Академический Документы
Профессиональный Документы
Культура Документы
-1-
20) Resource Requirements is an output from Resource planning not INPUT
Look at from this angle also.
21) Cost Estimating: Cost estimating involves developing an approximation
(estimate) of the costs of the resources needed to complete project
activities. In approximating cost, the estimator considers the causes of
variation of the final estimate for purposes of better managing the project
22) Your project is plagued by frequent but minor changes to the project
scope. In this case, you should Issue a Budget Update
23)
QUALITY MANAGEMENT
1) You have been assigned the task of trying to determine the potential
cause for the variations as to why the Circuits are not accurate
YOU WILL USE CONTROL CHARTS not Ishikawa Dig / Pareto /
Inspection VERSUS… Cause and Effect Diagrams, also called Ishikawa
diagrams or fishbone diagrams illustrate how various factors might be
linked to potential problems or effects (This is for PROBABLE CAUSES
OF PROBLEMS)
2) Modern Quality Management complements Project Management.... This
requires a combination of conformance to requirements (the project must
produce what it said it would produce) and fitness for use (the product or
service produced must satisfy real needs)
3) PMI believes that providing more functionality (gold plating) is not a good
practice - even if it satisfies the customer Still it is a quality failure if you
give more than what you are supposed to give
-2-
4) Cost of quality refers to the total cost of all efforts to achieve
product/service quality, and includes all work to ensure conformance to
requirements. There are three types of costs that are incurred: prevention
costs, appraisal costs and failure costs.
5) For the Design of Experiments Dollars, Pounds, KGs are Measures but not
VARIABLES; Weight is a Variable that can be used.
6) The project management team must have a working knowledge of
statistical quality control, especially sampling and probability, to help it
evaluate quality control outputs.
7) You are the project manager for an automobile company. Because of
change in Government regulations, the emission norms for
automobile vehicles have been made stricter. As a project manager,
you are concerned that your project will not satisfy the required
quality standards. This could be done through Quality Assurance
-3-
11) Information will be gathered for optimistic (low), pessimistic (high) and most
likely scenarios if triangular distributions are used; or on mean and standard
deviation for the normal and log normal distributions (pmstudy notes: How much
a set of data is different from the curve it should make when plotted on a graph.
Or, the square root of the average of the squares of deviations about the mean of a
set of data. Standard deviation is a statistical measure of spread or variability. A
sample Normal Distribution that shows standard deviation (sigma) as
distance of the measurement from the mean value.
12) A quality audit is a structured review of other quality management
activities. The objective of a quality audit is to identify lessons learned that
can improve performance of this project or of other projects within the
performing organization.
13) The cost of quality includes quality planning, quality planning, quality
assurance and rework. Because of the costs associated with quality, it is
not necessary that the cost of the project will decrease because of better
quality. However, better quality provides
• Improved Cost Effectiveness
• Better Customer Satisfaction
• Increase in Productivity
14) 3-Sigma can go upto 99.7%, 2-Signma upto 95%, 1-Sigma upto 68%, - See
below graph
-4-
17)
-5-
23) Cost of quality refers to the total cost of all efforts to achieve
product/service quality, and includes all work to ensure conformance to
requirements, as well as all work resulting from nonconformance to
requirements. There are three types of costs that are incurred: prevention
costs, appraisal costs, and failure costs.
SCOPE MANAGEMENET
-6-
11. pmstudy notes: As the project becomes more complicated, there are
several parameters in the project which can impact the scope - so the
uncertainty of the scope increases
12. Inspection(which is a Tool for Scope Verification) includes activities such
as measuring, examining and testing undertaken to determine whether
results confirm to requirements. Inspections are variously called reviews,
product reviews, audits and walk-throughs
13. A value adding change (e.g. an environmental remediation project is able
to reduce the costs by taking advantage of technology that was not
available when the scope was originally defined).
14. If the project is terminated early, the scope verification process should
establish and document the level and extent of completion.
15. For a project to be successful, what is the primary requirement?
Customer Satisfaction
16. If there is a major change to the project, the Project Manager should try to
influence the change to minimize the impact the project. Usually the
project manager is advised to do the following:
1. Evaluate the impact of the change within the team
2. Let the customer(or person requesting the change) know about the
impacts of the change
3. If changes is required, then open a change control and get it approved
- definitely inform the management and the change control board about
the impact of the changes
4. If changes are approved by the change control board, then make the
appropriate changes in the project plan
1. Economic Models
2. Multi Objective Programming
3. Decision Trees
4. Logical Framework Analysis
-7-
and then using financial measures such as return on investment or
payback period to assess relative desirability of the identified alternatives.
22. A WBS is a deliverable-oriented grouping of project components that
organizes and defines the total scope of the project; work not in the WBS
is outside the scope of the project. As with the scope statement, the WBS
is often used to confirm a common understanding of the project scope
23. The items at the lowest level of the WBS may be referred to as work
packages, especially in organizations that follow Earned Value
Management practices. These work packages may in turn be
decomposed in a subproject work break-down structure. Generally this
type of approach is used when the project manager is assigning a scope
of work to another organization, and this other organization must plan and
manage the scope of work at a more detailed level than the project
manager in the main project.
24) Project charter should include, either directly or by reference to other
document:
• Business Need that the project was undertaken to address.
• The product description
25) Question: A well-constructed Scope Statement can provide all the
following benefits EXCEPT: 4
1. Provide a documented basis for making future project decisions
2. Develop common understanding of project scope among stakeholders
3. Provide knowledge of project justification, deliverables and objectives
4. Provide a basis for time and cost estimates
26) You are the project manager for an initiative aimed at releasing a new
product in the market. But because of Government Regulation, you will have
to make some changes to the project scope. Any modifications to the contents
of the scope statement should be done through Scope Statement updates
27) Your project is very critical for the company and must be completed
within 6 months. The project charter has been signed, but Scope
Statement is not yet prepared. Management asks you to go ahead
with the project without the scope statement being approved. What
should you do? (SELECT BEST ANSWER) Meet the Management
and mention the problems you will face without a Scope Statement
28) Please note that it is Very Important to ensure that Customer does
formal Scope Verification after each project phase or major project
deliverable. Otherwise, there is a very good possibility that the project will
not meet the customer requirements.
29) A project charter is a document that formally authorizes a project.
30) Change requests: Changes may require expanding the scope or may
allow shrinking it. Most changes are the result of:...
-8-
31) Question: In your project, you use configuration management to
record and report the change and its implementation status. In this
context, you are using change control as a technique for: 2
1. Performance Measurement
2. Overall change control
3. Change Control System
4. Scope Definition
• Penalty Power: The ability to gain support because the project personnel
perceive the project manager as capable of directly or indirectly
dispensing penalties that they wish to avoid. Penalty power usually
derives from the same source as reward power, with one being a
necessary condition for the other
-9-
reward and recognition systems since the systems of the performing
organizations may not be appropriate
04) As a project nears completion, you notice that the functional managers are more
interested in trying to find a new position, rather than concentrating on their project work.
Their motivation is SAFETY
• Theory X: This assumes that the workers are inherently lazy and require
supervision
• Theory Y: The average worker finds that physical and mental effort on the
job satisfying, and likes his work.
06) Expertise of the project manager is the most important factor in getting
support from the project personnel; least important factor is ability to penalize
- 10 -
07)
09) All the following roles can exist in a Roles and Responsibility Matrix
PARIS – Participant, Accountable, Review Required, Input Required, Sign
Off Required
11) You have been given a high priority task that needs to be completed
within a short time frame. Since you know what has to be done, you
instruct you assign tasks to the different team members and tell them when
and how the tasks should e done. The management style that you are
following is Directing
- 11 -
< P>
12)
13) Direct and indirect costs for training are generally paid by the performing orga
- 12 -
14)
15) You are the blue eyed boy of your Vice Chairman, who appreciates the
way in which you handle projects. This helps you in managing
interpersonal relationships with your team-members because you have the
following power LEGITIMATE
16)
- 13 -
17) You are the project manager for a complicated construction project
which involves building highways in the whole state of North Carolina. You
have several groups working with you in the project. To plan resources for
this project, you should use Responsibility Assignment Matrix
1. Confrontation
2. Compromise
3. Smoothing
4. Forcing
5. Withdrawal
Justification:
COMMUNICATIONS MANAGEMENT
- 14 -
1.
5.
6. If too much dis-order at meeting prepare agenda You can’t influence
all communication channels as there would be n(n-1)/2 channels.
- 15 -
7. The sender is responsible for making the information clear, unambiguous,
and complete, so that the receiver can receive it correctly, and for
confirming that it is properly understood. The receiver is responsible for
making sure that the information is received in its entirety and understood
correctly.
8. Question: All the following are inputs for Information Distribution
EXCEPT 4
Work Results
Project Plan
9.
- 16 -
delivering organization)
- 17 -
All the remaining options are inputs to Communication Planning:
PROFESSIONAL RESPONSIBILITY
1. If standard deviation is slightly more than 0.002 then do not accept or reject it
but Document the lower quality level, ask the contractor for explanation and try to
find a solution - Any decrease in quality level should be documented and
discussed with the contractor. If there is a small decrease from the
required quality, rejecting the product outright(Choice 3) is extremely
harsh. Similarly, allowing for lower quality (Choice 1 and Choice 4) is not
advisable.
2. Requirements for PMP Code of Professional Conduct
- 18 -
5. Your project is close to completion, when you are informed by the
customer that they would like to see an additional feature in the
project. You realize that the feature was discussed with the project
sponsor in an earlier meeting, and he categorically mentioned that
he did not want this feature. What is the BEST course of action
Deny the customer request, and ask him to open a change request
6. For Professional Responsibility questions, please note that the Project
Manager should always try to solve the problem
7. You have scheduled a contractor conference after 2 days with
potential contractors to discuss procurement. Today, you were
informed by Management that there is a very high probability for the
project to be cancelled. You should CANCEL THE MEETING AS
There is no point in having the meeting and wasting time if there is a high
probability for the project to be cancelled.
8. You are managing a project in a foreign country, where you realize that to
get things done in your project, you may have to pay some tips to the
government officials. You should: refuse to pay as the same is unethical
and it is bribery
9. Certified PMP Duties are:
1. Ensure that there is no conflict of interest that can compromise the
legitimate interests of a client or customer
2. Disseminate PMP Code of Professional Conduct to other PMI
certificants.
3. Cooperate with PMI concerning ethics violation and the collection of
related information
4. As a PMP Certified project manager, you are responsible to comply with
all organizational rules and policies
- 19 -
As a PMP Certified project manager, you are responsible for all the
following EXCEPT: 3
10. Knowledge gained in one company is not proprietary information and can
be used in subsequent jobs. Choice 1, Choice 3 and Choice 4 are
inappropriate because you may have to work in projects for the competitor
which will adversely impact products of the first company you worked for.
This is acceptable so as long as you do not unethically use any contacts
or proprietary information from the first company.
11. When you join a new company, you realize that all the project managers in
the new company have the responsibility of managing individual product
releases of a software product and the co-ordination of these releases over
time. Since you are a Certified PMP, you realize that the situation is
program because it involves several projects being done simultaneously, and
elements of ongoing operations
12. You have been informed by the project sponsor that there has been a
revaluation of projects within your company and your project will not be
getting any additional funding. In this case, you should Means it is not
going to continue and hence you need to PERFORM ADMIN CLOSURE
13. You are the project manager for a construction company which
wants to build a water treatment plant close to a residential locality.
Although the project owner and sponsor have got the legal approval
for constructing the water treatment plant, some of the owners of
residential properties have approached you with concerns regarding
the potential impact to the environment - in this case, you must
Try to find appropriate resolution of issues between the different
stakeholder
14. A project manager disclosed some crucial information to a
prospective seller. Which code of professional conduct did he violate
preventing conflict of interest
15. You are aware that an employee in your project may potentially get a
promotion - however, there is a possibility that he may get
transferred after his promotion, thus impacting your project. In this
situation, you should After the employee gets the promotion and is
told of the transfer, you ask him to prepare a transition plan you are not
sure whether the resource will get a promotion or get transferred. So, after
the promotion/transfer are confirmed, you should ask him to do a proper
transition
- 20 -
16. You are in the vendor management department of your company
which sources computer hardware from companies. You recently
visited a marketing conference for a leading computer hardware
provider, where you were offered a gift-voucher for $ 200 for
attending the conference. You should Return the gift because it
could be construed as personal gain (I think coz. It is in conference and
within USA)
17. There have been too many disagreements within two team-members
in your project regarding the design of a particular product. You
would like to incorporate the best features of the two designs - and
want to create an environment that avoids conflicts and emphasis
similarities. The conflict-handling mode you would like to emphasize
is smoothing
18. One of your team-members provided you with a critical report 10
minutes before a bidders conference. You notice some serious
errors in the report. The best thing for you to do is to Cancel the
Meeting and reschedule to a later date
19. A project Managers responsibility is that upon a reasonable and clear
factual basis to report possible violations of the PMP Code of Professional
Conduct by individuals in the field of project management.
20. You are doing some work under contract, when the buyer requests
you to add some additional requirements which were not defined in
the original contract. Since satisfying the buyer is of paramount
interest, you go ahead and incorporate the requirements as part of
the project. You are violating which Code of Professional Conduct
Responsibility to maintain and satisfy the scope and objective
21. You are managing a project in a foreign country, where you realize
that you will have to pay a fee to some government agencies to get
your work done. You should PAY FEE – No problem as it is not
same as Bribe
22. If a risk emerges that was not anticipated in the risk response plan, or its
impact on objectives is greater than expected, the planned response may
not be adequate. It may be necessary to perform additional risk response
planning to control the risk.
23. Question: As a PMP Certified project manager, you are responsible
to comply with all organizational rules and policies. In this context,
you have the responsibility to all of the following except 4 as he
need not inform PMI but to client, parties etc.
1. Provide accurate and truthful representations concerning all
information directly or indirectly related to all aspects of the PMI
Certification Program
2. Report possible violations of the PMP Code of Professional Conduct
by individuals in the field of project management.
3. Cooperate with PMI concerning ethics violations and the collection of
related information
- 21 -
4. Disclose to PMI about significant circumstances that could be
construed as a conflict of interest or an appearance of impropriety
- 22 -
32. Lessons Learned is an output of all the processes mentioned above
Except Contract closeout (It is output of ICC, Schedule Control,
Administrative Control)
33. Defining Requirements gives Customer Satisfaction
34.
35. You are in the build phase of your project, when you realize that
because of a design error, the product will not meet the performance
parameters specified by the customer. In this context, what should
you do first Discuss with your team to try to find out alternatives
means to solve the issue
TIME MANAGEMENT
1. Graphical Evaluation and Review techniques are similar to PERT but have
the distinct advantages of allowing for looping, branching, and multiple
project end results.
2. In a Normal Distribution, the PERT duration (also called mean)
= (Pessimistic + 4* (Most Likely) + Optimistic)/6
= (10 + 4 * 13 + 16)/6
- 23 -
= 13
- 24 -
13. As with the WBS, the activity list must include descriptions of each activity
to ensure that the project team members will understand how the work is
to be done.
14. The different classes of estimates are (DCA-FO) 35-25-15 (10 range),
10-5 (5 Range)
• Definitive: + 5%
• Capital Cost: + 10-15%
• Appropriation: + 15 - 25%
• Feasibility: + 25 - 35%
• Order of Magnitude > + 35%
15. The objective of duration compression includes all the following
except:3 Duration Compression includes fast-tracking but not
simulation
1. Shorten the project schedule without impacting scope
2. Do compression of tasks for the least incremental cost
3. Do simulation to calculate distribution of probable reasons for the
whole project
4. Do activities in parallel which would normally be done sequentially
16. Milestone Events, as such will have ZERO duration these are better
choice to give presentations to management
17. As different techniques like crashing, fast tracking, resource reallocation
etc. are being considered for Resource Leveling, there is a real potential
for the costs to increase but it increases project duration, Utilization of
weekends, extended hours or multiple shifts, Productivity increases by
using different technologies and/or methodologies
18. The length of the different paths are:
Since the longest path is Start -> 4 -> 5 -> End, this is the critical
path. Length of the critical path is 12.
- 25 -
So, Slack in Task 3
= Late Finish - Early Start =3-2=1
- 26 -
Note that the 1,2,3,6 Sigma Values are 68%, 95%, 99.7%, and
99.9%
25. Question: All the following statements about float are correct except:
3
1. Float refers to amount of time an activity can be delayed from its
early start without delaying the project finish date.
2. Float changes as the project progresses and as changes are made
to the project plan
3. Float is the amount of time an activity can be delayed without
delaying early start of any immediately following activity.
4. Float can also be referred to as Slack, Total Float or Path Float.
26. The project Network Diagram is an input to what process Sch Dev
27. If shipment gets delayed in 2 weeks Review the performance reports
to determine which planned dates have not been met, and the impact on
critical path
28. The moment slack is being asked, check if it is on CRITICAL PATH
29. If management wants to complete the project in 20 weeks, then project
float will be : 20 - 23 = -3 weeks. The project float compares the critical
path with an externally imposed date and may be negative. (you may be
forced to fast-track or perform crashing to ensure that the project is
completed within the dates required by management). But, there will be no
change to the critical path
30. Schedule Development means determining the start and finish dates for
project activities. If the start and finish dates are not realistic, then the
project is unlikely to be finished as scheduled
1. Activity Sequencing
2. Activity Duration Estimating
3. Schedule Development
4. Activity Definition
- 27 -
31.
INTEGRATION MANAGEMENT
- 28 -
about the project. The performance measurement baselines will usually
change intermittently, and then generally only in response to an approved
scope of work or deliverable change
2. Project Management Information system (PMIS): A PMIS consists of tools
and techniques used to gather, integrate and disseminate the outputs of
project management processes
3. Corrective Action is an output of Integrated Change Control and not a
"Tool".
4. Which common tool is required for Project Plan Development,
Project Plan Execution and Integrated Change Control PMIS
5. To integrate the various processes and measure the performance of
the project throughout project lifecycle, a project manager should
use EVM
6. Question: Which of the following is not an example of project
integration management?
1. Integrating the work of the project with the ongoing operations of the
performing organization.
2. Making tradeoffs between competing objectives and alternatives to
meet or exceed stakeholder needs and expectations.
3. Integrating product scope and project scope
4. For change in scope of the project, figuring out what the impact will be
to the project from a cost and schedule perspective
7. A lower position in a project organization can often be helpful in avoiding
and resolving conflict Note a reason of Conflict
8. The project plan includes the Risk Management plan. Risk Management
plan includes defining key risks, including constraints and assumptions,
and planned responses and contingencies
9. Integrated change control requires:...Ensuring that changes to the product
scope are reflected in the definition of the project scope
10. Question: You are the Project Manager for an aircraft manufacturing
company developing a new range of supersonic fighter planes. Since
government funding is essential for your project, you hire a lobbying
firm to get Government support for funding your project. This is an
example of: 1
1. Integrated Change Control
2. Risk Management
3. Cost Management
4. Project Planning Methodology
11. In many application areas, configuration management is a subset of the
change control system and is used to ensure that the description of the
projects product is correct and complete.
12. Question: Because of the change in scope of your project, you may
have to do all the following except:
1. Co-ordinate changes across knowledge areas
2. Do Scope Planning
3. Make changes to the project baselines
- 29 -
4. Perform Configuration Management
13. Task Dependencies are not evident in a WBS. WBS does not specify the
time frame in which different tasks should be accomplished.
14. Question: You are the Project Manager for a construction company
responsible for developing an estate. During implementation time,
you spend some time with your team overseeing the work being
done by them. You will require all the following tools except 4
1. Product Skills and Knowledge
2. Work Authorization system
3. Organizational procedures
4. Earned value Management
15. During Project Plan Execution, which area will the Project Manager
spend least time on Documentation
16. Anytime there is a potential request for a change from a customer,
1. Understand what functionality was requested - Talk with team-
members to access the implication of the change
2. Open up a Change Control if there is a formal Change Control
Mechanism
3. Communicate the change to Management, and inform Customer about
the impact of the change (e.g. increase in sizing, schedule etc.)
4. If change is accepted, go ahead and implement the changes
17. Lessons Learned: The causes of variances, the reasoning behind the
corrective action chosen, and other types of lessons learned should be
documented so that they become part of the historical database for both
this project and other projects of the performing organization. The
database is also the basis for knowledge management.
18. Integrated change control is concerned with a)influencing the factors that
cause changes to ensure that changes are agreed upon b) determining
that a change has occured, and c) managing the actual changes when
and as they occur. The original defined project and the integrated
performance baseline must be maintained by continuously managing
changes to the baseline, either by rejecting new changes or by approving
changes and incorporating them into a revised project baseline.
19. If you would like to find out who will be approving changes in your
project, you can refer to the CCS
20. Integrated change control includes coordinating changes across
knowledge areas. For example, a proposed schedule change will often
- 30 -
affect cost, risk, quality and staffing.
Please note that amongst the available alternatives, Procurement will not
be impacted unless you have outsourced some work and that work will be
impacted by your schedule change. All the remaining control processes
(i.e. Cost, Scope and Staffing) are directly impacted by a proposed
schedule change
1. Projects involve doing something that has not been done before and
which is, therefore, unique. A product or service may be unique even if the
category to which it belongs is large....
- 31 -
9. Preparing a financial plan requires both Project Management and Industry
specific skills
10. Project life cycles generally define what technical work should be done in
each phase
11. Question: Which of the following statement(s) about project
customer and project sponsor is (are) correct? 4
1. Along with the customer, the sponsor threshold for risks should be
taken into account
2. Along with the customer, this sponsor may provide key events,
milestones, and deliverable due dates
3. Along with the customer, the sponsor formally accepts the product of
the project.
4. All of the above.
12. Politics is about getting collective action from a group of people who may
have quite different interests. It is about being willing to use conflict and
disorder creatively. The negative sense, of course, derives from the fact
that attempts to reconcile these interests result in power struggles and
organizational games that can sometimes take on a thoroughly
unproductive life of their own.
13. In a matrix organization, Project Manager does not have authority about
doing Personnel Performance Management; this task is done by the
Functional Managers.
14. As a project Manager, Problem solving is high in your list of
priorities. Which statement about Problem Solving is not accurate?
4
1. Problem solving involves a combination of problem definition and
decision-making
2. Problems may be technical, managerial or interpersonal.
3. Decision Making includes analyzing the problem to identify viable
solutions, and then making a choice from among them
4. You should try to solve a problem as soon as it is identified
- 32 -
18. Core processes: Some planning processes have clear dependencies that
require them to be performed in essentially the same order on most
projects. For example, activities must be defined before they can be
scheduled or costed.
19. You are one of ten full-time project managers in your organization.
You all share two administrative persons. There are generally 30 - 40
projects per year that involve about 30% of the organization
employees - however, these employees do not report to you. Your
organization can best be classified as: 2
1. Projectized
2. Balanced
3. Strong Matrix
4. Weak Matrix
• Establishing Direction...
• Aligning People...
• Motivating and Inspiring...
22. Subprojects within projects may have distinct project life cycles. For
example, an architectural firm hired to design a new office building is first
involved in the owners definition phase when supporting the construction
effort. The Architects design project, however, will have its own series of
phases from conceptual development through definition and
implementation and closure
23. Question: You are a project manager in an Information
Technology(software) company, but you recently got an offer as a
project manager in a construction company with 25% salary hike.
You have excellent technical knowledge in software field, but do not
have much exposure to the Construction Industry. In this context,
3
1. You should attend training classes related to construction industry
to get more technical expertise in the field
2. You should not take up the assignment because you will lose out
on the experience and skills gained in Information Technology field
- 33 -
3. You should take up the assignment because similar project
management skills will be required in the Construction company, as
was required in the software company
4. You should try to get more information about project management
in the Construction Industry and then make an informed decision about
whether to take up the new opportunity
24. When properly defined, the scope of the project - the work to be done -
should remain constant even as the product characteristics are
progressively elaborated
25. Major categories of socio-economical influences are:
• Standards and Regulations
• Internationalization
• Cultural Influences
• Socio-Economic Environmental Sustainability
- 34 -
TOTAL NUMBER OF QUESTIONS IN FRAMEWORK = 54
10. The only situation where a contract may be nullified is because it violates
the law of the country.
11. A procurement audit is a structured review of the procurement process
from procurement planning through contract administration.
- 35 -
12. Evaluation Criteria are an input to Source Selection, not contract
administration
13. Incentives are provided in contracts to ensure that the goals of both the
buyer and seller are the same
14. Independent Estimates (which is a Tool/Technique for Source Selection):
For many procurement items, the procuring organization may prepare its
own independent estimates as a check on proposed pricing.
- 36 -
21.
22.
- 37 -
24. Statement(s) of Work: The statement of work (SOW) describes the
procurement item in sufficient detail to allow prospective sellers to
determine if they are capable of providing the item. "Sufficient detail" may
vary, based on the nature of the item, the needs of the buyer, or the
expected contract form.
25. Procurement audits: A procurement audit is a structured review of the
procurement process from procurement planning through contract
administration. The objective of a procurement audit is to identify
successes and failures that warrant transfer to other procurement items on
this project or to other projects within the performing organization.
26. Early Termination of a contract is a special case of contract closeout
27. The product description is generally broader than a statement of work. A
product description describes the ultimate end product of the project; a
statement of work describes the portion of that product to be provided by a
seller to the project. However, if the performing organization chooses to
procure the entire product, then the distinction between the two terms
disappears.
28. The statement of work(SOW) describes the procurement item in sufficient
detail to allow prospective sellers to determine if they are capable of
providing the item. "Sufficient detail" may vary, based on the nature of the
item, the needs of the buyer, or the expected contract form.
RISK MANAGEMENT
- 38 -
2. Analyzing numerically the probability of each risk and its impact on the
project objectives
3. Determining actions to enhance opportunities and reduce threats to
project objectives
4. Keeping track of identified risks and ensuring execution of risk plans
1. Risk Mitigation
2. Risk Avoidance
3. Simulation
4. Project Assumptions Testing
10. 10. Question: While doing risk response planning, you realize that there is
a very critical risk which may have a high impact on the project
completion. So, you create a fallback plan which could include any of the
following conditions EXCEPT: 1
1. Subcontracting the project to an outside Vendor
2. Developing Alternative Options
3. Allocation of Contingency Reserves
4. Changing project scope
11. The probability of the activity happening every year is 25%. So, the
probability that the task will happen in the 3rd year is also 25%
12. Qualitative Risk Analysis requires accurate and unbiased data if it is to be
helpful to project management. Data Precision Ranking is a technique to
- 39 -
evaluate the degree to which the data about risks is useful for risk
management.
13. Workarounds are unplanned responses to emerging risks that were
previously unidentified or accepted. Workarounds must be properly
documented and incorporated into the project plan and risk response plan.
14. Question: All the following statements relating to transferring of risk
to a contractor are true EXCEPT: 2
- 40 -
1. Suggest that the project to proceed ahead
2. Suggest that the project to be stopped
3. Communicate to your senior management that you cannot make a
decision about whether to proceed with the project
4. Start working on the project and ask your finance manager for
additional information.
- 41 -
26. S-curve: Graphic display of cumulative costs, labour hours, percentage of
work, or other quanitities, plotted against time. The name derives from the
S-like shape of the curve (flatter at the beginning and end, steeper in the
middle) produced on a project that starts slowly, accelerates and then falls
off. Also a term for the cumulative likelihood distribution that is a result of a
simulation, a tool of quanitative risk analysis.
27.
28. The risk response plan (sometimes called the risk register) should be
written to the level of detail at which actions will be taken.
Framework 54
Integration Mgt 47
Scope Management 71
Cost Management 63
Time Management 75
Quality Management 48
HRM 47
Communications Mgt 47
Risk Mgt 53
Procurement Mgt 48
Professinal Resp 47
- 42 -
600
- 43 -