VENTBLOCK INSTALLATION METHOD STATEMENT

1. MORTAR MIXES

1.1. Sand shall be washed and free from clay, chalk, shells, organic materials and other impurities.
1.2. Ratio for the mix should be 1 part Ordinary Portland Cement : 3 parts sand (1:3).
1.3. The ingredients shall first be mixed dry before water is added to the mix.
1.4. Mortar shall be used within 30 minutes of mixing. No mortar, which has achieved its initial set,
shall be used in the work, and no water is to be added to the mortar, after the initial mix.

2. BLOCK WORK:

2.1. The area is to be cleaned, all loose materials to be removed.


2.2. Keep a maximum of 6 courses being built in a section in any one day.
2.3. Where block work abuts structural concrete columns or walls it shall be tied to the concrete with
300mm length R6 dowel bar at every interval of 3 layers block height horizontally, unless
otherwise specified.
2.4. Use wire mesh at every interval of 3 layers block height horizontally.
2.5. Blocks shall be filled by buttering the vertical end of the unit and then sliding into position
against its neighbor and pressed into horizontal mortar bed and tapped into final position so as to
embed fully in mortar.
2.6. All joints shall be in concave joint finish solidly filled with mortar mixed and the thickness of
the joints shall not exceed 10mm.
2.7. All mortar joints shall be racked to minimum 5 mm depth using racking tool while the mortar is
still in thumbprint hard unless otherwise specified.
2.8. Cutting of blocks shall be kept to a minimum. Cut with motor driven masonry saws, using either
an abrasive or diamond blade. Cut neatly and locate for best appearance.
2.9. Installation of VentBlock with fair face finish (without plastering) must be executed by skilled
installer. Courses shall be truly horizontal and vertical joints truly vertical. Installer must check
workmanship frequently. All work shall be cleaned at the end of work day.
2.10. Curing of block work should be done for at least 7 days.