Академический Документы
Профессиональный Документы
Культура Документы
www.SipsEco.co.uk
INTRODUCTION TO SIPS ECO PANELS GENERIC FOUNDATION LOCATION PLAN (FLP)
CONTENTS IMPORTANT INFORMATION
FOUNDATION LOCATION PLAN 2 ■ S ips Eco Panels are pre-engineered, insulated, load bearing panels, which form
the exterior envelope of the building.
TYPICAL EXTERNAL ■ Sips Eco Panels replace traditional construction methods by combining structure,
WALL CONSTRUCTION 3 insulation, air and vapour barriers into one component.
EXTERNAL SOLEPLATE DETAIL 4 ■ Air leakage associated with traditional construction and timber frame is virtually
eliminated when using Sips Eco Panels. The insulation is continuous eliminating
INTERNAL SOLEPLATE DETAIL 5 thermal bridges and providing the end user with comfort and low energy costs.
■ Sips Eco Panels are stronger than conventional timber frame construction.
SOLEPLATE UPSTAND IMAGES 6 They are recognised for resistance to lateral loads caused by high winds and NON SHADED WALL
even earthquakes. DENOTES NON-LOAD
HOLDING DOWN STRAP DETAILS 6
■ Sips Eco Panels are lightweight and easy to install, but they sound solid. This BEARING WALL
STEEL POST UPSTAND DETAIL 7 means a solid andconsistent quality.
■ The speed of assembly combined with energy savings benefits and eco friendly
STEEL POST FIXING PROCEDURE 8 construction makes them the logical choice.
■ Sips Eco Panels are composed of expanded polystyrene insulation laminated DENOTES STEEL POST
PANEL TO PANEL CONNECTION 9
between 2 sheets of OSB (oriented strand board). AND POINT LOAD
OPENINGS AND FIXINGS 10 ■ The strength of all connection details and components that tie Sips Eco Panels
to all other structural elements must be selected to ensure adequate vertical
JUNCTION DETAILS 11 and horizontal load paths within the structure.
■ The specification and design of these items must be determined by the building
METAL WEB JOISTS IMAGES 11
engineer responsible for the stability of the building. Guidance on the design of
JOIST DETAILS 12 connection details must be sought from Sips Eco Panels
■ In general Sips Eco Panels do not incorporate lintels. Spanning over openings SHADED WALL DENOTES
WINDOW FIXING DETAILS 13 is achieved through the use of rim beams at floor or roof level. The sizing and LOAD BEARING WALLS
bearing of the spanning rim beam shall be determined in the design process.
ROOF DETAILS 14 In some cases lintels will be required below high point loads.
ROOF PURLINS SUPPORTING ■ Sips Eco Panels are packaged for weather protection. When they arrive on site,
ROOF PANELS 14 they should be stored on level blocking. They must be protected from rain,
snow or morning dew. By taking these measures, the panels will be easier
RENDER SYSTEM WITH NO CAVITY 15 to install.
■ Panels are joined together using splines. The panel joints must be structurally
CONSTRUCTION METHODS fastened to ensure the integrity of the panel system
FOR Sips Eco Panels 16 ■ Panel annotations (where relevant) on drawings show a reference number and
VERSATILITY OF Sips Eco Panels 16 this number must face to the outside of the building when panels are being
installed.
INNOVATIVE DESIGNS ■ Screws are used to fasten panels.
WITH Sips Eco Panels FC ■ Please read the manual and consult the manufacturer for instructions.
■ Read the manual in numerical order.
i1
ISSUE 9
■ Cut out openings for windows and doors without approval from manufacturer. the system.
GENERIC FOUNDATION
2014
GENERIC TYPICAL EXTERNAL WALL BUILD UP GROUND FLOOR EXTERNAL SOLEPLATE DETAIL
THE EXTERNALTHE
WALL CONSISTS
EXTERNAL OF TWO
WALL PARTS;OF TWO PARTS;
CONSISTS Sips Eco Panels recommends the brickwork should not be started
THE Sips
THE LOADBEARING Eco PanelsSips
LOADBEARING Eco
& THE PanelsCLADDING
OUTER - THIS
& THE OUTER MAY BE A- THIS
CLADDING HEAVYWEIGHT CLADDING SUCH
MAY BE A HEAVYWEIGHT AS
CLADDING SUCH AS
BRICKWORK SUPPORTED
BRICKWORK INDEPENDENTLY OFF OF FOUNDATIONS,
SUPPORTED INDEPENDENTLY OR A LIGHTWEIGHT
OFF OF FOUNDATIONS, OR ACLADDING ATTACHED
LIGHTWEIGHT TO ATTACHED TO
CLADDING before the sips frame has been erected.
THE TIMBER FRAME SUCH AS;
THE TIMBER RENDER,
FRAME SUCH HANGING TILESHANGING
AS; RENDER, OR TIMBER BOARDING.
TILES OR TIMBER BOARDING. Restraint straps (supplied by Sips Eco Panels
to be fixed at 1200mm c/c. built into brickwork
Sips Eco PanelsSips Eco Panels and set below lean mix concrete cavity fill (if
required). these must be fitted by bricklayer to
suit brick courses. d.p.m lapped wi
Sips Eco Panels
BATTENS FOR SERVICE
BATTENSVOID
FOR SERVICE VOID
(WHERE REQUIRED).
(WHERE REQUIRED).
open perpends
Restraint straps (supplied by Sips Eco Panels at 1500mm c/c
to be fixed at 1200mm c/c. built into brickwork screed on
and set below lean mix concrete cavity fill (if vapour barrier on
VAPOUR CONTROL LAYER
VAPOUR CONTROL LAYER required). these must be fitted by bricklayer to insulation on
suit brick courses. d.p.m lapped with wall vapour barrier on
(VCL) [BEHIND] (VCL) [BEHIND]
structural base
FLOOR FINISH FLOOR FINISH
FFL
ground level 150mm below lowest timber D.P.C.
OPEN PERPENDS TO PERPENDS TO
OPEN D.P.C.
min.150
min. 225
VENTILATE ANDVENTILATE
DRAIN AND DRAIN
cavity
THE CAVITY SPACED
THE CAVITY SPACED
clear
AT MAX. 1500mm
ATC/C
MAX. 1500mm C/C
EXTERNAL
open perpends
at 1500mm c/c 440 x floor f
SIMPSON STRONGTIE
SIMPSONSWT50 WALL SWT50 WALL
STRONGTIE Concrete Blo
TIES OR SIMILAR SPACED
TIES AT MAX
OR SIMILAR SPACED AT MAX D.P.C. bedding - to
600c/c HORIZONTALLY AND 450c/c
600c/c HORIZONTALLY AND 450c/c also be used
300 min.
VERTICALLY. VERTICALLY. min 225mm ventilated void
N.B. The blo
FFL to suit ground conditions.
ground level 150mm below lowest timber D.P.C. amount due
FINISHED FINISHED D.P.C. and the erec
min.150
over the out
min. 225
GROUND GROUND
cavity
DPC DPC water pondin
clear
LEVEL LEVEL
EXTERNAL WALL that to avoid
VENTILATED VENTILATED 440 x floor finish x wall width. 7N/mm2 Dense and frame (c
CAVITY CAVITY DPC Concrete Blocks, Density 1950kg/m3 on 15mm Mortarmay query th
SOLEPLATE - THIS PROVIDES
SOLEPLATE A LEVEL
- THIS PROVIDES A LEVEL DPC FLOOR DPM LAPPED
FLOOR DPM LAPPED
300 min.
min 225mm ventilated void
WHICH THE SUPERSTRUCTURE WILL BE FIXED, WILL BE FIXED,
WHICH THE SUPERSTRUCTURE TO LAP WITH VAPOUR
TO LAP WITH VAPOUR to suit ground conditions.
N.B. The block may overhang the cavity by a small
INCLUDING THEINCLUDING
FLOOR IN THE
THECASE
FLOOROFIN THE CASE OF CONTROL LAYER.
CONTROL LAYER. amount due to difference in width from the SIP panel
and the erectors must ensure that the DPC is lapped
SUSPENDED TIMBER GROUND
SUSPENDED FLOORS.
TIMBER GROUND FLOORS.
over the outside face of the coursing bricks to stop
IT ALSO PROVIDES A NAILING
IT ALSO PLATE
PROVIDES FOR
A NAILING PLATE FOR water ponding on top of the overhang. It is possible
THE SIPS PANEL AND
THE PROTECTS
SIPS PANEL AND THEPROTECTS
DPC. THE DPC. that to avoid this the block could be flush with the floor
and frame (cavity side), but a Building Inspector
THE CONSTRUCTION
THE CONSTRUCTION
OF EXTERNAL WALLS
OF EXTERNAL
MUST COMPLY
WALLS MUST
WITH COMPLY WITH may query the internal cold bridge - this should be
Work to written
SOLEPLATE
APPROVED DOCUMENT
APPROVED B OF
DOCUMENT
THE BUILDING
B OFREGULATIONS
THE BUILDING IN
REGULATIONS
MANY IN MANY
dimensions only. Inspector.
CASES. PARTICULARLY
CASES. PARTICULARLY
IF THE CLADDING
IF THE
IS COMBUSTIBLE
CLADDING IS AND
COMBUSTIBLE AND
WITHIN 1M OF THE
WITHIN
BOUNDARY,
1M OF THEWITH
BOUNDARY,
PARTICULAR
WITH
ATTENTION
PARTICULARTO ATTENTION TO DO NOT SCALE.
i2 i2EXTERNAL
ISSUE 9
ISSUE 9
2014
EXTERNAL
WALL BUILD
WALL BUILD
UP UP This drawing is to be read in conjunction with the Building Regulations notes and
drawings.
House
For foundation setting out refer to foundation setting
location out(FLP).
plan relies on (FFL) Finished Floor Level = external DPC level.
This drawing shows traditional trench fill Top
foundations and is may
of soleplate not site specific.Floor
require cutting and
out at internal and external door positions.
foundation depths/design to be approvedNo by brickwork
the buildingisinspector and to suit local DPC level (to external cavity skin) until after
to be constructedbelow
ground conditions.
the SIP frame has been erected (to ensure that a nominal 50mm cavity is maintained
This drawing is to be read in conjunction with the Building Regulations notes and
drawings. between sip frame and outer skin).
House setting out relies on (FFL) Finished Floor Level = external DPC level.
Upstands must be dense concrete blocks or concrete. These are Top of soleplate may require cutting out at internal and external door positions.
No brickwork is to be constructedbelow DPC level (to external cavity skin) until after
built to the same height as the finished floor for external and the SIP frame has been erected (to ensure that a nominal 50mm cavity is maintained
internal walls. between sip frame and outer skin).
Work to written dimensions only. DO NOT SCALE. If in doubt ask.
7N Insulation
BLOCK
dense 7N
150
Insulation DPM lapped
INSULATION
7N dense
concrete GROUND
with DPC
DPM Insulation
DPM dense concrete
block DPM
DPM
LEVEL
Concrete slab block
concrete STRUCTURAL Alternative holding
DPM Concrete slab DPM BASE
block down detail.
Concrete slab D.P.C. Fischer FBS6 concrete
screw or equal and
approved to give safe
working uplift force ˃ 3KN
i6
ISSUE 9
Work to written dimensions only. DO NOT SCALE. If in doubt ask. Work to written dimensions only. DO NOT SCALE. If in doubt ask.
DETAILS
01787 377388 admin@sipseco.co.uk SipsEco.co.uk Self Installation Manual: Issue 9. 2015
5 6
STEEL POST UPSTAND DETAIL STEEL POST FIXING PROCEDURE
80
finished floor level. A DPC is fitted and then the steel post be positioned vertically plumb by using steel shims.
up by others
FFL
base plate is positioned.
ground level
80
by others
ground level
up build
Floor
Floor build
STEEL COLUMN DETAIL-SECTION
With the steel base plate in position, holes are drilled into the Bolts are slotted into the holes and left to set in position in
padstone and then filled with resin. the resin.
Reinforced concrete pad
(Designed by others)
Reinforced concrete pad
(Designed by others)
fillet weld
fillet weld
STEEL POST
7 8
4
300 min
Should laps be necessary in
300
breather paper, the upper
Should layers
laps be should
necessary
bein lapped
breather paper, the upper
horizontally
layers should be lapped
over lower layers
splines and rails fitted into 45mm deep rebates horizontally over lower layers and
by at least 100mm
a
around edge of panels and screwed at 200c/c staggered.
by at least 100mm and The sheets should
top railThe sheets should
staggered.
be lapped at least 150mm
2397
2397
be lapped at least 150mm
vertically. b
a
vertically. Cross section 300 b
or
Should laps be necessary in 750
Min
breather paper, the upper
layers should be lapped
horizontally over lower layers
by at least 100mm and 2394 2394
SCREW 35
staggered.35 The sheets should
X 3.5mm
at least SCREW
be lappedwoodscrews 150mm
for fixing
35
35 X 3.5mm
vertically.panels to splines and
woodscrews
top and bottom plates for fixing
at 200mm panels
crs and to splines and
50mm in from
topend.
and bottom plates
at 200mm crs and
50mm in from end.
BOTTOM RAIL SCREW 35
35 X should
3.5mm on
breather paper cti
be lapped woodscrews
over the for fixing se
i9
ISSUE 9
erection. It should be fitted strictly in accordance with manufacturer's instructions. Below is Ifthe object is not suitable for mounting
at regular intervals to prevent damage by wind. Nails should be galvanised, sheradizes or austenitic stainless steel,
bronze or silicon bronzeCONNECTION
a brief installation guide. directly onto a wall panel it should be
phosphor and staples should be of austenitic stainless steel. To prevent damage by wind,
The breather membrane should be fitted with the silver side facing out and in such a way as to shed water away from A heavy object such as a boiler attached separated by a 75mm gap or an
fixingsthe
should be at regular
sheathing and below the lowest intervals oftimber.
not more than
Upper 500mm
layers shouldc/c.
be Itlapped
is essential that over
horizontally the lowest timbers
lower layers in least
by at the wall are to the wall. The object should be fitted additional layer of 12.5mm plasterboard
protected by the breathable membrane.
100mm and staggered. The sheets should be lapped at least 150mm vertically. Membrane should be nailed or stapled using fully threaded screws/nails. [25mm total].
If gapsatare evident
regular in roof
intervals panels damage
to prevent these should beNails
by wind. filledshould
with expanding
be galvanised,foam.
sheradizes or austenitic stainless steel, 100kg x 1000mm x 250mm
phosphor bronze or silicon bronze and staples should be of austenitic stainless steel. To prevent damage by wind, PLAN CROSS SECTION
Work to written dimensions only. DO NOT SCALE. If in doubt ask.
fixings should be at regular intervals of not more than 500mm c/c. It is essential that the lowest timbers in the wall are Work to written dimensions only. DO NOT SCALE. If in doubt ask.
protected by the breathable membrane.
i9
ISSUE 9
i10
ISSUE 9
PANEL TO PANEL
If gaps are evident in roof panels these should be filled with expanding foam.
OPENINGS AND
ISSUE 2014
2014
CONNECTION
Work to written dimensions only. DO NOT SCALE. If in doubt ask.
FIXINGS
Work to written dimensions only. DO NOT SCALE. If in doubt ask.
i9
9
PANEL TO PANEL
2014
JUNCTIONS DETAILS
EXTERNAL CORNER
FLOOR JOIST DETAILS
ESCR8.0x200mm screws
used for fixing SIPs wall
claddingEXTERNAL CORNER
panels to wall panels at
300mm c/c and 100mm in cladding
EXTERNAL CORNER
ESCR8.0x200mm
from topscrews
& bottom of panel
cladding used for fixing SIPs wall PAS 90 @ 300mm
ESCR8.0x200mm screws c/c into rim beam
panels to wall panels at SCREW 51
used for fixing SIPs wall cladding
300mm c/c and 100mm in 3.9 x 65mm grey
wallpanels
panels to wall panelsat at
from top & bottom of panelcladding phosphate at 300mm
300mm c/c and 100mm in
c/c for fixing flooring to
ESCR8.0x200mm
from top & bottom of panel screws
joists all around the
used for fixing SIPs wall
perimeter.
panels to wall panels at bottom rail first floor Sips Eco
300mm c/c and 100mm in Panels sit onto
from top & bottom of panel flooring
Sips Eco Panels SCREW 41
Sips Eco Panels 3.5 x 35mm grey
SCREW 51 phosphate at 200mm c/c
at 200mm and 50mm in from end
Sips Eco Panels c/c 1st floor joists
T Junction -
i11
ISSUE 9
internal partition
BENEFITS OF METAL WEB JOISTS
DETAILS
Work to written dimensions only. DO NOT SCALE. If in doubt ask.
i11
ISSUE 9
JUNCTIONS
2014
i11
ISSUE 9
JUNCTIONS
DETAILS
2014
T Junction -
internal partition
11
ISSUE 9
internal partition
JUNCTIONS
Plumbing is more easily fitted and manoeuvered in all directions MVHR (Mechanical Ventilation Heat Recovery)
2014
i12
ISSUE 9
i11
ISSUE 9
JUNCTIONS
2014
TYPICAL EAVES
ROOF PANELS FIXED
DOWN USING ESCR8.0x260
(NO CEILING)
Sips Eco Panels
20 HEADBINDER FIXED
WITH ESCR8.0x100 OR
SIMILAR AT 400mm c/c.
STAINLESS STEEL
SIMPSON STRONGTIE
SWT50 TIMBER EXTENDED RAFTER
CUT TO SUIT ON SITE BREATHER
FRAME WALL TIES AT Sips Eco Panel
ROOFING
JAMB TO BE SPACED MEMBRANE
PLASTERBOARD & SEALANT
AT 225mm c/c TYPICAL EAVES
VERTICALLY
VCL CONTINUES (NO CEILING)
AROUND JAMB. TIMBER JAMB PURLIN POSITIONED
WINDOW/DOOR CILL
TO SUIT DESIGN
CAVITY BARRIER A 400mm STRIP OF VCL MUST
NAILED TO JAMB BE FITTED BEFORE THE
STUDS AND FITTED ROOF PANEL FIXED DOWN PARTITION IS CONNECTED.
WITH DPC USING ESCR8.0x260 AT
400mm c/c TIMBER WEDGE FIXED
WITH ESCR8.0x100 AN
DOOR AND WINDOW FIXED
TO FRAME USING
PAS 90 TIMBER WEDGE FIXED
400mm c/c
i15PURLINS SUPPORTING
ISSUE 9
WHERE REQUIRED ESCR8.0 x100 AT 400mm c/c
D.P.C. DRESSED INTO
2014
RECESS IN FRAME AND FOR SHORT CILLS. EXTENDED
ROOF DETAILS
ROOF PANELS
STAPLE FIX TO BATTEN RAFTER CUT TO
LAP WITH VCL. SUIT ON SITE 45mm x 95mm PARTITION
i15
ISSUE 9
ROOF DETAILS
STUDS AND FITTED
WITH DPC
ELEVATION
Work to written dimensions only. DO NOT SCALE. If in doubt ask.
i14
ISSUE 9
WINDOW FIXING
Work to written dimensions only. DO NOT SCALE. If in doubt ask.
2014
01787 DETAILS
377388 admin@sipseco.co.uk SipsEco.co.uk Self Installation Manual: Issue 9. 2015
13 14
RENDER SYSTEM WITH NO CAVITY CONSTRUCTION METHODS FOR SIPS ECO PANELS
GENERAL APPICATION GUIDANCE - To be read in conjunction with the following data sheets;
PAREXDIRECT Acrylic render system
Maite Monocomposant
310 Primer, DPR finishes
95mm x 45mm timber studwork is used to construct internal Walls Sips Eco panels can easily be used to create curved walls
355 AVUmesh
WeatherTech Weatherseal Spray and Roll-On
DPR Textured Finishes
Paraguard AG
Knauf Aquapanel product and fixing information VERSATILITY OF SIPS ECO PANELS
Sips Eco Panels Building System Sips Eco panels are so easy to handle they can be used to build in the tightest situations.
DuPont SOFT
BREATHER
MEMBRANE
KNAUF AQUAPANEL
CEMENT BOARD
SIPS ECO panels can be used for house boats floating on the
RENDER BASE COAT water and supported on a steel hull
MESH
PRIMER
PAREXDIRECT
ACRYLIC RENDER
i17
ISSUE 9
NO CAVITY
4 houses were built at other end of this arch. Panels were carried
through and then erected.
PLEASE CONTACT OUR TECHNICAL DEPARTMENT WITH ANY QUERIES OR VISIT OUR WEBSITE
WWW.SIPSECO.CO.UK
Ground floor walls being erected First floor joists fitted
Sips Eco Panels, easi-wall system and easi-roof system, are an advanced yet affordable form of construction that
arrive on site pre-insulated and replace timber frame, blockwork or trusses for houses, extensions, garden rooms
and other forms of construction.
Panels are manufactured in our own factories and can be supplied as blank panels or pre-cut to suit.
Our panels have full third party accreditation and technical information is available on our web site
Sips Eco Panels offer air-tightness that is far superior to current Building Regulations, with U-values down to 0.12
in one layer through the whole wall structure, making homes super insulated - ensuring low running costs.
It is important all fixings are used properly to maintain the air-tightness benefits the system offers.
The details and information in this manual are for guidance of the erection of panels and flooring only. They
Roof on Dream Home
are not site specific. Refer to the relevant panel drawings for the site, which should be read in conjunction with
the approved Building Regulation drawings and must be adhered to and take priority over standard details. For
sundry items refer to Sips Eco Panels Construction Manual.
SipsEcoPanels
South Suffolk Business Centre
Alexandra Road, Sudbury,
Suffolk CO10 2ZX
Tel: 01787 377388
admin@sipseco.co.uk
Registered in England No 03722506
3661/SBM/0115
www.SipsEco.co.uk