|COMPARACIÓN DEL CAE PARA UN PROYECTO DE PAVIMENTACIÓN DE CALLES CON DOS

POSIBLES ALTERNATIVAS: CONCRETO HIDRÁULICO Y ASFALTICO.


CONCRETO HIDRÁULICO.
Periodo Año Inversión Balizamiento Reparación de juntas Costo de supervisión Valor de rescate Total de costos VPC
0 2019 $6,154,261.10 $184,627.83 $6,338,888.93 $6,338,888.93
1 2020 $35,567.35 $35,567.35 $32,333.95
2 2021 $35,567.35 $35,567.35 $29,394.50
3 2022 $35,567.35 $35,567.35 $26,722.28
4 2023 $35,567.35 $75,456.50 $2,263.70 $113,287.55 $77,376.92
5 2024 $35,567.35 $35,567.35 $22,084.53
6 2025 $35,567.35 $35,567.35 $20,076.84
7 2026 $35,567.35 $35,567.35 $18,251.67
8 2027 $35,567.35 $35,567.35 $16,592.43
9 2028 $35,567.35 $75,456.50 $2,263.70 $113,287.55 $48,044.98
10 2029 $35,567.35 $35,567.35 $13,712.75
11 2030 $35,567.35 $35,567.35 $12,466.14
12 2031 $35,567.35 $35,567.35 $11,332.85
13 2032 $35,567.35 $35,567.35 $10,302.59
14 2033 $35,567.35 $75,456.50 $2,263.70 $113,287.55 $29,832.15
15 2034 $35,567.35 $35,567.35 $8,514.54
16 2035 $35,567.35 $35,567.35 $7,740.49
17 2036 $35,567.35 $35,567.35 $7,036.81
18 2037 $35,567.35 $35,567.35 $6,397.10
19 2038 $35,567.35 $75,456.50 $2,263.70 $113,287.55 $18,523.42
20 2039 $35,567.35 -$1,230,852.22 -$1,195,284.87 -$177,671.48
TOTALES $6,154,261.10 $711,347.00 $301,826.00 $193,682.63 -$1,230,852.22 $6,130,264.51 $6,577,954.42

(ANUALMENTE SE VA A GASTAR) CAE= $772,644.06

CONCRETO ASFALTICO.
Total de costos(
Periodo Año Inversión Balizamiento Baches Riego de sello Reencarpetamiento Costo de supervisión Valor de rescate VPC
inversión+mantenimiento)
0 2019 $5,190,068.00 $155,702.04 $5,345,770.04 $5,345,770.04
1 2020 $35,567.35 $303,799.05 $9,113.97 $348,480.37 $316,800.34
2 2021 $35,567.35 $303,799.05 $9,113.97 $348,480.37 $288,000.31
3 2022 $35,567.35 $423,658.20 $303,799.05 $21,823.72 $784,848.32 $589,668.16
4 2023 $35,567.35 $303,799.05 $9,113.97 $348,480.37 $238,016.78
5 2024 $35,567.35 $303,799.05 $9,113.97 $348,480.37 $216,378.89
6 2025 $35,567.35 $1,389,425.35 $41,682.76 $1,466,675.46 $827,900.06
7 2026 $35,567.35 $303,799.05 $9,113.97 $348,480.37 $178,825.53
8 2027 $35,567.35 $303,799.05 $9,113.97 $348,480.37 $162,568.67
9 2028 $35,567.35 $423,658.20 $303,799.05 $21,823.72 $784,848.32 $332,852.30
10 2029 $35,567.35 $303,799.05 $9,113.97 $348,480.37 $134,354.27
11 2030 $35,567.35 $303,799.05 $9,113.97 $348,480.37 $122,140.24
12 2031 $35,567.35 $1,389,425.35 $41,682.76 $1,466,675.46 $467,328.00
13 2032 $35,567.35 $303,799.05 $9,113.97 $348,480.37 $100,942.35
14 2033 $35,567.35 $303,799.05 $9,113.97 $348,480.37 $91,765.77
15 2034 $35,567.35 $423,658.20 $303,799.05 $21,823.72 $784,848.32 $187,886.45
16 2035 $35,567.35 $303,799.05 $9,113.97 $348,480.37 $75,839.48
17 2036 $35,567.35 $303,799.05 $9,113.97 $348,480.37 $68,944.98
18 2037 $35,567.35 $1,389,425.35 $41,682.76 $1,466,675.46 $263,794.47
19 2038 $35,567.35 $303,799.05 $9,113.97 $348,480.37 $56,979.33
20 2039 $35,567.35 $303,799.05 $9,113.97 -$519,006.80 -$170,526.43 -$25,347.67
TOTALES $5,190,068.00 $711,347.00 $1,270,974.60 $5,164,583.85 $4,168,276.05 $473,817.08 -$519,006.80 $16,460,059.78 $10,041,408.76

(ANUALMENTE SE VA A GASTAR) CAE= $1,179,460.11

Página 1 de 2
Conclusión

El proyecto que se debió elegir es la pavimentación con concreto hidráulico, debido que el costo ($772,644.06) es menor
a lo largo del proyecto, aunque la inversión sea mas alta. El mantenimiento es menor con concreto hidráulico y su
durabilidad es mucho mayor en con comparación con el asfalto.

Consideraciones generales.

i. El costo por supervisión es igual al 3% de los costos de los trabajos.


ii. No hay supervisión para el balizamiento, sólo para reparación de juntas, en concreto hidráulico.
iii. Hay supervisión
iv. El valor de rescate para el concreto asfaltico es del 10% de la inversión inicial.
v. El valor de rescate para el concreto hidráulico es del 20% de la inversión inicial.
vi. La fórmula para calcular el valor presente de los costos es la siguiente.
𝑉𝐹𝐶
vii. 𝑉𝑃𝐶 = (1+𝑟)𝑚
viii. A partir de la suma de los valores presentes de los costos durante los 20 periodos considerando el periodo cero.,
se determina el CAE (Costo Anual Equivalente).
ix.

𝑟(1 + 𝑟)𝑚
𝐶𝐴𝐸 = 𝑉𝑃𝐶 [ ]
(1 + 𝑟)𝑚 − 1

Donde

R Tasa de descuento social= 10% (FOPADEM)


m= Periodos

x. Para emplear el criterio del CAE es necesario comparar dos proyectos con el mismo nivel de beneficios.
xi. El CAE puede emplearse para proyectos con diferentes periodos.