PROJECT

• Jijiga Higher Secondary School

LOCATION

• Jijiga, Ethiopia

CLIENT
• The Somali Regional State Bureau of Ed uca
tion and Culture

DUTIES
Design , Supervision and Contract Ad
ministration
PROJECT DATA

• Start of study April 1996


• Completion of study: July 1996
• No.Man /Month: 44
• Professional Staff participated in the p
roject:
Architects , Engineers , Planners & sur
veyors
PROJECT

• Agro−pastural Collegl
LOCATION

• Jijiga, Ethiopia
CLIENT

• The Somali Regional State Bureau of


Ed ucation and Culture
DUTIES
Design , Supervision and Contract Ad
ministration
PROJECT DATA

• Start of study feb.19986


• Completion of study: April,1998
• No.Man /Month: 44
• Prof. Staff participated in the proj.
Architects,Engineers,Planners&surveyor
PROJECT
• Sheygosh Boarding School
LOCATION

Sheygosh , Ethiopia

CLIENT

• The Somali Regional State Bureau of


Ed ucation and Culture

DUTIES
• Design , Supervision and Contract
Administration

PROJECT DATA

• Start of study Dec/ 1995

• Completion of study: May/ 1997

• No.Man /Month: 20

• Prof , Staff participated in the proj


.
Architects. Engineers,Planners&surveyors

PROJECT
• Sheep Breeding Center
LOCATION
• Jijiga, Ethiopia
CLIENT
• The Somali Regional State Bureau
of Agriculture
DUTIES
• Design , Supervision and Contrac
t Administration
PROJECT DATA
• Start of study May / 1996
• Completion of study: Aug. /1996
• No.Man /Month: 36
• Profess . Staff participated in the p
roj
Architects , Engineers , Planners & surveyors
PROJECT
• Gode Rural Technology Center
LOCATION
• Gode , Ethiopia

CLIENT
• The Somali Regional State Bureau
of Agriculture
DUTIES
Design , Supervision and Contract Ad
ministratio
PROJECT DATA
• Start of study Dec. /1994

• Completion of study: Feb. /1995


• No.Man /Month: 36
• Professi. Staff participated in the proj.
• Architects ,Engineers,Planners &surve
yor
PROJECT
• ArbaMinch Air Port Pax Terminal
& Auxiliary Buildings
LOCATION
• Arba Minch , Ethiopia

CLIENT

• Ethiopian Civilaviation Authority


OBJECTIVE PROJECT DATA

A Pax Terminal Block Having Office , De • Start of study April 196


parture & Arrival Lounge, Shops Waiting • Completion of study: July 1996
Area etc. and a Control Tower . The Esti • No.Man /Month: 44
mated Cost of This Project is About Birr • Professional Staff participated in the project:
12 Million. Architects , Engineers , Planners & surveyors
• No. of Staff :− 11 ( Eleven )
DUTIES • Start of Construction : Oct /1996
Design , Supervision and Contract, Adm • Construction Completion Date: Sep/ 1998
inistration
PROJECT
• Office & Shop e complex
LOCATION
• Addis Ababa, Ethiopia
CLIENT
• MEKWOR Ethiopia

DUTIES
Design

PROJECT DATA
• Start of study April 1993
• Completion of study: Jan 1994
• No.Man /Month: 48

• Professional Staff participated in the proj


ect:
• Architects , Engineers , Planners & sur
veyors
• Construction Completion Date: 1998
PROJECT
• Office Building

LOCATION
• Awassa, Ethiopia
CLIENT
• Commercial Bank of Ethiopia

DUTIES
Design , Supervision

PROJECT DATA
• Start of study Jan 1991
• Completion of study: Dec..1993
• No.Man /Month: 36

• Professional Staff participated in the proj


ect:
Architects , Engineers , Planners & surveyors
PROJECT
• Office & Shop e complex

LOCATION
• Addis Ababa, Ethiopia

CLIENT
• W/O Rosina Tsitotaw

OBJECTIVE
• To Build modern office & shoping complex DUTIES
worthing Eth.Birr 5 m . Design , Supervision and Contract Administ
ration

PROJECT DATA
• Start of study sep.1992
• Completion of study: Dec,1992
• No.Man /Month: 24

•Professional Staff participated in the proj


ect:
Architects , Engineers , Planners & surveyors
• No. of Staff :− 6 (six)
• Start of Construction : feb.1993
• Construction Completion Date: April1995
PROJECT DATA
• Start of study feb.1995
• Completion of study: April .1995
• No.Man /Month: 30

• Professional Staff participated in the proj


ect:
Architects , Engineers , Planners & surveyors
• No. of Staff :− 10 (TEN)
• Start of Construction : May 1995
PROJECT • Construction Completion Date: March 1997

• Medical hospital

LOCATION
• Addis Ababa, Ethiopia

CLIENT
Ato Ibrahim Nawd
PROJECT DATA
• Start of study sep.1999
• Completion of study: Dec,1999
• No.Man /Month: 24

PROJECT
• Medical hospital

LOCATION
• Harar, Ethiopia

CLIENT
ATO SEBRI AHMED OMAR

DUTIES
Design , Supervision and Contract Administ
ration
PROJECT DATA

• Start of study feb.2000


PROJECT • Completion of study: Jully.2001
• No.Man /Month: 60
• Medical hospital
• Professional Staff participated in the proj
LOCATION ect:
Architects , Engineers , Planners & surveyors
• Addis Ababa, Ethiopia • No. of Staff :− 10 (TEN)

CLIENT
W/O Mulumebet Abebe
DUTIES
Design , Supervision and Contract admin.
PROJECT
• Medical College and Teaching hospital

LOCATION
• Addis Ababa, Ethiopia

CLIENT
Dr,. Amude
DUTIES
Design , Supervision and Contract admin.

PROJECT DATA

• Start of study June 2001


• Completion of study: Jully.2003
• No.Man /Month: 120

•Professional Staff participated in the proj


ect:
Architects , Engineers , Planners & surveyors
• No. of Staff :− 10 (TEN)