Brief status of Progress of activities for Sasan UMPP-As on 31.01.

10

1.0 General:
Name of Developer –M/s Sasan Power Limited (Reliance Power Ltd.)
Date of LOI – 01.08.2007
Date of Transfer of SPV to developer – 07.08.2007
Date of signing of PPA (Effective date) –07.08.2007

2.0 Commissioning Schedule:

Unit Months from Schedule COD as Revised schedule of Scheduled COD as informed
No. the date of PPA worked out from date COD as per revised PPA during presentation in MOP
signing of signing of PPA signed by SPL and on 15.10.09*
(7.8.2007) Procurers on 15.10.2008
1. 69 06.05.2013 Dec. 2011 March. 2012
2. 76 06.12.2013 Mar. 2012 June , 2012
3. 83 06.07.2014 Jun. 2012 Sept , 2012
4. 90 06.02.2015 Sept. 2012 Dec, 2012
5. 97 06.09.2015 Dec. 2012 March, 2013
6. 104 06.04.2016 Mar. 2013 June, 2013

3.1 Land Acquisition status (Area in Acres)


Total Area Acquired

Main Plant 2034.46 1462.21


Ash pond 811.1 367.52
Colony 448.38 399.07
Misc. 52.364 ---
Coal Transportation 144.15
Total 3486.9 2228.8 (63.92%)

3.2 MOEF Clearance for Forest Land: Final Clearance from MOEF received on 16.04.09
for forest land of 773.1acres. Forest area of 363 acres has been handed over to SPL.

4.1 Coal Mine development:


Type of land Total Area Acquired Remarks
(acres) (acres)

Govt. Land 320.43 - Survey and land valuation completed for


Mohar and Mohar Amlohri.
For Chhatrasal- Revised application
submitted in Dec,08.
Pvt. Land 878.18 - Section 6 completed for entire area of
land for Mohar and Mohar Amlohri
blocks in Aug. 08.
For Chhatrasal- Revised application
submitted in Dec,08

-2-
Forest land 4913.64 - For Mohar and Mohar Amlohri blocks
stage-1 clearance received in Nov,09.
Applicaion for forest clearance of
Chhatrasal block submitted on 16.7.09.
Total 6112.25* -
* Excluding land for R&R

4.2 Environment Clearance for Coal Mine (Mohar and Mohar Amlohri): Environment
Clearance received on 10.12.08.
Forest Clearance for Coal Mine (Mohar and Mohar Amlohri): Stage I Clearance
received on Nov,09.
Environment Clearance for Coal Mine (Chhatrasal): Presentation to EAC made
on 25.11.2009. MOEF querries raised are being addressed.
Forest Clearance for Coal Mine (Chhatrasal): Application for forest clearance
submitted on 16.7.09

5.0 Development of Transmission Lines:


Signed on

Signing of BPTA for revised COD 15.10.08


Signing of PPA for revised COD 15.10.08
Transmission lines To be implemented by PGCIL

6.0 Others:
Remarks

Financial Closure Achieved on 20.04.09


Order for Main Plant Order placed on M/s SEC China, NTP issued to EPC
contractor on 1.7.08.
Order for BOP Yet to be awarded.
MGR Under discussion with suppliers.

7.0 Progress at site:


Construction of boundary wall at more than 65 % area, storage sheds are in
progress. Foundation work in Boiler, PH building, ESP, and Chimney in final stage. 33 KV
sub-station charged. 6.8 Km, 11 KV ring-man completed and charged. Balance is in
progress.

8.0 Status of Preconstruction Activities:


S. No. Activity Schedule Actual Status/Remarks
date Date
8.1.0 Studies & Investigation
8.1.1 Survey & Soil Investigation April 08 - Study in progress
8.1.2 Drainage Jul 08 Jun 08 Completed
8.1.3 Water intake study May 08 Jul 08 Completed
8.1.4 Bathymetric survey for May 08 Apr 08 Completed
intake water
8.1.5 Testing of construction Apr 08 Jul 08 Completed
material and mix design

-3-
8.1.6 Seismic study Jun 08 Jul 08 Completed
8.1.7 Ash pond leaching study Apr 08 Jul 08 Completed
8.1.8 Geo-hydrological study Apr 08 Feb 08 Completed
8.1.9 Logistic study Jun 08 Jul 08 Completed
8.1.10 MGR route study Dec 08 Aug 08 Completed
8.2.0 Engineering
8.2.1 Appointment of Apr 08 May 08 Consultant Appointed
engineering consultant
8.2.2 Appointment of Dec 08 - Lead procurer has issued NIT.
Independent Engineer
8.3.0 Pre-Award Works
8.3.1 Site Office, Stores & Apr 08 Package awarded
Miscellaneous Civil
Works
8.3.2 Boundary Wall/Fencing Feb 09 Apr 08 Package awarded
8.3.3 Site leveling Sep 09 Jun 08 Package awarded. Work in
progress.
8.3.4 General area lighting May 08 Jun 08 Package awarded
8.3.5 Construction colony Jan 09 - Tenders invited. Possession of
land delayed.
8.3.6 Construction water May 08 Dec 07 Package awarded
8.3.7 Construction power Apr 08 Apr 08 Package awarded
8.3.8 Labour Camp Nov 08 May 08 Package awarded
8.4.0 Financing
8.4.1 Appointment of Jun 08 Mar 08 Completed
advisor/arranger
8.4.2 Appointment Lender’s Jun 08 May 08 Completed
Engineer
8.4.3 ECB Approval Oct,08 April,08 In principle approval of RBI
received for raising ECBs of USD
2 Billion. Final approval obtained
from RBI for ECB of USD 486
Million tied up with IIFCL.

9.0 The activity wise time schedule communicated by SPL vide their letter dt 21.01.10:

S. No. Activity Start finish Status


1 Appointment of Engg. Consultant May-08 completed
2 Main Plant Vendor Finalisation Jun-08 completed
3 Zero Date (EPC Contract) 01-Jul-08 completed
4 Effective Date for BTG Vendor 26-Jul-08 completed
5 Area Grading (BTG area) 31-Jul-09 completed
6 Foundation work 31-Jul-09 First few Foundations
completed.
7 Boiler Structure Erection Start 01-Dec-09 Being started.
8 Boundary Wall 31-Dec-09 Revised to 31-Mar-10
9 Pressure Parts erection start 01-Jun-10 Revised to 01-Sep-10
10 Condenser Erection Start 01-Sep-10 Revised to 01-Dec -10
11 Turbine Erection Start 01-Nov-10 Revised 01-Feb -11

-4-
12 Switch yard Ready for Start Up 31-Dec-10 Revised to 31-Mar-11
Power - 400 KV
13 DM Plant commissioning (part) 15-Jan-11 Revised to 15-Apr-11
14 Boiler Hydro Test Complete 01-Mar-11 Revised to 31-Jul-11
15 Chimney Complete 30-Apr-11 Revised to 30-Jul-11
16 Boiler Light up 30-Jun-11 Revised to 31-0ct-11
17 Turbine Box UP 01-Aug-11 Revised to 01-Nov-11
18 Fuel Transportation System Ready 31-Aug-11 Revised to 31-Nov-11
19 Cooling Tower Ready 15-Sep-11 Revised to 15-Dec-11
20 TG Oil Flushing & Restoration 20-Sep-11 Revised to 20-Dec-11
21 TG on Barring Gear 22-Sep-11 Revised to 22-Dec-11
22 Ash Handling Plant Ready 30-Sep-11 Revised to 30-Dec-11
23 Coal Handling Plant Ready 30-Sep-11 Revised to 30-Dec-11
24 Steam Blow, SVF & Restoration 25-0ct-11 Revised to 25-Jan-12
25 Ash Dyke Ready 31-0ct-11 Revised to 31-Jan-12
26 Synchronization Unit 1 31-0ct-11 Revised to 31-Jan-12
27 COD Unit 1 31-Dec-11 Revised to March 2012
28 Synchronization Unit 2 31-Jan-12 Revised to 31-Apr-12
29 COD Unit2 31-Mar-12 Revised to June 2012
30 Synchronization Unit 3 30-Apr-12 Revised to 31-Jul-12
31 COD Unit 3 30-Jun-12 Revised to Sep. 2012
32 Synchronization Unit 4 31-Jul-12 Revised to 31-Oct-12
33 COD Unit4 30-Sep-12 Revised to Dec. 2012
34 Synchronization Unit 5 31-0ct-12 Revised to 31-Jan- 2013
35 COD Unit 5 31-Dec-12 Revised to March 2013
36 Synchronization Unit 6 31-Jan-13 Revised to 30-Apr- 2013
37 COD Unit 6 31-Mar-13 Revised to June 2013

-5-
Brief status of Progress of activities for Mundra UMPP-As on 31.01.10

1.0 General:
Name of Developer –Coastal Gujarat power Ltd (CGPL) of Tata Power Ltd.
Date of LOI – 28.12.2006
Date of Transfer of SPV to developer – 22.04.2007
Date of signing of PPA (Effective date) – 23.04.2007

2.0 Commissioning Schedule:


Unit Months from the Schedule COD as Revised schedule of COD as
No. date of PPA worked out from the per revised PPA signed by
signing date of signing of PPA CGPL and procurers on
(22.4.2007) 31.7.2008.
1. 64 Aug. 2012 Sept. 2011
2. 70 Feb. 2013 March 2012
3. 76 Aug. 2013 July 2012
4. 82 Feb. 2014 Nov. 2012
5. 88 Aug. 2014 March 2013

3.1 Land Acquisition status: (area in acres)

Sl. Type of Land Total area Area acquired


No
(i). Government Land 1240.42 1240.42
(ii). MSEZ land 541.14 541.14
(iii). Private Land 447.24 444.77
(iv) Forest Land 321.2 321.2
(v) Approach cum public Road 12.35 12.35
(vi) Others 662.21 -
Total 3224.6 2559.88

3.2 MOEF Clearance for Forest Land: Final Forest Clearance received on 10.6.09.

4.0 Development of Transmission Lines:


Actual/expected date

Signing of BPTA for revised COD 31.7.08


Signing of PPA for revised COD 31.7.08
Transmission lines Under Implementation by PGCIL

5.0 Others:
Financial Achieved on 24.4.08.
Closure
Order for i) For Turbo Generator – order placed on Toshiba Corporation of Japan
Main on 20.8.07
Plant ii) For Steam Generator order placed on Doosan Heavy Industries &
Construction Company, Korea on 15.5.07.
Order for All packages awarded.
BOP

-6-
6.0 Progress of work at site:
S. No. Activity Schedule Actual Status/Remarks
date Date
6.1.0 Boiler Structural
Erection
6.1.1 Unit-1 12.05.08 5.06.08 Balance Structural Erection in
progress. Boiler Mechanical,
coal silo, mills, ESP structures
erection in progress.
6.1.2 Unit-2 21.08.08 2.09.08 Balance Structural Erection in
progress. Mechanical erection,
ESP Str. in progress.
6.1.3 Unit-3 25.12.08 12.02.09 Balance Structural Erection in
progress. Mechanical erection in
progress.
6.1.4 Unit-4 30.04.09 12.05.09 Balance Structural Erection in
progress. Mechanical erection in
progress.
6.1.5 Unit-5 03.09.09 - Balance Structural Erection in
progress.
6.2.0 TG Structural Erection
6.2.1 Unit-1 14.08.08 13.08.08 Concreting almost completed.
Structure erection in progress.
6.2.2 Unit-2 19.12 08 12.02.09 Concreting and Structure
erection in progress. TG deck
cast.
6.2.3 Unit-3 24.04.09 29.05.09 Concreting and Structure
erection in progress
6.2.4 Unit-4 1.7.08 10.10.08 Structure erection started on
23.10.09. Concreting and
fabrication in progress.
6.2.5 Unit-5 4.11.09 20.11.08 Concreting and fabrication in
progress
6.3.0 Chimney(Shell
concreting)
6.3.1 No.1(2-flue) 2.01.09 8.12.08 Shell concreting Completed.
Flue Can in progress. Insulation
in progress.
6.3.2 No.1(3-flue) 3.06.09 24.03.09 Shell concreting completed.
(Total height 269 metre)

-7-
Brief status of Progress of activities for Krishnapatnam UMPP-as on 31.01.10

1.0 General:
Name of Developer -Coastal Andhra Power Ltd. (CAPL) Reliance Power Ltd.
Date of LOI – 30.11.2007
Date of Transfer of SPV to developer – 29.1.2008
Date of signing of PPA (Effective date) – 23.03.2007

2.0 Commissioning Schedule:

Unit Months from the Schedule COD as Scheduled COD as informed


No. effective date i.e. worked out from the during presentation in MOP
Transfer of SPV(29.1.08) date of Transfer of SPV on 15.10.09*
1. 68 September, 2013 First Unit - September, 2013
2. 75 April, 2014 Last Unit - June 2015
3. 81 October, 2014
4. 87 April, 2015
5. 93 October, 2015

* During the Seventh JMC meeting held on 18.11.09 the developer informed that the order
for supply of main plant equipment have been placed for 4x1000 MW units in the month of
Oct,2009 with COD of 1st Unit in Sept,2013 and Last i.e 4th Unit in June,2015.

3.0 Land Acquisition status: (Area in Acres)


Total Area Acquired

Main Plant & Colony 1915.90 1905.27


Ash pond 533.56 484.03
Misc. 176.22 14.64
Total 2625.68 2403.94

4.0 Development of Transmission Lines:


PGCIL has planned development of Transmission lines as per commissioning schedules as
informed during presentation in JMC meeting held on 18.11.09.Land for the proposed
substation has been identified except for substation at Pune.
5.0 Others:
Status
Financial Closure Yet to be achieved
Order for Main Plant BTG awarded by R Infra in Oct. 2009.
Order for BOP Yet to be placed
Progress at site: For Boundary Wall / Fencing-Foundation, Plinth beam works
and brick wall in progress. Area grading in Main Plant –
completed. .BTG area ready for piling work. Leveling in
other area is in progress. Batching plant completed. Site
office and store completed.

-8-
6. Status of Preconstruction Activities:
Sl.No. Activity Schedule Actual/ Status/Remarks
date Schedule
Date
6.1.0 Studies & Investigation
6.1.1 Soil Investigation Mar 09 May 09 Draft Final report received.
6.1.2 Area Drainage Studies Mar 09 Jan 10 Draft Report received and SGL,
area drainage finalized
6.1.3 Water intake study Dec 08 Dec. 08 MoEF(CRZ) clearance obtained on
12.06.09 for on shore pump house.
6.1.4 Testing of construction Jan 09 Jan 09 Completed
material and mix design
6.1.5 Seismic study Sep 08 Sep 08 Completed
6.1.6 Ash pond leaching study Mar 09 Nov. 09 Draft report received
6.1.7 Fuel Logistic study Dec 08 Dec 08 Completed
6.1.8 Railway Siding study Mar 09 Feb,09 In principle approval received from
South Central Railway on 17.07.09.
6.2.0 Engineering
6.2.1 Main Plant Equipment As per - a. LOI for BTG issued by EPC
PPA Contractor.
b. As discussed during the 7th
JMC,NTP & execution of
supplementary PPA to be firmed up
upon resolving some of the
technical issues with the equipment
supplier.
c. Plant Engineering being finalized
6.2.2 Appointment of Issue taken up with the lead
Independent Engineer procurer. Lead procurer to take
necessary action.
6.3.0 Pre-Award Works
6.3.1 Site Office, Stores & Apr 09 June 09 Completed
Miscellaneous Civil Works
6.3.2 Boundary Wall/Fencing Sep,10 Sep, 10 Work in progress. Work stopped by
land owners at some places due to
non payment for CJFS land disputes
6.3.3 Area grading in main plant Dec.09 Dec.09 In progress. BTG area filled upto 2-9
area m and ready for pilling work.
6.3.4 Construction power Mar 09 May. 09 1st line-6.5 Km out of 10 Km
substation (Within Plant completed. Works for balance route
boundary) stopped by private land owners for
which land acquisition is to be
expedited by Distt. Administration.
Based on last JMC meeting
APSPDCL agreed to extend
construction power supply from
neighboring APGENCO plant. .
Work started on 18.12.09,
completion byFeb,10.
6.4.0 Financing

-9-
6.4.1 Appointment of Dec 08 Dec 08 IDBI appointed as lead arranger for
advisor/arranger Rupee loan. PFC as Co lead
arranger.
6.4.2 Appointment Lender’s Oct 08 Oct 08 M/s Mott Mac Donald conducting
Engineer Lenders Engineer due diligence.
6.4.3 Financial Closure Appraisal in progress. .IDBI and
PFC have sanctioned Rupee Loan
(Part).
6.5.0 Others
6.5.1 Escrow Account Feb.08 Procurers Opening of Escrow Account by
to open procurers awaited.
Escrow
Account

- 10 -
Brief status of Progress of activities for Tilaiya (Jharkhand) UMPP as on31.01.10

1.0 General:

• Name of Developer – Reliance Power Ltd.


• Date of LOI – 12.02.2009
• Date of Transfer of SPV – 07.08 .2009
• Date of signing of PPA
(Effective date) – 07.08 .2009

. First JMC meeting held on 07.12.09.

2.0 Commissioning Schedule:


Unit No. Months from the effective Schedule COD as worked
date i.e. out from effective date
Transfer of SPV(07.08.09)
1. 69 May 2015
2. 74 Oct. 2015
3. 79 March 2016
4. 84 August 2016
5. 89 Jan 2017
6. 93 June 2017

3.0 Land Acquisition Details.


Total Acquired Remarks
Area

Main Plant & 1406 186* Private land-187acres-payment made to


Colony villagers. Land to be handed over.
Forest land-1219 acres –First Stage
Forest clearance awaited.
Ash pond 978 68* Private land-290 acres-payment made for
68 acres, remaining expected in 3-4
months.
Govt. land-688 acres – survey under
progress.
Ash corridor 3.3 - Private land-1.5 acres ,Section -4 to be
issued for 1.4 acres
Govt. land -1.8 acre-survey under
progress.
Water corridor 27 - Private land-2.6 acres-Section-4
notification to be issued.
Total 2415 - -

* Advance possession.
3.0 Forest clearance for the power plant. First stage forest clearance for power plant
land received. The conditions of the clearance to be completed and proposal to be
submitted for final clearance.

- 11 -