Eng M 530 – Engineering Project Management

Laboratory Development Project

In-Class Assignment: Risk Register

Team Members:

Luke Glistak
Sean Hodgson
Shannon MacDonald
Mk Nimesh
Anand Rohit

Phone: 780.235.0191 | Fax: 780.483.2519 | 6819-95 Avenue, Edmonton, AB, T6B 1A9 | www.chromeeng.com
Risk Register

Probability Probability Cost Schedule Risk Risk


# Risks Risk Type Impact Rating
Level Rating Impact Impact Owner Response
Roger
Physical injury
Marchand /
1 (during moving Safety 0.10 0.80 8.0% Medium $10,000 2 days Call 911
Mike
or installation)
Lipsett
Late arriving Mike
2 Equipment 0.30 0.05 1.5% Low $0 7 days Call vendors
furniture Lipsett
Power failure
during lab Roger Reschedule
3 Equipment 0.10 0.05 0.5% Low $0 1 day
equipment Marchand move
commissioning
Contact IT
Failure of UWS department for
4 Equipment 0.10 0.05 0.5% Low $200 4 days AICT
connectivity placement of
wireless router
Order
Damaging replacements
Roger
5 equipment Equipment 0.10 0.20 2.0% Low $1,000 14 days from Vendors
Marchand
during move (inform
Students too)
Movers are Roger Reschedule
6 Personnel 0.10 0.10 1.0% Low $500 2 days
absent Marchand move
Order
replacements
Damaging Mike
7 Research 0.10 0.05 0.5% Low $1,000 7 days from Vendors
experiments Lipsett
(inform
Students too)
Reschedule
Roger
8 Failed drainage Facility 0.10 0.05 0.5% Low $4,000 21 days move, assess
Marchand
damage
Exploding Mike Call 911,
9 Facility 0.10 0.80 8.0% Medium $20,000 31 days
equipment Lipsett evacuate
Roger
10 Pipe burst Facility 0.10 0.40 4.0% Low $10,000 31 days Reverse move
Marchand
Available
inventory Mike
11 Equipment 0.10 0.10 1.0% Low -$1,000 -7 days Don't order!
matches Lipsett
requirements
Update move
Power outlets
Mike map, update
12 don't match Facility 0.20 0.10 2.0% Low $50 4 days
Lipsett schedule
layout
accordingly
Roger
Fire alarm
Marchand / Reschedule
13 pulled during Facility 0.10 0.10 1.0% Low $0 1 day
Mike move
move
Lipsett
Update
Building codes requirements
change for Roger for
14 Facility 0.10 0.20 2.0% Low $2,000 14 days
regulatory Marchand procurement
items and move
schedule
Reschedule
15 Elevator fails Facility 0.10 0.05 0.5% Low $0 4 days Facilities
move
Team #1 – Personnel Listing

Shannon MacDonald
Project Manager
Mec E

Mk Nimesh
Devil’s Advocate
Eng. Mgmt.

Luke Glistak
Team Member
Mec E

Sean Hodgson
Team Member
ECE

Anand Rohit
Team Member
ECE