Key Points
No SHE incidents reported in this period
Witnessed successful performance test of Train 2 Compressor and successful gas leak test of Train
1 Compressor.
Completed installation of sewage tank for Tokaju Camp
Completed fence work for Main Construction Camp, Phase 1
Worker Grievance Process issued by Contractor
Weekly Progress
Incremental Plan: 0.4%
Incremental Actual: 0.4%
Cumulative Plan: 11.4%
Cumulative Actual: 13.0%
Upcoming Events
Construction Risk Assessment Workshop (22 February 2011)
Workshop with DPE to discuss Permit-to-Construct (early March)
Main Generator String test (to commence week of 21 February 2011).
HGCP SITE
EPC4 Weekly Report
22 February 2011 Teamwork at its Highest
Working at heights
EPC4 Weekly Report
22 February 2011 Teamwork at its Highest
Narrative
Summary
Overall progress for week ending February 11th, Planned 1.45%, Actual 1.50%.
Evaluating flare area settlement option to optimize earthworks and flare location.
Attended Drilling/Operations PNG Subsurface Workshop in Melbourne (Process Eng / Ops)
Provided action plans (28) and close outs (14) to items identified in the HGCP Site Seismic Risk
Assessment (Civil Eng)
Witnessed successful gas leak test of train 1 compressor on 14 Feb 11.
PO’s place for API 675 Injection Pumps and Non Process Utility Pumps.
Final recommendations issued RA’s for CCR, Security Fence changes and Community Affairs
building changes.
Engineering audit at 60%progress-Singapore carried out and 1 observation raised.
Received Post-Weld Heat Treatment ITT for review
Completed installation of sewage tank for Tokaju Camp
Completed fence work for Main Construction Camp, Phase 1 (razor wire remaining)
Held safety awareness training on Lock-Out / Tag-Out and Isolation
Prepared safety training material for fire warden and fire extinguishers
Reviewed and commented on Tokaju Camp Management Plan
Worker Grievance Process issued by Contractor
Deugro issued PoM Wharf-to-Jackson Airport Route Survey report
Procurement status: 130 of 144 RFQs issued; 124 bids received; 90 bid evaluations completed; 76
purchase orders issued. 3 Spare Orders placed v. 10 planned (of 106 total).
Subcontract status: 38 of 66 subcontracts executed; 30 Individual Subcontract Plans approved; 16
packages in progress.
Near Term Activities:
o Complete foundations for Tokaju Pioneer Camp.
o Solar string tests for Units 1& 2 commence in San Diego week of February 21st.
o Award purchase orders for ball valves, prefab steel buildings, permanent fencing and sewage
treatment plant.
o Award Storage Tanks, Piling subcontracts
Engineering
Overall progress for week ending February 11th, Planned 1.45%, Actual 1.50%.
Evaluating flare area settlement option to optimize earthworks and flare location.
EPC4 Weekly Report
22 February 2011 Teamwork at its Highest
Process
Produced Water IFC-H P&IDs issued (tank farm interconnectivity completed)
MEG System IFC-H P&IDs issued
Systems Description Manual - Upstream Facilities reviewed with comments
Firewater Biocide Injection Package datasheet reviewed with comments
Returned comments on 41 SDV Datasheets for purchase.
Attended Drilling/Operations PNG Subsurface Workshop in Melbourne.
o Reached alignment on Annulus monitoring and venting.
o Reached alignment on HGCP compatibility for well start-up - No facilities modifications required
Piping
Reviewed isometric comments from construction, engineering and DCC with CBI Piping group to
incorporate into latest format
Reviewed material handling with operations and maintenance
Completed review of piping line class specifications
Mechanical
Completed pre-award HVAC technical clarification with Vendor.
Instrumentation / MICC
Establishing a weekly and monthly set of metrics to include in management reports.
Electrical
Solar string tests for Units 1& 2 commence in San Diego on February 21st.
Civil Structural
Clarified concrete testing requirements and clarification of tank foundation leak detection
requirements.
Provided action plans (28) and close outs (14) to items identified in the HGCP Site Seismic Risk
Assessment
Continuing study for flare area possible optimization. CV report with potential impacts due for
Company review 24/2.
Infrastructure bulk earthworks:
o reviewing proposed alternative laydown locations
o Outstanding earthworks drawings (70) planned to be complete in 1-3 weeks.
Rotating Machinery
Conducted workshop visits to Florence on 14 Feb 11 and Massa workshop visit on 17 Feb 11.
Witnessed successful gas leak test of train 1 compressor on 14 Feb 11.
Found Train 1 compressor Drive End Secondary seal Stationary face damaged (crack) during visual
inspection. Seal sent back to Flowserve for detailed inspection and RCA. Report expected 22 Feb
11.
Witnessed successful Train 2 Compressor Performance test on the 18 Feb 11.
EPC4 Weekly Report
22 February 2011 Teamwork at its Highest
Quality Management
No NCR/CAR reported this period
Audit observations close out follow up
Engineering audit at 60%progress-Singapore carried out and 1 observation raised.
Pre-Inspection Meetings are ongoing as per agreed schedule
CV quality inspectors sourcing/interview/ hiring under progress.
Engineering & Procurement quality surveillance checks are on going
Procurement
76 Purchase Orders issued.
130 RFQs issued; 124 bids received; 91 bid evaluations completed.
3 Spare Orders placed v. 10 planned (of 106 total)
Subcontracting
Bid evaluation in progress for Storage Tanks
Received Post-Weld Heat Treatment ITT for review
Reviewed subcontract ‘punch-list’ to clarify remaining subcontracts to develop and execute
16 packages in progress.
30 Individual Subcontracting Plans approved.
39 of 66 subcontracts awarded
Logistics
Onshore logistics continue to support construction activities on site. Kentz inventory storied at 11
Mile for security and maintenance reason
Convoy #15, #19, # 17 and #18 dispatched from 11 Mile
Deugro initiated AN124 marshalling yard land survey at Jackson Airport, POM
Deugro issued PoM Wharf-to-Jackson Airport Route Survey report
Interface Management
Final C1 drawings for Area 41 partially received, Area 40 now due late March.
Plans underway to visit OSL to get as-built information to finalize layout of Wellpad E.
SELCA
EPC4 Weekly Report
22 February 2011 Teamwork at its Highest
Systems Completion
Reviewed SC CP2 Organizational Model with PMT
Commenced Turnover of Systems Completion Database to Contractor
Developed draft Venture Level Systems Completion FAT Coordination Schedule
Working with JV on processes and procedures to be used during Static Commissioning
Contractor SC deliverables under review: Guidelines (Temporary Overrides, Flange Management);
TCPs (Utility/Instrument Air, Fuel Gas, Potable Water, Waste Water Treatment).
Operations Readiness
Attended HAZOP Action Closeouts sessions
Participation in weekly Model Review
P&ID review of changes
Participated in Sub Surface workshop in Melbourne (16/17th Feb)
Review/comment System Description Manual draft sections
Evaluating Lube/Chemical storage & handling requirements
Review Diesel custody transfer, metering and Gas Chromatograph standardization opportunities
MICC- progressing alarm management/prioritisation
Input of Spares/PO data into SPID
Creation and loading of Equipment Templates into SPID
Train CB&I Material CoOrds input process to SPID; review RSPL submittals from vendor
Conducted joint CBI/EM Manual Handling and dropped Object Review (Pilot Exercise)