Вы находитесь на странице: 1из 4

Volume 6, Issue 2, February – 2021 International Journal of Innovative Science and Research Technology

ISSN No:-2456-2165

Construction Service Project Scheduling Analysis


Using Critical Path Method (CPM), Project
Evaluation and Review Technique (PERT)
Popy Yuliarty Novia Nila S Rini Anggraini
Department of Industrial Engineering Department of Industrial Engineering Department of Mechanical
Universitas Mercu Buana Universitas Mercu Buana Engineering
DKI Jakarta, Indonesia DKI Jakarta, Indonesia DKI Jakarta, Indonesia

Abstract:- The success or failure of a project is largely To overcome this problem, the researcher makes a
determined by the planning and control of the project. study using the Critical Path Network (CPM) and Project
The failure of project implementation was due to lack of Evaluation and Review Technique (PERT) Methods. By
planning and lack of ineffective control so that project using the CPM and PERT methods, it can be seen in more
activities became inefficient. This resulted in delays, detail about the time difference between the initial
reduced quality of work, and unexpected costs of conditions and the repair conditions, when the initial
implementation. Problems in this research object is a conditions often experience delays in processing time from
delay in completing a gondola project because there are preparation to completion and result in poor quality [5].
several obstacles or problems that occur. Optimization of Therefore, it must be noted which work should get more
working time is quite important for companies in attention because if the work is delayed it will affect the
working on projects, because in this work time efficiency results of other work [6]. This research will answer the
is needed because the gondola is needed by the client. question of how to determine the optimal time for project
The implementation of the project requires optimal completion and how to determine the critical path to get
project planning using the CPM (Critical Path Method) more attention compared to other activities on the
and PERT methods. With the CPM method, 13 critical contrusction service project.
activities were obtained, with total duration of 55 days
was also applied to the Gantt Chart. And with the PERT II. METHODS
method (Program Evaluation and Review Technique)
obtained 13 critical activities, and a total duration of 53 The situation faced here is that there is a difference
days with a probability of project completion is 86.65%. between the project implementation time and the
predetermined project plan time. The project planning time
Keywords:- Project Management, CPM,PERT, Activities is usually shorter than the project implementation time [7].
The analysis technique used in this research is the CPM
I. INTRODUCTION (Critical Path Method) and PERT (Project Evaluation and
Review Technique) approaches.
The construction of a construction project has
objective goals that must be in line with strategic goals, thus A. Stage 1 : CPM analysis
the performance of a project will affect its achievement [1] . At this stage a network analysis is carried out using the
Projects generally have a deadline, which must be completed CPM method. To be able to set up a CPM network, research
before or at the agreed time. However, in reality in the field, requires several steps [8]. The steps in compiling a CPM
there are still many project completion times that are network are:
delayed or not completed on schedule [2]. Projects are  Review and identify the project scope, describe it, break
dynamic, non-routine, multi-activity with varying intensity, it down into activities or groups of activities that are
short cycles, have starting and ending points, and limited project components.
funds [3]. According to [4] in a project it is necessary to  Rearrange the components in point 1, into links in the
confirm the relationship between activities to plan a project. order according to the dependency logic.
CV. KCT collaborates with PT. GKL in working on gondola  Provide an estimated timeframe for each of the activities
projects, which is usually when PT. GKL won the project resulting from the breakdown of the project scope.
tender, entrusted to CV. KCT. The problem in this company  Identify the critical path (critical path) and float on the
is an internal problem, namely the implementation of the network.
gondola project that was not completed on time.During the
implementation of the gondola project in 2019-2020 there Perform forward and backward calculations. From the
were 5 projects that have been completed, but 3 of the 5 two calculations, it is identified which activities are on the
projects have experienced delays / delays. critical path.

IJISRT21FEB430 www.ijisrt.com 477


Volume 6, Issue 2, February – 2021 International Journal of Innovative Science and Research Technology
ISSN No:-2456-2165
B. Stage 2 : PERT analysis IV. DISCUSSION
At this stage, PERT analysis is carried out to determine
the duration of each work from the data that has been 1. Critical Path Method. The initial step in creating a
obtained and to determine the probability of the company network using the CPM method is to detail each activity
reaching the target schedule. To be able to apply the PERT then proceed with the stage of determining the sequence
method, research requires the following steps: of dependence between one activity and another, because
 Determine the estimated activity time in the formation of a network using the CPM method, it
 Determine the standard deviation of project activities is necessary to know what preceded activities because
 Determine the variety of activities from project activities future activities can be carried out after activities
 Knowing the probability of reaching the schedule target beforehand or in other words can be done in parallel [10].
a. Relationship Between Project Activities. The relationship
III. RESULT between activities is arranged into a chain or network
diagram for the Activity On Node (AON) in the
 Description of Activities. In this step, an assessment and following order as shown in figure 1:
identification of the project scope is carried out by
G H
describing and breaking it down into activities or groups 3
3
5

5
3
3
5

5
13 8
of activities that are project components. This H1 H2
F 3 5 3 5
arrangement is done based on experience and or data in 3
3
10
5

5 3
6
5 3
4
5
G4 I
the project in the past [9].The details of its activities are A B C D E F1 F2
5

5
10

10 G6 H3
5

5
10

10
3 3 4 7 5 5 3
0 1 0 1 0 1 0 1 1 3 3
as shown in Table 1 below : 0
5
1 0
2
1 0
2
1 0
5
1 1
1
3 4
8
5
5

5
4
10

10
G5
3
3
5 3
2
5
5 10

5 10
F3 6
3 4

Activities Duration Delay 4 5

Type of work 7

code (days) (days) G1 G2 G3


5 10 5 10 5 10

Create gondola design & - 5 10 5 10 5 10

A 5 3 9 5

spesification Fig 1:- AON Network Diagram


B Material selection 2 -
Ordering material & 2 b. Critical Path Method. The critical path in this packaging
C 2 packaging project is a path that consists of a series of
negotiating
Purchase & deliveri of 3 activities which in case of delay will result in overall
D 5 delay [11]. This step is preceded by performing forward
material
E Material checking 1 2 and backward calculations. The forward calculation is
done to determine the Early Start (ES) and Early Finish
Steel Frame fabrication - (EF), while the backward calculation is to determine the
F 10
work Latest Start (LS) and Latest Finish (LF). From these two
Cutting steel rods - calculations, it can be identified the critical path that can
F1 according to the type and 8 be calculated float / slack, which is the allowance for the
dimension of need completion time of an activity.
Basic painting for anti- -  Forward Calculation. For advanced calculations in the
F2 4
rust table above, the Activity On Node (AON) network
Making a transportation - diagram is as shown in figure 2 below :
F3 7
system
G Erection work 13 - 25
G
38 38
H
46

3 5 3 5
13 8
Measurement of setting 1
G1 3 H1 H2
plate & anchor plate 15
3
F
25

5
42
3
48

5
48
3
52

5
10 6 4
Drilling and planting of - 27
G4
34 52
I
55
G2 9 5 10 5 10
angkur 0
A
5 5
B
7 7
C
9 9
D
14 14
E
15 15
F1
23 23
F2
27
7
39
G6
42 48
H3
50 3

0 1 0 1 0 1 0 1 1 3 4 5 5 10 3 5 3 5

G3 Anchor tensile test 5 1 5 2 2 5 1 8 4


27
G5
33
3 2

5 10
F3 6

G4 Gondola frame erection 7 - 15

4
7
22

G5 Gondola basket assembly 6 - G1 G2 G3


22 25 25 34 34 39

Instalation of steel slings 2 5


3
10 5
9
10 5
5
10
G6 3
& gondola basket Fig 2:- Advanced Calculation AON Network Diagram
H Post erection work 8 -
Check of instalation & 1  Backward Count. In the countdown, the calculation
H1 6 moves from the event terminal to the event core. In the
joints
H2 Re-painting anti-rust pain 4 - backward calculation, this project is intended to find out
the time or date of the most recent project end in order to
H3 Gondola test 2 -
be able to start and end each activity without delaying the
I Finishing 3 - entire project completion period. Here is the equation for
Table 1:- Types of Project Activities the countdown. The countdown network diagram
Activity On Node (AON) is shown in Figure 3

IJISRT21FEB430 www.ijisrt.com 478


Volume 6, Issue 2, February – 2021 International Journal of Innovative Science and Research Technology
ISSN No:-2456-2165
G H
25
31
13
38

44
38
44
8
46

52
following is the Activity On Node (AON) network diagram
F H1
48
H2
52
for the project's critical path in Figure 5:
15 25 42 48

21 31 42 48 48 52
10 6 4
G4 I
27 34 52 55 G H
25 38 38 46
A B C D E F1 F2 32 39 G6 H3 52 55
15 15 23 7 42 50 3 29 42 42 50
0 5 5 7 7 9 9 14 14 23 27 39 48
13 8
0 5 5 7 7 9 9 14 14 15 20 28 28 32 39 42 50 52
5 2 2 5 1 8 4 G5 3 2
27 33
F H1 H2
15 25 40 46 46 50
33 39
F3 6
15 22 19 29 40 46 46 50
10 6 4
15 22 G4 I
7 27 34 50 53

A B C D E F1 F2 30 37 G6 H3 50 53
15 15 23 7 40 48 3
0 5 5 7 7 9 9 14 14 23 27 37 46
G1 G2 G3
22 25 25 34 34 39 14 18 26 37 40 48 50
0 5 5 7 7 9 9 14 15 26 30
5 2 2 5 1 8 4 G5 3 2
22 25 25 34 34 39 27 33
3 9 5
31 37
F3 6
Fig 3:- The countdown network diagram Activity On Node 15

15
21

21
6
(AON)
G1 G2 G3
21 24 24 32 32 37

21 24 24 32 32 37

 Total Float Calculation. Total Float is the amount of time


3 8 5

Fig 5:- PERT AON Critical Path Network Diagram


that the completion time of an activity can be postponed
without affecting the quickest time of completion of the
Based on the calculation of variance and standard
overall project. This stage is the stage of determining the
deviation, the time to complete activities that pass through
critical path, which is the longest implementation path,
the critical path is 1,802 days. By using a normal curve of
which determines the project completion time.
the probability of the project completion time using the
 Critical Path. The critical path is the path with the longest
following formula:
amount of time compared to all other possible passes.
The duration of the overall Project completion time is 55 𝑇(𝑑) − ∑ 𝑇𝑒 𝑘𝑟𝑖𝑡𝑖𝑠
days.Therefore, another way that can also be used to find 𝑧=
the critical path is by calculating the length of each 𝑆
55 − 53
existing path. The critical path can be seen in Figure 4 𝑧=
below: 1.802
𝑧 = 1.11 ̴ 0.8665
G H
25 38 38 46

31
13
44 44
8
52
From the figures above, the figure is 0.8665 in table Z
15
F
25 42
H1
48 48
H2
52 normal distribution, then the possibility of completing the
21
10
31

27
G4
34
42
6
48 48
4
52

52
I
55
project in 53 days is 86.65%. This means that the completion
0
A
5 5
B
7 7
C
9 9
D
14 14
E
15 15
F1
23 23
F2
27
32
7
39
39
G6
42 48
H3
50
52
3
55 of the project analyzed using the CPM method has a great
0
5
5 5
2
7 7
2
9 9
5
14 14
1
15 20
8
28 28
4
32
27
G5
33
39
3
42 50
2
52
chance of being completed with the duration given by the
15
F3
22
33
6
39
company.
15 22
7

22
G1
25 25
G2
34 34
G3
39 3. Results of Comparative Analysis of CPM and PERT.
22
3
25 25
9
34 34
5
39
In this research, the methods used for scheduling are
Fig 4:- AON Critical Path Network Diagram CPM and PERT. The comparison of the working time of the
gondola project with these two methods can be seen in the
2. PERT (Project Evaluation Review Technique) Method. table 2 and figure 6 below:
Like the CPM method, PERT also uses an arrow chart to
illustrate the project trajectory. In terms of understanding
and calculation, critical activity is the same, the critical Description CPM PERT Difference
path or float in PERT is known as slack. The difference
Time (days) 55 53 2
between CPM and PERT which is clearly visible is in the
Table 2:- Comparison of Time Using the CPM and PERT
estimation of activity duration [12]. If in CPM the time is
Methods
estimated with certainty (deterministically), then in
PERT there are 3 time estimates, namely:
By using PERT network planning to improve the
a. Optimistic time (To), namely the possibility that
project work system, each related section can understand the
activities can be completed in a shorter time.
process flow in detail, know which activities can be carried
b. The most frequent occurrence (Tm), namely the
out in parallel / concurrently, and prioritize activities that are
estimated time that usually occurs under normal
considered critical so that they do not affect the overall
conditions.
project delay. When compared with the results of the
c. Time pessimistic (Tp), which is the possibility that the
completion of this gondola project, which was completed in
activity can be completed in a longer time.
113 days, with the improvement of the work system and the
use of the PERT method, this time efficiency was 60 days
Referring to the information above, time estimation
faster.By using the PERT method, a Gantt Chart for project
data for optimistic time and pessimistic time are needed.
implementation can be made.
This data was obtained through interviews and discussions
with field parties. Based on the calculation of slack using the
PERT method, 13 critical trajectories were found, namely:
A, B, C, D, E, F3, G1, G2, G3, G6, H1, H2, and I. day. The

IJISRT21FEB430 www.ijisrt.com 479


Volume 6, Issue 2, February – 2021 International Journal of Innovative Science and Research Technology
ISSN No:-2456-2165
V. CONCLUSION [8]. M. Jufriyanto and M. Z. Fathoni, “Project
Development Management of Rungkut Tower
The conclusions of this study are: Apartments with Critical Path Method Approach and
1. Project completion using the CPM scheduling method is Pert,” Int. J. Sci. Eng. Inf. Technol., 2019.
55 days. The PERT project method can be completed in [9]. T. I. Julkarnaen, L. Herlina, and Kulsum, “Analisa
53 days. Meanwhile, without using these two methods, Perbaikan Penjadwalan Perakitan Panel Listrik
the project completion time will take 113 days. From Dengan Metode CPM dan PERT ( Studi Kasus : PT .
both the CPM and PERT methods by considering the Mega Karya Engineering ),” J. Tek. Ind. Untirta,
actual ideal conditions, the PERT method produces a 2015.
shorter duration of completion of the entire project [10]. A. Rijaluddin and A. P. Ajie, “PENERAPAN
compared to the CPM method. PENJADWALAN WAKTU MENGGUNAKAN
2. Activities that are considered critical in the gondola METODE CPM (CRITICAL PATH METHODE)
project are activities A (making gondola designs), B DAN PERT PADA PEMBANGUNAN GEDUNG
(material selection), C (ordering materials and INSTALASI RAWAT JALAN RSUD
negotiating), D (purchasing and delivering materials), E MAJALENGKA,” J-Ensitec, 2020.
(checking materials), F3 (manufacture of anchoring [11]. S. R. Jannah, L. Muzdalifah, and E. F. Kurniawati,
system), G1 (measurement of setting plate & anchor “Optimasi waktu penjadwalan proyek pembangunan
plate)), G2 (drilling and planting of anchors), G3 (tensile perumahan menggunakan Critical Path Method
anchor test), G6 (mounting steel slings on gondola (CPM) /Program Evaluation and Review Tehnique
baskets), H1 (checking all installations and joints) , H2 (PERT) dan Simulasi Monte Carlo (Studi Kasus CV.
(repainting anti-rust paint), and I (finishing). From the Granada Property),” Pros. SNasPPM, 2018.
calculation of the PERT method, the probability value or [12]. P. Yuliarty, R. Anggraini, and T. Wastiono,
probability of completing the gondola project is 86.65%. “PENJADWALAN PROYEK MESIN AUTO
This means the possibility of completion of the gondola ASSEMBLY MEMBRANE REGULATOR
project by CV. KAT on time is quite high. VALVE DI PT. OMG METODE CRITICAL PATH
METHOD (CPM),” Ind. Inov. J. Tek. Ind., 2020,
REFERENCES doi: 10.36040/industri.v10i1.2531.

[1]. A. Dwiretnani and A. Kurnia, “OPTIMALISASI


PELAKSANAAN PROYEK DENGAN METODE
CPM (CRITICAL PATH METHODE),” J. Talent.
Sipil, 2018, doi: 10.33087/talentasipil.v1i2.8.
[2]. A. E. Husin, F. Fahmi, S. Rahardjo, I. P. Siregar, and
B. D. Kussumardianadewi, “M-PERT and lean
construction integration on steel construction works
of warehouse buildings,” Int. J. Eng. Adv. Technol.,
2019.
[3]. M. Kholil, B. Nurul Alfa, and M. Hariadi,
“Scheduling of House Development Projects with
CPM and PERT Method for Time Efficiency (Case
Study: House Type 36),” 2018, doi: 10.1088/1755-
1315/140/1/012010.
[4]. M. Kholil, B. N. Alfa, and Supriyanto,
“Optimization of Production Process Time with
Network/PERT Analysis Technique and SMED
Method,” 2018, doi: 10.1088/1757-
899X/453/1/012050.
[5]. D. W. Arian, “Manajemen Operasi Jasa,” Manaj.
Operasi, 2014.
[6]. M. Hanefi Calp and M. Ali Akcayol, “Optimization
of project scheduling activities in dynamic CPM and
PERT networks using genetic algorithms,” arXiv.
2019, doi: 10.19113/sdufbed.35437.
[7]. A. Maulana and F. Kurniawan, “TIME
OPTIMIZATION USING CPM, PERT AND PDM
METHODS IN THE SOCIAL AND
DEPARTMENT OF KELAUTAN BUILDING
DEVELOPMENT PROJECT GRESIK DISTRICT,”
IJTI (International J. Transp. Infrastructure), 2019,
doi: 10.29138/ijti.v2i2.784.

IJISRT21FEB430 www.ijisrt.com 480

Вам также может понравиться