Академический Документы
Профессиональный Документы
Культура Документы
1. Purpose
This method of statement is the control document as well as the instructions manual for
the application of Paint Work for Jabal Omar Development Programm - Project.
2. References
Sections Internal Painting-09660
Matrial Submittal
3. Equipments / Tools
Scrapper.
Trowel.
Roller.
Paint Brushes.
Sanding Paper.
Plastic Sheets.
5. Materials
Subject to compliance with requirements:
Proposed System
PENGUARD CLEAR SEALER 1 Coat @ DFT 50 Microns by Spray/Roller
/Brush
7. Site Inspection
Up on arrival of materials on site, the supervisor shall check the delivery note and
conduct a visual inspection of the delivery for the quantity and any patently obvious
damage. After checking the quantity the Supervisor shall inform the Quality Control
Engineer to conduct inspection for the quality of materials, if the inspector Deemed
that material have complied with Kocache own QA/QC inspection, we will then
complete the Material Inspection Report which shall be conducted by Consultant.
8. Application
8.1 Examination
Prior to commencement of Painitng Application Kocache Will Submit
Request to start (R.T.S.) to Consulatnt to obtain the approval to start the
Application for the mentioned Area in the request.
Kocache Enterproses Ltd Page 3
Document No: JODP MS05
Issue Date: Nov 2014
Iss: Rev: 0
Rev: App:
After that Kocache should received copy from the approved inspections
attached with the clearance form Consultant to start the Application of
paint.
In case of any defects will be found a (NCR) will be submitted to the
Engineer to take the necessary action.
Concrete substrate must be fully cured, sound clean, dry and free from any
contamination such as laitance, loose particle, oil, grease, curing compound, shuttering
oil, algae growth etc. Recommended pre-treatment methods are light grit blasting
(Sweep blasting).
Unsound concrete, blowholes, pinholes and other surface defects should be repaired
using approved repair products/systems. The moisture content in the concrete substrate
must be = 6% by volume.
1. Mix 4 parts of Penguard Clear Sealer Comp A with 1 part of Penguard Clear Sealer
comp. B
and wait for 30 minutes for induction.
2. Apply one full coat of Penguard Clear Sealer on the entire surface ( If required, can be
thinned up to 5% with thinner # 17) to a Wet Film thickness(WFT) of 115 microns
which
corresponds to Dry Film Thickness(DFT) of 50 microns .
3. The Penguard Clear Sealer shall be applied directly from the can after stirring and
should be
used within 8 hours after mixing and allowed to dry.
4. Mix 4 parts of Penguard Top Coat Comp. A with 1 part of Penguard Top Coat comp
B.
5. Apply 1st coat of Penguard Top Coat ( If required, can be thinned up to 5% with
thinner # 17)
to a Wet Film thickness(WFT) of 100 microns which corresponds to Dry Film
Thickness(DFT)
of 50 microns
6. Broadcast Jotafloor Non-Slip Aggregate evenly onto the wet surface of Penguard Top
Coat until
total coverage is achieveddry.
7. Apply the 2nd Coat of Penguard Top Coat as above to the same thickness. Follow
recoat
interval as per substrate temperature mentioned in the TDS.
8. The Penguard Top Coat shall be applied directly from the can after stirring and should
be used
within 8 hours after mixing and allowed to dry.
9. During application please ensure that the application guidelines related to temperature,
relative
humidity and dew points are strictly followed as per the Technical data sheet of the
above
products. (Refer to TDS)
10. Good ventilation is required in confined areas to ensure proper drying. The coating
should not
be exposed to oil, chemicals or mechanical stress until cured.
Inspection request (I.R) with the checklists after the application of putty and
after the application of finish coats to Consulatnt
Upon receipt of the said document Kocache will rectify the defects /snags
immediately as notified by the inspector.
Conduct final inspection until final approval and acceptance.
13. Mock-Up
Kocache will undertake the specified size Mock Up prior to commencement of the overall
application and offer the area for inspection via IR.
14. Safety
Prior to commencing any activity, the work force shall receive a Toolbox talk on the
project site safety regulations by the foreman. Any process that is adopted but may have
a particular safety risk will be assessed and addressed as required. All the hazards and
the corresponding safety precautions in the respective Risk assessment shall be adhered
to and communicated to the workers before starting work.
Ref. no. Bldg Level Item description S/C initials Date M/C initials Date Comments
This notification is issued because no action has been taken following verbal/ written request made
about deficient material and/or workmanship.
Works Subcontractor/Supplier:
Work Package:
TO BE SIGNED BY SUBCONTRACTOR/SUPPLIER
Signed:
Recommended action:
Name: Signed:
Position: Project Manager
KOCACHE Date:
ENTERPRISES LTD Snag List Form Contract ref:
Riyadh - KSA
Site Code: Lot No.: Enterprise:
Site Name: JABAL OMAR DEVELOPMENT PROGRAM Description: Code:
Tower
Lifting Approval of Comment Lifting
Comment Bldg Level Comment Description Reason for Not Lifting
Date SPM CONS QA/QC
10
11
12
13
14
Note: MC CONS QC/QA Subcontractor
Lifting date should not exceed one month from Comment date
RIYADH, KSA
Location/ Area:
Date:
Architectural
Structural
Electrical
Mechanical
Surveyor
Others
Subcontractor
Prepared by: Noted;
main Contractor
Approved by: Comments
In charge
In charge