Академический Документы
Профессиональный Документы
Культура Документы
OTC 18681
The modification of these oil tankers that worked as FSOs swivel stack to receive the large number of risers that would
almost continuously for more than 5 years was minimal. The bring the oil from subsea manifolds.
FSOs/FPSOs of this phase were typically fast-track and Instead of leaving a floating hose in the water to export the
limited scope conversions of mid-size tankers (Panamax or oil, submerged hoses stored between offloading operations in
Aframax size), for temporary production or storage, without a cradle alongside the ship were used to connect the FPSOs to
any gas exportation or water injection facilities, moored by dedicated Shuttle Tankers that were equipped with Bow
CALM buoys. Other important characteristics of those units Loading Systems (BLS).
are shown in Table 2. In the first units, the ship Main Steam Boiler was used to
We can consider this first phase, the beginning of our generate energy for the FPSO, as it was a common practice in
learning curve - P.P.Moraes was a floating lab to test the the marine industry. However, after experiencing severe
design and the operation of an FPSO. The most important problems in the operation of P-31 boilers, we concluded that
lessons learned from this phase were related to the best way to this equipment was too cumbersome to be used in an offshore
moor ship-shaped floating units in the Campos Basin, the permanent facility. So, beginning with the FPSO P-35, it was
behavior of those units under beam seas conditions and the decided to fully remove the existing Steam System of the ship
effect of the movements over the process plant. and install new Turbine Generators to supply the energy
Long 15 years after the first use of P.P. Moraes as a demand required by the FPSO.
production unit, we decided, in 1994, to use this ship in a large In order to comply with the expected field life where the
Pilot System for the giant Barracuda Field renaming the old FPSO would be designed to operate, all existing systems of
lady to FPSO “PETROBRAS-34”. Due to the large number of the vessel were refurbished (“As-New” philosophy). Another
risers (34), it was decided to use a turret system to moor the life-extension strategy was to use some special materials,
FPSO. This was the first turret moored FPSO in the Campos especially in marine systems, such as Copper-Nickel in the
Basin (Fig.4). A new process plant, including Gas Firewater System, Centrifuged Cast Steel (CCS) in the Oil
Compression facilities was installed at the FPSO that began Cargo System and FRP in the Sea-Water Lift System.
operation in 1997 and operated continuously for more than 6 After this first series, when 5 FPSOs were contracted even
years until its demobilization in 2003 (Ref.1 and 9). before the first one had entered into operation, we contracted
We can consider P-34 conversion as the transition design the conversion of two FSOs for the new Roncador (P-47) and
from Phase I to Phase II. In this project, the unit was still mid- the Marlim South (P-38) fields. Those Units had similar
sized, for an Early Production Project, without Water Injection characteristics of the 5 FPSOs, such as turret moorings and
facilities. On the other hand, the unit already showed points full scope of marine conversion to comply with the long term
that would characterize the large FPSOs of Phase II, such as design life.
the extensive refurbishment scope, the large turret mooring All those Units are still in operation today and the first one
and the unit conversion done in one big Lump-sum, installed, the FPSO P-31, is in continuous operation for more
Engineering Procurement and Construction (EPC) Contract. than eight years, now. Despite the limitations that those Units
present in the Oil and Water Treatment plants, some minor
Phase II structural problems that were found in the hull (fatigue cracks
In the beginning of the 90s, the continuous increase in inside tanks) and the operational problems in the oil export
production output from the Campos Basin led to a re- systems, those FPSOs have so far been presenting a very high
evaluation of the Basin export system, since the existing operational efficiency, above the average of the Campos Basin
pipelines were already operating at maximum capacity. For Units (that include also fixed and semi-submersible production
the transport of oil from the new Marlim and Albacora giant platforms). These results demonstrated that the use of FPSOs
deep water fields, it was concluded that using FPSOs would be in the Campos Basin was a correct strategy, but also that there
more attractive than the standard solution of FPUs (based on was some room for improvement in the design.
semi-submersible platforms) which would require duplication
of the existing onshore pipeline network (Ref. 6, 7). Transition Phase II-Phase III:
So, we began, almost at the same time, the conversion of 4 In the beginning of 2000, we began the project for two new
FPSOs, namely Vidal de Negreiros (P-31) for the Albacora FPSOs for the Barracuda and Caratinga Fields (P-43 and P-
Field, and Cairu (P-32), Henrique Dias (P-33) and Jose 48), in the Campos Basin. These projects can be seen as a
Bonifacio (P-35) for the Marlim field. All of them were based transition from Phase II to Phase III, since we can already see
on conversion of VLCC tankers (Very Large Crude Carriers) points that would characterize the FPSOs of Phase III, such as
from our own fleet. A few months later, a fourth FPSO for the the Spread Mooring System, the process plant modularization
Marlim Field (P-37) was also contracted. philosophy and the use of Moto-Compressors instead of
For the first time in Brazil, FPSOs were to be used as Turbine Compressors. The reasons for adopting these
permanent production facilities for the full life of the oilfields solutions may be summarized as follows:
(20 years). In order to comply with this task, the Units were all 1) Elimination of subsea manifolds: aiming to reduce the
converted from large sized tankers (VLCCs) that received subsea production losses and to take the subsea equipment
large process plants (100,000 bpd) installed in a production supply out of the critical path of the project;
deck (“pancake”) over the ship’s deck, with full Gas 2) Spread Mooring: without the restrictions in the number
Compression, Water Treatment and Water Injection facilities. of risers presented by the turret, the SMS allowed the
All Units comprised large diameter internal turrets with a big connection of all risers and umbilicals (almost 100) directly to
the Unit, aiming to eliminate the subsea manifolds;
OTC 18681 3
3) Plant Modularization: allowed the division of the plant present in the injected water, there was a high risk of scale
construction work scope by several different yards, working in formation that would clog the production wells. In the FPSO
parallel, aiming to expedite the construction time; P-50, the installation of a Sulphate Removal plant allows the
4) Use of Moto-Compressors: aiming to increase the reduction of sulphate content in seawater from the original
reliability of the Compression System and to reduce its 2,800 mg/l concentration to 100 mg/l or less, with
commissioning time; approximately 75% of efficiency.
5) All-new conversion philosophy (adopted since P-37 Another benefit of the SRU is that it reduces the
project): aiming to guarantee the equipment and piping design probability of souring (generation of H2S inside the reservoir
life; by sulphate reduction bacteria).
6) Metallization: Thermal Spray Aluminum was
extensively used in pressure vessels and piping operating at P-50 Design Concept
high temperatures as well as in critical areas for maintenance, In order to face the challenges presented with the
such as the flare boom and the crane pedestals, aiming to increasing size and complexity of the plant some objectives
reduce the operational maintenance cost; were pursued in the P-50 design. It was of paramount
7) Cargo Handling System: a monorail was installed along importance to improve the Unit’s constructability, operability
the ship, from the quarters´ area up to the turret, passing and reliability (Ref. 10). The main strategies used to achieve
through all the process plant, aiming to facilitate the these objectives were the modularization philosophy, the use
movement of equipment and parts inside the FPSO. of self-contained equipment packages and the life-
enhancement measures adopted, as explained below:
Phase III
The main characteristics of the FPSOs of this phase that begun Modularization
with the FPSO P-50, are shown in Table 2. It is important to In the first wave of FPSOs, the equipment skids were directly
stress that the development strategy for the P-50 project installed over a pancake structure over the ship-deck.
presented two basic differences from our previous offshore Beginning with the P-37 project, the design was changed in
projects: order to divide the plant in large modules that would be built
i) The EPC Contract was divided into 5 separate packages separately and would be later integrated over the ship.
(Compression, Generation, Process, Utilities and Modules Arrangement
Conversion/Integration) as described in Ref. 13; The modules arrangement typically presents the Gas
ii) A longer FEED was developed, giving the opportunity Compression and Treatment in the bow. The Separation
to improve the FPSO design, taking into account all the Modules are installed amid-ships followed by the Gas
experience we had gathered from the design and operation of Generators. The Utilities (Electrical, non-electrical) and Water
previous FPSOs. Injection Modules are installed more to the stern, closer to the
Ahead you will find the main characteristics of the P-50 FPSO quarters, as shown in figure 8.
project, which were replicated in our next two FPSO projects It is important to remark that the modularized design
(P-54 for the Roncador Field and P-53 for the Marlim Leste allowed the strategy of contracting the Generation and
Field). Compression Modules separately from the rest of the FPSO.
This strategy was used first in P-50 and repeated in all our
subsequent projects, because it allows a direct contact between
P-50 Project our PETROBRAS and the equipment supplier, facilitating the
The Challenge design improvement and the commercial relationship.
We can understand the challenge that was presented in the P- Module Support and Installation
50 project analyzing the graphic shown in figure 5 that Instead of a truss structure supporting the plant “pancake”
summarizes the increase in the capacity and complexity of the (figure 9), pyramidal stools (figure 10) were used to support
FPSOs from Phase I up to Phase III. With a topsides weight of the FPSO modules. All the necessary structural reinforcements
almost 20,000 mtons, P-50 presents the largest and heaviest to support the modules were done inside the tanks, in order to
plant ever installed in an FPSO in Brazil. Figure 6 shows the reduce the obstruction over the ship-deck. With this target in
evolution of the plant size from P-34 up to P-50 (figure 7). mind, only 4 supporting stools per module were used in P-50
Due to the characteristics of the Albacora Leste reservoir instead of the 6 that were used in previous FPSOs (P-
(Ref. 8), P-50 plant also required some specific treatment 37/43/48). On the negative side, this structural concept with
modules that had never been used in our previous FPSOs: large span module beams and huge stools resulted in a heavier
1) CO2 Removal System: structure – because of that, this concept is now under
Due to the high CO2 content in the Albacora Leste oil, a reevaluation and the use of truss structures is under analysis
CO2 Removal Unit was installed between the second and third for new projects.
stages of the gas compression system. The unit reduces the The operation of lifting P-50 modules and their installation
CO2 content from 5% to less than 2%, by means of an Amine over P-50 was made by the crane barge Kasei in 2004. The lift
(MEA) absorption process. of the Utilities Module (1,473 mtons) broke the record of the
2) SRU – Sulphate Removal Unit: heaviest lift ever made in Brazil (this record was broken again
The Albacora Leste reservoir water analyses showed the in January, 2007, when the same crane-barge lifted a 1,644
presence of barium (70 mg/l) and strontium (500 mg/l) in the mtons module from P-54).
reservoir. Since those salts can be combined with the sulphate
4 OTC 18681
After the installation of P-50 modules over the ship stools, Besides that, all the marine systems with connections to
it was verified that the modules supports did not perfectly the cargo and ballast tanks, such as the cargo, auxiliary,
match the stools positions, due to the differences in the as- loading and inert gas systems had their main headers built in a
built dimensions of the modules, fabricated in many different ring shape form instead of the traditional fishbone
sites, and the stools. It was necessary to install a large amount configuration seen in most FPSOs. The main target of this
of reinforcements in the modules supports and in the stools concept was to reduce the amount of transversal lines over the
which severely impacted the FPSO modules integration main deck, improving the arrangement of the Unit and the
schedule. Three different kinds of problems were detected ventilation and access to this area.
after the modules installation: 2) Sea Water Lift System for Water Injection:
Lack of support: In four modules, only 3 of the 4 The Sea Water Lift system for water injection uses flexible
supports made contact with the stool, due to vertical risers that go down to 30 m below the deck for water intake,
misalignment of the supports. In the worst case, one of aiming to obtain a better seawater quality for the injection
the module’s support was found “floating” 26 mm system. However, such injection system represents only 20%
above the stool top plate; of the total lift flow rate (the remaining is taken for cooling,
Insufficient contact between the module support industrial use, fire fighting, etc). So, we decided to use a
bottom plate and the stool top plate: this was a dedicated system for this function, with submerged electrical
generalized problem that happened due to the lack of lift pumps.
flatness of the plates, as it can be seen in the picture in Compared to the option of installing the pumps inside the
figure 11. The “bending” of the plates´ edges was pump room, this solution is much better in terms of
found to be much above the tolerance limits defined constructability and operationability, and contributed for a
for the structural fabrication; more efficient arrangement since the pumps are closer to the
Horizontal misalignment: in one third of the stools, the water injection module.
centerline of the module support was so displaced in 3) Fire Fighting System:
relation to the center line of the stool, that there was In our previous FPSOs, dry-mounted diesel hydraulic
not enough space for welding. firewater pumps were used. In P-50, it was used a new concept
These problems generated a lot of concern, because in our of diesel hydraulic pumps where a submerged hydraulic
next FPSO project (P-54) the same exact design was being booster pump was connected through a pipe-stack to the diesel
adopted, and the stools were already under fabrication. In P- driven lift pump that was installed in a dedicated compartment
54, however, a more rigid dimensioning control was adopted, over the main deck. In this concept, the booster pumps and the
as well as some preventive measures, such as the grinding of pipe-stacks were installed inside internal steel caissons, fitted
the stools´ top plates. Fortunately, those measures proved to be inside the ship’s original bunker tanks.
effective, and we did not find the misalignment problems that The main objective of this concept was to avoid the
were faced in P-50. installation of new pipelines (hydraulic and firewater lines)
Aiming to give more flexibility to construction and inside the Engine Room and to avoid the construction or
assembly, an improvement was adopted in our following conversion of compartments inside the Engine Room or the
FPSO project (P-53): a transition box (that was already used in ship’s Original Steering Gear Flat for the installation of
previous projects such as P-37 and P-43) was installed over booster and lift pumps.
the top of the stool (figure 12), giving space for adjustments 4) Offloading System:
during the modules installation. In our previous FPSOs, cradles were installed along the
Finally, in P-57 a more radical modification was conceived ship, from bow to stern, to store the offloading hoses, a system
- a shorter stool was designed to support the leg of the module that has the disadvantage of increasing the congestion of the
that was extended (figure 13). This is the same stool concept FPSO deck.
adopted in big FPSO projects in Africa, and, with this concept The first FPSO to use an Offloading Hose Reel in the
we are confident that the modules support adjustment will be Campos Basin was the FPSO Seillean, a chartered
much easier. Dynamically Positioned FPSO (Ref. 5) that was equipped with
a Hydraulic Reel designed to store a 350m-long, 12-inch hose.
Equipment Packages As P-50 was moored in a fixed azimuth by the spread
The intention of P-50 design was always to minimize the work mooring system, two Offloading Stations were required, one at
inside the FPSO hull and to maximize the new buildings in the the FPSO Bow and the other at the Stern. Each Hose Reel is
conversion in order to make the works easier and faster. The completely independent, with individual HPUs, what avoids
design of those systems, fully discussed in Ref. 10 and 11, is the need of hydraulic lines along the Unit.
summarized below. The first Offloading operation in P-50 was successfully
1) Marine Systems: performed in 19 may, 2006, with the Ataulfo Alves Shuttle
P-50 was our first FPSO project that adopted hydraulic Tanker from our own fleet (Transpetro).
submerged cargo and ballast pumps. The benefits in terms of 5) Chemical Products Injection System:
constructability for the project are evident, as there is no need P-50 Chemical Products Injection System was designed
to assemble neither a new cargo pump room, nor new cargo considering a centralized filling and distribution system for the
lines inside the tanks since all cargo lines will run over the chemical products, in order to increase the safety of the
deck. All cargo and ballast valves inside the tanks are also activities of receiving and handling these products.
eliminated with this kind of pumps.
OTC 18681 5
Fixed tanks that are supplied with products stored in large based on the feedback obtained from similar projects in the
containers were installed in P-50. Flexible hoses link the Campos Basin. Albacora Leste oil samples showed the
containers or gallons of chemical product and the rigid supply presence of CO2 (from 2.5% to 5.6% mol) in the crude
line to the fixed tank to be fed. A connector that may be composition, as well as a high level of chloride. Besides, the
quickly actuated and the opening of two valves allow the required separation temperature of 110ºC resulted in a
transference of the product by gravity, preventing the operator limitation of the material and coatings that could be used in
to come in direct contact with the dangerous chemical the plant.
products, making this operation safer than the conventional During the Front-End Engineering Design stage of the
system of handling small chemical products containers. project, a decision tree analysis for each stream of the process
6) Mooring System: plant was performed, in order to decide the most suitable
The use of a spread mooring system in P-50 lead to an material for all piping and equipment of the plant.
adequate and optimized subsea lay-out since all the wells For a better assessment of CO2 corrosion and other effects,
could be directly connected to the side of the FPSO, thus, the plant was subdivided into 13 branches, from the inlet lines
eliminating the need of subsea manifolds. at the platform manifold up to the gas dehydration system. The
The mooring system designed for P-50 is an 18-line, equipment data was collected and filled in a worksheet with
partially compliant spread mooring system, with 10 lines in some key process parameters, such as pressure, temperature,
the bow and 8 lines in the stern. Polyester ropes and steel CO2 percent mol, oil and water flow of all fluid in & outlet.
chain in a semi-taut configuration compose all mooring lines. The worksheet allowed the calculation of partial CO2 pressure
The concept and installation of P-50´s mooring system is fully and BSW%, and suggested the best material to be used,
described in Ref. 12. including special materials such as Duplex Stainless Steel.
The mooring system comprises one winch for the bow 2) Metallization and Coating:
lines and another winch for the stern lines. The mooring chain In our first FPSOs, it was necessary to repair large areas of
comes from vertical chain-pipes, passes through a horizontal the hull after a few years in operation in the site. We
sheave, the horizontal winch turn-down sheaves and then, concluded that the problems were caused by the conditions in
down to the fair-leads. which the paints were applied at the shipyard, specially the
During the hook-up of the mooring lines, a big problem high humidity that impaired the quality of the coating and
occurred with the turn-down sheaves: the sheaves plates begun provoked early paint warn out.
to distort (Fig. 14), reaching very high deformations with risk So, we started to test new kinds of paints in our
of structural collapse, even before the pre-tension load was laboratories, looking for paints with resistance to humidity and
achieved. A detailed structural analysis showed that the sheave salt presence in the substrate. After some years of tests, we
was not strong enough to resist the load imposed by the chain finally found a kind of paint that fulfilled our needs, because it
when it rotated around the sheave (Fig. 15). The sheaves had works with a different curing process, absorbing all the water
to be disembarked and reinforced to allow the conclusion of present in the surface in this process. This paint was also more
the pre-tension of the mooring lines. suitable to be used after hydro-blasting, which is a better
7) Pull-In System: surface preparation process (compared to dry-blasting) in
The Pull-in System comprises a lower riser structure, terms of elimination of the salinity present in the surface. This
where I-tubes guide the flexible lines and an upper riser kind of paint begun to be used in P-43 and was extensively
structure where the risers are supported. A pull-in structure used for the coating of P-50 hull as well as in all tanks, voids
over the upper riser structure supports the pull-in winches and and in the structures of the modules.
pulleys. All those structures were installed at the port side of Since P-43 also, we adopted the philosophy of increasing
the Unit. the use of metallization (TSA) in order to enhance the life of
The benefit of having the Mooring and Pull-in Systems piping and vessels that presented high rate of corrosion in
located at the ends and sides of the FPSO is clear when we former units. It was required that large structures such as crane
compare P-50 lay-out with P-53 layout. In P-53, a turret was boom and frame and flare boom as well as equipment with
used to moor the unit instead of a Spread Mooring System due operation temperature above 90ºC, should be metallized with
to subsea layout optimization reasons. The large diameter aluminum.
turret for 75 risers/umbilicals weighting almost 10,000 tons 3) Structural Life:
was installed in the bow, between tanks 2 and 3. This position Since the Phase II FPSOs, we were improving our criteria
of the turret, chosen in order to reduce the movements for Plate Renewal in order to guarantee that the ship’s
imposed to the riser resulted in a negative impact in the Unit’s structure could withstand the corrosion and fatigue
general arrangement: the gas treatment module had to be requirements for an excess of 20 years in the field, without
installed ahead of the turret and all the piping from the process dry-docking.
plant had to go around the turret, to reach the module. A In was required that no plates with thickness lower than the
comparison between the piping weight of P-50 and P-53 Substantial Corrosion thickness (as defined by the
demonstrates the advantage of P-50’s layout. Classification Society) at the end of the design life should be
allowed – non complying plates should be replaced. To
Life Enhancement Strategies: comply with this requirement, the actual thickness measured
1) Material Selection Process: were compared to the limits defined by a formula that took
The Albacora Leste Field’s characteristics motivated the into account the predicted corrosion in 25 years and the
review of the material selection philosophy for the P-50 FPSO minimum thickness required by the structural analyses. This
6 OTC 18681
180
160
Phase II Phase III
2
140
120
100
Phase I Phase IV
80
1
Oil Processing (1000 bpd)
60
Separation Temperature (0C)
40
Gas Processing (100000 m3/d)
Units
20
Electrical Demand (MW)
0 0
Water Injection (1000 m3/d)
1987 1990 1993 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 Phase I
Phase II
Year Phase III