceed to the equipment to be tested
and measure the earth-loop impedance at this point. Repeat for other items
on the circuit.
‡ The measured value must be less than the maximum values as tabulated at
Table B4.1 of the Wiring Rules.
‡ If an Rc operates during the test, the test result can be considered
satisfactory.
½½

 „

 
„ 
 
- *u cu
This is normally achieved by operation of the integral test device (typically test
button on the Rc ) to confirm:
1. the Rc is functioning correctly; and
2. the tripping device mechanisms are operating.
u: Operation of the integral test device provide a means of
checking:
‡ continuity of the main earthing conductor or the associated circuit protective
earthing conductor; or
‡ any earth electrode or other means of earthing or the associated electrical
installation earthing.
uu
When alterations are carried out to an existing electrical installation, it is
essential that the electrician tests the work to ensure compliance with the
relevant standards and specifications.
The tests described in this booklet must also be carried out on alterations and
additions to ensure the electrical installing work is safe to remain connected to
the electrical installation.
The majority of tests described in this booklet are designed to be carried out
without power being connected. When performing these tests, make sure that
electricity supplies are disconnected where necessary and that the appropriate
isolation and tagging has been carried out.
.   -,!/  "%"%  
! "!$
½º

 „

 
„ 
 
.
Before performing any tests, ensure that the test equipment is correctly set, is
functional and is in good condition, particularly the test leads.
Remember, when testing:
‡ check that the test equipment is operating correctly
‡ perform the required tests
‡ re-check the test equipment to confirm that it still operates correctly.
„ ""# ($  "+ " 
$"    "  ""
"$""$ 
Electrical test equipment is a very important part of an electrician¶s tools. Test
instruments should be tested at intervals not exceeding one year and records
kept to verify this.
½#

 „

 
„ 
 
u ½
%uu-uu -u  
Protective circuit - breakers Fuses
Type B Type c Type
evice Earthing isconnection times
Rating conductor
Size 0.4sec 0.4sec
A mm2 Maximum final subcircuit earth conductor
resistance 
6 1 3.08 1.65 1.00 3.69
10 1.5 1.85 1.00 0.60 2.06
16 2.5 1.16 0.62 0.38 0.99
20 2.5 0.93 0.50 0.30 0.68
25 2.5 1.07 0.57 0.34 0.76
32 2.5 0.72 0.38 0.23 0.51
40 2.5 0.66 0.35 0.21 0.44
50 4 0.54 0.29 0.17 0.34
63 4 0.44 0.23 0.14 0.26
½)

 „

 
„ 
 
u º
cu-uuu 'u 
uu
This table details the single phase voltage drop for a combination of conductor
size, maximum demand current and distance. It also displays the maximum
circuit length for a Type µc¶ circuit breaker (as normally used in most installations)
to ensure the operation of the circuit breaker during a earth fault. You will notice
that compliance for voltage drop is the predominant requirement compared to the
fault-loop distance for the given circuit breaker type.
½r
Notes:
#1: Maximum demand determined using (a) full load, and (b) half the rating of
the protective device assuming distributed load. Refer to Wiring Rules
clause 3.6.2
#2: Voltage drop determined using 230V @ 5% = 11.5V maximum allowable.
#3: istances obtained from Wiring Rules Table B5.1.
mm2 A A #1 V (11.5V = maximum)
1.0 10
10 10.3 - - - - 22* 55
5 5.2 7.7 10.3 - - 45* 55
1.5 10
10 6.6 9.9 - - - 35* 82
5 3.3 5.5 6.6 9.9 - 70* 82
2.5 16
16 5.8 8.6 - - - 40* 85
8 2.9 4.3 5.8 8.6 - 80* 85
4.0 25
25 5.6 8.4 11.2 - - 41* 67
12.5 2.8 4.2 5.6 8.4 10.2 82 67*
* enotes limiting parameter
conductor
Size
Protective
evice
Rating
Maximum
emand For
Voltage
rop #2
For Type c
circuit
Breaker #3
istance
20m 30m 40m 60m 80m
Voltage rop
Maximum istance
m

 „

 
„ 
 
2 u
For further information on testing electrical installing work, please contact the
Electrical Inspector at the relevant network operator, as listed in the manual WA
Electrical Requirements.
For further information, please contact:
EnergySafety
303 Sevenoaks Street
cannington WA 6107
Telephone: (08) 9422 5200
Facsimile: (08) 9422 5244
Email: energysafety@docep.wa.gov.au
Internet: www.energysafety.wa.gov.au
½0
Issued by
 „ 

c   
            
    
ESWA E022 1106
                 
          
        

         



        
       
                         
             
          c   
          
           ! 
  
           

|  
 
 

 

 

 ""#  $     %  
                  
                
   %       
               
               
           & &
c    
                         
                     '()*)+     
'  $     
       c             
   
        '  c   %            
,    ,  
c   - '( .                            
       -   
           /

! ‰      
! c                    
! &  
       
! $ c  c   
!        
! &   
! "        
! "        
! a       
 
! &  
  
! (                      

î
 
 
 

 

 "    #  $                   %     
   
            
 0 1(  " 
                 
                 | |î |
    %  
              î  
   
                 
     ,   ,
            2                   
,34,    2      |
     c  5
 
       
  +6      )76      !       
    

            
&                      
                          
 8   (  (  "#$+9:9'()*)+/;66:     
     8  /c    |  "         
   
              +66<  
    #  
     2     ,    ,

|
  
                  

!               %    


  
! 3               
! 3 
     =             
!      
34      
! $
       
 2  
! 3                   
! c              
! "     %        >        
!       
 
! 3 
                

                  ""   /

+ $ %      


; $ %   
 
? $ %    
   
@ 3    '()*)+               
  

    
 ""                      /

! V
  >+6        
! 
  >7        
!     


>7  
! ´  
 
  >?A7  
!   ´  !"  
!   

 (  &  >+ 

a                      /

! #            


! &           
     

       '()*)+/;66:3               

 0  (  " 


  "   (   4        
          
      
 %  B   


Вам также может понравиться