METHOD STATEMENT

PROJECT : CADANGAN MEMBINA DAN MENYIAPKAN LEBUHRAYA PANTAI TIMUR (HULU TERENGGANU - KUANTAN)

PREPARED BY: ARAH JITU SDN. BHD.

SEQUENCE OPERATION LABOUR PLANT MATERIAL ESTIMATED DURATION


METHOD
OF WORKS (No) Types (No) QUANTITY (Days)

EARTHWORK

1 Remove trees, undergrowth, bushes, scrub & - Hydraulic tracked excavator with backactor arm to grubbing up their roots. Operators- 3 1 - Excavated material- roots, 900m2 5
the like Hydraulic
trees, undergrowth,
excavator with
bushes, scrub
- Filling viod left by removal of roots with material araising from excavation. 1/2 m3 bucket

- Excavated materials loaded into lorries to be dumb 2km away from site. 5m3 Lorries 2 - lubrication oil, fuel
50.25
METHOD STATEMENT

PROJECT : CADANGAN MEMBINA DAN MENYIAPKAN BLOK TAMBAHAN SEKOLAH SECARA 'INDUSTRALISED BUILDING SYSTEM' (IBS) UNTUK SEKOLAH MENENGAH SRI PERHENTIAN, PONTIAN JOHOR.

PREPARED BY: NIA ASSOCIATES

SEQUENCE OPERATION METHOD LABOUR PLANT MATERIAL ESTIMATED DURATION


OF WORKS (No) Types (No) QUANTITY (Days)
1.0 Installation wall panel

Installation plastic plates


Install Plastic Plates used for precast panel levelling, which located at the centre 1 skilled labour, 3 general
1.1 line of wall panel. labour 50mmx50mm Plastic Plates 4 days

1.2 Filling mortar 7 days


Fill the mortar beside the plastic plates to prevent movement 4 skilled labour, 2 concretor cement and sand,

1.3 Fit M.S Guide Fit M.S Guide near the plastic plates and face to the panel line and support with 2 skilled labour, 2 general 50mmx50mm M.S Guide,
timber support labour 25mmx50mm timber

1.4 Erection Wall panel 3 skilled labour, 1 general 1 3m x 3m x 120mm thk Wall sum 5 days
Erect the wall panel by using crane labour 16 tonne crane panel

Installation supporting member


1.5 Support the panel with Prop and check vertical and horizontal allignment 2 skilled labour M.S Prop

Cleaning joint 4 days


Clean the joint between Floor Slab and Panel base from dust, oil and rubbish,
then insert Rubber Hose as backing piece before filling with Expandite Cement 4 skilled labour, 1 general 20mm dia. - 40mm dia.
1.6 Mortar labour Rubber Hose

Filling expendite cement Wet the joint before filling with the expendite cement mortar, and then fill and 5 days
compact expendite cement mortar properly and ensure there is no gap between
1.7 the panel and base slab. 4 skilled labour, 2 concretor Expendite Cement Mortar

Removal rubber hose After 1 hour, remove rubber hose and touch up the joint with expandite cement 3 days
1.8 mortar 4 skilled labour, 2 concretor Expendite Cement Mortar

Curing
1.9 After finishing grouting work, joint must be cured up to 7days

2.0 Wall finishes

Plastering 20mm Thk Cement and sand (1:6) plastering to joint 1 skilled labour, 2 general
2.1 2290 m2 6 days
labour

Painting Prepare and apply approved skim coating to the vertical surfaces of the
precast concrete wall, one coat of alkali resisting primer sealer and two 2 skilled labour, 1 general
2.2 2290 m2 4 days
coats of emulsion paint labour