Академический Документы
Профессиональный Документы
Культура Документы
Swapping GTMU1a for all GUA sites below with the new IP compatible GTMUc card.This is in
preparation of the SI IP Project.
GUA101,GUA204,GUA201,GUA205,GUA103,GUA110,GUA210,GUA202,GUA206,GUA209,GUA104,
GUA208, GUA212, GUA102, GUA207, GUA203, GUA105, GUA106, GUA107, GUA108 & GUA109.
Estimated Costs:
Services : Hardware : Software:
Service Outage Required : Yes / No (circle one) Planned Outage Duration: 5 – 10 Minutes per Site
Planned Activity Start Date/Time : Planned Activity Completion Date/Time :
05th Sep, 2017/ 1:00 pm 10th Sep, 2017
Actual Outage Start Date/Time : Actual Completion Date/Time :
Departments Affected :
Area of Service Outage : Areas around
GUA sites
The following checklist of pre-change issues has been met for this project. The actual detail of the
work to satisfy these check list items has been reviewed.
Signed:
Project Name
CR TEST RESULT FORM
SI IP Migration Project
Bemobile Ref #:
Vendor/Supplier Ref#:
Network Components Affected: Customers around GUA sites