CONSTRUCTION

The new FIDIC Contract:


Design Build Operate
By Edward Sunna, Head of Department
Construction and Engineering Department

The long awaited FIDIC Design Build Op-


erate Contract has finally been published
by FIDIC. The purpose of this article is to
provide readers with a general overview
of the new build contract and its intended
application.

The use of FIDIC based agreements in


the Gulf formed the subject of some of
our articles in our Law Up Date published
in 2007. The growth of the public - private
partnership model in infrastructure proj-
ects in the Gulf has strongly contributed
to the introduction of a standardized yet
sophisticated contract model produced
by FIDIC to service the ever expanding
range of projects in the Gulf region.

Characteristics of the new


DBO Contract
As the title suggests, the contract is
LAW UPDATE

intended to govern the relationship be-


tween the Principal and the Contractor
involved in a multidisciplinary contract:
to design, build and operate as opposed
to individual agreements to govern the
different facets of a project. The Contrac-
tor in these arrangements is ordinarily

29
CONSTRUCTION

a corporate entity specifically set up to operation, however it is needless to say ing the project specific terms and condi-
reflect the interests, roles, obligations that each project needs to be considered tions of the DBO, particularly during the
and liabilities of parties comprising the on its known requirements particularly in operation phase and the consequences
corporate entity e.g. a consortium. Each addressing issues such as early termina- of the Parties rights following early termi-
party will have a specific input into the tion or the transfer of the asset at the nation, transfer or closure of any Project
consortium such as funding, design, con- end of the term or following early termi- at any particular phase. In the Gulf, mar-
struction, operation and maintenance. nation. ket it is always importance to reconcile
The extent of the parties’ contribution will the contract provisions with the local
depend on the nature of the project and Advantages of a DBO laws, particularly of government which
the commercial and legal terms agreed The combination of a number of disci- may often contain implied provisions
with the sponsor of the project i.e. the plines and the reliance on a consortium unknown at the time of execution of an
employer. or a joint venture to deliver a project has agreement.
its obvious advantages in saving time
Contract Flexibility and simplifying contract administration.
The new form contract takes into account Multiple tasks can be undertaken simul-
the possibility of the varying types of DBO taneously without reliance on parties out
arrangements, the agreement itself is side the project team and with the opera-
designed on what is commonly known tion period, it is likely that the Contractor
as the ‘green field approach’ which es- will be the most suited to operate and
sentially follows the traditional structure maintain, if necessary, the facility it has
of the build operate, whereas the ‘brown designed and built. In this respect, it is in
field approach’ of operate, design and the interests of the contract to produce a
build albeit not adopted by FIDIC as the low maintenance quality design and op-
standard format can still be utilized by fol- eration given its long term commitment to
lowing the instructions in the guidelines operate the project on completion, which
produced along with the agreement. mutually serves the Employer’s interests
of having a quality built and designed low
Similarities with other FIDIC cost maintenance project.
Contracts
The new agreement adopts the same Conclusion
format of existing FIDIC contracts (RED, The new form FIDIC DBO is a welcomed
Yellow, Silver, White Books) and further addition to the FIDIC suite of agreements
retains the style and most of the common which can be credited with introducing a
definitions, paragraphs and structures structured regime for DBO projects which
that make FIDIC unique. are often complicated or disjointed. The
growth in popularity of DBO type projects
The core of the new agreement and its are expected to increase in the Gulf and
function is found in clause 9 entitled ‘De- FIDIC is likely to again be the preferred
sign – Build’ which specifically provides model for DBOs in the future. However
for necessary elements to administrate caution should always be had with draft-
the design and build component.

The reader should note new definitions


specific to DBO projects have been in-
cluded in the new form. An example is the
definition of the ‘License Agreement’ to
regulate the operation component of the
agreement and corresponding authority of
the Contractor. Another noteworthy defini-
tion is that of ‘Cost plus Profit’, although
FIDIC provides for such a definition, we
suspect that in its practical application,
we would define parties amending such
definitions to account for project specific
definitions and exhaustive itemisation of
the costs component to avoid doubt or
miscommunication.

The Operate Component


The striking feature of the DBO agree-
ment is the usual intention of the parties
LAW UPDATE

to define the length of operation, which


in utilities or infrastructure type projects
involves a relatively more extensive dura-
tion than civil engineering projects to reap
the return on the capital investment and
ensure the project is viable to the Prin-
cipal, the Contractor and investors. The
new agreement accommodates long term

30