Вы находитесь на странице: 1из 1

RATE ANALYSIS

Carriage of materials by mechanical transport


Quarry Sekmai Imphal W/site

1 km 22 km 2 km. 4.00 km
Total lead = 1 + 22 + 2 + 4/2 = 27 km Say 27 Km
(A) Stone metal 40mm and below.
0 - 5 Km = Rs.272.09
5 - 10 Km @ Rs.20.06 /km = Rs.100.30
10 - 20 Km @ Rs.15.42 /km = Rs.154.20
20 - 27 Km @ Rs.11.72 /km = Rs.82.04
Rs.608.63
Add 15% C.P. (+) Rs.91.29
Rs.699.92 …(A)
(B) Stone metal 40mm and above.
0 - 5 Km = Rs.295.03
5 - 10 Km @ Rs.21.75 /km = Rs.108.75
10 - 20 Km @ Rs.16.72 /km = Rs.167.20
20 - 27 Km @ Rs.12.71 /km = Rs.88.97
Rs.659.95
Add 15% C.P. (+) Rs.98.99
Rs.758.94 …(B)
Carriage charge of Sand gravel 95% of (A) Rs. 664.92
5% of (B) Rs. 37.95
Rs. 702.87

Carriage of materials by mechanical transport


Quarry Kanglatongbi Imphal W/site

2 km 30 km 2 km. 4.00 km
Total lead = 2 + 30.00 + 2 + 4/2 = 36 km Say 36 Km
(C) Stone aggregate 40mm & below.
0 - 5 Km = Rs.272.09
5 - 10 Km @ Rs.20.06 /km = Rs.100.30
10 - 20 Km @ Rs.15.42 /km = Rs.154.20
20 - 36 Km @ Rs.11.72 /km = Rs.187.52
Rs.714.11
Add 15% C.P. (+) Rs.107.12
Rs.821.23
75mm compacted thickness = Rs.1,094.97 ..(C)

(D) Stone aggregate 40mm & above


0 - 5 Km = Rs.295.03
5 - 10 Km @ Rs.21.75 /km = Rs.108.75
10 - 20 Km @ Rs.16.72 /km = Rs.167.20
20 - 36 Km @ Rs.12.71 /km = Rs.203.36
` Rs.774.34
Add 15% C.P. (+) Rs.116.15
Rs.890.49