BPU.PHB shall provide reliable poBPU.PHBr supply to all premises in UTM with
99.99% reliability equal to not more than 87 hours of breakdowns per year.
BPU.PHB shall ensure that all MV equipments in all the sub-stations are checked and
visited by Competent Professional Engineer according to the visit schedule.
According to act 447 clause 61.
BPU.PHB shall abide to Akta Bekalan Elektrik 447: 2000 and safe working practices.
BPU.PHB shall abide to Akta Bekalan Elektrik 447: 2000 and safe working practices
by SIRIM.
Users/Occupants shall make sure that budget is available with any new installations
of work cubicles, needing power supply.
Any new installation of socket outlets exceeding 1000 meter square of building
space, during any space renovation, during defect liability period of the renovated
space shall be forwarded to Upgrading Unit.
Any temporary electrical installation shall have permission from Head of Electrical
Unit BPU.PHB.
STREET LIGHTING P OLICY
All street lighting units owned by UTM are maintained to a standard that ensures as far as
possible their safe, functional and reliable operation. Main requirements are:
To ensure that essential electrical service is provided in selected areas of the University when
normal electrical supply is interrupted, emergency power systems supplied by generator sets can
provide an alternate source of electrical power in buildings and facilities as required.
As required by the UBBL for academic and office buildings, an emergency power system shall
be provided and have a power source and fuel supply sufficient to operate the following
equipment:
Firemen lift.
Alarm systems.
Communications systems.
Stair pressurization.
Main Information, Communication & Telecommunication System Room
Sensitive equipments connected to UPS, such as long duration tests done, due to
interruption of power supply there is a safety risk/hazard to the building occupants such as
spillage of toxic waste, explosion or radiation. (Client shall provide budget and annual
maintenance & operational expenditures shall be borne by client)
All maintenance work will be carried out in accordance with the Generator set Maintenance
Contract. This contract has a contract period of two years with extension possibilities and
contains all operational standards.
To ensure that very essential electrical service is provided in selected areas of the University
when normal electrical supply is interrupted, emergency power systems supplied by an
uninterruptible power supply (UPS) can provide an immediate source of electrical power in
equipments in not less than 15 minutes back-up time to allow users to conduct emergency
procedures such as equipment proper shutdown.
An UPS emergency power system shall be provided and have a power source and fuel/battery
supply sufficient to operate the following equipment:
Alarm systems.
Sensitive equipments such as long duration tests done, due to interruption of power supply
there is a safety risk/hazard to the building occupants such as spillage of toxic waste,
explosion or radiation. (Client shall provide budget and annual maintenance & operational
expenditures shall be borne by client)
All maintenance work will be carried out in accordance with the standard UPS Maintenance
Contract. This contract has a contract period of two years with extension possibilities and
contains all operational standards.