REHABILITATION OF MBABU ROAD (1.5KM), KANYAGEYA (3.5KM), KYONDO (2.3KM), LUGOKI ROAD (1.05KM), NSENYI – MUGHENDE – KAJWENGE
PROJECT
(4.0KM), KISINGA – MUGHENDE (2.1KM) AND NGOLERANDI SPUR (0.5KM) IN KASESE DISTRICT; TOTAL LENGTH = 14.95KM
MONTH Aug-20
CONTRACT NO. MoWT/Wrks/IP/19-20/027
CONTRACTOR Surface water Drainage
BILL NO 21 Surface Water Drainage
ITEM Construct culvert end structures. Using stone masonary and cement sand mortal 1:3, and finish with plaster.wall thickness of 115mm to 345mm as directed by the
22.17
DESCRIPTION Engineer.
_____
R
h d f
c
b
a c e
Cluster 1: Mbabu Road (1.7 km), Kanyageya (3.5 km), Kyondo (2.5 km), Kalenge Road (0.9 km); Total Length = 8.6 km
SIZE WINGWALLS HEADWALL APRON AREA OF STONE
h a b Thick c Thick e Thick Previous Total to
CHAINAGE TYPE POSITION d R f MASONRY This IPC
(m2) IPC Date
(Ø mm) (m) (m) (m)
(m) (m) (m) (m) (m) (m) (m) (m)
Kalenge Road
0+000 INLET 0.90 0.86 0.60 0.30 1.45 1.00 0.30 0.30 2.5 0.0 2.5 2.5
CPC 600
OUTLET 0.80 0.50 0.50 0.30 1.60 1.10 0.30 0.30 2.1 0.0 2.1 2.1
0+020 INLET 0.80 0.90 0.45 0.25 1.50 1.10 0.30 0.30 2.5 0.0 2.5 2.5
CPC 600
OUTLET 0.70 0.60 0.50 0.27 1.40 1.00 0.30 0.30 1.8 0.0 1.8 1.8
0+360 INLET 1.00 1.00 0.50 0.29 1.40 1.20 0.30 0.30 2.9 0.0 2.9 2.9
CPC 600
OUTLET 0.90 0.70 0.40 0.30 1.60 0.90 0.30 0.30 2.1 0.0 2.1 2.1
0+500 INLET 1.00 1.20 0.70 0.30 2.40 1.35 0.45 0.30 4.6 0.0 4.6 4.6
CPC 900
OUTLET 1.20 1.10 0.60 0.30 2.30 1.60 0.45 0.30 5.0 0.0 5.0 5.0
Mbabu
0+080 INLET 0.90 1.10 0.30 0.23 1.50 1.00 0.30 0.23 2.5 0.0 2.5 2.5
CPC 600
OUTLET 0.90 0.80 0.30 0.30 1.60 1.00 0.30 0.30 2.3 0.0 2.3 2.3
0+420 INLET 0.80 0.60 0.40 0.27 1.50 1.00 0.30 0.27 1.9 0.0 1.9 1.9
CPC 600
OUTLET 0.40 0.50 0.20 0.27 1.40 1.00 0.30 0.27 1.4 0.0 1.4 1.4
1+500 INLET 1.40 1.40 0.65 0.30 1.60 1.50 0.45 0.30 4.6 0.0 4.6 4.6
CPC 900
OUTLET 1.50 0.90 0.80 0.30 2.10 1.70 0.45 0.30 5.0 0.0 5.0 5.0
Kanyangeya
0+050 INLET 0.60 0.40 0.10 0.28 1.85 0.90 0.30 0.30 1.7 0.0 1.7 1.7
CPC 600
OUTLET 0.60 0.45 0.20 0.26 1.76 1.05 0.30 0.30 1.9 0.0 1.9 1.9
0+430 INLET 0.50 0.97 0.30 0.30 2.07 1.30 0.45 0.30 2.8 0.0 2.8 2.8
CPC 900
OUTLET 0.70 0.50 0.30 0.20 2.09 1.25 0.45 0.30 2.5 0.0 2.5 2.5
1+700 INLET 0.60 0.60 0.30 0.20 1.80 1.00 0.30 0.20 2.1 0.0 2.1 2.1
CPC 600
OUTLET 0.80 0.80 0.40 0.20 1.70 1.00 0.30 0.20 2.4 0.0 2.4 2.4
2+300 INLET 0.60 0.50 0.20 0.26 2.00 0.90 0.30 0.30 1.9 0.0 1.9 1.9
CPC 600
OUTLET 0.70 0.80 0.20 0.27 1.80 1.00 0.30 0.27 2.2 0.0 2.2 2.2
3+120 INLET 0.45 0.50 0.20 0.27 1.65 0.85 0.30 0.27 1.4 0.0 1.4 1.4
CPC 600
OUTLET 0.80 0.45 0.25 0.22 1.50 1.00 0.30 0.22 1.7 0.0 1.7 1.7
Kyondo
0+156 INLET 0.80 0.70 0.40 0.30 1.00 1.40 0.30 0.30 2.0 0.0 2.0 2.0
CPC 600
OUTLET 0.80 0.50 0.40 0.30 1.20 1.50 0.30 0.30 2.1 0.0 2.1 2.1
0+800 INLET 0.80 0.80 0.35 0.29 1.55 0.95 0.30 0.29 2.1 0.0 2.1 2.1
CPC 600
OUTLET 0.25 1.00 0.25 0.30 1.30 1.00 0.30 0.30 1.5 0.0 1.5 1.5
0+980 INLET 1.00 0.80 0.30 0.26 1.30 1.00 0.30 0.26 2.1 0.0 2.1 2.1
CPC 600
OUTLET 1.50 0.50 0.60 0.30 1.50 1.19 0.30 0.30 2.6 0.0 2.6 2.6
1+200 INLET 0.30 0.70 0.30 0.30 1.35 0.90 0.30 0.30 1.4 0.0 1.4 1.4
CPC 600
OUTLET 0.90 0.70 0.40 0.30 1.60 0.90 0.30 0.30 2.1 0.0 2.1 2.1
2+300 INLET 0.70 0.40 0.50 0.30 1.65 1.00 0.30 0.30 1.8 0.0 1.8 1.8
CPC 600
OUTLET 0.60 0.40 0.30 0.30 1.60 0.90 0.30 0.30 1.5 0.0 1.5 1.5
Total Cluster 1 to BoQ 81.1 0.0 81.1 81.1
................................................. ….....................................
Contractor Supervisor
Date.................................... Date...............................
RECORD OF SITE MEASUREMENTS AND CALCULATION OF QUANTITIES
REHABILITATION OF MBABU ROAD (1.5KM), KANYAGEYA (3.5KM), KYONDO (2.3KM), LUGOKI ROAD (1.05KM), NSENYI – MUGHENDE – KAJWENGE (4.0KM), KISINGA – MUGHENDE (2.1KM)
PROJECT
AND NGOLERANDI SPUR (0.5KM) IN KASESE DISTRICT; TOTAL LENGTH = 14.95KM
MONTH Oct-20
CONTRACT NO. MoWT/Wrks/IP/19-20/027
CONTRACTOR Surface water Drainage
BILL NO 21 Surface Water Drainage
ITEM
22.10 (a) Steel Reinforcement, High tensile steel bars (T16)
DESCRIPTION
h d
b
a c
Cluster 1: Mbabu Road (1.7 km), Kanyageya (3.5 km), Kyondo (2.5 km), Kalenge Road (0.9 km); Total Length = 8.6 km
WINGWALLS HEADWALL
CHAINAGE TYPE
SIZE POSITIO a Dimensions
b No of Bars (pcs) Length of Bars (m) c Dimensions No of Bars Length of Bars (m)
(Ø mm) N Thick d Thick
Nn Total Np Nr Ln Lp Lr R Total Nk Nl Total Nm Nq Lk Ll Lm Lq
Horizontal (m) Vertical Horizontal
(m) (m) (m)
(m) (m) Mbabu (m)
CHAINAGE TYPE
SIZE POSITIO a Dimensions
b No of Bars (pcs) Length of bars (m) c Dimensions No of Bars (pcs) Length of Bars (m)
(Ø mm) N Thick d Thick
Nn Total Np Nr Ln Lp Lr R Total Nk Nl Total Nm Nq Lk Ll Lm Lq
Horizontal (m) Vertical Horizontal
(m) (m) (m)
(m) (m) Ngolerandi Spur (m)
Nsenyi - Mughende - Kajwenge
3+700 INLET 2.60 2.30 1.80 0.25 30.00 34.00 6.00 28.00 60.13 14.40 26.95 3.70 3.10 1.25 0.30 24.67 16.00 8.00 20.00 8.00 12.00 10.40 25.60 10.40 45.60
SPC 2500 X 2
OUTLET 2.60 2.30 1.80 0.25 30.00 34.00 6.00 28.00 60.13 14.40 26.95 3.70 3.10 1.25 0.30 24.67 16.00 8.00 20.00 8.00 12.00 10.40 25.60 10.40 45.60
Total length 224.49 53.40 104.20 74.00 131.20 79.60 253.30
Total mass tones 0.20 0.05 0.09 0.07 0.12 0.07 0.22
Total Cluster 2 to BoQ 0.82
CONTRACTOR DISTRICT ENGINEERS REPRESENTATIVE CONTRACT MANAGER
Name
Signature
Date