Вы находитесь на странице: 1из 16

g

GER-4209

GE Power Systems

Economic Evaluation of
Plant Upgrades Using
Plant Optimization
Software

Rodney R. Gay
Steve Adelman
Shrikant Chickerur
Ivan Johnson
Robert Bell
GE Enter Software, LLC
Davis, CA
Economic Evaluation of Plant Upgrades Using Plant Optimization Software

Contents

Abstract . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
Build Plant Model. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
Plant Configuration. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
Gas Turbine Model . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
HRSG Model . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
Steam Turbine Model . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
Economic Model. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
Operational Limits . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
Test Model vs. Data . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
Yearly Budget Analysis . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
Example Plant Monthly Budget Analysis. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
Yearly Budget Calculation. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
Yearly Budget Analysis of Upgraded Plant . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
Summary and Conclusions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
List of Figures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
List of Tables . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11

GE Power Systems GER-4209 (10/00)


■ ■ i
Economic Evaluation of Plant Upgrades Using Plant Optimization Software

GE Power Systems GER-4209 (10/00)


■ ■ ii
Economic Evaluation of Plant Upgrades Using Plant Optimization Software

Abstract Plant optimization software (Plant Payback™)


contains the necessary plant economic and per-
Equipment vendors typically quote the per-
formance models to perform the benefit evalu-
formance gain that can be expected from an
ation. An optimizer contains mathematical
equipment upgrade, but often cannot calculate
models of the power plant performance, and of
the impact of the upgrade on overall power
the economic revenue and cost streams associ-
plant economics. The economic benefit from
ated with the plant. This model can be exer-
equipment upgrade results from the interaction
cised in the “what-if” mode to simulate the plant
of many complex economic and plant perform-
yearly budget with and without the upgrade.
ance parameters.
The benefit of the upgrade is the difference in
To calculate the economic benefit of an the yearly operational profits calculated with
upgrade the analysis must account for configu- and without the upgrade.
ration and performance characteristics of the
Optimization software is well suited for plant
power plant; operational profile; electric sales
operational economic analysis because the opti-
and fuel purchase contract stipulations; and
mization automatically determines the proper
prices of fuel, electricity, makeup water and
plant operational mode and plant control set-
other variable costs.
tings. For example, if the price of electricity is
This paper describes the application of plant high, the optimizer will automatically turn on
optimization software (Plant Playback™) to duct burners or peak-load the plant. At part
perform plant upgrade benefit analysis at a load, the optimizer will turn off inlet coolers,
combined-cycle power plant. and set the gas turbine power levels at the most
economic levels. If a traditional heat balance
Introduction code were used, the software user would need
Equipment vendors typically quote the expect- to specify the duct burner fuel flows and the gas
ed performance gain that can be achieved from turbine power levels.
an equipment upgrade, but often cannot calcu- Often electric sales and fuel purchase contracts
late the impact of the upgrade on overall power are tiered. That is, the price changes with vol-
plant economics. The payback from equipment ume. In addition, some plants run at fixed load
upgrades results from the interaction of many levels while others can vary production with
complex economic and plant performance economic conditions. The economic value of
parameters. To calculate the economic benefit an upgrade is strongly dependent upon the type
of an upgrade the analysis must account for: of electric sales contracts in place. The opti-
■ Configuration and performance mization software includes modeling of these
characteristics of the power plant contract features and predicts the plant rev-
■ Operational profile (i.e., expected enues and expenses as operations change. The
variations in loads and ambient interaction of price levels and plant perform-
conditions) ance is a key feature of the optimization.
■ Electric sales and fuel purchase The procedure to perform an upgrade analysis
contract stipulations is:
■ Prices of fuel, electricity, makeup water 1. Build a plant performance model
and other variable costs 2. Test the model by comparison to plant

GE Power Systems GER-4209 (10/00)


■ ■ 1
Economic Evaluation of Plant Upgrades Using Plant Optimization Software

data or vendor performance curves Plant Configuration


3. Predict a yearly budget for the facility Plant Payback™ software models a combined-
4. Upgrade the plant model and rerun cycle power plant that consists of gas turbines,
the yearly budget prediction heat recovery steam generators, steam turbines,
condensers, auxiliary boilers and process steam
5. Compare the plant budgets with and
loads. The user configures a plant model by
without the upgrade to compute the
using the “Plant Wizard” to set the numbers of
benefit
gas turbine, steam turbines, auxiliary boilers,
and steam loads.
Build Plant Model
The first step in thermo-economic analysis is to The plant schematic of Figure 1 illustrates the
build an accurate performance model of the equipment modeled by the Plant Payback™
power plant. Building a plant model when software. The notation (i) on the diagram indi-
using the Plant Payback™ software involves cates that that equipment may have a number
inputting reference data, performance curves of replications. Thus, a Plant Payback™ model
and coefficients that specify the equipment per- may have any number of gas turbines, HRSGs,
formance over a range of operating conditions. steam turbines/condensers, auxiliary boilers at
To build a power plant model, one starts with three different pressure levels, and process
the gas turbine, then proceeds to the HRSG steam loads at three different pressure levels.
(heat recovery steam generator) and the steam Each replication of plant equipment is modeled
turbine/condenser. The paragraphs below with its own set of performance data, and may
describe the input data that is required to operate at different operating conditions from
model a combined-cycle power plant. the other replications. The HRSGs are limited
to producing steam at up to three pressure lev-

Figure 1. A general plant schematic modeled in the Plant Payback™ software

GE Power Systems GER-4209 (10/00)


■ ■ 2
Economic Evaluation of Plant Upgrades Using Plant Optimization Software

els (HP, IP and LP), and the steam turbines may ■ Change in exhaust temperature per
only accept admissions from those three pres- MW of underfiring
sure levels. The steam turbines may exhaust ■ Change in exhaust temperature per
steam to four different pressure levels MW of peak (over) firing
(HPPROC, IP, LP and Cond). A complete set of
■ Change in power, heat rate, and exhaust
bypass flows and letdowns is allowed so that
temperature per unit steam injection
steam may be directly transferred from a given
pressure level to any other, lower pressure level. ■ Curve of exhaust flow change vs.
IGV angle
Gas Turbine Model This set of reference values and performance
The gas turbine performance model requires curves uniquely determines the gas turbine per-
the user to supply the following data: formance anywhere within the turbine’s allow-
1. Rating of the gas turbine performance able range of operation. Additional inputs spec-
at a reference inlet air temperature. ify the existence and performance constants of
Included in this data are the following: inlet cooling, inlet chilling and/or inlet heat-
ing.
■ Inlet temperature
■ Gross power HRSG Model
■ Gross heat rate The exhaust of the gas turbine and the duct
■ Exhaust temperature burner are the energy sources for steam gener-
■ Exhaust gas flow rate ation in the heat recovery steam generator
(HRSG). The Plant Payback™ user must input
■ Steam/water-injection rate
HRSG rating data, which specifies the reference
2. Baseload performance curves relating steam generation of the HRSG at the reference
air inlet temperature to the baseload gas turbine exhaust conditions and at a refer-
values of: ence duct burner fuel energy input rate. In
■ Gross power addition, the user must input coefficients that
specify the change in steam generation per unit
■ Gross heat rate
change in the gas turbine exhaust temperature
■ Exhaust temperature and exhaust flow rate. The user also inputs a
■ Exhaust gas flow rate curve of duct burner fuel conversion efficiency
3. Part-load constants that specify how (energy that goes to steam production divided
the heat rate, exhaust temperature by total fuel input energy) vs. duct burner load
and exhaust flow change as the engine level as a fraction of the maximum fuel flow
power is reduced below the baseload rate.
value. Some of the important
Steam Turbine Model
constants that must be input are:
The steam turbine power generation is mod-
■ Fuel flow fraction at zero load
eled as a linear function of the flows into and
■ Control action used to reduce power: out of the steam turbine plus a constant times
inlet guide vane (IGV) or underfiring the change in condenser pressure plus a steam
■ Change in exhaust temperature per turbine exhaust loss term. Linear coefficients
degree of IGV control must be inputted to model the change in steam
GE Power Systems GER-4209 (10/00)
■ ■ 3
Economic Evaluation of Plant Upgrades Using Plant Optimization Software

turbine power per unit change in inlet (throt- which become mathematical constraints on
tle) pressure, inlet (throttle) flow, admission plant operation. Operational limits constrain
flow rates, extraction flow rates and condenser the optimization such that it does not suggest
pressure. A curve of the exhaust pressure loss plant operation where the plant operator can-
(MW) versus exhaust flow rate is also a required not actually run the plant. The maximum gas
input. turbine power may be set by limits on the gen-
erator, the minimum power level may be an
Economic Model environmental constraint imposed by a regula-
The Plant Payback™ optimization software con- tory body. The Plant Payback™ software user is
siders plant revenues and expenses and then able to input a maximum and a minimum
predicts the plant operating condition that allowed value for most of the heat balance val-
maximizes operational profits. The user may ues calculated by the software.
model contracts to buy fuel and make-up water,
and to sell electricity, gas and/or steam (see Test Model vs. Data
Table 1). Each contract stipulation is modeled
Once the necessary performance data has been
simply by specifying a price and maximum and
supplied, the model is ready to be tested. The
minimum quantities. Each of the revenue and
objective of the optimization modeling is to be
expense streams may be modeled by inputting
able to predict overall plant thermo-economics,
contract stipulations.
not just equipment performance. Thus, the
Variable maintenance costs are inputted as plant model needs to be checked against over-
hourly costs associated with operation of gas all power plant performance data to confirm
turbines, steam turbines and auxiliary boilers. that the optimizer can accurately predict overall
Peak firing the gas turbines increases mainte- plant performance.
nance costs by a user input cost per MWh of
The ideal test methodology is to acquire meas-
over-firing.
ured data from the operating power plant over
Revenues a wide range of operating conditions. Data on a
Sales of Electricity hot day, cold day, at full load and at part-load is
Sales of Steam desirable for this evaluation. The model is
Sales of Gas Fuel checked against plant data by manually
Expenses inputting values into Plant Payback™ for
Cost of Fuel (three types allowed per model) parameters that are controlled by plant opera-
Purchases of Electricity tors (inputs in the table below) and then com-
Purchases of Make-up Water paring predicted outputs from Plant Payback™
Variable Maintenance Costs to measured data.
Fixed Costs Table 2 lists Plant Payback™ inputs and outputs
for testing of optimizer predictions vs. plant
Table 1. Revenues and expenses considered in a
data.
Plant Payback ™ model
Figure 2 illustrates the comparison of Plant
Payback™ software predictions to plant test
Operational Limits data. At a power plant in Florida, the gas tur-
A very important element in optimization mod- bine steam injection rate was changed over
eling is the specification of operational limits, time. Measured values of the inlet air tempera-

GE Power Systems GER-4209 (10/00)


■ ■ 4
Economic Evaluation of Plant Upgrades Using Plant Optimization Software

Measured Parameter Plant Payback™ Model Status


Inlet Air Temperature to Gas Turbine Input
Steam/Water Injection Rate to Gas Turbine Input
Gas Turbine Gross Power Input
Duct Burner Fuel Energy Input Rate Input
Process Steam Mass Flow Rates Input
Auxiliary Boiler Fuel Energy Input Rates Input
Gas Turbine Heat Rate Output
Gas Turbine Exhaust Temperature and Flow Output
Steam Production Rate in HRSG Output
Steam Turbine Power Output
Condenser Pressure Output
Overall Plant Net Power Output
Overall Plant Net Heat Rate Output
Auxiliary Boiler Steam Production Rate Output

Table 2. Inputs and outputs used in Plant Payback™ when comparing predictions to plant data

ST Power During 30 PPM Plant Test

44.0

43.0

42.0

Measured
MW

41.0 Plant Payback

40.0

39.0

38.0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43
Time

Figure 2. Comparison of predicted to measured steam turbine power during a plant test

ture, gas turbine power, and steam/fuel ratio rate to within 1% of the actual plant data. GE
were inputted to Plant Payback™. An optimiza- Enter Software has compared optimizer predic-
tion case was executed with input data taken at tions to measured data from over forty com-
five-minute intervals during the plant test. bined-cycle power plants, and found that this
Predicted (output) steam turbine power from level of accuracy may be achieved. If no plant
Plant Payback™ was compared to measured test data is available, the optimization model
plant data. can be compared to vendor predictions of over-
In general, the Plant Payback™ software should all plant performance at various operating con-
be able to predict overall plant power and heat ditions.

GE Power Systems GER-4209 (10/00) ■ ■ 5


Economic Evaluation of Plant Upgrades Using Plant Optimization Software

Yearly Budget Analysis This plant consists of two gas turbines rated at
approximately 210 MW and a 213 MW steam
The power plant yearly budget analysis is per-
turbine. It has duct burners on the HRSG and a
formed by predicting plant thermo-economics
process steam load supplied with steam from
at a selected number of anticipated plant oper-
the IP steam header.
ating conditions over each month of the year.
These predictions are combined to form a The yearly budget was simulated using three
monthly budget. This monthly budget process analysis cases per month resulting in a total of
is repeated over the 12 months of the year to 36 cases to simulate the year of operation. The
result in the yearly budget. three cases per month modeled typical daytime
operation, typical nighttime operation and
The budget analysis needs to account for the
operation during high spot prices of electricity.
complete operational profile of the power
Figure 3 shows a list of analysis cases used.
plant. Does the plant run at full load during the
day, and at reduced load at night? Do process The user inputs for the analysis cases are sum-
steam demands vary over the year of operation? marized in Figure 4. Over the course of the year
Do electric prices occasionally peak at high val- ambient temperatures change with the seasons,
ues a few days per month or year? Can the plant and process loads change on a monthly basis.
sell to a spot market or is the plant load set by The plant has three customers who might pur-
contract with the electric customer? All of these chase electricity. The first customer pays a price
possibilities must be considered in a budget of $50 per MWh and demands 600 MW during
analysis. the day, but only pays a price of $35/MWh at
night for a demand of 400 MW. The second
Example Plant Monthly Budget Analysis customer pays a price of $25/MWh, and will
To illustrate budget analysis methodology, a purchase any amount up to 100 MW during the
budget was prepared for a sample power plant. day but zero at night. The third customer rep-

Figure 3. Screen showing 18 of the 36 analysis cases used for yearly budget

GE Power Systems GER-4209 (10/00)


■ ■ 6
Economic Evaluation of Plant Upgrades Using Plant Optimization Software

Figure 4. Input and output summary screens display results of yearly budget analysis

resents spot electric prices, which are modeled time loads to Customer 2 and Customer 3 are set
at a price of $100/MWh, and are limited to 80 to zero. Thus, no electricity is sold to these two
MW during peak electric periods. customers at night.
Each gas turbine was assessed an hourly main- Finally the third analysis case per month (spot
tenance charge of $200, and the steam turbine electric operation) forces 600 MW to be sold to
has an hourly maintenance cost equal to $100. Customer 1 (at a price of $50/MWh), and allows
These maintenance costs are intended to up to 100 MW (at $25/MWh) to Customer 2 and
account for equipment overhauls, whose cost is up to 80 MW (at $100/MWh)to Customer 3. The
associated with hours of operation. The plant inputs to the Plant Payback™ software for all
was modeled with a fixed cost of $4500/hr, these cases are shown on Figure 4 in the window
which is intended to account for capital and labeled “Summary Inputs.” Figure 4 also shows
overhead costs that do not vary with the mode some of the calculated results in the window
of operation of the plant. labeled “Summary Outputs.”
These three electric customers are the driving The advantage of using optimization is demon-
force that resulted in three analysis cases per strated in the above analysis. The software user
month. The first case per month (daytime oper- only needs to prepare a plant model and input
ation) has both minimum and maximum ambient conditions, process load demands and
demand from electric Customer 1 set to 600 MW. electric contract specifications in order to cal-
This forces the plant to sell exactly 600 MW to culate the predicted plant economics. The opti-
that customer at a price of $50/MWh. mization solver automatically sets the power
The second analysis case per month (nighttime level on the gas turbines, and turns on the duct
operation) forces 400 MW to be sold to Customer burners when economic (increases plant prof-
1 at a price of $35/MWh. The maximum night- it). In effect, the optimization performs the

GE Power Systems GER-4209 (10/00)


■ ■ 7
Economic Evaluation of Plant Upgrades Using Plant Optimization Software

function of plant operators, freeing the soft- Notice, also, that the plant does not sell elec-
ware user from that task. tricity to electric customer number two at a
Looking at the predicted results for January, price of $25/MWh in February. It was econom-
notice that during daytime operation, the Plant ical to sell at this price in January but not in
Payback™ software runs the plant at 656 MW, February. This is because the plant incremental
which is baseload on the gas turbine engines, heat rate is better in January than in February.
and the plant heat rate is 6789 Btu/kWh. At Yearly Budget Calculation
night, the plant is forced to run at 400 MW. In
The 36 analysis case results must be combined
this case, the Plant Payback™ software sets the
together to estimate the yearly budget. This
optimal power levels on the gas turbines at
analysis is most easily done in a spreadsheet. All
146.9 MW and 152.6 MW respectively. These
of the scenario results were exported to
power levels result exactly in a plant net power
Microsoft® Excel (via the “Export to Excel”
of 400 MW and achieve the maximum opera-
selection under the “Tools” menu within the
tional profit at that load level. Notice that
Plant Payback™ software). The economic fig-
Engine Number Two is operated at a higher
ures predicted by Plant Payback™ are for one
power than Engine Number One. This is as
hour of plant operation. To calculate the
expected because Engine Number Two is rated
monthly revenues, costs and profits, the three
at 211 MW and 9850 Btu/kWh at an ambient
cases of operation for each month must be mul-
temperature of 21°C, while Engine Number
tiplied by the number of hours of operation at
One has a lower power generation capability,
each mode. Excel was used to perform the cal-
210 MW, and a poorer efficiency, 9870
culations. For the purposes of this example,
Btu/kWh.
each month was assumed to consist of 730
When spot electricity can be sold at a price of hours of plant operation. The yearly budget cal-
$100/MWh, the Plant Payback™ software auto- culation used 350 hours per month of daytime
matically turns on duct burners so as to sell operation, 300 hours per month of nighttime
more electricity. Eighty MW are sold to electric operation and 80 hours per month of spot price
Customer 3. Notice that the plant heat rate operation.
degrades to 6817 Btu/kWh when the duct burn-
ers are utilized, but plant profits increase (as do Yearly Budget Analysis of
costs and revenues). The optimization maxi-
mizes plant profit; it does not minimize plant
Upgraded Plant
costs. The procedure for performing the plant budg-
et analysis after the gas turbine upgrade is sim-
The predicted plant power during spot electric
ply to enter a new set of gas turbine reference
operation in February (case Feb-3) is only 677.7
data and then repeat the yearly budget analysis
MW even though 80 MW could be sold on the
described above. Figure 5 shows the gas turbine
spot market at a price of $100/MWh. Thus, only
ratings before and after the upgrade. The
77.7 MW are sold to the spot market. This is
upgrade considers a 6 MW power increase and
because the maximum plant net power with the
a 2% reduction in gas turbine heat rate.
duct burners at maximum firing is only 677.7
MW at the higher process steam load and The yearly budget after the upgrade was calcu-
warmer ambient temperatures in February vs. lated using the same yearly budget scenario that
January. was used before the upgrade; only the gas tur-

GE Power Systems GER-4209 (10/00)


■ ■ 8
Economic Evaluation of Plant Upgrades Using Plant Optimization Software

Figure 5. Gas turbine ratings showing power and heat rate before and after the upgrade

bine properties were changed. The benefits of ation in August. Note that the analysis assumed
the gas turbine upgrade come from two pri- 62 hours of spot electric operation per month,
mary factors. First the plant heat rate is lower, 300 hours of nighttime operation and 350
which results in cost savings at all operating hours of daytime operation per month.
points throughout the year. During most of the
year the plant operates at either 600 MW or 400 The yearly benefit of the upgrade is equal to the
MW. (See Figure 6). There is little benefit to the change in yearly plant operating profit. The
increased power generation capacity of the benefit was calculated to equal $1,592,052 per
upgrade when the plant runs at the same power year. Operating profits increased from
level as before. $66,050,600 to $67,642,652 per year.

However, the power generation capacity


increase does come into play during spot elec- Summary and Conclusions
tric pricing. In this case, the plant is now able to Plant thermo-economic modeling combined
sell the maximum spot electric generation with optimization on plant operational profit
equal to 80 MW. This is considerable benefit. In offers several advantages for plant upgrade
the original budget analysis the plant was to analysis. The prediction of the savings or bene-
generate approximately 618 MW during fit from a plant upgrade can account for the
August; but after the upgrade, the plant can run changes in plant operation that are likely to
at 630 MW during August. Note that the plant occur because of the upgrade. The optimiza-
power increased only 12 MW on a hot August tion automatically picks the plant operating
afternoon. This seems low because the gas tur- mode and sets plant controllable parameters
bine ratings were increased by 12 MW, and one such as engine power levels, power augmenta-
would expect the steam turbine power to also tion steam injection, peak firing, duct firing and
increase due to the higher exhaust temperature operation of auxiliary boilers. Since the soft-
of the upgraded turbines. Unfortunately, the ware automatically sets the plant operating
high ambient temperature in August lowers the mode the analysis is much faster to perform and
gas turbine power, and reduces the impact of the user is able to concentrate on understand-
the upgrade (on an absolute basis, but not on a ing the results instead of performing the analy-
relative basis). The benefit is approximately sis. Often the optimization will run the power
$1100 per hour during spot electric price oper- plant in a manner that the user never envi-

GE Power Systems GER-4209 (10/00)


■ ■ 9
Economic Evaluation of Plant Upgrades Using Plant Optimization Software

sioned. As a result, savings (benefits) may be Optimization modeling (such as the Plant
realized which are greater than the user may Payback™ software) is able to predict power
have anticipated. Thus, the benefit calculation plant power generation capability and heat rate
for a power plant upgrade will be more accurate with a precision of 1% over a wide range of
than a benefit calculation that assumes a plant operating conditions. GE Enter Software has
operational mode for the upgraded plant, but proven this by comparison of optimization pre-
does not determine the optimal way to operate dictions to plant measured data at nearly forty
the upgraded power plant. combined-cycle power plants.

Figure 6. Predicted plant budget after the gas turbine upgrade is shown on summary screens

GE Power Systems GER-4209 (10/00)


■ ■ 10
Economic Evaluation of Plant Upgrades Using Plant Optimization Software

List of Figures
Figure 1. General plant schematic modeled in the Plant Payback™ software

Figure 2. Comparison of predicted to measured steam turbine power during a plant test

Figure 3. Screen showing 18 of the 36 analysis cases used for yearly budget

Figure 4. Input and output summary screens display results of yearly budget analysis

Figure 5. Gas turbine ratings showing power and heat rate before and after the upgrade

Figure 6. Predicted plant budget after the gas turbine upgrade is shown on summary screens

List of Tables
Table 1. Revenues and expenses considered in a Plant Payback™ model

Table 2. Inputs and outputs used in Plant Payback™ when comparing predictions to plant data

GE Power Systems GER-4209 (10/00)


■ ■ 11
Economic Evaluation of Plant Upgrades Using Plant Optimization Software

GE Power Systems GER-4209 (10/00)


■ ■ 12

Вам также может понравиться