Академический Документы
Профессиональный Документы
Культура Документы
Mary’s Lane, Suite 250, Houston, TX 77079 Tel: +1 281 870 5200
Drilling facilities
o Number, type and location of drilling rig
Production facilities
o Weight, area and center of gravity
Drilling / production risers
o Number and arrangement
Well systems
o Number of wells, completion and workover methods, minimum well
spacing and well bay location
Hull compartmentalization
o Damage stability considerations
Air gap requirements
o New metocean criteria
As illustrated in the following figure, the relative hull responses of the three designs vary
considerably. In all cases the objective is to minimize the response to the environment.
5 10 15 20 25 30
Wave Periods
(secs)
FloaTEC, LLC 14701 St. Mary’s Lane, Suite 250, Houston, TX 77079 Tel: +1 281 870 5200
Hull weight estimates are based on global sizing which is determined by the naval
architectural and structural design. Global sizing is a key engineering design process in
both the concept selection stage and design phase of a floating structure. The sizing of
a moored floating structure considers relationships among the payload, the size of the
hull, and the mooring system. During the concept selection phase, efforts are
concentrated on the main dimensions and weights under the consideration of design
standards and performance requirements without a high degree of engineering detail.
Finalized dimensions and main properties of the floating structures will be determined in
the front-end engineering and design (FEED) stage through various analyses.
Spar Technology
The first Spars were based on the Classic design. This evolved into the Truss Spar by
replacing the lower section of the caisson hull with a truss. Truss Spars are often
considered along with TLPs for dry tree solutions because they offer favorable vertical
motions. However, Truss Spars are
different from both Semis and TLPs
with regards the mechanism of
motion control. One of the
distinctions of the Truss Spar is that
its center of gravity is always lower
than the center of buoyancy which
guarantees a positive GM. This
makes the Truss Spar
unconditionally stable. The Truss
Spar derives no stability from its
mooring system, so it does not list
or capsize even when completely
disconnected from its mooring.
ship shaped FPSOs and Semis. The deep draft, along with protected centerwell,
significantly reduce the current and wave loading on the riser system These loads
normally control the tension and fatigue requirements of the production risers on TLP or
Semis.
One of the principal advantages of the Truss Spar over other floating platforms lies in its
reduced heave and pitch motions. Low motions in these degrees of freedom permit the
use of dry trees. Dry trees offer direct vertical access to the wells from the deck, which
allows the Truss Spar to be configured for full drilling, workover operations, production
operations, or any combination of these activities.
The trussed mid-section of the hull is an X-braced space frame constructed of tubular
members and flat
plates called “heave
plates.” The heave
plates increase the
added mass in the
vertical direction and
thereby increase the
natural heave period of
the Truss Spar and
bringing it above the
range of periods in the
wave energy. In a
Truss Spar, they also
increase heave
damping.
The Truss Spar hull includes two access shafts. These shafts contain the ballast and
utility piping and instrumentation. They also allow direct personnel access to the piping
and to every void tank without requiring workers to pass through an intermediate
compartment. Only one void need be open at a time. Access shafts are painted, lighted,
and vented, as required, for entry.
The seawater ballast system has a dedicated centrifugal pump at the bottom of each
access shaft for discharging ballast water. Ballast water is supplied to the tanks from the
utility seawater manifold. Each seawater ballast discharge pump services the same two
ballast tanks served by its access shaft. All ballasting is over the top of the hull, so that
ballast tanks have to be intentionally filled by the ballast operator. This eliminates the
possibility of inadvertent flooding, which can occur if a sea-chest system is used.
TLP Technology
The main principal of the TLP is to assure that the vertical forces acting on the platform
are in balance, i.e. fixed and variable platform loads plus tendon tension are equal to its
displacement. The VCG
should be close to the
platforms geometrical center.
Positive displacement is
obtained by locking the
platforms draft below the fixed
and variable payload
displacement draft. This will
result in an upward force
applied to the tendons,
thereby keeping them in
constant tension.
As an evolution of the Classic TLP design, the ETLP (Extended Tension Leg Platform)
has been developed. Some of the drivers behind this design development are:
Wider tendon base for greater pitch stiffness (stability)
Smaller spacing of deck supports for more efficient structure
Lower rotational inertia for hull and deck for lower pitch natural period
A large moonpool can accommodate conventional top tension risers.
De-coupling of tendon porch separation distance from the topsides deck design
produces maximum design flexibility.
0.014
No Tide, Max Riser
0.012
0.01
0.008
0.006
0.004
0.002
0
0.00 10.00 20.00 30.00 40.00
Period (sec)
FloaTEC, LLC 14701 St. Mary’s Lane, Suite 250, Houston, TX 77079 Tel: +1 281 870 5200
Semisubmersible Technology
Semi units offer a number of benefits, including large payload capacity, limited
sensitivity to water depth, quayside integration and the ability to relocate after field
abandonment. A typical Semi design has four columns connected at the bottom by
pontoon with a nominally rectangular cross-section. A truss structure connects the
column tops and supports topsides
modules. This arrangement provides a
high degree of flexibility in fabrication
methodology.
2.5
Surge
RAO (ft/ft or deg/ft)
2.0
Sway
1.5 Heave
1.0 Roll
Pitch
0.5 Yaw
0.0
3 6 9 12 15 18 21 24 27 30
Wave Period (Sec)