PROJECT : CADANGAN MEMBINA DAN MENYIAPKAN LEBUHRAYA PANTAI TIMUR (HULU TERENGGANU - KUANTAN)
EARTHWORK
1 Remove trees, undergrowth, bushes, scrub & - Hydraulic tracked excavator with backactor arm to grubbing up their roots. Operators- 3 1 - Excavated material- roots, 900m2 5
the like Hydraulic
trees, undergrowth,
excavator with
bushes, scrub
- Filling viod left by removal of roots with material araising from excavation. 1/2 m3 bucket
- Excavated materials loaded into lorries to be dumb 2km away from site. 5m3 Lorries 2 - lubrication oil, fuel
50.25
METHOD STATEMENT
PROJECT : CADANGAN MEMBINA DAN MENYIAPKAN BLOK TAMBAHAN SEKOLAH SECARA 'INDUSTRALISED BUILDING SYSTEM' (IBS) UNTUK SEKOLAH MENENGAH SRI PERHENTIAN, PONTIAN JOHOR.
1.3 Fit M.S Guide Fit M.S Guide near the plastic plates and face to the panel line and support with 2 skilled labour, 2 general 50mmx50mm M.S Guide,
timber support labour 25mmx50mm timber
1.4 Erection Wall panel 3 skilled labour, 1 general 1 3m x 3m x 120mm thk Wall sum 5 days
Erect the wall panel by using crane labour 16 tonne crane panel
Filling expendite cement Wet the joint before filling with the expendite cement mortar, and then fill and 5 days
compact expendite cement mortar properly and ensure there is no gap between
1.7 the panel and base slab. 4 skilled labour, 2 concretor Expendite Cement Mortar
Removal rubber hose After 1 hour, remove rubber hose and touch up the joint with expandite cement 3 days
1.8 mortar 4 skilled labour, 2 concretor Expendite Cement Mortar
Curing
1.9 After finishing grouting work, joint must be cured up to 7days
Plastering 20mm Thk Cement and sand (1:6) plastering to joint 1 skilled labour, 2 general
2.1 2290 m2 6 days
labour
Painting Prepare and apply approved skim coating to the vertical surfaces of the
precast concrete wall, one coat of alkali resisting primer sealer and two 2 skilled labour, 1 general
2.2 2290 m2 4 days
coats of emulsion paint labour