Вы находитесь на странице: 1из 3

Resume

Resume MANISH VAISH


Permanent Address: Address for Sr. Engineer Design
SURENDRA KUMAR VAISH Correspondence: Reporting to: HOD Electrical
CHOONA MANDI 2ND FLOOR,D-101 Mobile: 7833957838
BUDAUN, 243601 SECTOR 26, Email:
NOIDA- 201301 manishvaish68@gmail.com
Career Objective:
To work in an organization, where innovation and excellence is the way of life, where my full
potential is explored and where I will expand the scope for technology/designs with innovative
ideas.
Key Skills:

 Electrical Design and Engineering


 Substation Design
 Thermal power plant Engineering.
 Project Engineering.
 Railway 132kV/25kV TSS
 Tender Engineering & Support
 Distribution.
Professional Experience

 July-2018 to till Date: - KEI Industries Limited


Project handled – 132kV Arunachal Pradesh (PGCIL)
(EPC of) 132kV Jammu & Kashmir RailwaysTSS@1600MTR
MSL(IRCON/NR)Tender Engineering of 400kV, 220kV, 132kV etc.

 Oct-2015 to July-2018: - Angelique International Ltd.


Project handled – 66/33 kV GIS at Kongolotte, Mozambique.
(EPC of) 6.6/33 kV S/S for Hydro project at Mpanda, Republic of Burundi
11/132 kV Chapali S/S, 66 kV GIS S/S for Lanchur S/S (Nepal
project)

 Oct-2011 to Aug-2014: - Shirpur Power Pvt. Ltd.


Project handled – 2x150MW Thermal Power Project
(Client) Electrical Design of 33kv construction power,

 Sep-2010 to Oct-2011: -A2Z Power Tech Ltd.


Project handled – Engineering calculation of Distribution Loss on identified. i.e. from
(EPC of) DTR (meter to consumer meter shall be brought down to 6% by
way of (include AT&C loss)

1. From July-2018 to till Date

Substation work - Preparation of SLD, Plan & Section Layout, EKD, Equipment layout,
Earthing Calculation. Cable trench layout, Review of LT switchgear and HT switchgear GA
and control wiring, Preparation of Cable Design Calculation, Illumination Design calculation
and Lightning calculation. Preparation power and control cable schedule.
Review of Electrical Equipment’s (Power Transformer, CT, PT, LA, Isolator, Circuit
Breaker, Erection Hardware like clamp & Connector, Conductor, Insulator, BPI C&R panel
etc.)
Tender Work – Quantity calculation of Erection material like, clamp & connector, Insulator,
BPI, Conductor, IPS tube, JB’s, Earthing Material above ground and below ground,
Resume
Lightning protection material, power & control cable and vetting of electrical equipment like,
Power transformer, CRP etc.

2. From October 2015 to June 2018

Electrical Package Done:


Review the GTP of Power Transformer, HT Switchgear, LT Switchgear, Auxiliary
Transformer, Bus duct, DC system, HT Power Cable Layout)
Preparation of GA electrical Layout, Cable trench layout, Earthing Layout, Lightning
Protection Layout, Illumination, Cable Support Structure drawing.
Technical Evaluation and finalization of Fire Fighting System package etc.

Design Calculation: Earthing Calculation, Lightning Protection Calculation, Bus Duct


Sizing, Battery & Battery Charger Sizing, Bus Bar Sizing, HT & LT Cable Sizing, etc

Sub-Station Engineering: 66KV/33KV,11Kv etc. Preparation, Plan & Section Layout


EKD, Cable Tray Layout, Lightning Protection Calculation & Layout Preparation, Earthing
layout along with calculation. Bid Evaluation, Review & approval of Electrical Equipments
(CT, PT, LA, Isolator, Circuit Breaker, Clamp & connector, Insulator BPI, conductor etc.),
C&R panel etc.

3. From October 2011 to August 2014

Electrical Package Done:


Design of Auxiliary Transformer, Review the electrical GA and control wiring schedule of
HT Switchgear, LT Switchgear Prepare Power & Control Cable schedule, Review the GA
and GTP of DG system, CT and PT circuit breaker etc.
Prepared layout of Office Lighting, sizing of Control room building. .
Inspection
Participate of varies electrical equipment testing i.e ACDB, DCD, ACSR Moose Conductor
and HT cable.

4. From September-2010 to October -2011

Electrical Package Done


Review of engineering drawings, technical specifications, cost estimates. Monitoring
projects with respect to budgeted cost, demand forecasts, time over-runs to ensure timely
execution of projects.
The Detailed Engineering activities as follows:
 Preparation of Plant Single Line Diagram, HT SWGR SLD, LT SWGR SLD etc.
 Developed Railways TSS layout, SLD, and feeding post drawing etc. for higher altitude up
to 1600mtr MSL.
 Preparation detail BOQ for Procurement of material.
 Design/Procurement specification of electrical equipment’s: Power Transformers, Auxiliary
Transformer, HT Switchgear, LT Switchgear, DG, Battery & Battery Charger, Feeder
detailing, HT cable, LT power & Control cable, Cable trays.
 Power Transformer & Auxiliary Transformer: Bid evaluation & Preparation of TER, review &
approval of electrical drawings (GA, GTP etc).
 HT & LT Switchgear: Bid evaluation & Preparation of TER. Preparing the panel load list.
Review & Approval of electrical control interlocking wiring diagrams. Review & approval of
GA, SLD & GTP of Switchgear. Preparation & finalization of bill of material.
 HT & LT Power & Control cables: Preparation & finalization of bill of material. Bid
evaluation & Preparation of TER. Review & Approval of GA & GTP.
 Participate in regular discussion with client and vendor for drawing and equipment
approval.
Resume
 Participate and visit to site for RMU testing activity.
 Preparation all the documents as per ISO 9001:2015 guide line.
 Preparation of Al. Cutting Schedule
 Prepare Cable Schedule.
 Sub-Station: Review & approval of GA & GTP of CT, PT, LA, Isolator, Circuit Breaker,
Erection Hardware like clamp & connector, Insulator, BPI & Schematics of C&P panel etc.
 Layout: Preparation of electrical room layouts such as: cable tray & cable routing layouts,
Earthing Layouts, Equipment layouts, Lightning protection layout of buildings, power house
& switchyard. Finalization and release of drawing for construction.
 Regular discussion to client/vendor to procurement of equipment’s for higher altitude
(1600mtr MSL).
 Make & issue the technical clarification on bid to vendors. Technical discussion in pre
award meetings, Preparation the MOMs. Preparation of Technical Evaluation Report
(TER).
 Preparation of lighting layout, power layout, conduit layout, cable tray layout, lightning
protection layout, cable raceway layout, earthing layout etc for various residential as well
as public buildings.
 Design as per NBC (national building code), NEC (National Electricity code), National
Electricity Act and other government codes/standards like CPWD, CBIP etc.
 Knowledge of all package related Indian Standards.
Computer Proficiency:
 Operating System: Windows’s 7 & 10
 Micro Soft Office: Word, Excel, Power Point, Access
 AutoCAD
 Dialux
Professional Qualifications:
Class Subject Duration Institution Univ./Board CGPA
Master of Pyroelectric
IIT, Mandi
Science Energy 2015-2018 Central Univ. 7.5
(H.P)
(M.S) harvesting
SMIT
Electrical (Sikkim SMU
B. Tech. &Electronic 2007-2011 Manipal (Manipal 6.2
Engineering Institute of Univ.)
Technology)

PERSONAL DETAILS
Name MANISH VAISH
Date of Birth 09th Dec. 1986
Sex Male
Nationality Indian
Marital Status Married
Mother Tongue Hindi
Languages Known English, Hindi

Declaration:

I hereby declare that the information provided above is true & to the best of my knowledge and
belief.

DATE: (MANISH VAISH)

Вам также может понравиться