Appendix B

Systems Engineering Life Cycle

Table of Contents

1. Introduction .............................................................................................................. 1
1.1 Purpose
1.2 Applicability
1.3 DHS SELC Process Overview
1.4 Relationship to the DHS Acquisition Review Process and the Capital Planning and Investment
Control Process
1.4.1 Alignment with the DHS Acquisition Review Process
1.4.2 Alignment with the DHS Capital Planning and Investment Control Process
1.5 Governance, Roles and Responsibilities
1.6 Document Organization

2. SELC Overview ...................................................................................................... 13


2.1 Overview of DHS SELC Elements
2.1.1 SELC Entry Criteria
2.1.2 SELC Stages
2.1.3 SELC Stage Reviews
2.1.4 SELC Exit Criteria
2.2 DHS Development Methodologies
2.2.1 Types of Development Methodologies
2.2.2 Selecting an Appropriate Development Methodology
2.3 Project Tailoring, Deviations, and Waivers
2.4 Refine Documentation
2.5 Other SELC Considerations

3. Stage A: Solution Engineering ............................................................................. 21


3.1 Solution Engineering Activities
3.1.1 Document the Concept of Operation
3.1.2 Identify and Analyze Potential Solution Alternatives
3.1.2.1 Analysis of Alternatives Study Plan
3.1.2.2 Study Plan Review
3.1.3 Develop Life Cycle Cost Estimate
3.1.4 Define Operations Requirements
3.1.5 Develop Acquisition Plan
3.1.6 Develop the Integrated Logistics Support Plan (ILSP)
3.1.7 Establish Acquisition Program Baseline
3.2 Documents
3.2.1 Solution Engineering Review Participants
3.2.2 Exit Criteria

4. Stage 2: Planning................................................................................................... 28
4.1 Planning Entry Criteria
4.2 Planning Activities
4.2.1 Develop SE Risk Management Plan
4.2.2 Develop SE Quality Assurance Plan
4.2.3 Develop Training Plan
4.2.4 Develop Configuration Management Plan
4.2.5 Complete Privacy Threshold Analysis (As Applicable)

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-i


Interim Version 1.9 November 7 2008
4.2.6 Develop Section 508 Electronic and Information Technology Accessibility Plan (As
Applicable)
4.2.7 Develop System Data Management Plan (IT Only)
4.3 Documents
4.4 Stage Review and Exit Criteria
4.4.1 Exit Criteria

5. Stage 2: Requirements Definition......................................................................... 34


5.1 Requirements Definition Activities
5.1.1 Develop Functional Requirements
5.1.2 Develop Requirements Traceability Matrix
5.1.3 Evaluate Infrastructure and Environmental Aspects
5.1.4 Develop Test and Evaluation Master Plan
5.1.5 Developmental Test Plan
5.1.6 Complete Information Security Activities (IT Only)
5.1.6.1 Develop Security Requirements Traceability Matrix (IT Only)
5.1.6.2 Develop Plan of Action and Milestones (IT Only)
5.1.6.3 Initiate Development of System Security Plan (IT Only)
5.1.6.4 Develop Security Risk Assessment (IT Only)
5.1.6.5 Develop Security Test and Evaluation Plan (IT Only)
5.1.7 Develop Service Level Agreements
5.1.8 Develop Disaster Recovery Plan (IT Only)
5.1.9 Map Project Data to HLS EA Data Architecture (IT Only)
5.1.10 Map Documents to the HLS EA Technical Reference Model (IT Only)
5.2 Documents
5.3 System Definition Review and Exit Criteria
5.3.1 Exit Criteria

6. Stage 3: Design ...................................................................................................... 45


6.1 Design Activities
6.1.1 Define System Requirements and Update the Requirements
Traceability Matrix
6.1.2 Develop Logical Design
6.1.3 Develop Data Architecture (IT Only)
6.1.4 Conduct Preliminary Design Review
6.1.5 Develop System Design
6.1.6 Validation and Verification (IT Only)
6.1.7 Develop Technology Insertion Decision Request (IT Only)
6.1.8 Develop Interconnection Security Agreements (IT Only)
6.1.9 Initiate Privacy Impact Assessment (IT Only)
6.1.10 Initiate System of Records Notice (IT Only)
6.2 Documents
6.3 Stage Reviews and Exit Criteria
6.3.1 CDR Participants
6.3.2 Exit Criteria

7. Stage 4: Development ........................................................................................... 56


7.1 Development Activities
7.1.1 Build, Construct, and Configure the System
7.1.2 Conduct Unit Testing
7.1.3 Develop Test Case Specifications
7.1.4 Develop Version Description Document (IT Only)
7.1.5 Develop Documentation
7.1.5.1 Develop Operators Manual
7.1.5.2 Develop Maintenance Manuals
7.1.5.3 Develop User Manuals
7.2 Documents

B-ii DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
7.3 Test Readiness Review and Exit Criteria
7.4 Exit Criteria

8. Stage 5: Integration and Test................................................................................ 60


8.1 Integration and Test Activities
8.1.1 Conduct System Testing and Generate Test Reports
8.1.2 Verify and Validate User Documentation
8.1.3 Conduct Acceptance Testing
8.1.4 Generate Section 508 Assistive Technology Interoperability Test
Results (As Applicable)
8.1.5 Conduct Security Test and Evaluation (IT Only)
8.1.6 Prepare Security Certification Documentation (IT Only)
8.1.7 Complete Privacy Impact Assessment (IT Only)
8.1.8 Complete System of Records Notice (IT Only)
8.1.9 Complete Insertion Packages (IT Only)
8.2 Documents
8.3 Production Readiness Review and Exit Criteria
8.3.1 Exit Criteria

9. Stage 6: Implementation ....................................................................................... 66


9.1 Implementation Activities
9.1.1 Conduct Pilot
9.1.2 Complete Preparation of Operational Sites and Deploy Solution to Production
Environment
9.1.3 Perform Data Conversion and Load Production Data (IT Only)
9.1.4 Coordinate Changes to Corresponding Business Practices
9.1.5 Publish System of Records Notice and Acquire Privacy Office Affirmation (IT Only)
9.1.6 Obtain Authority to Operate Letter (IT Only)
9.2 Documents
9.3 Operational Readiness Review and Exit Criteria
9.3.1 Exit Criteria

10. Stage 7: Operations and Maintenance ................................................................. 70


10.1 Operations and Maintenance Activities
10.1.1 Operate System and System Documentation
10.1.2 Identify and Make System Enhancements
10.1.3 Test Disaster Recovery
10.1.4 Document Post Implementation Review Results
10.1.5 Conduct Operational Analyses
10.1.6 Develop Lessons Learned Report
10.1.7 Perform Continuous Monitoring (IT Only)
10.1.8 Develop Section 508 Accessibility Incident Remediation Report (IT Only) .......................
10.2 Documents......................................................................................................................................

11. Stage 8: Disposition .............................................................................................. 74


11.1 Disposition Activities .......................................................................................................................
11.2 Documents......................................................................................................................................

ATTACHMENTS

Attachment B1. Systems Engineering Life Cycle Development Methodologies ... 76


B1-1 Spiral Development Methodology...................................................................................................
B1-2 Iterative/Incremental Methodology..................................................................................................

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-iii


Interim Version 1.9 November 7 2008
B1-3 Waterfall Methodology ....................................................................................................................

Attachment B2. Other SELC Considerations ........................................................... 81


B2-1 Index of Required Project Elements
B2-2 Project Management
B2-3 Organizational Change Management
B2-4 Enterprise Architecture Alignment
B2-5 Requirements Definition
B2-6 Prototyping
B2-7 Information Security
B2-8 Privacy Compliance
B2-9 Critical Infrastructure Protection
B2-10 Human Factors Engineering
B2-11 Section 508 Electronic and Information Technology Accessibility
B2-12 Risk Management
B2-13 Independent Verification & Validation
B2-14 Electronic Records Management
B2-15 National Information Exchange Model (NIEM)
B2-16 SELC and Service Oriented Architecture (IT Only)

Attachment B3: Summary of Exit Criteria .............................................................. 103

Attachment B4: SELC Document Matrix ................................................................ 104

Attachment B5: Acronyms ...................................................................................... 110

Attachment B6: Glossary ........................................................................................ 113

Attachment B7: References ................................................................................... 127

List of Tables
Table 1-1. DHS SELC Approval Authorities
Table 1-2. DHS SELC Stakeholder Roles and Responsibilities
Table 1-3. Document Organization and Descriptions
Table 2-1. Development Methodology Selection Guide
Table 2-2. Summary of Recommended Project Elements
Table 3-1. Solution Engineering Stage Documents
Table 3-2. Participants for Solution Engineering Review
Table 3-3. Solution Engineering Stage Exit Criteria
Table 4-1. DHS IT Project Management Plan Elements
Table 4-2. Planning Stage Entry Criteria
Table 4-3. Planning Stage Documents
Table 4-4. Planning Stage Exit Criteria
Table 5-1. Requirements Definition Documents
Table 5-2. Requirements Definition Stage Exit Criteria
Table 6-1. SRD Elements
Table 6-2. Logical Design Elements
Table 6-3 Detailed Design Elements
Table 6-4. Deployment Plan Elements
Table 6-5. Design Stage Documents
Table 6-6. Participants for Critical Design Review
Table 6-7. Design Stage Exit Criteria
Table 7-1. Development Stage Documents
Table 7-2. Development Stage Exit Criteria
Table 8-1. Integration and Test Documents
Table 8-2. Integration and Test Exit Criteria

B-iv DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
Table 9-1. Implementation Stage Documents
Table 9-2. Implementation Exit Criteria
Table 10-1. O&M Security Monitoring, Security Updates, and Security Reporting
Table 10.2. O & M Documents
Table 11-1. Disposition Documents

List of Tables - Attachments


Table B1-1. Spiral Methodology: Advantages vs. Disadvantages
Table B1-2. Iterative/Incremental Methodology
Table B1-3. Waterfall Methodology: Advantages vs. Disadvantages
Table B2-1. Index of Required Project Elements
Table B2-2. Common Phases and Activities in a Project Life Cycle
Table B2-3. Integration Checklist
Table B4-1. Governing Authorities, DHS Organizations, and Websites
Table B4-2. Full Artifact Matrix

List of Figures
Figure 1-1. DHS SELC Process
Figure 1-2. DHS SELC Alignment with ARP and CPIC
Figure 2-1. SELC Summary Snapshot
Figure 5-1 Developmental Testing and Operational Testing and Key Documents

List of Figures - Attachments


Figure B1-1. Spiral Methodology
Figure B1-2. Iterative Methodology
Figure B1-3. Incremental Methodology
Figure B1-4. Waterfall Methodology

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-v


Interim Version 1.9 November 7 2008
1. Introduction
1.1 Purpose
A Systems Engineering Life Cycle (SELC) is a systems engineering framework for
enabling efficient and effective delivery of capability to users, and is one of several key
Department of Homeland Security (DHS) processes for managing acquisitions of
programs and their related projects. Carnegie Mellon’s Software Engineering Institute
(SEI) defines systems engineering as:
“The interdisciplinary approach governing the total technical and
managerial effort required to transform a set of customer needs,
expectations, and constraints into a product solution and support that
solution throughout the product’s life. This includes the definition of
technical performance measures, the integration of engineering specialties
towards the establishment of a product architecture, and the definition of
supporting life-cycle processes that balance cost, performance, and
schedule objectives.”
An SELC guides the definition, execution, and management of an interdisciplinary set of
tasks required to plan, define, design, develop, implement, operate, and dispose of
systems.

This DHS SELC Guide documents the Systems Engineering (SE) methodology and its
application throughout the DHS enterprise. To support the stated purpose, the SELC
Guide describes the SELC and its relationship to other DHS enterprise-wide processes
and defines the following:
• DHS SELC roles and responsibilities
• DHS SELC elements (stages, including activities and products, entry/exit criteria,
and reviews)
• System development methodologies, guidance on their usage, and methods for
customization
The purpose of this DHS SELC Guide is to standardize the system life cycle process
across DHS Components and to ensure that DHS capabilities are efficiently and
effectively delivered. The DHS SELC Guide is designed to ensure that appropriate
activities are planned and implemented in each stage of the life cycle to increase the
project’s success.
The following key concepts form the basis for the DHS SELC Guide:
• The DHS SELC represents the systems engineering guidance for the acquisition
management process.
• The DHS SELC is the framework used to guide all DHS projects with specific
guidance provided for each type of acquisition mechanism (capital investment IT and
non-IT, enterprise services, etc).
• The SELC provides flexibility by supporting tailoring based on the unique
characteristics of a project (e.g., size, scope, complexity, risk, and security

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-1


Interim Version 1.9 November 7 2008
categorization) documented in the Project Tailoring Plan. The project and program
managers are responsible for tailoring the SELC process for the project’s specific
characteristics as appropriate. Tailoring is the cornerstone of any life cycle process.
• The scope of the SELC Guide begins with the Solution Engineering stage (i.e., ADE
1), and continues through Disposal.
• The SELC specifies stage reviews that are based on defined exit criteria to assess
progress, quality, and readiness to proceed. Signed stage review approval letters,
the Project Tailoring Plan, and the updated Project Management Plan (along with
project schedule) must be delivered to the DHS Periodic Reporting team following
the conclusion of each stage review.
• The Component is responsible for:
o Ensuring that all SELC entry criteria are satisfied.
o Conducting SELC stage reviews to authorize projects to move to next stage.

The DHS SELC Guide discusses nine process stages. The following figure, DHS SELC
Process – Capital Assets, summarizes the SELC process. Each element of the process
is discussed in the following pages.

ADE ADE
ADE
1 2 3

SPR SER PPR SDR PDR CDR TRR PRR ORR PIR

Stage 7:
Stage A: Stage 2: Stage 5:
Stage 1: Stage 3: Stage 4: Stage 6: Operations Stage 8:
Solution Requirements Integration &
Planning Design Development Implementation Disposition
Engineering Definition & Test Maintenance
Engineer the Plan the project and Analyze user needs Transform Convert the Integrate and test System moved to The system is The system is
program solution to acquire and document requirements into system design with other systems; Production operated to carry disposed
ensure all resources needed functional detailed into system conduct UAT; environment; out
alternatives are to achieve solution requirements system design develop C&A Production data has intended function
considered been loaded

SPR: Study Plan Review Key Note: A Project Tailoring Plan must be developed that defines what
SER: Solution Engineering Review TRR: Test Readiness Review stages, activities, and artifacts will be completed for the project. The
PPR: Project Planning Review PRR: Production Readiness Review Project Tailoring Plan should reflect the unique characteristics of the
SDR: System Definition Review ORR: Operational Readiness Review
project and provide the best opportunity to deliver the system effectively.
PDR: Preliminary Design Review PIR: Post Implementation Review
CDR: Critical Design Review

DHS SELC Process – Capital Assets

The new Acquisition Management Process applies to Enterprise Services (as well as
Capital Assets). The figure on the next page depicts a modified life cycle tailored for
Enterprise Services.

B-2 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
DHS SELC Process – Enterprise Services

1.2 Applicability
The DHS SELC Guide is applicable to all DHS projects throughout Components or
other DHS organizations (unless specifically exempted) whose purpose is to deliver a
DHS capability.
IT Specific
The DHS SELC applies to all DHS IT projects. As defined in MD 0007.1, IT is:
“Any equipment or interconnected system or subsystem of
equipment/software, or any national security system, that is used in the
automatic acquisition, storage, manipulation, management, movement,
control, display (including geospatial technologies), switching,
interchange, transmission (wired or wireless telecommunications), or
reception of data, voice, video, or information by an executive
agency…equipment is used by DHS if the equipment is used by DHS
directly or is used by DHS organizational partners (including other
Federal agencies, State and local governments and private
contractors) under a contract with DHS which (a) requires the use of
such equipment, or (b) requires the use, to a significant extent, of such
equipment in the performance of a service or the furnishing of a
product. It includes computers, ancillary equipment (including imaging
peripherals, input, output, and storage devices necessary for security
and surveillance), peripheral equipment designed to be controlled by
the central processing unit of a computer, software, firmware and
similar procedures, services (including support services), and related
resources. It does not include any equipment acquired by a contractor

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-3


Interim Version 1.9 November 7 2008
incidental to a contract, or equipment which contains imbedded
information technology that is used as an integral part of the product,
but the principal function of which is not the acquisition, storage,
analysis, evaluation, manipulation, management, movement, control,
display, switching, interchange, transmission, or reception of data or
information..” 1
For the purpose of the SELC, IT projects include the following;
• IT projects and systems across all IT environments (e.g., mainframe, client-server,
embedded, firmware, network).
• IT projects and systems across all classifications (unclassified, classified, and
national security).
• IT projects and systems for applications, systems, and infrastructure, including those
acquired, contractually developed, and developed in-house.
• IT projects from non-IT investments or acquisitions that involve the development of
an IT system.
While minor enhancements and modifications are expected during the Operations and
Maintenance (O&M) stage, major enhancements to systems in O&M require a project to
be treated as a new IT project and comply with the full life cycle requirements of the
SELC. Major enhancements constitute any combined change that exceeds $2.5 million
in cost from planning through deployment (excluding O&M).

1.3 DHS SELC Process Overview


Given that the SELC is the systems engineering methodology for an acquisition, the first
stage of the SELC is one that focuses on the larger acquisition program, whereas the
remainder focus on the projects associated with the program. The DHS SELC
methodology is composed of nine process stages:
• Solution Engineering (focuses on the Acquisition Program)
• Planning
• Requirements Definition
• Design
• Development
• Integration and Test
• Implementation
• Operations and Maintenance
• Disposition
Each stage has a defined set of activities that represents a logical unit of work. Each
stage has associated documents to record the results of the activities performed. Stage
Reviews are held at an appropriate point in time to validate that the acquisition has
completed requirements for that stage and is ready to advance to the next stage. Exit

1
MD 0007.1, section IV.J.

B-4 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
criteria are directly related to the function of the stage and to the activities performed in
the stage.

For purposes of illustration, the DHS SELC stages and stage reviews are represented
sequentially in Figure 1-1, which is traditionally how they have been performed.

ADE ADE
ADE
1 2
3

SPR SER PPR SDR PDR CDR TRR PRR ORR PIR

Stage 7:
Stage A: Stage 2: Stage 5:
Stage 1: Stage 3: Stage 4: Stage 6: Operations Stage 8:
Solution Requirements Integration &
Planning Design Development Implementation Disposition
Engineering Definition & Test Maintenance
Engineer the Plan the project and Analyze user needs Transform Convert the Integrate and test System moved to The system is The system is
program solution to acquire and document requirements into system design with other systems; Production operated to carry disposed
ensure all resources needed functional detailed into system conduct UAT; environment; out
alternatives are to achieve solution requirements system design develop C&A Production data has intended function
considered been loaded

SPR: Study Plan Review Key Note: A Project Tailoring Plan must be developed that defines what
SER: Solution Engineering Review TRR: Test Readiness Review stages, activities, and artifacts will be completed for the project. The
PPR: Project Planning Review PRR: Production Readiness Review Project Tailoring Plan should reflect the unique characteristics of the
SDR: System Definition Review ORR: Operational Readiness Review
project and provide the best opportunity to deliver the system effectively.
PDR: Preliminary Design Review PIR: Post Implementation Review
CDR: Critical Design Review

Figure 1-1: DHS SELC Process

1.4 Relationship to the DHS Acquisition Review Process and the Capital
Planning and Investment Control Process
As one of the foundational elements of the DHS acquisition process, the objective of the
DHS SELC Guide is to provide a framework to guide effective and efficient enterprise-
wide capability delivery. Understanding the relationship of the DHS SELC to other DHS
enterprise governance processes is essential to this objective. The primary applicable
DHS governance processes are the DHS Acquisition Review Process (ARP), as
mandated by Directive 102-01, and the CPIC Process, as mandated by MD 4200. The
CPIC process will use the products and information produced in the ARP to fulfill its’
reporting requirements. These processes are focused on selecting and managing both
IT and non-IT acquisitions (also referred to as programs and projects). Each acquisition
may comprise multiple programs and projects. The SELC applies to the level of activity
at which capabilities are produced and delivered, which may be at a singular acquisition
level or through the related efforts of multiple types of acquisition. The applicability is
determined through the SELC tailoring process based on the individual needs and
conditions of each acquisition.
For purposes of illustration, the alignment of the Systems Engineering processes from a
sequential point of view (see section for other delivery patterns) is depicted in Figure 1-
2. This view provides insight into the alignment of the different phases of each
governance process, as well as the alignment of some of the SELC stage reviews with
those of the ARP. It is important to note that the responsibility for ensuring compliance
with both the ARP and the SELC lies with a single project team, which may be part of a
program team. The SELC is tightly integrated with the ARP. Therefore, there are
dependencies between deliverables in each process (e.g., the Functional Requirements
Document in the SELC is dependent upon the information found in the ARP’s Mission
Needs Statement [MNS], Concept of Operations [CONOPS] and Operational
Requirements Document [ORD]).

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-5


Interim Version 1.9 November 7 2008
B-6
Pre-
Select
Select

CPIC Control

Evaluate
0 1 2A 3
2B
Analyze/
ARP Need Obtain Produce/Deploy/Support
Select

Solution Requirements Integration Operations &


SELC Planning Design Development Implementation Disposition
Engineering Definition & Test Maintenance

SPR SER PPR SDR CDR TRR PRR ORR PIR


PDR

Interim Version 1.9 November 7 2008


SLC Stage Reviews
ARP Acquisition Decision Events
SPR: Study Plan Review
0: Collect Needs TRR: Test Readiness Review
SER: Solution Engineering Review
1: Validate Needs PPR: Project Planning Review PRR: Production Readiness Review
2A: Approve Approach SDR: System Definition Review ORR: Operational Readiness Review

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


2B: Approve Mechanisms PIR: Post Implementation Review
PDR: Preliminary Design Review
3: Approve Deployment/Support CDR: Critical Design Review

Figure 1-2. DHS SELC Alignment with ARP and CPIC


1.4.1 Alignment with the DHS Acquisition Review Process
The DHS Acquisition Review Process (ARP) (Directive 102-01) is one of the
departmental governance processes that establishes governance bodies (e.g.,
Acquisition Review Board [ARB]) and ensures oversight, control, reporting, and
review of all investments. Directive 102-01 defines acquisitions as any capital
investment program/project, service contract, or interagency agreement used for the
purpose of delivering Homeland Security capabilities, and categorizes investments
according to investment levels. The SELC is tailorable for each type of acquisition.
The ARP process, in conjunction with the SELC, ensures that acquisitions directly
support and further the DHS mission(s), provide the intended benefits and
capabilities to stakeholders and customers, and enhance investment sharing
opportunities though standardization.
The alignment of many of the SELC stage reviews with Acquisition Decision Events
(ADEs) in the ARP provides opportunities to leverage deliverables and products to
comply with the needs of both the ARP and the SELC (e.g., Risk Management Plan).
Acquisition reviews may result in conditions being levied on the acquisitions or result
in cancellation of an acquisition.
Prior to entering the acquisition phases, the Department and Components create
and collect needs based on capability gaps and shortfalls. Gaps and capability
deficiencies may be identified via over-budget requests in the Planning,
Programming, Budgeting, and Execution (PPBE) process, executive direction,
legislative mandates, or from operational/user groups within the Components. ADE
0 is the decision point where Department and Component mission area owners
select their initiatives to form the basis of the activities in the Need phase.
The phases of the Capital Asset ARP are contained in the Directive 102-01
Guidebook.
1.4.2 Alignment with the DHS Capital Planning and Investment Control
Process
The CPIC process (MD 4200), as described in the DHS CPIC Guide, integrates
strategic planning, enterprise architecture, portfolio management, privacy, security,
budgeting, procurement, and the management of assets. The Department’s portfolio
of capital investments comprises acquisitions that have been determined to provide
the requisite mission capability by the DHS ARP and have been approved for funding
through the DHS PPBE process as mandated in MD 1330. The overall portfolio of
acquisitions comprises assets and services designed to achieve DHS’ strategic
goals and objectives with an affordable life cycle cost and acceptable risk. CPIC will
utilize information provided in the ARP and its’ approved documentation set to
complete its’ reporting requirements.

CPIC emphasizes the selection of investments/programs/acquisitions. In


Directive102-01, these three terms are considered to be congruent concepts,
although the use of one or another of them tends to emphasize different decision

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-7


Interim Version 1.9 November 7 2008
support systems. For example, the use of the term “investment” emphasizes the
PPBE decision system.

It is the intent of DHS to interlink the key decision support systems. CPIC is a part of
acquisition considered in the broadest sense: that of providing the organization with
the capabilities it needs to accomplish the mission. However, as noted above, there
are some differences between CPIC processes and documentation, and acquisition
processes and documentation. The plan to use acquisition information as the source
information for the CPIC process is the first important step towards interlinking these
DHS decision systems.

CPIC is important to the SELC process because it levies several requirements on


investments. Depending on the CPIC investment thresholds and the operational
state of the investment (e.g., Development, Steady-State), it requires PMs to:
• Complete an OMB Business Case Exhibit 300
• Complete an annual Exhibit 53 report
• Conduct Periodic Reporting
• Conduct Operational Analysis

The CPIC process includes four phases: Pre-Select, Select, Control and Evaluate.
• Pre-Select Phase. All proposed IT initiatives must go through the Pre-Select
Phase, during which time the sponsor presents the new initiative to review
authorities for consideration. During this phase of the CPIC process, the
Department identifies all new, ongoing, and operational investments for the
Department's IT portfolio. Within this phase, proposed IT initiatives are screened,
scored, and ranked relative to other initiatives. The principal objectives of the
Pre-Select phase are to determine whether the initiative is viable and whether the
appropriate level of analysis and documentation has been completed.
The Pre-Select decision is made at the Component level. Key outcomes resulting
from the assessment process include: (1) defining the level of review required to
approve the initiative for funding, and (2) defining the appropriate set of
analysis/documentation needed to characterize the initiative fully as it moves
forward in the process.
• Select Phase. The Select Phase ensures that Resource Allocation Plan
(RAP)/Capital Investment Plan (CIP) submissions include the resource
requirements for investments. Additionally, it ensures that new and existing
investments are assessed against a uniform set of evaluation criteria and
thresholds. The Exhibit 300 business case is the primary artifact used in the CPIC
Select Phase to support the annual review and (re-)selection of both new and
continuing investments. It is a formal justification for a project or program that
outlines the associated benefits, cost, risks, and alignment with organizational

B-8 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
objectives. The Exhibit 300 is updated annually as part of the CPIC process to
reflect the performance of the investment. Exhibit 300s are reviewed and scored
against OMB scoring criteria. Poorly scoring Exhibits 300 must be updated to
meet the required threshold or risk not being included in the annual budget
submission.
• Control Phase. The objective of the Control Phase is to ensure that the project is
performing within acceptable cost, schedule, and performance parameters and to
ensure the continual assessment and mitigation of potential risks through periodic
reporting and IT acquisition reviews. The CPIC Guide describes the requirements
for managing and reporting performance per periodic reporting. The Acquisition
Program Baseline (APB) defines the critical cost, schedule, and performance
parameters for the investment and is the baseline against which programs report
their progress. Periodic reporting is required throughout the CPIC Control phase.
• IT Specific: It should be noted that, as part of the CPIC Control Phase, all IT
procurements (contracts) must be reviewed. As mandated by Management
Directive 0007.1, the DHS CIO reviews and approves all procurements of $2.5M
or more; the Component CIOs review procurements of less than $2.5M. The DHS
CIO has a review process for approving IT procurements that informs the ARP.
Additional information on the DHS CIO’s IT review can be found on DHS
Interactive (https://interactive.dhs.gov/suite/portal.do?$p=2041) or by contacting
the review coordinator (DHSCIOITBUY@dhs.gov). For Component reviews,
please contact the offices of the Component CIOs for review policies and
procedures.
• Evaluate Phase. The purpose of the Evaluate Phase is to: 1) determine how well
the investment is meeting its performance, cost, and schedule objectives, and 2)
determine the extent to which the CPIC process improved the outcome of the
investment. The two primary activities in the CPIC Evaluate Phase are the Post-
Implementation Review (PIR), which is conducted approximately six months after
deployment, and the Operational Analysis (OA), which is conducted annually to
determine if the investment is meeting its performance goals.

1.5 Governance, Roles and Responsibilities


Table 1-1 lists the approval authority for each of the SELC stage reviews for each
project type. Table 1-2 lists the key DHS stakeholders and describes their role in the
DHS SELC. It also identifies ARP and CPIC roles.

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-9


Interim Version 1.9 November 7 2008
Table 1-1: DHS SELC Approval Authorities

Project Type
SELC Stage
Review Capital Investment Capital Investment Enterprise Service
IT Non-IT
AoA Study Plan APMD/CIO APMD/CIO APMD/CIO
Review
(SPR)
SER CIO Component SE group1 Component SE group1
PPR Component CIO Component SE group1 Component SE group1
SDR Component CIO Component SE group1 Component SE group1

PDR Component CIO Component SE group1 Component SE group1

CDR Component CIO Component SE group1 Component SE group1


TRR Component CIO Component SE group1 Component SE group1
1 1
PRR Component CIO Component SE group Component SE group
ORR Component CIO Component SE group1 Component SE group1
PIR Component CIO Component SE group1 Component SE group1
1
Monitored by APMD

Table 1-2: DHS SELC Stakeholder Roles and Responsibilities

Role Definition
Program / Project Manager A Program Manager is the responsible person who, with significant discretionary
authority, is uniquely empowered to plan the scope of work, life cycle cost,
schedule, and performance acceptability levels (for an assigned program[s]), and
who is responsible and accountable for accomplishing program objectives or
production requirements through the acquisition of in-house, contract or
reimbursable support resources, as appropriate, and as agreed to in an approved
APB. The Program Manager is responsible for management of the project
manager(s) and ensuring the project within the program is successfully completed.
The Program / Project Manager is responsible for establishing the project team,
completing the documentation set, presenting the business case and status of the
project through all phases of the review and approval process, scheduling and
coordinating the SELC stage reviews, and managing the performance of the project
throughout the life cycle. The Program / Project Manager must be certified at the
appropriate level, per Management Directive 0782.
IT Specific
Component CIO IT Approving Authority: The Component CIO is the most senior Federal executive in
the Component exercising leadership and authority over mission-unique IT policies,
programs, services, solutions, and resources. The Component CIO acts to
implement the policies of the DHS CIO. This includes compliance of IT acquisitions
with the DHS SELC. The Component CIO is responsible for:
1. Ensuring that all SELC entry criteria are satisfied.
2. Conducting SELC stage reviews.
Designated Accrediting The DAA is responsible for operating a system at an acceptable level of risk based
Authority (DAA) on the System Security Plan (SSP)and final risk assessment, and is accountable for
the risk he or she accepts.

B-10 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
Role Definition
DHS Chief Information The DHS CIO is responsible for ensuring that DHS IT projects are aligned with DHS
Officer (DHS CIO) strategic business objectives and that system development projects comply with
DHS policies. He or she is also responsible for the proper level of oversight over IT
projects and for the IT architecture.
DHS Chief Information The CISO issues Department-wide IT security policy, guidance, and architecture
Security Officer (CISO) requirements for all DHS IT systems and networks. The CISO implements and
manages the Department-wide IT Security Program and ensures compliance with
the Federal Information Security Management Act (FISMA) and OMB requirements.
DHS Chief Privacy Officer The Chief Privacy Officer ensures that technology implementations across DHS
sustain privacy protections as mandated by Section 208 of the E-Government Act of
2002 and Section 222 of the Homeland Security Act.
DHS Enterprise The DHS EAB, in support of the DHS investment review process, is responsible for
Architecture Board (EAB) the following:
1. Reviewing individual investments and making recommendations to the DHS
CIO for approving them consistent with the criteria and thresholds identified in
DHS Directive 102-01, Acquisition Management Process.
2. Requiring that each IT investment aligns with the HLS EA and is approved by
the EAB before submission to the CIO for final approval and inclusion in the
annual budget submission.
3. Directing, overseeing, and approving the HLS EA and ensuring compliance with
OMB Federal Enterprise Architecture (FEA) guidance.
DHS Enterprise Data The EDMO is the organization within the DHS OCIO that coordinates and facilitates
Management Office the establishment and maturation of the DHS enterprise data management policies,
(EDMO) governance processes, and data stewardship programs.
DHS IT Portfolio Managers The IT Portfolio Manager acts as an agent of the DHS CIO in managing an assigned
IT portfolio, regardless of funding sources, across a number of IT projects. The
primary responsibilities of the IT Portfolio Manager are to:
1. Apply DHS IT portfolio management processes.
2. Provide oversight of investments/projects within the portfolio.
3. Support budget formulation.
4. Review portfolio acquisitions and performance.
5. Support the development and implementation of EA targets.
6. Develop and review IT business cases.
Information System The ISSO ensures that appropriate steps are taken to implement information security
Security Officer (ISSO) requirements for information systems throughout the life cycle and works closely with the
ISSM to interpret and apply IT security policies and implement procedures.
Information Systems The ISSM is the principal interface between the Office of the CISO and the ISSOs
Security Manager (ISSM) and other security practitioners. As such, the ISSM plays a critical role in ensuring
that the DHS IT Security Program is both implemented and maintained throughout
the Components and their IT systems.
Office on Accessible OAST is responsible for establishing Departmental policies, practices, and
Systems and Technology procedures to ensure that the Electronic Information Technology (EIT) that is
(OAST) – Section 508 procured, developed, maintained, or used is accessible to DHS employees and
customers with disabilities. Additionally, OAST is responsible for providing
programmatic and technical assistance to DHS Components regarding
implementation of 29 U.S.C. Section 508, as amended by P.L. 105-220, August
1998 EIT Accessibility.
Project Sponsor The project sponsor represents the operational needs of the business unit and the
system users; and, participates in all life cycle stages to ensure that the system
meets the requirements and business need.

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-11


Interim Version 1.9 November 7 2008
1.6 Document Organization
Table 1-3 below provides an overview of organization of the document and includes a
description of the document’s sections and attachments.

Table 1-3. Document Organization and Descriptions

Section Description
Section 1: Introduction Describes the purpose of the SELC and provides background regarding its development,
objectives, and benefits. Additionally, this section covers the SELC-related authorities,
provides a high-level overview of the process and its relationship to the DHS investment
review and CPIC processes. It also documents the applicability of the SELC to IT projects
and describes roles and responsibilities.
Section 2: SELC Describes the elements that constitute the SELC, the transition at DHS to a Service
Overview Oriented Architecture (SOA) and how this transition impacts system development. It also
covers development methodologies and how projects are tailored. Finally, it identifies the
required elements that all Project Managers must ensure are incorporated in IT projects.
Section 3: Solution Describes the elements (activities, documents) associated with the solution engineering
Engineering Stage needed to properly define the program capability solution.
Section 4: Planning Describes the entry criteria, activities, documents, stage review, and exit criteria for the
Stage Planning Stage.
Section 5: Describes the activities, documents, stage review, and exit criteria for the Requirements
Requirements Definition Stage.
Definition Stage
Section 6: Design Describes the activities, documents, stage review, and exit criteria for the Design Stage.
Stage
Section 7: Describes the activities, documents, stage review, and exit criteria for the Development
Development Stage Stage.
Section 8: Integration Describes the activities, documents, stage review, and exit criteria for the Integration and
and Test Stage Test Stage.
Section 9: Describes the activities, documents, stage review, and exit criteria for the Implementation
Implementation Stage Stage.
Section 10: Operations Describes the activities, documents, stage review, and exit criteria for the Operations and
and Maintenance Maintenance Stage.
Stage
Section 11: Describes the activities to ensure users are notified of the disposition of the system,
Disposition secure and archive the system and associated data in accordance with DHS and Federal
policies regarding retention of electronic records, and to dispose of the system assets.
Attachment B-1: SELC Describes the Spiral, Iterative/Incremental, and Waterfall methodologies and illustrates
Development how they are implemented in the SELC.
Methodologies
Attachment B-2: Work Provides work patterns (also referred to as pre-tailored plans) suitable for usage or for
Patterns further tailoring. Work patterns are provided for each of the three development
methodologies, as well as for projects with special focus (service delivery, Commercial
Off-the-Shelf [COTS], and infrastructure) efforts.
Attachment B-3: Other Provides detailed DHS information on the required elements that must be incorporated in
SELC Considerations all projects.
Attachment B-4: Lists all of the SELC exit criteria by SELC stage.
Summary of Exit
Criteria

B-12 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
Section Description
Attachment B-5: SELC Lists all the documents required throughout the life cycle and denotes when they are
Artifact Matrix updated.
Attachment B-6: Lists the definitions of acronyms used in the document.
Acronyms
Attachment B-7: Defines key terms.
Glossary
Attachment B-8: Lists the references consulted in the development of this Guide.
References

2. SELC Overview
This section defines the DHS SELC framework and the elements it comprises. As such,
it provides the basis for the detailed information on each stage of the SELC in
subsequent sections of this document. For IT acquisitions, this section also provides
information regarding the transition that DHS is making to a Service Oriented
Architecture (SOA). Lastly, it discusses different development methodologies and
technical approaches and how they may be used to tailor a project to best achieve
project success.

2.1 Overview of DHS SELC Elements


This section presents general information on each element (i.e., Entry Criteria, Stages,
Stage Reviews, and Exit Criteria) of the SELC framework as a preface to the detailed
information on each DHS SELC stage that follows in Sections 3 through 11.

2.1.1 SELC Entry Criteria


The following represent the SELC entry criteria for the solution engineering stage.
• Mission Needs Statement (MNS) approval
• ADE 1 Acquisition Decision Memo (ADM)

2.1.2 SELC Stages


The SELC consists of the following nine stages:
1. Solution Engineering (program focused)
2. Planning
3. Requirements Definition
4. Design
5. Development
6. Integration and Test
7. Implementation
8. Operations and Maintenance
9. Disposition

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-13


Interim Version 1.9 November 7 2008
Each SELC stage requires the completion of a set of related activities. The SELC guide
provides a description of each of these activities and the requisite documents for each
stage. The outputs from the activities performed in each stage are recorded in
documents that are placed under Configuration Management (CM) control. Many
documents are created in one stage and updated in subsequent stages as additional
details become available. The completion of these activities, unless tailored out, is
generally considered a prerequisite for moving to the next stage of the SELC.

2.1.3 SELC Stage Reviews


The SELC process is governed through stage reviews (see Figure 1-1) that provide the
opportunity to assess project progress against defined exit criteria. These reviews
provide a knowledge point or mechanism for management to determine how and if a
project should proceed (e.g., does more work need to be done before the project is
ready to enter the next stage of the life cycle?). Stage reviews are conducted at fixed
points in the SELC and have a specified list of participants and evaluation criteria. Stage
reviews are conducted at the end of each stage to ensure all exit criteria for the stage
have been satisfactorily addressed. For IT projects, the one exception is the final
review, the PIR, which should be performed six months after deployment. 2
Stage reviews are conducted by management teams specific to the organization
defined by the project (e.g., by the project sponsor and Component CIO) and may also
include DHS level organizations (e.g., DHS IT Portfolio Managers). The
Program/Project Manager is responsible for arranging, coordinating, and leading the
stage reviews while the decision authority is responsible for sign-off that the project has
satisfied all the exit criteria and is ready to proceed to the next stage. However, it is
expected that the decision authority will rely on the appropriate experts (e.g., EA,
testing, security, infrastructure, budget) to evaluate the readiness to proceed. Some key
experts are identified in the lists of stage review participants in the following sections.
Evidence of decision authority sign-off must be delivered to the DHS Periodic Reporting
Team and be maintained as part of the project documentation. A scanned electronic
copy of the signed stage review approval letter along with the updated project
management plan (and associated project schedule) must be emailed to the DHS
Periodic Reporting Team at Periodic.Reporting@dhs.gov following the conclusion of
each stage review.
Stages may be modified as part of the project tailoring process. If stages are combined
as part of an approved tailoring plan, only one stage review will be held at the end of the
combined stages (e.g., a single Design/Development stage review would be held rather
than two stage reviews, one for the Design Stage and one for the Development Stage).
Stage review participant listings can be found in each of the detailed descriptions of the
stages in Sections 3-11. The SELC documents or pointers to the authority where the
latest template can be obtained have been posted on DHS Online under
Components/Management/CIO/EBMO/SELC. The following URL is the location of the
template listing. DHS SELC Website:

2
Per guidance in the DHS CPIC Guide.

B-14 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
https://dhsonline.dhs.gov/portal/jhtml/community.jhtml?community=MGMT&index=151&i
d=2039580019

2.1.4 SELC Exit Criteria


Each SELC stage is associated with specific exit criteria that must be satisfied before a
project can proceed to the next stage. Exit criteria are presented in question format and
categorized by domain (e.g. project management, enterprise architecture) to provide
content-centered guidance rather than merely a checklist of documents to be
completed. It is critical to understand that the determination of project readiness to
transition to the next stage is made by satisfactory compliance with the content of the
exit criteria, NOT by the evidence of documents produced. Project Managers should
review the exit criteria at the start of each SELC stage and plan the stage activities
accordingly to ensure successful completion of the exit criteria and to avoid rework or
delays.
Factors critical to successful stage reviews are:
• All exit criteria for each stage review must be satisfactorily fulfilled, including required
documents, to obtain authorization for moving to the next stage.
• The downstream consumer of the products produced in a stage (e.g., a development
manager dependent on using the design documentation) must attend, review, and
sign-off on stage completion. The PM must review any significant issues identified,
assess the impact to the project, and determine if proceeding to the next stage is
desirable. This is to ensure that the next stage can effectively begin and to minimize
the need to return to a previous stage to correct incomplete activities. To minimize
issues with availability, the downstream consumers may be limited to the lead of the
next stage. For example, following Requirements Definition, the Design lead would
be expected to review the requirements while the Development lead may not be
expected to review the requirements in preparation for the Requirement Definition
stage review.
• At each stage review, evidence must be provided that clearly substantiates the
successful completion of the exit criteria. For example, in testing requirements, tests
must successfully produce the required results to be used as evidence of
“successfully” meeting exit criteria. The act of testing in itself is not sufficient
evidence if tests fail to produce required results.
For a complete listing of exit criteria for each stage of the DHS SELC, reference
Attachment B-4 to this document.

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-15


Interim Version 1.9 November 7 2008
B-16
ADE ADE ADE
1 2 3

SPR SER PPR SDR PDR CDR TRR PRR ORR PIR

Stage A: Stage 7:
Stage 2: Stage 5: Stage 8:
Stage 1: Stage 3: Stage 4: Stage 6: Operations
Solution Requirements Integration
Planning Design Development Implementation & Disposition
Engineering Definition & Test Maintenance
Engineer the Plan the project and Analyze user needs Transform Convert the Integrate and test System moved to The system is The system is
program solution to acquire and document requirements into system design with other systems; Production operated to carry disposed
ensure all resources needed functional detailed into system conduct UAT; environment; out
alternatives are to achieve solution requirements system design develop C&A Production data has intended function
considered been loaded

• CONOPs • PMP • FRD • SRD • Training Materials • System Test Report • Pilot Results Report • Performance • Disposition
• ORD • DHS Periodic • SLAs • Logical Design • Test Case • Acceptance Test • ORR Approval Letter Reports Approval Request
• AP Reporting • Site Prep Plan Document Specification Report IT Specific • Operational • Archived System
• AoA • Risk Management • RTM • System Design • System • DHS Periodic • Authority To Analyses IT Specific
• CBA Plan • TEMP Document Acceptance Test Reporting Operate (ATO) Letter • Lessons Learned • Archived Data
• LCCE • Quality Assurance • SDR Approval Letter • Deployment Plan Procedures • PRR Approval Letter • PIR Results
• APB Plan IT Specific • PDR Approval Letter • Operators IT Specific IT Specific
• Project Tailoring • Training Plan • SRTM • CDR Approval Letter Manuals • Section 508 • FISMA metrics
Plan(s ) • PPR Approval Letter • POA&M IT Specific • Maintenance Assistive Technology reports
• MS2B ADM IT Specific • SSP • ISA Manuals Interoperability Test • Security Incident
IT Specific • CM Plan • Contingency Plan • Data Architecture • User Manuals Report reports
• Service Reuse Plan • PTA • DR Plan Document • Initial System • EA Insertion • C&A Updates
• HLS EA Program • Section 508 EIT • SRA • Technology Implementation Packages • Privacy
Alignment DR Accessibility Plan • ST&E Plan Insertion Decision • TRR Approval • SAR Documentation
• Map to Business • DM Plan • Map to the Data Request Letter • Security
Architecture Architecture • PIA IT Specific Accreditation

Interim Version 1.9 November 7 2008


• Map OCIO Portfolios • NIEM IEPD • SORN • VDD package
• FIPS 199 Security • Map to TRM
Categorization
• Preliminary SRA

SPR: Study Plan Review Key

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


SER: Solution Engineering Review
Note: A Project Tailoring Plan must be developed that defines hatw stages,
TRR: Test Readiness Review
PPR: Project Planning Review PRR: Production Readiness Review activities, and artifacts will be completed for the project. eTh
Project
SDR: System Definition Review ORR: Operational Readiness Review Tailoring Plan should reflect the unique characteristics of theproject and
PDR: Preliminary Design Review PIR: Post Implementation Review provide the best opportunity to deliver the system effectively.
CDR: Critical Design Review

Figure 2-1: Summary Snapshot (summarizes the SELC stages, reviews, and products)
2.2 DHS Development Methodologies
Projects vary in the challenges they present. They can range from a simple installation
and configuration to intense software development; from tried and tested technology to
bleeding edge integration; and from software development to systems development.
Given the variety of project types and project characteristics, a single development
methodology is not sufficient to meet the needs of all projects. This section discusses
various methodologies and provides a guide for selecting the one most appropriate for
optimizing project success.

2.2.1 Types of Development Methodologies (IT)


History demonstrates that building information systems is a complex undertaking with
high degrees of risk and uncertainty. Therefore, PMs must select the appropriate
development methodology given their project’s unique characteristics. Though the spiral
development methodology is the preferred development methodology in DHS for IT
acquisitions, the characteristics of some project types may be best suited to other
development methodologies, and PMs may choose to use other development
methodologies more appropriate for their project. For a description of the Spiral,
Iterative/Incremental and Waterfall methodologies, see Attachment B-1. For a
description of the associated work patterns, see Attachment B-2.
Regardless of the development methodology chosen, an approved Project Tailoring
Plan, as described later in this section, must be developed and must justify the use of
the chosen development methodology. Choosing an alternative development
methodology does not relieve a Project Manager from adhering to the SELC or the
ARP. The Project Tailoring Plan must describe how the proposed development
methodology aligns with the SELC and ARP and why it is the best option for
successfully completing the project.

2.2.2 Selecting an Appropriate Development Methodology (IT)


PMs are responsible for selecting the development methodology best suited to address
the characteristics of the project. The most important criterion is that the method
selected for use is one that provides the project the best opportunity for successful
delivery. As part of the selection process, the business requirements, risks, operational
environment, and organizational impact should be considered. The Development
Methodology Selection Guide presented in Table 2-1, adapted from the Department of
the Air Force, Guidelines for Successful Acquisition and Management (GSAM)
Condensed Version, February 2003, lists the system development methods addressed
in the SELC Guide and the criteria to use in evaluating their suitability for a project.
Depending on the characteristics of the project, PMs may elect to utilize a methodology
other than one of those listed in Table 2-1. However, a Project Tailoring Plan must be
approved (e.g., for Level 1 and Level 2 acquisitions, Table 2 in Directive 102-01). The
use of Incremental and Spiral methodologies may require multiple ADE 2B reviews.

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-17


11-05-08
Table 2-1: Development Methodology Selection Guide
Iterative/
No. Project Criteria Waterfall Spiral
Incremental
1 Requirements are known and stable Õ Õ
2 User needs are unclear/not well defined Õ
3 New capability is innovative for organization Õ
4
Many external dependencies (legislative approval,
trade agreement, etc.) exist
Õ 9
5 An early initial operational capability is needed Õ 9
Early functionality is needed to refine requirements
6
for subsequent deliveries
Õ Õ
7 Task duration/effort can be accurately predicted Õ 9
8 Significant risks need to be addressed 9 Õ
9 Must interface with other systems 9 9 9
10 Need to integrate new or future technology 9 Õ
11 Software is large and complex 9 Õ
12 Software is small or limited in functionality Õ
13 Software is highly interactive with user 9 Õ
14 User interface is major design factor 9 Õ
15 Initial cost and schedule estimates must be followed Õ Õ 9
16 Detailed documentation is necessary Õ Õ 9
17 Minimize impact on current operations Õ 9
18 Full system must be implemented Õ 9
19 Project management must be simpler Õ 9
20 System must be responsive to user needs 9 Õ
21 Progress must be demonstrated early Õ
22 User feedback is needed Õ 9
23 Reduce the costs of fixes and corrections 9 9
Key:
For the criterion the methodology is: Õ = Recommended 9 = Satisfactory [none] = Not Recommended

2.3 Project Tailoring, Deviations, and Waivers


The DHS SELC Guide should be applied in a tailored manner appropriate to project
size, scope, complexity, risk, and security categorization. Tailoring is a technique that
facilitates the flexibility in the design and application of an appropriate development life
cycle to fit project characteristics, while ensuring compliance with requirements of the
SELC Guide. Thus, the number of SELC activities and documents required for
development efforts may differ between acquisitions due to tailoring based on project
characteristics. Specific SELC requirements may be waived as part of an approved
Project Tailoring Plan. Deviations – the approved alteration of the standard
requirements of the DHS SELC Guide – are also part of the tailoring process.

B-18 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
For example, for acquisitions that are less complex than the average project, the SELC
may be tailored to allow one or more required documents to be combined to form a
single artifact. Whether the SELC is tailored or not, the project must provide evidence
proving successful completion of required SELC activities and must ensure that project
documents record them in sufficient detail. A product called the Project Tailoring Plan
(for IT and non-IT) is required to document the development approach for the
program/project and is developed as an entry criterion to the Planning Stage of the DHS
SELC (i.e., part of the ARP ADE 2B). The Project Tailoring Plan may be a discrete sub-
set of the overall Project Management Plan rather than a stand-alone artifact.

In accordance with Directive 102-01, for Level 1 and Level 2 programs (where not
delegated), the Project Tailoring Plan is approved at the HQ level at ADE 2B, and any
subsequent changes to it must be coordinated with the approval authority. For Level 3
and below projects, approval is at the Component level. The approval of the Project
Tailoring Plan is granted as Project Managers are responsible for developing a Project
Tailoring Plan that is best suited to address the characteristics of the project. In order to
assist Project Managers, this DHS SELC Guide provides six work patterns in
Attachment B-2. A work pattern is a tailored version of the DHS SELC and is based on
either a standard development methodology (e.g., spiral) or other special use (e.g.,
COTS implementation).

Project Managers may select one of the work patterns as is or tailor the selected work
pattern further to meet the needs of the project. The Project Tailoring Plan should
indicate how the chosen methodology will fit with the ARP review cycle. For example,
spiral or incremental acquisitions may require separate 2B (or a 2A review when
requirements, AoA’s, ORD segments, costs and other planning for a new spiral were
not approved at a prior 2A). Most important is that the Project Tailoring Plan define the
optimal development methodology that provides the project the best opportunity for
successful delivery and meets all of the required standards for reviews. Evidence of plan
approval should be maintained with the project documentation.

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-19


11-05-08
2.4 Refine Documentation

Many documents are prepared in the life cycle of a project; some are created and
finalized in a single DHS SELC stage while others are updated in successive stages
after creation. Project baselines, the Project Management Plan, and the System
Security Plan (SSP) are examples of documents that are refined over multiple stages.
This applies particularly to security, privacy, and Section 508 Accessibility
documentation (29 U.S.C. Section 508, as amended by P.L. 105-220, August 1998. For
more information on project documents and their status per stage, refer to the DHS
SELC Artifact Summary, found in Attachment B-5 of this document.

2.5 Other SELC Considerations


The DHS SELC requires the use of a best practice project management methodology
(e.g., PMI’s Project Management Body of Knowledge [PMBOK]). The requirement to
use a best practice project management methodology is intended to increase the
probability of successful project completion.
In addition to the project management requirement, the DHS SELC requires Project
Managers to evaluate and incorporate the project activities described in Table 2-2.
Some of the elements described in the table, such as organizational change
management, are best practices. Others, however, such as Information Security, are
prescribed by DHS policy. The PM should evaluate these activities as a part of the
project tailoring activity. The Project Tailoring Plan, therefore, should reflect the
incorporation of the applicable and/or required activities. Detailed information, including
a description of each activity, its benefits, and associated considerations, is located in
Attachment B-3 of this document.

Table 2-2: Summary of Recommended Project Elements

Element High-Level Description


Project/Program A best practice methodology used to apply proven knowledge, skills, tools,
Management Process & and techniques to a broad range of activities in order to meet the cost, scope,
Plan and schedule requirements of a project. The project management plan must
contain all applicable elements from both the best practice methodology
selected for use and the requirements found in the DHS SELC Guide.
Organizational Change The process of assessing the impact of change in an enterprise (e.g., a
Management (OCM) change in mission, strategy, and IT systems) to the people and culture of an
organization.
Requirements Definition The practice of determining and recording stakeholder needs through
requirements gathering, analysis, specification, verification, validation, and
management.
Prototyping The creation of a temporary system for validating the interpretation of the
requirements, as well as for eliciting new requirements. 3
Critical Infrastructure The identification and protection of vital systems and assets that, if damaged,
Protection would present a severe impact to security, economic security, and national
public heath and/or safety.

3
Guide to the Software Engineering Body of Knowledge, IEEE Computer Society, 2004 Version.

B-20 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
Element High-Level Description
Human Factors A discipline devoted to optimizing the interaction of people, including persons
Engineering with disabilities, with the devices and applications they must use in order to
minimize errors and maximize efficiency.
Risk Management A structured process for identifying and managing risk with the objective of
balancing cost, schedule, and performance goals within program funding
constraints.
IT Specific
Enterprise Architecture A strategic information asset base that defines the mission, the information
Alignment and technologies necessary to perform the mission, and the transitional
processes for implementing new technologies in response to the changing
mission needs. An EA includes a baseline architecture, target architecture,
and a sequencing plan. EA alignment refers to how well activities support the
transition to the Homeland Security Target Architecture.
Information Security A set of practices to address the protection of information and information
systems from unauthorized activities and to promote a variety of assurances.
DHS requires that all solutions using IT in any form are certified and
accredited in accordance with DHS security policies before they are deployed
in an operational environment.
Privacy Compliance A structured review process to ensure that all privacy compliance
requirements are met prior to final project implementation.
Section 508 EIT Federal law that requires that Electronic and Information Technology (EIT) is
Accessibility accessible to people with disabilities. 29 U.S.C. Section 508, as amended by
P.L. 105-220, August 1998 was enacted to eliminate barriers in information
and data, to make available new opportunities for people with disabilities, and
to encourage development of technologies to achieve these goals. Section
508 standards are closely related to Human Factors Engineering (HFE). Any
human factors engineering initiative needs to be inclusive of persons with
disabilities, as optimizing interaction with devices and applications often has
a significant impact on accessibility. Human Factors Engineering for users
with disabilities is based on Section 508 EIT Accessibility Standards.
Independent Validation & An examination and certification of the project performed by an organization
Verification (IV&V) independent of the development organization. The IV&V results enable more
effective decision making.
Electronic Records Requirements related to the creation, maintenance, use, and disposition of
Management electronic records.

3. Stage A: Solution Engineering


The purpose of the Solution Engineering Stage is to conduct the systems engineering
necessary to determine the optimal solution set to solve the problem defined in the
MNS, which is approved at or prior to ADE 1. This stage will define the projects and
other activities that will deliver capability to DHS users and stakeholders. It is important
to note that this stage is the only SELC stage that focuses on the program and total
capability including potentially non-materiel solutions. To distinguish this difference it is
labeled as Stage A while the remaining stages are numbered 1-9.

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-21


11-05-08
3.1 Solution Engineering Activities
The following sub-sections describe the activities performed in the Solution Engineering
stage.

3.1.1 Document the Concept of Operation


The Concept of Operations (CONOPS) describes the operational view of the proposed
solution(s) from the user’s perspective. A CONOPS is used to communicate high-level,
conceptual, future business and mission operations to the project sponsors, end-users,
planning and design teams, and other stakeholders. Specifically, it provides the
framework for the development of an operational capability and provides an
understanding of the organizational impact of the proposed solution (e.g., the Business
Impact Assessment). The content of the CONOPS includes a description of the
operations processes and associated roles and responsibilities of operators. It
addresses the full Doctrine, Organization, Training, Materiel, Leadership, Personnel and
Facilities (DOTMLPF) and Regulations/Grants (RG) spectrum. For example, a
CONOPS might describe how combinations of additional trained personnel, new
doctrine and modernized materiel systems could fill specific capability gaps. The
CONOPS enables users to visualize how the proposed solution will operate in the real
world environment. Therefore it should account for likely situations, conditions and
external events. Scenarios, mission threads and use cases are ways to add a sense of
realism to the CONOP and help assess its’ robustness. The CONOP is also a vehicle to
communicate the impact of the proposed solutions and investments to leaders and
decision makers. CONOPS guidance is provided as Appendix F: Concept of
Operations, of Instruction/Guidebook 102-01-001.

3.1.2 Identify and Analyze Potential Solution Alternatives


An Analysis of Alternatives (AoA) is an analytical comparison of the operational
effectiveness and other benefits, suitability, and risk of alternatives that satisfy
established capability needs. Initially, the AoA process typically explores numerous
conceptual solutions across DOTMLPF/RG with the goal of identifying the most
promising options to achieve the desired capabilities, thereby guiding the Concept
Refinement Phase. Subsequently, at ADE 2, the AoA is used to justify the rationale for
formal initiation of the acquisition program.
Ideas, concepts and options across the DOTMLPF/RG solution space are identified and
assessed against such criteria as effectiveness, suitability, feasibility, alignment (e.g., to
the EA) timeliness, cost and risk. The AoA seeks to reach a balanced solution that
changes one or more of these elements to maximize mission outcomes. Therefore, the
AoA process should trade-off combinations of options within and across the
DOTMLPF/RG factors and present a recommended solution for consideration by
decision makers. It is important to understand that non-materiel solutions such as
training or additional personnel may represent considerable investments and may need
to be costed out. The AoA process incorporates cost analysis, benefit analysis, risk
analysis, and is a precursor to Life Cycle Cost Estimates (LCCEs), Acquisition Plans,
and other implementation plans. The AoA should be developed in parallel with the ORD
so that requirements, costs, and risks can be balanced. The DHS AoA process does not

B-22 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
assume that any one factor is held constant a priori. It assumes that decision makers
will be given the information they need to make trade offs among all factors including
requirements and costs. The Study Team should be aware of services that exist within
DHS and should maximize their use and avoid duplication. Generally, COTS, reuse and
common solutions are preferred to unique solutions, The Study Team may recommend
a preferred solution or solution set for decision makers or present decision makers with
a range of alternative solutions for selection. The results of the analysis are documented
in the AoA report.

3.1.2.1 AoA Study Plan


The AoA Guidance in Appendix G: Analysis of Alternatives of Instruction/Guidebook
102-01-001 contains additional details and formats. The AoA is guided by an AoA
Study Plan (AoASP) The AoASP will set assumptions, bounds and constraints on the
analysis of alternatives. It may rule out certain alternatives or may include others to
open up the field of possibilities. A key purpose of the AoASP is to ensure unbiased
exploration of a broad range of feasible alternatives, and balanced solutions that
address the DOTMLPF/RG spectrum. The SP will identify the participants and roles of
the analysis team, the review and approval process for the AoA, and required resources
including the need for Subject Matter Experts from Components, Industry and
FFRDCs/Labs. The AoASP is developed jointly by a representative from Headquarters
appointed by the DUSM or designee and a representative from the lead Component
appointed by the Component Head or designee. AoASP development should start
shortly after ADE-1 and be completed within 30 days or less. Review and approval of
the joint AoASP will depend on the program’s scope, size, criticality and other key
factors.

3.1.2.2 Study Plan Review (SPR)


The purpose of the SPR is to review the initial study plans assumptions and the scope
and methods of analysis. The Lead Component or development agent holds the (SPR)
with Headquarters representation. Level of HQ participation will vary depending on
several factors, for example, an AoASP for a program that has a significant impact on
several components may have representation from the DHS DUSM office and multiple
CXOs.

3.1.3 Develop Life Cycle Cost Estimate


The Life Cycle Cost Estimate (LCCE), documented with related assumptions and risks,
is created using information from the Acquisition Plan, Work Breakdown Structure
(WBS), project schedule, and information from entry criteria documents. The results are
used to help define the Acquisition Program Baseline (APB). The LCCE estimates the
total cost of a system from initiation through disposal. The LCCE is often developed at
a more granular and precise level of detail than the Cost Benefit Analysis (CBA) cost
estimates for the preferred or recommended solution. Guidance for the LCCE is
provided in Appendix I: Life Cycle Cost Estimate of Instruction/Guidebook 102-01-001.

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-23


11-05-08
3.1.4 Define Operational Requirements
ORD Guidance in Appendix H: Operational Requirements Document of Instruction
/Guidebook 102-01-001 contains a discussion on guidance for details and formats.
Operational requirements are defined to capture the business or operational user needs
without regard to the technical aspects of the system. Operational requirements are
high-level requirements that describe the mission, objectives, and operational
capabilities that are desired in the capability and project solution.

3.1.5 Develop Acquisition Plan


The Acquisition Plan (AP) defines how all Government human resources, contractor
support services, support services, facilities, hardware, software and
telecommunications and other capabilities are acquired during the life of the program
and project(s). The purposes of the AP is to ensure that best alternatives and strategies
for acquisition are used, Federal and DHS regulations and guidance are followed, and
required resources can be obtained and are available when needed, across the entire
lifecycle of the acquisition. For additional guidance refer to Appendix E: Acquisition
Plan Guide of Instruction/Guidebook 102-01-001.
Based on the acquisition strategy selected, PMs may need to solicit and award support
contracts to support resource requirements that are not available to be filled from within
DHS and related stakeholder organizations. Elements of resource planning which may
affect project schedule include activities such as training and the time required for
project personnel to acquire security clearances.

3.1.6 Develop the Integrated Logistics Support Plan (ILSP)


The Integrated Logistics Support Plan (ILSP) is a preliminary document at ADE-2 used
to support the ADE-2A decision; a high-level strategy for providing supportability and
sustainment that will be updated through the course of the acquisition cycle with
increasing detail and fidelity as the program progresses. It should provide critical insight
into the approach, schedule, and funding requirements for integrating supportability
requirements into the systems engineering process to ensure supportability of the
design and for developing/obtaining sustainment products. The ILSP provides the basis
for assumptions and planning for life cycle costs reflected in the APB and LCCE, and is
integrated with SELC requirements. Acquisitions will be independently assessed as
meeting the approved ILSP at each succeeding ADE. Specific assessment criteria and
certification requirements are under development. Guidance is provided as Appendix J:
Supportability and Sustainment of Instruction/Guidebook 102-01-001.

3.1.7 Establish Acquisition Program Baseline


Baseline performance measures should be established as the minimum standard for
operations. Performance metrics should be developed to measure improvement and/or
operational consistency. These metrics should be quantitative, to the extent possible, in
order to avoid inconsistent evaluation of the data collected and resulting analyses. The
Acquisition Program Baseline (APB):

B-24 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
• Establishes project performance requirements, schedule requirements, and a life
cycle cost estimate (note that APBs should be detailed to the project level) as a
“contract” between the Acquisition Decision Authority (ADA) and the PM.
• Includes parameters that, if not met, will result in the ADA reevaluating the project
and potentially considering alternative program concepts or design approaches and
re-baselining.
The Acquisition Program Baseline is a requirement of Directive 102-01. Additional
Guidance is provided in Appendix K: Acquisition Program Baseline (APB) of the
Instruction/Guidebook 102-01-001.

3.2 Documents
The project team records the results of their efforts in a set of documents, which are
presented in Table 3-1, Solution Engineering Stage Documents. All documents should
be placed under CM control.

Table 3-1: Solution Engineering Stage Documents


ARP Phases
PRODUCE/
ANALYZE/ DEPLOY/
NEED SELECT OBTAIN SUPPORT

Governing SELC Stages


PRODUCT Authority

Implementation
Requirements

Development

Operations &
Integration &

Maintenance
Engineering

Disposition
Definition
Planning
Solution

Design

Test
Mission Need Statement ARP (DIR 102-01) C F
Capability Development Plan (CDP) ARP (DIR 102-01) C/F
Acquisition Plan ARP (DIR 102-01) C U U U F
CONOPS ARP (DIR 102-01) C/F
Analysis of Alternatives / Alternatives Analysis ARP (DIR 102-01) C/F
Lifecycle Cost Estimate (LCCE) ARP (DIR 102-01) C U U U U
Operational Requirements Document (ORD) ARP (DIR 102-01) C/F
Integrated Logistics Support Plan (ILSP) ARP (DIR 102-01) C U U F
Acquisition Program Baseline ARP (DIR 102-01) C U F
Project Tailoring Plan DHS SELC C/F
Service Reuse Plan DHS SELC C U U U U U U F F
HLS EA Program Alignment Decision Request DHS EA Process C U U U F F
Program Alignment Documentation Matrix DHS EA Process C U U U F
Map to Business Architecture DHS EA Process C U U U F
Map to OCIO Portfolios DHS EA Process C U U U F
Section 508 National Security Exception
Determination DHS OAST C/F
Critical Infrastructure Protection Report DHS CISO C F
FIPS 199 Security Categorization DHS CISO C U
Preliminary Security Risk Assessment DHS CISO F
Project Authorization Review Approval Letter DHS SELC C/F

C = Create; F = Finalize, and U = Update

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-25


11-05-08
If the program is not approved, due to issues and/or risks, a remediation plan must be
developed and approved by the approval authority. The approval authority will establish
the timeframe for the next SER approval opportunity.

3.2.1 Solution Engineering Review Participants


Table 3-2 lists the suggested participants for the SER. Because acquisitions have
different characteristics, additional subject matter experts (e.g., architecture,
performance, data, contracting, budget, infrastructure, etc.) may be needed for specific
expertise.

Table 3-2: Participants for Solution Engineering Review


Participant Responsibility
Program Sponsor • Validates that the program is aligned with the project’s objectives
• Validates that the program is within cost, schedule, and performance constraints
• Validates that all risks are defined and manageable
Program Manager • Presents program status across all aspects of program (technical, cost, schedule, risk)
For IT Acquisitions
CIO • Validates that the program has been sufficiently engineered to enter the project stages
and begin delivering incremental capabilities
• Validates that all exit criteria are met
• Approves/disapproves program to proceed
DHS IT Portfolio • Validates that IT Portfolio objectives are appropriately documented in requirements
Manager(s) • Identifies/validates if an overlap of functionality exists between the program and
investments/systems in the IT Portfolio
For Non-IT Acquisitions
Component Acquisition • Validates that the program has been sufficiently engineered to enter the project stages
Group and begin delivering incremental capabilities
• Validates that all exit criteria are met
• Approves/disapproves program to proceed
APMD with Component • Validates that Portfolio objectives are appropriately documented in requirements
Acquisition Group • Identifies/validates if an overlap of functionality exists between the program and
investments/systems in the Portfolio

3.2.2 Exit Criteria


The objective of the SER is to evaluate the documents produced and to ensure that all
exit criteria are satisfied for a given program. Table 3-3 lists the exit criteria for the
Solution Engineering stage.

B-26 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
Table 3-3: Solution Engineering Stage Exit Criteria
Domain Exit Criteria
Program Management • Have all documents defined in the approved Project Tailoring Plan been completed
and reviewed for completeness?
• Has a CONOPS for the proposed system been developed and validated by users that
shows how the preferred solutions would work in the real world environment, and fill
existing gaps and meet new challenges?
• Does the AoA address the full spectrum of DOTMLPF/R/G/S alternatives?
• Does the AoA address all possible options, and is it unbiased toward one or another
(type) of solution?
• Have the feasible options been traded-off in the AoA to arrive at an optimized solution
that balances mission effectiveness, suitability performance, cost, schedule and risk
within realistic constraints?
• Has an ORD been developed that captures Key Performance Parameters (including
interoperability if applicable), Critical Operational Issues for operational testing, and
derived technical parameters, as well as IOC and FOC requirements?
• Have non-materiel solutions been identified to provide holistic solutions to gaps?
• Have the total lifecycle costs, including support/sustainment been captured within
sensitivity ranges in a LCCE?
• Have all changes to policies and/or regulations that require long lead times been
identified and included in the plans, and is the likelihood of such changes been
included in the risk analysis?
• Has an APB been developed that is aligned to program formulation, includes an
integration segment if applicable (e.g., for SoS) and provides realistic and pertinent
performance, cost and schedule parameters for each project (useful segment) been
produced, and it is consistent with the ORD, AOA, CONOPs and other projects?
• Does the schedule include time for staff to acquire security clearances If necessary?
• Has a Project Management Plan (PMP), including documentation of project scope,
tasks, schedule, allocated resources, and interrelationships with other projects, been
developed?
• Does the integrated master schedule include project resourcing, discrete work
packages, internal and external dependencies, and critical path, to the extent program
formulation has identified projects?
• Does the Business Strategy adequately address the most effective mechanisms for
each project?
• Have the risks been reviewed and are they deemed acceptable to move to the next
stage?
• Is the Service Reuse Plan still accurate and complete?
• Does the cost estimate in the APB and LCCE fit within the existing budget?
• If the project does not qualify for a National Security Exception, has a Section 508 EIT
Accessibility Plan been prepared?
Requirements • Have operational scenarios been analyzed and defined in the CONOPs?
• Have the business requirements collected to date been specified in clear, meaningful,
and testable format using “shall” statements?
• Have all the business requirements been reviewed by the acceptance test team to
ensure that the requirements are clear, meaningful, and testable?
Information Security • Has the security categorization been completed?
• Has the preliminary risk assessment been completed?
Privacy Compliance • Has a Privacy Threshold Analysis (PTA) been completed and approved by the Privacy
Office?
Software Engineering • Have business or operational requirements been validated by end users?
Data Management • If appropriate (if performing inter-component or inter-agency information exchanges),
has information exchange scenario planning been completed?

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-27


11-05-08
4. Stage 2: Planning
The purpose of the Planning Stage is to validate that sufficient analysis and planning
have been conducted to begin the project. All facets of the project are analyzed to
ensure that the cost, scope, and schedule are technically feasible and acceptable to
stakeholders. This includes, but is not limited to, creating a project plan for the
development of the proposed capability that addresses the stated business need. At the
end of the Planning Stage, the project team and stakeholders should have a
comprehensive project management plan (Table 4-1) that includes an integrated
schedule for development, and cost estimates.
The stage Exit Review for the Planning stage, the Project Planning Review (PPR), is
held at the completion of the Planning Stage and ensures that project resources,
activities, schedules, and tools are allocated and baselined prior to advancing to Stage
3, Requirements Definition.

Table 4-1: DHS IT Project Management Plan Elements

DHS SELC Common Project Management Plan Elements

No. Element Name


Project initiation documents: project charter, authority, sponsor, scope, project team
1
organizational structure, list of stakeholders, and stakeholder roles and responsibilities
2 Resource plan
3 Relationship agreements (if any)
4 Work Breakdown Structure
5 Integrated Master Schedule
6 Identification/definition of management processes to be used
7 Identification of management reviews and oversight authority
8 Communication plans

4.1 Planning Entry Criteria


Relative to the ARP, the Planning Stage occurs after ADE-2B. Many activities are
performed and documents produced as part of the DHS Analyze/Select and Obtain
phases of the ARP and the pre-select and select phases of the CPIC process that occur
prior to the initiation of DHS SELC processes for a project. (See Section 1.5 for more
information on the alignment of the SELC to the DHS ARP.) A high-level assessment of
the need (documented in the Mission Need Statement) is developed into an ORD,
alternative solutions are analyzed, a lifecycle cost estimate is developed, an APB is
developed, an AP is developed, and with approval of the acquisition at ADE-2A and 2B,
contracting and development actions can begin.

B-28 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
Additionally, the DHS SELC requires two new documents that must be approved by the
ADE-2B ADA: the Project Tailoring Plan and the Service Reuse Plan (for IT only). The
Project Tailoring Plan is developed to define any SELC adaptation required to meet the
needs of the project and the technical solution, while the Service Reuse Plan is created
to define those services that the project will create for reuse by other systems and those
that are already in service and the project plans to reuse. Table 4-2 lists the specific
SELC documents that must be approved by the ADE-2B ADA to enter the Planning
stage. Refer to the Directive 102-01 for the complete list of documents required for the
ADE.

Table 4-2: Planning Stage Entry Criteria

Line No. Documents Description


The Project Tailoring Plan documents the system development
1 Project Tailoring Plan approach in terms of the proposed SELC stages, activities, documents,
and exit criteria.
The Service Reuse Plan identifies the service(s) that a project plans to
reuse, enhance, or create new as part of the HLS EA Alignment review.
2 Service Reuse Plan (IT Only)
The Service Reuse Plan identifies and defines the use of DHS services
to meet project needs and to support deployment of the DHS SOA.

4.2 Planning Activities


Following the successful completion of the ADE-2A of the ARP process, the SELC
process begins with SELC Stage 1, Planning. The following sub-sections describe the
activities performed in the Planning stage.

4.2.1 Develop SE Risk Management Plan


The Risk Management Plan details the process used to identify, document, track,
mitigate, and report project risk. Numerous best practices are available to provide
guidance on the development of an effective and efficient Risk Management Plan, such
as those from organizations like the Software Engineering Institute (SEI) (developer of
the Capability Maturity Model Integrated [CMMI]) and the Project Management Institute
(PMI). Acquisitions are encouraged to use an automated risk management tool.

4.2.2 Develop SE Quality Assurance Plan


The Quality Assurance (QA) Plan documents the mechanism for verifying that the
delivered products satisfy contractual agreements, meet or exceed quality standards,
and comply with the processes specifically identified for use via the tailored instance of
the DHS SELC Guide approved for the project. The QA Plan identifies the
requirements, approach, activities, and approvals required to assess and validate
project products and deliverables against requirements.

4.2.3 Develop Training Plan


The Training Plan outlines the objectives, needs, strategy, and curriculum for training
users on the new or enhanced system. The plan presents the activities needed to
support the development of training materials, coordination of training schedules,

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-29


11-05-08
reservation of personnel and facilities, planning for training needs, and other training-
related tasks. If appropriate, the training plan should be jointly created with the project’s
Organizational Change Management team. Training activities are developed to teach
user personnel the use of the system as specified in the training criteria. The plan
includes the target audience and topics on which training must be conducted. It includes
how the topics will be addressed, the format of the training program, and the list of
topics to be covered, materials, time, space requirements, and proposed schedules.

4.2.4 Develop Configuration Management Plan


The CM Plan describes the process that will be used to identify, manage, control, and
audit the system documentation and baseline. The plan should define the CM policy,
procedures, structures, and roles/responsibilities to be used in executing configuration
management. The plan should address the identification of configurable Items, an
assessment of the impact of change, and the configuration management tool and
process (e.g., document versioning, storage, retrieval). The plan should also define the
Change Control Board (CCB) and identify the processes used by the CCB in evaluating
and approving changes to the system. The process should include assessments of both
the cost and schedule impact of making changes. Acquisitions have the option of using
a program-level CM Plan, if one exists. However, the PM is responsible for reviewing
the program-level CM Plan to ensure that it directly applies to the project as it is written.
If changes are needed to the program-level CM Plan, the PM should update the CM
Plan to specifically address the project’s needs.

4.2.5 Complete Privacy Threshold Analysis (As Applicable)


As part of the planning process, the project must complete a Privacy Threshold Analysis
(PTA) to determine if the proposed technology, system, or program collects, maintains,
and/or shares information in a form that could possibly identify or be used to identify
individuals. The PTA defines the initial assessment of privacy protection issues.
The PTA is a short form that asks for information related to:
• The type and status of the project
• Whether the project collects, maintains, or shares information that could relate in any
way to an individual
• The nature of the information used by the project
• The status of the project in the C&A process
The PTA Template is available from the website of the DHS Privacy Office found on
DHS Online and via email: pia@dhs.gov. Once completed, the PTA form should be sent
to the DHS Privacy Office for review and validation. The information from the PTA is
used by the DHS Privacy Office for an initial determination regarding the existence of
potential privacy issues that would trigger more comprehensive privacy compliance
documentation, the Privacy Impact Assessment (PIA), and the legal document called
the System of Records Notification (SORN).

B-30 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
4.2.6 Develop Section 508 Electronic and Information Technology Accessibility
Plan (As Applicable)
Section 508 (citation: 29 U.S.C. Section 508, as amended by P.L. 105-220, August
1998), mandates access to the use of information and data for persons with disabilities
that is comparable to that enjoyed by persons without disabilities. All DHS IT system
development efforts must have a Section 508 Electronic and Information Technology
Accessibility Plan that defines its approach to meeting Section 508 requirements. In the
initial stage of planning, it is important to determine if Section 508 technical standards
apply or whether any exception to Section 508 applies based on the information
available. Most exceptions cannot be determined at this point, as most are driven by the
business needs and often do not fully exempt an entire project from providing
comparable access. One exception that should be reviewed at this early stage is the
Section 508 National Security Exception (36CFR1194.2a).
If the project or part of the project qualifies for a National Security Exception, this would
reduce the required planning for the remainder of the life cycle. Section 508 National
Security Exceptions require approval from the DHS Office of Accessible Systems and
Technology (OAST). The determination of whether or not a Section 508 National
Security Exception applies can be ascertained from the answers to the following
questions regarding project scope:
• Is it for the command and control of military forces?
• Is it intended to be part of a weapons system?
• Does it include cryptologic activities used to support National Security?
For a complete description of the determination criteria, refer to National Institute of
Standards and Technology (NIST) Special Publication 800-59, Guideline for Identifying
an Information System as a National Security System.
If the project does not qualify for a National Security Exception as determined by OAST,
a Section 508 EIT Accessibility Plan must be developed and include both functional and
technical requirements, design, integration, and testing as well as continued operations
and support. Information on EIT Accessibility is presented in Attachment B, section
B2.11 later in this document.

4.2.7 Develop System Data Management Plan (IT Only)


The Data Management Plan identifies the information needs, data requirements, data
conversion, and data security strategies. The goals of data management include re-use
of existing resources through the discovery of available data services and data
repositories in order to provide timely, accurate information and supporting data
protection. Project staff need to know: 1) what data are available, 2) the quality of the
data, 3) how the data are used, 4) how to incorporate the data into resource
management decisions, and 5) how the data will be managed over time.
The Data Management Plan is a document whose content evolves over multiple
phases. Incorporation of reviews of the Data Management Plan after each stage by key
reviewers and data management resources ensures that impacts to the Component and
Enterprise data architecture are evaluated and incorporated, where necessary.

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-31


11-05-08
A key activity in the Data Management Plan is the assessment of alignment products to
the DHS Data Reference Model. The assessment results in the creation of several
products (i.e., the Program Data Architecture alignment, Data Asset and Logical Data
Model registration as well as Information Exchange planning).
If inter-Component or inter-agency information exchanges (transfer of information
between two parties) will be developed, the information exchanges must be developed
in accordance with the National Information Exchange Model (NIEM) IEPD. The Data
Management Plan must address NIEM scenario planning activities. Scenario planning is
a business analysis approach to identifying information exchanges and is the first phase
in the IEPD development methodology. For more information on the data management
plan, refer to the Enterprise Data Management Office (EDMO).

4.3 Documents
The project team records the results of their efforts in Stage 1 Planning in a set of
documents, which are presented in Table 4-3, Planning Stage Artifact Summary.
Documents must be traceable to the project Work Breakdown Schedule (WBS). All
documents should be placed under CM control. For a full listing of the documents,
including others that get updated during the Planning stage, see Attachment B-5 of this
document.

Table 4-3: Planning Stage Documents


ARP Phases
PRODUCE/
ANALYZE/ DEPLOY/
NEED SELECT OBTAIN SUPPORT

Governing SELC Stages


PRODUCT Authority

Implementation
Requirements

Development

Operations &
Integration &

Maintenance
Engineering

Disposition
Definition
Planning
Solution

Design

Test

Project Management Plan (Includes Integrated


Master Schedule) (PMP) DHS SELC C U U U U U F
Configuration Management Plan DHS SELC C F
Privacy Threshold Analysis (PTA) Privacy Office C/F
Section 508 EIT Accessibility Plan DHS OAST C U U U U U F
Risk Management Plan DHS SELC C/F
Quality Assurance Plan DHS SELC C/F
Data Management Plan DHS SELC C F
Training Plan DHS SELC C/F
Project Planning Review Approval Letter DHS SELC C/F

4.4 Stage Review and Exit Criteria


The objective of the Project Planning Review ( PPR) is to evaluate project readiness to
proceed to Stage 2, Requirements Definition. The PPR is conducted by the project sponsor
and the Project Manager to evaluate whether or not the products produced satisfy stated
requirements, with results being approved by the approval authority. As the basis for
evaluation, the PPR uses the set of exit criteria to evaluate completion of activities and
products from Stage 1.

B-32 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
If approved, the results of the PPR are recorded in a document called the Project
Planning Review Approval Letter, which must be signed by the approval authority.
However, it is expected that the approval authority will rely on the appropriate experts
(e.g., EA, testing, security, budget) to evaluate the readiness of each project to proceed.
The PPR Approval Letter is countersigned by the PM. A scanned electronic copy of the
signed stage review approval letter, the latest version of the Project Tailoring Plan, and
the updated project management plan (and associated project schedule) must be
emailed to the DHS Periodic Reporting team at Periodic.Reporting@dhs.gov.
If the project is not approved due to issues and/or risks, a remediation plan must be
developed and approved by the approval authority. The approval authority will establish the
timeframe for the next PPR approval opportunity.

4.4.1 Exit Criteria


The objective of the PPR is to evaluate the products produced and to ensure that all exit
criteria are satisfied for a given project. Table 4-4 lists the exit criteria for the Planning stage.

Table 4-4: Planning Stage Exit Criteria


Domain Exit Criteria
Project Management • Have the risks been reviewed and are they deemed acceptable to move to the next
stage?
• Do the plans accurately reflect the type of development methodology (e.g., spiral,
waterfall, iterative) identified in the Project Tailoring Plan?
• Have all products defined in the approved Project Tailoring Plan been completed and
reviewed for completeness?
• Has a Business CONOPS for the proposed system been developed?
• Have all changes to policies and/or regulations that require lead times been identified
and included in the schedule?
• Has access to the Risk Management Database been granted to appropriate project
team members?
• Has a WBS been fully developed?
• Is the project schedule executable (technical, cost,)?
• Does the schedule include time for staff to acquire security clearances?
• Does the integrated master schedule include project resourcing, discrete work
packages, internal and external dependencies, and critical path?
• Has a Project Management Plan (PMP), including documentation of project scope,
tasks, schedule, allocated resources, and interrelationships with other projects, been
developed?
• Is the Service Reuse Plan still accurate and complete?
• Does the updated cost estimate fit within the existing budget?
• If the project does not qualify for a National Security Exception, has a Section 508 EIT
Accessibility Plan been prepared?
Requirements • Have operational scenarios been analyzed and defined?
• Have the business requirements collected to date been specified in clear, meaningful,
and testable format using “shall” statements?
• Have all the business requirements been reviewed by the acceptance test team to
ensure that the requirements are clear, meaningful, and testable?
Information Security • Has the security categorization been completed?
• Has the preliminary risk assessment been completed?
Privacy Compliance • Has a Privacy Threshold Analysis (PTA) been completed and approved by the Privacy
Office?

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-33


11-05-08
Domain Exit Criteria
Configuration • Has an initial CM Plan been defined?
Management • Have CM tools and processes been specified, and has tool access been granted to
appropriate project team members?
Software Engineering • Have business requirements been validated by end users?
Data Management • If appropriate (if performing inter-component or inter-agency information exchanges),
has information exchange scenario planning been completed?

5. Stage 2: Requirements Definition


The purpose of the Requirements Definition stage is to gather, analyze, and document
requirements including functional, performance, and data requirements. Documents
related to requirements from earlier activities (i.e., MNS, ORD, CONOPS) form the
basis for further user needs analysis and the development of detailed functional
requirements. If analysis activities reveal new insights into the overall requirements, all
documents, must be revised to reflect this new information.
Multiple iterations of the Requirements Definition stage may occur in the project life
cycle, especially if the project strategy includes life cycle segments for prototypes or
pilots, or if it uses a spiral or iterative/incremental development methodology. During
each iteration, the documents appropriate for the subset of project requirements
allocated to the specific iteration are revisited and further refined, as necessary. The
Requirements Definition Stage continues until the requirements are defined in enough
detail such that design can begin.
Requirements must include considerations for performance, capacity, growth and
continuity of services (Continuity of Operations and Disaster Recovery), Accessibility
(29 U.S.C. Section 508, as amended by P.L. 105-220, August 1998), and must include
entries to meet the needs of persons with disabilities as required by the Rehabilitation
Act of 1973, as amended in 1998. Requirements should also include security, privacy,
entries for electronic record management, record disposition schedule, and
requirements unique to that Component. Acquisitions are encouraged to use an
automated requirements management tool.
Formal establishment of Service Level Agreements (SLA) should begin during the
Requirements Definition stage to allow time for all parties to establish an agreement that
meets the needs of the project. The writing of a Memorandum of Understanding (MOU)
or an SLA should simply be the restating of a subset of the requirements captured
during the Requirements Definition stage.
A System Definition Review (SDR) verifies that the exit criteria for the Requirements
Definition Stage have been met; successful completion of the SDR authorizes the
project to proceed to the Design Stage.

5.1 Requirements Definition Activities


The following sub-sections describe the activities performed in the Requirements
Definition Stage.

B-34 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
5.1.1 Develop Functional Requirements
The Functional Requirements Document (FRD) formally describes requirements in
terms of system function, inputs, processes, outputs, external interfaces, performance,
system availability, and maintainability. Each requirement must be measurable,
testable, and traceable to a source.
Source documents from which the functional requirements are derived include the ORD,
MNS, CONOPS, and other appropriate sources. Requirements identification and
analysis should ensure that hidden requirements critical to the success of the mission
are identified and are captured in the FRD. The FRD is the complete listing of user
oriented functional and data requirements for the system, including functional
(36CFR1194.31) and technical requirements (36CFR1194.21-26) as set forth in 29
U.S.C. Section 508, as amended by P.L. 105-220, August 1998. The functional
requirements serve as the foundation for the definition of the system requirements and
for the design and development of the solution. At a minimum, requirement definitions
should include a unique number, priority, criticality, feasibility, risk, source, and type.
Note non-functional requirements (requirements that specify criteria that can be used to
judge the operation of a system, rather than specific behaviors, such as availability)
must also be captured and described. The system will not be correctly specified unless
these requirements are also identified. In the case where inter-Component or inter-
Agency information exchanges are being developed, NIEM requirements must be
documented in the NIEM IEPD document.

5.1.2 Develop Requirements Traceability Matrix


The requirements traceability matrix (RTM) is created to map each detailed functional
requirement to its source and is updated throughout the systems engineering life cycle.
The RTM provides traceability from business requirements and other sources to the
FRD and into the test cases. As the life cycle progresses, additional traceability will be
added from FRD to the System Requirements Document (SRD), into high-level design
elements, into detailed design components, and finally into test cases and procedures.

5.1.3 Evaluate Infrastructure and Environmental Aspects


In addition to traditional IT requirements identification, DHS IT project teams must also
evaluate technology infrastructure, environmental and process needs, and non-IT
aspects. Any requirements identified during this evaluation must also be documented in
the FRD. Findings from the infrastructure evaluation should be used to develop the Site
Preparation Plan, which describes activities required to prepare facilities and
environments (e.g., development, integration, test, production, data center, off-site
storage) in time for installation and operation of the solution at all locations, based on an
analysis of existing conditions and the solution design requirements. This includes all
aspects of facilities preparation (construction, electrical, networking) and compliance
with all applicable legal requirements, including environmental requirements and those
for Section 508 Accessibility, privacy, and security.
With regard to environmental impact, the National Environmental Policy Act (NEPA)
requires Federal agencies to integrate environmental values into their decision making

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-35


11-05-08
processes by considering the environmental impacts of their proposed actions and
reasonable alternatives to those actions. To meet this requirement, Federal agencies
prepare a detailed statement known as an Environmental Impact Statement (EIS).
While this activity does not apply to some projects, PMs should consider the impact of
their efforts on the environment. For example, if a project plans to deploy wireless
technology, the project should consider possible effects the wireless communications
equipment might have on the environment.

5.1.4 Develop Test and Evaluation Master Plan


The Test and Evaluation Master Plan (TEMP) is the overarching program-level planning
document for Test and Evaluation (T&E)-related activities for major acquisition
programs. The TEMP describes the necessary Developmental Test and Evaluation
(DT&E) and Operational Test and Evaluation (OT&E) that needs to be conducted to
determine system technical performance, operational effectiveness / suitability, and
limitations. The TEMP identifies all critical technical characteristics and operational
issues and describes the objectives, responsibilities, resources, and schedules for all
completed and planned T&E, including modeling and simulation tools used in the T&E
process. Also, the TEMP describes all subordinate plans (e.g., DT&E and OT&E
plans), required reports (e.g., DT&E and OT&E reports), and assigns responsibility for
preparing and approving these plans and reports. Most acquisition programs are
required to have an approved TEMP and subordinate test plans prior to commencing
associated T&E unless a specific waiver is granted by the DHS Science &Technology
(S&T) Director, T&E and Standards Division. Appendix L:Test and Evaluation Master
Plan, of Instruction/Guidebook 102-01-001 provides guidance and a Template for the
TEMP.
The PM is responsible for coordinating the overall T&E strategy and approach for the
program. The PM should prepare a TEMP in accordance with the TEMP template as
outlined in this document after approval of the initial Operational Requirement
Document (ORD). The program’s TEMP should be approved by the Component
Acquisition Executive (CAE) and the DHS S&T Director, T&E and Standards Division
prior to formal submission to the Acquisition Decision Authority (ADA) at Acquisition
Decision Event (ADE) 2.
The fundamental purpose of T&E in an acquisition program is to verify attainment of
technical performance (in Developmental Testing), and required operational
effectiveness and suitability (in Operational Testing). As a system undergoes design,
development, and integration, the emphasis in testing moves gradually from DT&E,
which is concerned mainly with validating the contract requirements and the attainment
of engineering design goals and manufacturing process objectives, to OT&E, which
focuses on verifying operational effectiveness and suitability. The TEMP ensures that,
at a minimum, critical capabilities of the system are adequately tested and can be
implemented. The TEMP documents the scope, content, methodology, sequence,
management of, and responsibilities for test activities. The PM must consider the
appropriate testing approach. Usually, depending upon the system being developed,
more than one approach is needed, e.g., functional (behavioral), specification based
(requirements), stress, and exploratory tests.

B-36 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
Figure 5-1 shows the relationship of developmental and operational testing, the types of
tests conducted under each, and the capstone governing documents for each. Under
the overall strategic guidance of the TEMP, the PM develops a Developmental Test
Plan (DTP). The TEMP describes testing at a strategic (mission, goals, objectives level)
and the DTP at a tactical, more technical level.

Figure 5-1: Developmental Testing and Operational Testing and Key Documents

5.1.5 Developmental Test Plan


The Developmental Test Plan (DTP), guided by the capstone strategic TEMP, describes
the purpose, activities, scope, responsibilities, schedule, resources, and other
information for developmental testing. It is prepared by the PM. Unit, integration, and
functional testing are performed under the direction of the PM. System Testing,
Security Test and Evaluation (ST&E for IT systems) and User Acceptance Testing are
performed independently of the development team. Acceptance tests will be performed
by user groups in a test environment that duplicates the production environment as
much as possible. The user groups must ensure that:
• Requirements are defined in a manner that is verifiable

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-37


11-05-08
• Requirements support the traceability from the source documentation to the design
documentation to the test documentation
• Functional requirements are properly implemented by the system in the production
environment
The DTP should have a schedule for DT that shows the DT activities in the context of
the TEMP schedule of activities and describes any dependencies between DT and OT.
The DTP should also address the data required to test the system and any procedures
required to develop test data or to protect sensitive data. Note that any DHS data (non-
fictitious data containing information about people or resources) used in testing must
meet privacy compliance requirements, which do not distinguish between the use of
data for operational systems and use of data during testing, pilots, or prototypes. This
means that before actual testing occurs, all required privacy compliance documentation
must be completed and approved. This policy also applies to OT.

5.1.6 Complete Information Security Activities (IT Only)


The Office of Information Security maintains both a classified and an unclassified
version of the CISO-approved C&A tool. DHS 4300A, Sensitive Systems Handbook
applies to all unclassified systems and used throughout this document as reference. For
classified systems, all references should be made to DHS 4300B, National Security
Systems Handbook. Access to the classified or unclassified version of the CISO-
approved C&A tool should be made through the Component’s Information System
Security Manager (ISSM).

5.1.6.1 Develop Security Requirements Traceability Matrix (IT Only)


During the Requirements Definition stage, initial steps toward the system C&A are
accomplished. The purpose of these initial steps is to analyze the threats to and
vulnerabilities of the system, to determine the potential for losses or compromise, and to
use the analysis as a basis for identifying appropriate security controls for reducing risk.
The Security Requirements Traceability Matrix (SRTM) documents the security
requirements for each system. It is automatically generated by the CISO-approved C&A
tool through the use of a questionnaire that facilitates the selection of appropriate
requirements and controls, prior to generating the SRTM. Each IT project must develop
an SRTM, which becomes the basis for the security design, certification, and
accreditation activities for the project.

5.1.6.2 Develop Plan of Action and Milestones (IT Only)


The Plan of Action and Milestones (POA&M) document is a tool that describes plans
and associated tasks to correct identified weaknesses that can potentially be harmful to
DHS systems. The POA&M is also used to document progress in correcting previously
identified weaknesses; it is updated often throughout the systems engineering life cycle.
For more information on the POA&M, refer to DHS 4300A.

B-38 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
5.1.6.3 Initiate Development of System Security Plan (IT Only)
The System Security Plan (SSP) provides an overview of the security requirements of
the system and describes the controls that are currently in place or planned to meet
security requirements. The SSP details the management, technical and operational
security controls required for the system based on the type of information being
processed and the degree of sensitivity and risk. DHS 4300A and DHS 4300B prescribe
the SSP requirements based on the C&A process appropriate for the system. The
CISO-approved C&A tool currently provides SSP templates. Additionally, the security
team must:
• Develop the ST&E in support of the C&A process.
• Identify necessary security metrics and plan for data collection and reporting.
• Enter initial system information in the CISO-approved tool for FISMA reporting; a
completed and validated Privacy Threshold Analysis must also be loaded into the
Trusted Agent FISMA tool.

5.1.6.4 Develop Security Risk Assessment (IT Only)


Like the SRTM, the Security Risk Assessment (SRA) is part of the system C&A
process. As outlined in the Department of Homeland Security Certification and
Accreditation Guidance for SBU Systems User’s Manual, the steps for conducting a
security risk assessment include:
• Inventory and System Boundary Verification
• Information Security Categorizations 4
• Determination of E-Authentication Requirements 5
• Risk Assessment
• Creation of C&A package using the CISO-approved C&A tool
The Department of Homeland Security Certification and Accreditation Guidance for SBU
Systems User’s Manual contains step-by-step directions for completing the security risk
assessment as well as information about obtaining accounts for the CISO-approved
C&A tool. The CISO-approved C&A tool contains templates for completing the Risk
Assessment document. If contractors are used on a project, the contract must include
the appropriate Homeland Security Acquisition Regulations clauses that identify the
appropriate level of security clearance required of the personnel fulfilling the resource
requirement for the project team, as well as to indicate the method to be used to ensure
that these and other security requirements are met. For more information regarding the
SRA, refer to DHS 4300A.

4
DHS Information Security Categorization Guide.
5
DHS Information Security Categorization Guide.

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-39


11-05-08
5.1.6.5 Develop Security Test and Evaluation Plan (IT Only)
The ST&E Plan, part of the System Security Plan, is a document developed to support
the certification and accreditation process in accordance with DHS policy found in DHS
4300A. The ST&E Plan documents the specific testing of the security features to be
implemented within the system and other related systems. For more information
regarding the ST&E, refer to DHS 4300A.

5.1.7 Develop Service Level Agreements


In order to facilitate project success, formal agreements – SLAs – should be developed
with all organizations (internal and external) that will contribute to and/or share
resources with the project. In this case, the term “resources” refers to infrastructure
assets, DHS SOA services, personnel, and funding. SLAs may or may not require a
monetary exchange, but will always involve some type of exchange transaction. Thus,
these agreements should be in the form of a Memorandum of Agreement (MOA) or an
MOU so that both parties are aware of and formally agree to the defined terms and
conditions. For IT systems that have interfaces to other systems, an SLA, at minimum,
should be developed. An Interface Control Document (ICD) or IEPD may be needed.
See Attachment C.15 for more guidance.
When the SLA is defining the interaction for an IT service (which is not already in the
service component reference model), the service(s) should be submitted for insertion
into the HLS EA service component reference model. The service component reference
model categorizes both “above the line” services (services that cross component
organization boundaries) and “below the line” services (services that are internal to a
Component). The insertion process varies depending whether the service is “above the
line” or “below the line.”
“Above the line” services require submission of the Service Insertion Packet (SIP). The
SIP documents the service from a business, service level, and technical context. The
SIP requires exchange partners to agree to the inputs and outputs at a business and
technical level and the level of service to be provided. The exchange should be
documented in the form of an ICD that identifies the data exchanged and documents
the protocols used to exchange the data. The data exchanged should be documented in
the form of a NIEM IEPD if the exchange is inter-Component or inter-Agency. If an IEPD
is developed in lieu of an ICD, supplemental documentation is required to explain the
protocols used to implement the exchange.
Upon approval, the SIP is registered in the HLS EA as a Department-wide service. This
human readable registry is intended to foster reuse and consolidation of IT services
throughout the Department.

5.1.8 Develop Disaster Recovery Plan (IT Only)


The project team must develop a disaster recovery plan. This plan describes the
organized process for implementing emergency responses, back-up operation, and
post-disaster recovery to ensure the availability of critical IT resources and to facilitate
continuous operations in a disaster. A Disaster Recovery Plan takes effect when normal
procedures fail to resolve a problem.

B-40 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
5.1.9 Map Project Data to HLS EA Data Architecture (IT Only)
To identify and evaluate data requirements for the project, the project team needs to
map the data required to support the business requirements to the HLS EA Data
Architecture. This activity begins in Requirements Definition and is updated as data
needs are clarified at points throughout the lifecycle, to be finalized in the O&M stage.
The purpose of this activity is to determine the information that is required by the project
to accomplish the mission, regardless of functional, procedural, or organizational
boundaries. 6
The Map to the Data Architecture document is used for documenting the mapping of the
project data to the HLS EA Data Architecture. EDMO will use this mapping to identify
potential involvement and support needs as well as impacts to the HLS EA Data
Architecture. The Enterprise Architecture Board (EAB) uses the information in the Data
Architecture to ensure data consistency and availability and to promote data sharing
across the enterprise. For more information on data architecture alignment, refer to the
EAB Process Guide.

5.1.10 Map Documents to the HLS EA Technical Reference Model (IT Only)
The Technical Reference Model (TRM), a component of the HLS EA, provides guidance
to ensure that proposed IT solutions are consistent and to promote interoperability
across the DHS enterprise. The implementation of the TRM is accomplished through
the use of the Standards Profile (SP). The DHS Standards Profile reflects the industry
standards and actual documents that have been adopted for use throughout DHS. DHS
IT project teams are responsible for mapping proposed solutions to the DHS TRM (and
Target TRM) and Standards Profile in order to ensure compliance with existing
standards and with the future architecture. Where no standard is in place, projects
should identify the standard to be used. Projects may propose refinements to the TRM
via the DHS Technology Insertion Process. For more information on DHS Technology
Standards and Documents, refer to the EAB Process Guide.

5.2 Documents
The project team records the evidence of its work in the set of documents listed in Table
5-1. The tailored plan approved for use in the project determines the documents
applicable for the project. The project WBS must include the corresponding line items
for completion of each artifact. All documents should be placed under CM control. For a
full listing of the documents, including other items that get updated during the
Requirements Definition stage, see Attachment B-5 of this document.

6
EAB Governance Process Guide Version 3.0, March 31, 2006, Department of Homeland Security Enterprise
Architecture Board, Appendix G, p. 121.

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-41


11-05-08
Table 5-1: Requirements Definition Documents
ARP Phases
PRODUCE/
ANALYZE/ DEPLOY/
NEED SELECT OBTAIN SUPPORT

Governing SELC Stages


PRODUCT Authority

Implementation
Requirements

Development

Operations &
Integration &

Maintenance
Engineering

Disposition
Definition
Planning
Solution

Design

Test
Functional Requirements Document (FRD) DHS SELC C U U U U F
Requirements Traceability Matrix (RTM) DHS SELC C U U U U F
Test and Evaluation Master Plan (TEMP) DHS SELC C U F
Security Requirements Traceability Matrix (SRTM) DHS CISO C U F
Plan of Action & Milestone (POA&M) DHS CISO C U U F
System Security Plan (SSP) DHS CISO C U U U F
Contingency Plan DHS CISO U F
Disaster Recovery Plan DHS SELC C U F
Security Risk Assessment (SRA) DHS CISO C U F
Security Test & Evaluation (ST&E) Plan DHS CISO C F
Map to the Data Architecture DHS EA Process C U U F
Map to the Business Architecture DHS EA Process C U U F
Map to Technology Standards & Products DHS EA Process C U U F
System Definition Review Approval Letter DHS SELC C/F

5.3 System Definition Review and Exit Criteria


The objective of the SDR is to evaluate the readiness of a project to proceed to Stage 3,
Design. The SDR is conducted by the project sponsor and the Project Manager. As the
basis for evaluation, the SDR uses a set of exit criteria to evaluate completion of
activities and products for this stage of the SELC. The results of the SDR review are
recorded in a document called the System Definition Review Approval Letter, which
must be signed by the approval authority along with the project sponsor, who attests
that the requirements satisfy the business need. However, it is expected that the
approval authority will rely on the appropriate experts (e.g., EA, testing, security,
budget) to evaluate the readiness of each project to proceed. The SDR Approval Letter
is countersigned by the PM. A scanned electronic copy of the signed stage review
approval letter, along with the updated project management plan (and associated
project schedule), must be emailed to the DHS Periodic Reporting team at
Periodic.Reporting@dhs.gov.
If the project is not approved due to issues and/or risks, a remediation plan must be
developed and approved by the approval authority. The approval authority will establish
the timeframe for the next Project Planning Review approval opportunity.

5.3.1 Exit Criteria


The objective of the SDR is to evaluate the products produced and to ensure that all exit
criteria have been satisfied for a given project. Table 5-2 lists the exit criteria for the
Requirements Definition stage.

B-42 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
Table 5-2: Requirements Definition Stage Exit Criteria
Domain Exit Criteria
Project Management • Have the risks been reviewed and are they deemed acceptable to move to the next
stage?
• Is the project on schedule or have remediation plans been developed to correct for
schedule loss?
• Have all Action Items from the PPR been resolved?
• Have all products defined in the approved Project Tailoring Plan been completed and
reviewed for completeness?
Requirements • Are the business performance metrics defined?
• Can the requirements for this project support any other organizations?
• Have the requirements collected to date been specified in clear, meaningful, and
testable format using "shall" statements?
• Have all the business requirements been reviewed by the acceptance test team to
ensure that the requirements are clear, meaningful, and testable?
• Has requirements interdependency been considered and/or analyzed?
• Have scalability, availability, and reliability been addressed?
• Have interface requirements for both external and internal system interfaces been
identified and defined?
• Do the user interface requirements clearly define all the human interface needs?
• Do the training requirements accurately account for the users and administrators of
the system?
• Have the Section 508 EIT Accessibility requirements been documented?
• Do the reporting requirements ensure that the business users get the information they
need?
• Have “as-is” and “to-be” business processes been defined and reflected in the ORD?
Information Security • Has an ISSO been assigned?
• Has the boundary and inventory information been validated by the CISO?
• Has the e-authentication analysis been completed?
• Has the preliminary risk assessment been completed?
• Has the C&A package been generated in the CISO-approved C&A tool?
• Has the SRTM been developed?
• Has the SSP been drafted?
• If appropriate, has an ISA been developed?
• Has the ST&E plan been developed?
• Has the Contingency Plan been completed?
Performance • Do the existing SLAs of any service providers to be used satisfy the project‘s needs?
• Has the initial Capacity and Performance analysis included business capability and
performance requirements?
• Has the preliminary workload characterization for the project been documented based
on the business volumetrics?
• Have system's life-cycle costs been updated based on the updated capacity and
performance analysis?
• Have the performance requirements been specified completely in clear, meaningful,
and testable "shall" statements?

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-43


11-05-08
Domain Exit Criteria
Data Management • Have the data supporting the business processes been specified to a conceptual
level?
• Have data management requirements been defined?
• Do data retention requirements meet the business need?
• Does the data conversion plan (documented in the data management plan) account
for possible cleansing and data quality issues as well as performance impacts to the
existing Data Architecture?
• Are modifications to the Data Architecture necessary to accommodate the proposed
system?
• Has alignment to the HLS Data Architecture been provided?
• Have data architecture alternatives been categorized, prioritized, and cost-justified?
Configuration • Are all documents, especially requirements, under CM control?
Management • Have Configurable Items (CIs) for the project been identified and submitted to the CM
team?
Testing • Does the Test and Evaluation Master Plan (TEMP) identify those responsible for
developing the test procedures, running the test, and identifying which reports will be
provided?
• Does the schedule include enough time to conduct integration testing, performance
testing, Section 508 Accessibility testing, and acceptance testing while the developers
are re-working the code?
• Is the DTP adequate and linked with the TEMP?
• Does the DTP describe the independent role of the acceptance test team?
• Has the test lead for acceptance testing been appointed?
• Does the DTP specify defect severity level definitions?
• Are all functional requirements stated such that they are testable?
Enterprise • Are the technologies identified in the solution consistent with the target TRM?
Architecture • Does the technical approach embrace re-usability?
• Will the outcome result in new Service Components that can be registered in DHS
Service Registries?
• Is the data required by this project already available or will it be made available to
others?
• Are modifications to the EA necessary to accommodate the proposed system and
have they been through the Technology Insertion (TI) Decision Request Process?
• Are the technologies identified in the solution consistent with the technology patterns
and IT components?
• Does the solution conform to DHS data standards?
• Are the IT components identified in the Application Architecture?
• Does the project provide an enterprise-wide solution?
• Have elements been identified for re-use, enhancement, or creation of new services
for the SOA?
• Is the project aligned with a DHS IT Portfolio?
Software Engineering • Have business processes been specified to a logical level?
• Have processes been documented (e.g., use cases, flow diagrams)?
• Do the priorities listed for each requirement accurately represent the business'
capability needs?
• Are sources documented for each requirement?
• Have business requirements been validated by end users?
• Do the SLAs address the needs of all parties by defining the expectations of each?
• Does the design include processes and capabilities to monitor and review all aspects
of the SLAs?

B-44 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
Domain Exit Criteria
Infrastructure • Has an illustration depicting the conceptual network been developed and
documented?
• Has the technical infrastructure been specified to a conceptual level?
• Have locations and types of infrastructure components been identified and
documented?
• Have all infrastructure requirements (e.g., heating, ventilating, and air conditioning,
power, fail-over, communications, redundancy, facility space) been defined?
• Have critical infrastructure designations as defined in HSPD-7 been analyzed and
completed?
Operations and • Have system management and support processes (e.g., call center, help desk) for the
Maintenance system been identified?
• Has an initial Disaster Recovery Plan been developed?
Transition • Has a Business Impact Assessment (BIA) been initiated as part of Organizational
Change Management activities?

6. Stage 3: Design
The objective of the Design stage is to transform the baselined requirements into
comprehensive, logical, and detailed designs to efficiently and effectively guide
development. The decisions made in this stage address, in detail, how the system will
meet the variety of defined requirements. Activities performed in this stage also ensure
that the following objectives are met:
• The detailed design specifications align with the HLS EA (including SOA), Section
508 Accessibility standards, privacy requirements, and security requirements
• Mechanisms to handle system disruptions are considered and planned
• All required technology insertions into the DHS EA TRM are completed and
approved
Design activities may be conducted in an iterative fashion, producing first a logical or
preliminary design of the solution that emphasizes the functional features of the system,
then a more detailed design that expands the logical design by providing all the
technical detail required to implement the logical design and that allows system
development to begin. Projects are encouraged to use an automated design tool. If
appropriate, prototyping should be used to help refine requirements, provide
stakeholders with an initial view of the system, and gain their approval to proceed with
development. More information on prototyping can be found in Attachment B2, section
B2.6.2.
The Design stage includes a Preliminary Design Review (PDR) and a Critical Design
Review (CDR). The PDR is conducted during the Design stage while the CDR is
conducted at the end of the Design stage. For information on Developing the
Deployment Plan activities, see Appendix J: Supportability and Sustainment Guide of
the Instruction/Guidebook 102-01-001.

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-45


11-05-08
6.1 Design Activities
The following sections present typical activities that are performed as part of the Design
stage. The set of activities actually performed for a given project in the Design stage
may differ, depending upon the SLC tailoring approved for the project.

6.1.1 Define System Requirements and Update the Requirements Traceability


Matrix
System requirements are defined at the lowest level of granularity sufficient for system
and sub-system generation, and are documented in the SRD. System requirements are
driven by the functional requirements and ensure that all design elements can be built
and tested. The RTM is updated to ensure that all requirements are directly traceable to
their source and are accounted for in the design. This process of updating requirements
may include scope changes and be governed by a change control board or other
control.
Table 6-1 lists the SRD elements that should be addressed unless they do not apply
due to the characteristics of the project.

Table 6-1: SRD Elements


Typical Elements Addressed in the SRD
• Data Requirements (IT only) • System Portability
• Process Requirements • Operational Scenarios
• User and System Interface Requirements • Security Requirements
• Hardware and Software Interfaces • Privacy Requirements (IT only)
• Communication Interfaces (IT only) • Section 508 Accessibility Requirements
• Data Currency and Retention (IT only) • System Process Models
• Audit Trail Requirements (IT only) • Data Flow Diagrams
• System Availability, Reliability, and Recoverability • Context Diagrams
• System Performance • Interoperability
• Fault Tolerance • Capacity

6.1.2 Develop Logical Design


The logical design (often called “preliminary” or “high-level” design, as opposed to
“system design” or “detailed design”) identifies, analyzes, defines, and relates the
functional features of the solution to the architectural components of the system and is
the foundation for development of the detailed design of the system. The logical design
addresses the data, applications, technical infrastructure, business processes,
organizational, and location aspects of the solution. 7 Elements commonly found in a
logical design document are presented in Table 6-2.

7
Enterprise Life Cycle Guide v2.0, Internal Revenue Service, May 1, 2006, p.47.

B-46 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
Table 6-2: Logical Design Elements
Common Elements in the Logical Design Document 8
• Alignment with higher-level designs and HLS EA • Identification of required common services
• Functional application subsystems and flows (IT • Software architecture strategy (IT only)
only) • Security
• User-system interface and/or prototype • Privacy (IT only)
• Interface (internal/external) designs • Performance
• Requirements allocated to logical components • Application builds (IT only)
• Updated RTM
• Verification of technical infrastructure (development
and test environments)

6.1.3 Develop Data Architecture (IT Only)


The Data Architecture describes the data and data relationships required for the
proposed solution, as well as the approach for data storage, access, continuity, and
implementation. The Data Architecture document includes a logical data model, a
process model to describe data management, a mapping of data entities to business
function, requirements, data flows, and data interoperability requirements. Data
Architecture development also aligns the data quality assurance plan and data security
plan with the data management goals and business requirements. The data architecture
document is complemented by the Data Management Plan (DMP). For additional details
on Data Architecture documentation, see the Data Architecture template.
A key step in the development of the data architecture is maintaining the traceability
mappings of the Logical Data Model (LDM) to the EDMO Enterprise LDM and the HLS
EA Conceptual Data Model. Additionally, the Data Architecture must maintain data
alignment documents and develop metadata for data assets as critical elements of the
Data Reference Model (DRM) artifact library. The DRM artifacts are submitted to the EA
Center of Excellence (COE) and the EDMO as the Data Insertion package to be
registered in the DHS Data Asset Catalog.

6.1.4 Conduct Preliminary Design Review


The Preliminary Design Review (PDR) is a multi-disciplinary technical review intended
to ensure that the system under review can proceed into detailed design and that it can
meet the stated performance requirements within cost (program budget), schedule
(program schedule), risk, and other system constraints. Generally, this review assesses
the system preliminary design, as captured in performance specifications and logical
designs, and ensures that each function in the functional baseline has been allocated to
one or more system configuration items. It determines whether the hardware, human,
and software preliminary designs are complete, and whether the team is prepared to
start detailed design and test procedure development. Often the program performs
Early Operational Assessment at this time (e.g., using modeling and simulation).

8
Ibid, p. 45-47.

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-47


11-05-08
The PDR evaluates the set of requirements to determine whether they correctly and
completely satisfy all system requirements allocated to the subsystem. The PDR also
determines whether subsystem requirements track with the system design. Any
concerns as to whether the logical design is aligned and supportable by the technical
architecture should be raised and resolved before the detailed design begins. The PM
should tailor the review to the technical scope and risk of the system.
Typical PDR success criteria include affirmative answers to the following exit questions:
• Have all critical design issues been resolved?
• Can the preliminary design, as disclosed, satisfy the requirements?
• Is the preliminary design producible within the production budget?
• Is the logical design aligned and supportable by the technical architecture?
• Have human integration design factors been reviewed and included, where needed,
in the overall system design?
• Are the risks known and manageable for development testing and operational
testing?
• Has security been addressed throughout the design?
• Have data stores and interchanges been addressed?
• Is the program schedule executable (technical/cost risks)?
• Is the program properly staffed?
• Is the program executable with the existing budget?
• Does the updated cost estimate fit within the existing budget?
The PM should conduct the PDR when all major design issues have been resolved and
work can begin on detailed design. The PDR should address and resolve critical,
system-wide issues.

6.1.5 Develop System Design


The detailed design expands on the logical design to define all elements of the solution
to the lowest level of granularity required to facilitate development and satisfy
requirements. During system design, the allocation of requirements to configuration
items and then to components of the configuration items is documented in the RTM by
adding columns containing references to configuration items and components. In this
way, a clear relationship between system components and requirements is established
for use during subsequent Validation and Verification (V&V) activities.
If current information needs to be converted/migrated/transitioned to the new system,
strategies shall be designed for those purposes, especially if converting means re-
engineering existing processes. Strategies must also be designed to initiate new and/or
update existing agreements, plans, privacy compliance documentation, and
assessments (e.g., the Data Management Plan, System Security Plan) to reflect the
impact of these conversion and implementation plans. Elements commonly found in a
detailed design document are presented in Table 6-3.

B-48 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
Table 6-3: Detailed Design Elements
Common Elements in the Detailed Design Document 9
• Demonstrated alignment with higher-level designs, • Security design
other design components, and HLS EA • Section 508 Accessibility approach
• Application, transactions, subsystems, interfaces (IT • Performance analysis
Only)
• Coding standards (IT Only)
• Data designs (IT Only)
• Internal interfaces and relationships designed
• Infrastructure designs
• External interface designs
• Proof of concept/prototype

6.1.6 Validation and Verification (IT Only)


The sooner a mistake in the development of a system is discovered, the less expensive
it is to fix. Therefore, once the design is complete, each project must conduct a
requirements review, V&V, to verify that the system design adequately addresses the
requirements. The partitioning of requirements, allocation of requirements, identification
of derived requirements, and definition of interfaces are all as important as the
development of the initial requirement. See Attachment B, section 2B.13 for more
information regarding V&V.

6.1.7 Develop Technology Insertion Decision Request (IT Only)


If there are items in the design that are not compliant with the HLS TRM, the project
must initiate an EA Technology Insertion (TI) Decision Request process. The TI must be
approved by the EAB before any purchases are made and before the project can move
beyond the Design stage. For more information regarding the EA TI Decision Request
process, refer to the DHS EAB Governance Process Guide.

6.1.8 Develop Interconnection Security Agreements (IT Only)


Other systems (if any) that interface with the system under development must be
identified, including the exchange of data or functionality that will occur. All connecting
areas need to be documented for security and information flow purposes. System
interconnection requirements must be documented in the SSP. OMB Circular A-130
requires that written management authorization (an MOU or MOA) be obtained prior to
connecting with other systems and/or sharing sensitive data or information. The written
authorization details the rules of behavior and controls that must be maintained by the
interconnecting systems. A description of the rules for interconnecting the systems and
for protecting shared data must be included with the security plan.
The system interface requirements are documented in one or more Interconnection
Security Agreements (ISA). ISAs provide the formal documentation used to record and
control interface agreements among participating systems. Formal agreements should

9
Enterprise Life Cycle Guide v2.0, Internal Revenue Service, May 1, 2006, p.48.

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-49


11-05-08
be negotiated and initiated between/among DHS Components, other government
agencies, and non-government stakeholders as appropriate.
For more information, refer to DHS 4300A, Attachment N, Preparation of
Interconnection Security Agreements, which identifies the DHS requirements for ISAs.

Table 6-4: Deployment Plan Elements


Elements in the Deployment Plan
• Process flow of deployment activities • Support requirements
• Description of resources/support materials required • Support personnel requirements
• Description of site preparation/facilities work required • Support documentation requirements
• Roles and responsibilities • Acceptance test requirements at development site
• Deployment schedules • Acceptance test requirements at deployment site
• Issue resolution plan

6.1.9 Initiate Privacy Impact Assessment (IT Only)


The completed and validated Privacy Threshold Analysis determines the applicability of
the Privacy Impact Assessment (PIA) requirement. Generally, a PIA is required when
technology uses (i.e., collects, maintains, disseminates) personally identifiable
information. The PIA serves as the primary mechanism for conducting and documenting
the privacy analysis. It is a longer form than the Privacy Threshold Analysis and the
System of Records Notice, and is organized into nine sections:
1. Information Collected and Maintained
2. Uses of the System and the Information
3. Data Retention
4. Internal Sharing and Disclosure
5. External Sharing and Disclosure
6. Notice
7. Individual Access, Redress, and Correction
8. Technical Access and Security
9. Technology
Each section includes a list of specific questions all of which are focused on identifying
the information in the system and the different ways that information is used and
shared. The PIA must be completed by the PM and approved by the DHS Chief Privacy
Officer prior to system implementation. The PIA need not be completed at the end of the
SLC Design stage, but it must be completed by the end of the SLC Integration and Test
stage.
PIAs are published to the public via the DHS Privacy Office website
(www.dhs.gov/privacy – follow the links to the PIA section). The only PIAs that are not
published publicly are those for national security systems; PIAs still must be completed
for all systems in this category. The DHS Privacy Office distributes the PIA template

B-50 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
along with specific guidance for completing the PIA as part of the PTA finalization
process. In addition, the PIA template and guidance are available from the DHS Privacy
Office website (both internal and external) and directly from the office via email:
pia@dhs.gov.

6.1.10 Initiate System of Records Notice (IT Only)


The DHS Privacy Office will coordinate a determination as to whether a System of
Records Notice (SORN) is required for the collection(s) of information related to the
system. Part of this determination includes a review of existing SORNs to identify any
SORNs that may already cover the data and/or any existing SORNs that could be or
must be updated to accommodate the intended uses of the system’s data.
The SORN, which is drafted in coordination with the Office of General Counsel (OGC),
is generally organized into seven sections covering the following issue areas:
1. Categories of individuals covered by the system
2. Categories of records (information) covered by the system
3. Authority for maintaining the system
4. Purpose(s) of the system
5. Routine uses (external sharing)
6. Policies for accessing, storing, and disposing of information
7. Procedures for notice and contesting information in the system
SORNs are published to the public in the Federal Register and are also published on
the DHS Privacy Office website. The project cannot be implemented until the SORN is
finalized, approved, and published for a period of at least 30 days. The nature of the
system and the use of data may sometimes require additional steps related to the
SORN. These additional steps could include a longer period for publication prior to
system implementation. Hence, additional time should be built into the pre-
implementation stages to accommodate the privacy compliance documentation
requirements. While the SORN does not need to be completed at the end of the Design
stage, it must be completed by the end of the Integration and Test stage.

6.2 Documents
The project team records the results of their efforts in Stage 3, Design in the set of
artifacts presented in Table 6-5. Artifacts must be traceable to the project WBS. Table 6-5
only shows the artifacts that are first created in the Design stage. All artifacts should be
placed under CM control. For a full listing of the artifacts, including others that get
updated during the Design stage, see Attachment B-5 of this document..

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-51


11-05-08
Table 6-5: Design Stage Documents
ARP Phases
PRODUCE/
ANALYZE/ DEPLOY/
NEED SELECT OBTAIN SUPPORT

Governing SELC Stages


PRODUCT Authority

Implementation
Requirements

Development

Operations &
Integration &

Maintenance
Engineering

Disposition
Definition
Planning
Solution

Design

Test
Service Level Agreements DHS SELC C U F F
System Requirements Document DHS SELC C U U U F F
Interconnection Security Agreement (ISA) DHS CISO C/F
Logical Design Document DHS SELC C/F
Data Architecture Document DHS SELC C/F
System Design Document DHS SELC C U U F
Technology Insertion Decision Request DHS EA Process C/F
Site Prep Plan DHS SELC C/F
Critical Design Review Approval Letter DHS SELC C/F

C = Create; F = Finalize, and U = Update

6.3 Stage Reviews and Exit Criteria


The fundamental purpose of the Design stage is to fully design all aspects of the system
so that the development organization can build the system and the test organization can
begin developing test procedures to verify the attainment of technical performance
specifications, operational effectiveness, and suitability. The PDR should have been
conducted during the Design stage to ensure that the logical design and architecture
satisfy the requirements. For more information on the PDR, see Section 6.1.4 of this
document.
At the end of the Design stage, the Project Manager and Project Sponsor conduct a
CDR, evaluating the exit criteria to ensure that all exit criteria have been met. A CDR is
deemed successful when the project team demonstrates that the design is complete
and accurate in its specification and can produce the results defined in the baseline
requirements.
The approval authority evaluates the design and signs the CDR Approval Letter
certifying that the design is sufficiently detailed for the development team to build
without further change to the design. Should change to the design be required, another
CDR with appropriate sign-offs shall be conducted. It is expected that the approval
authority will rely on the appropriate experts (e.g., EA, testing, security, budget) to
evaluate the readiness of each project to proceed. (Some key experts are identified in
the following list of stage review participants.) The PDR and CDR Approval Letters are
countersigned by the PM. A scanned electronic copy of the signed stage review
approval letter along with the updated project management plan (and associated project
schedule) must be emailed to the DHS Periodic Reporting team at
Periodic.Reporting@dhs.gov.
For IT systems, the Critical Design Review cannot be completed until all technology
insertions required for the system have been completed and are approved by the EA
COE.

B-52 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
6.3.1 CDR Participants
Table 6-6 lists the participants for the CDR.

Table 6-6: Participants for Critical Design Review


Participant Responsibility
Component CIO • Validates that the project has sufficiently detailed design elements to allow the
development stage to begin
• Validates that all exit criteria have been met
• Approves/Disapproves project to proceed to Development Stage and signs CDR
Approval Letter
DHS IT Portfolio • Validates that IT Portfolio objectives are accounted for in the system design
Manager(s)
DHS PADRT • Validates that the design is sufficiently defined to allow development to begin
Component EAB • Validates that the design aligns with the Component EA and that all products/tools
comply with the Component TRM
Project Sponsor • Validates that the project is aligned with the project’s objectives
• Validates that the project is within cost, schedule, and performance constraints
• Validates that all risks are defined and manageable
Project Manager • Presents project status across all aspects of the project (technical, cost, schedule,
risk)
Business Stakeholder • Validates that the design accurately and completely reflects the business needs
Representatives (number
differs with each project)
ISSO • Validates that the design will provide sufficient security safeguards for the system
System Development • Validates that the design is sufficiently defined to allow development to begin with
Manager (one responsible no re-work of system design
for developing/building the • Signature required on CDR Approval Letter indicating design is sufficient and is
system) approved to build
OAST or Component • Approves certain exceptions for Section 508
Section 508 Coordinator • Validates that Section 508 requirements are fully accounted for in the system
design

6.3.2 Exit Criteria


Table 6-7 lists the exit criteria for the Design stage.

Table 6-7. Design Stage Exit Criteria


Domain Exit Criteria
Program Management • Have the risks been reviewed and are they deemed acceptable to move to the next
stage?
• Is the project on schedule or have remediation plans been developed to correct for
schedule loss?
• Have all Action Items from the SDR been resolved?
• Have all artifacts defined in the approved IT Project Tailoring Plan/Project Tailoring
Plan been completed and reviewed for completeness?
• Has the development organization been identified and is it ready (possibly under
contract) to begin development?
• Has the development manager approved the design as sufficient to develop the

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-53


11-05-08
Domain Exit Criteria
solution?
• Have all documents from previous stages been updated as necessary to reflect new
information and decisions from the current stage?
• Has the Cost Benefit Analysis been updated to reflect the final system design?
• Has the Concept of Operations for the proposed system been updated in accordance
with the final system design?
Requirements • Have the functional requirements been logically decomposed to an acceptable level of
detail in the system requirements?
• Do the business requirements represent the needs of the system to perform
successfully while in production?
• Have Section 508 Accessibility requirements been addressed in the design?
• Are the system requirements allocated to software components?
• Are the infrastructure requirements defined?
• Have all the system requirements been reviewed by the acceptance test team to
ensure the requirements are clear, meaningful, and testable?
• Do users agree that the user interface design meets the business need?
Information Security • Has security been designed-in as an integral component of the preliminary system
design?
• Has a contractor been identified to conduct ST&E?
• Does the security test and evaluation plan provide for the testing of all security
controls?
• Does the security design satisfy the specified security categorization (FIPS 199)?
• Does the system design provide the security reports needed to audit and monitor the
system in production?
• Does the design include sufficient auditing to re-create user/administrator activities?
Privacy • Does the design appropriately protect and limit the use of personal data?
Performance • Do the system performance requirements meet the business need?
• Has the model/simulation of the preliminary system design been refined to the level of
detail sufficient to assign performance budgets to subsystems?
• Have performance budgets been assigned to subsystems for the amount of time
allowed to complete a task and the resources available for that task?
• Has the model/simulation of the final system design been refined to the level of detail
sufficient to predict system component performance in the development, test and
production environments?
Data Management • Have all major functions performed by the application been defined to a level
sufficient to account for transformation of all data elements processed by the
function?
• Have data capacities been analyzed and incorporated into the design?
• Has test data been identified for unit testing, integration testing, and acceptance
testing?
• Has the design demonstrated that the data architecture will provide the capacity to
meet functional and performance requirements?
• Are the requisite Information Sharing Agreements in place?
• Has the Data Management plan been updated?
• Has the DRM been updated and LDM aligned with Enterprise models?
Configuration • Is the system design under configuration management control?
Management

B-54 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
Domain Exit Criteria
Testing • Has a contractor been identified for Independent Verification and Validation?
• Are all system requirements stated such that they are testable?
• Has the source for development and test data been identified?
• Have technical plans been made to conduct testing with legacy systems (either using
their test environment or production environment)?
• Have specific Section 508 compliance testing requirements been identified?
Enterprise Architecture • Is the final system design aligned with the Homeland Security EA?
Software Engineering • Do the system requirements represent a final decomposition of the functional
requirements?
• Has the logical design of all business processes been specified?
• Have all software development tools (e.g., IDE, CM) been installed and configured?
• Have requirements been updated based on the user review of the proof-of-concept,
pilot, and/or prototype?
• Do software vendors acknowledge that all proposed software products have been
previously integrated?
• Have human integration design factors been reviewed and included, where needed, in
the overall design?
• Have Section 508 technical standards been selected so that functional performance
criteria are fulfilled?
• Has the software system design been specified in sufficient detail that a different
contractor could perform all coding without any additional information from the design
team?
• Is each design element traceable to its source requirement?
• Has the development manager reviewed the system design and concur that the
design is sufficiently detailed to develop code?
• Are all system and functional requirements accounted for in the design?
• Will the design meet the specified performance requirements?
• Are all interfaces between software components and infrastructure defined?
• Does the bill of materials for acquisition of equipment and software represent the
entire list for equipment and software?
• Is the structure of each to-be-built component and its interfaces defined?
• Are the installation and configuration parameters of all COTS products specified?
Infrastructure • Has the logical architecture specified all infrastructure components (new and existing)
by type and capability?
• Have impacts to existing equipment (e.g., routers, servers, mainframes, network
circuits) been analyzed?
• Has the physical design specified all infrastructure components by vendor, model, and
version?
• Is the infrastructure design specified in sufficient detail that a new contractor could
build out the design without any additional information from the design team?
• Is the development environment ready for use?
Operations and • Has an initial Disaster Recovery Plan been updated?
Maintenance
Transition • Have communications been developed notifying users of transition to the new
system?
• Have changes to organizational structure (e.g., help desk, O&M staff) been
developed?
• Have plans been developed for retiring system(s) that this system replaces? (I.e.,
removing h/w, s/w, closing out unneeded interfaces, archiving/subsuming
documentation.)

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-55


11-05-08
7. Stage 4: Development
The objective of the Development stage is to build and test the components designated
by the products of the Design stage. Although much of the activity in the Development
stage centers around the creation of the elements that make up the system, activities
also take place to develop user documentation (operator, maintenance, and user
manuals), establish the “integration and test environment” (where testing and
verification takes place), etc.
The Development stage includes activities for building, configuring, and preparing for
testing system components against their allocated requirements. For a complex system
design with multiple system components, there may be several simultaneous instances
of the Development stage in play during the project life cycle. Development stage test
activities are typically performed in the development environment. When all
Development stage activities have been completed, all system components that
constitute the system will be ready for the Integration and Test Stage.

7.1 Development Activities


The following sections represent the typical activities performed as part of the
Development stage. The set of activities actually performed for a given project in the
Development stage may differ depending upon the SELC tailoring approved for the
project.

7.1.1 Build, Construct, and Configure the System


This activity includes the steps required to transition from the Detailed Design, which
consists primarily of a detailed written description of the system, to an implementation of
the design. This activity may be accomplished through internal (i.e., DHS staff)
development, through a procurement/acquisition (e.g., using contractors, purchasing
COTS/Government Off-the-Shelf [GOTS] software and/or equipment), or a combination
of both. The approach to be used will be described in the Acquisition Plan and the PMP.
Regardless of the approach (internal, contracted, or combined), the system must be
developed and/or acquired in accordance with the Design Specification. Changes to the
Detailed Design and/or documented requirements must continue to be managed in
accordance with the approved CM Plan. The result of this activity is an initial system
implementation that can be tested and eventually deployed.

7.1.2 Conduct Unit Testing


As modules or subroutines are developed or updated, the development team must test
to verify the module or subroutine work appropriately. This is the lowest level of
developmental testing (DT) that can be done on a code module or unit.

7.1.3 Develop Test Case Specifications


There are essentially two sets of test cases that need to be developed, one for the
independent test team (documented in the Test Case Specification) and one for the

B-56 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
user acceptance team (documented in the System Acceptance Test Procedures). To
provide feedback to the PM, test cases need to be developed that test the requirements
and capabilities of the system. A test case is a document that describes an input, action,
or event and an expected response; it is used to determine if a feature of a system is
working correctly. A test case should contain particulars such as test case identifier, test
case name, objective, test conditions/setup, input data requirements, steps, and
required results.
An important potential byproduct of test case development is the identification of
problems in any aspect of the requirements or design of a system, including any
inconsistencies with mandated requirements, since the team must consider all possible
scenarios to develop a complete set of test cases. To complete this activity, the test
teams must develop both the Test Case Specification and the System Acceptance Test
Procedures.

7.1.4 Develop Version Description Document (IT Only)


The Version Description Document (VDD) is developed to describe the component
version to be released. It specifies equipment configurations and dependencies and
inventories materials released, including software contents, software installation files,
and software source files. VDDs must be updated through deployment to accurately
reflect the system configuration.

7.1.5 Develop Documentation


A variety of user documentation must be developed to assist those who operate,
maintain, and use the new system. It is expected that documentation will be updated
with a full description of the system components, end user information, and
troubleshooting information as the system progresses through the Development and
Integration & Test stages. Unless exceptions are granted, manuals should conform to
Section 508 requirements for accessibility. The following subsections define the
documents required to be produced.

7.1.5.1 Develop Operators Manuals


Documentation must be produced that describes the components of the system and
how the system is to work from the perspective of those who are to operate it.
Everything that is required to operate and support the operation of the system needs to
be provided in the operator’s manual, including a full description of the system
components, the expectations for system operation, system functionality, and
operational trouble shooting.

7.1.5.2 Develop Maintenance Manuals


The Maintenance Manual describes the components of the system and the practices
required to keep the system functioning. Performance monitoring, periodic testing of
facilities and system functionality, and periodic maintenance activities to ensure the
system functions as expected are included in the manual. Trouble shooting guides and
other help content are also included.

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-57


11-05-08
7.1.5.3 Develop User Manuals
User Manuals describe how the end users – those for whom the system was developed
– are to interact with the system in order to receive the benefits it provides. Information
describing the functionality that the system provides and how to access it is included in
the user manual. User scenarios that depict common interactions are often provided, as
are instructions for help desk access, guidance for general troubleshooting from the
user’s perspective, and where to go for training.

7.2 Documents
The project team records the results of its efforts in Stage 4, Development in a set of
documents, presented in Table 7-1. Documents must be traceable to the project WBS.
All documents should be placed under CM control. For a full listing of the documents,
including other items that get updated during the Development stage, see Attachment
B-5 of this document.

Table 7-1: Development Stage Documents


ARP Phases
PRODUCE/
ANALYZE/ DEPLOY/
NEED SELECT OBTAIN SUPPORT

Governing SELC Stages


PRODUCT Authority

Implementation
Requirements

Development

Operations &
Integration &

Maintenance
Engineering

Disposition
Definition
Planning
Solution

Design

Test
Training Materials DHS SELC C/F
Test Case Specification DHS SELC C/F
System Acceptance Test Procedures DHS SELC C/F
Test Readiness Review Approval Letter DHS SELC C/F

7.3 Test Readiness Review and Exit Criteria


The Project Manager and the project sponsor conduct the Test Readiness Review
(TRR) at the end of the Development stage in order to review the results of the stage
and to ensure that all exit criteria have been met. Unit testing should be complete for all
configuration items, test cases should all be approved, and the test environment should
be ready to use. The TRR includes the participation of the approval authority, who
confirms that all exit criteria have been satisfied by signing the TRR Approval Letter to
indicate the project can proceed to the Integration and Test Stage. It is expected that
the approval authority will rely on the appropriate experts (e.g., EA, testing, security,
budget) to evaluate the readiness of each project to proceed. The TRR Approval Letter
is countersigned by the Project Manager. A scanned electronic copy of the signed stage
review approval letter, along with the updated project management plan (and
associated project schedule), must be emailed to the DHS Periodic Reporting team at
Periodic.Reporting@dhs.gov. If it is determined that all exit criteria have not been
satisfied, another TRR with appropriate sign-offs shall be conducted.

B-58 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
7.4 Exit Criteria
Table 7-2 lists the exit criteria for the Development stage.

Table 7-2: Development Stage Exit Criteria


Domain Exit Criteria
Program Management • Have the risks been reviewed and are they deemed acceptable to move to the next
stage?
• Is the project on schedule or have remediation plans been developed to correct for
schedule loss?
• Have all products defined in the approved Project Tailoring Plan have been
completed and reviewed for completeness?
• Have all Action Items from the CDR been resolved?
• Has the independent test team been identified and is it prepared to begin testing?
• Have all documents from previous stages been updated as necessary to reflect new
information and decisions from the current stage?
• Has the Cost Benefit Analysis been updated to incorporate the built-out System
Design?
Information Security • Have all security controls been unit tested?
Privacy • Have all obligations and limitations identified in the privacy compliance
documentation been met?
Performance • Has the model/simulation of the developed system been calibrated using the results
of unit/development performance tests?
Data Management • Have all changes to the Data Architecture design been recorded in the
corresponding documents?.
Configuration • Is all development code under CM control?
Management • Are all COTS product configurations under CM control?
Testing • Do the test cases (integration and acceptance) appropriately test all the
requirements?
• Are all the planned test scenarios traceable to the requirements?
• Have all development test issues been resolved?
• Has the test team lead (integration and acceptance) reviewed the code summary
metrics and deemed the system ready for testing?
• Have the integration and acceptance test schedules been approved by the
appropriate test leads?
• Do unit test results for components, subsystems, and systems form a satisfactory
basis for proceeding into integration and acceptance testing?
• Has the test plan been reviewed and does it provide an actionable plan that
completely validates that the system satisfies all the requirements?
• Have test cases for testing Section 508 technical standards and functional
performance requirements been developed?
Software Engineering • Has the software been documented sufficiently so that a different contracting team
could understand the coding?
• If applicable, have independent code reviews been passed successfully?
Infrastructure • Is the test environment (integration and acceptance) ready for use?
• Have upgrades to existing equipment (e.g., routers, servers, mainframes, network
circuits) been contracted for?
Operations and • Have all user, operator, and maintenance manuals and procedures been developed?
Maintenance • Has the final Disaster Recovery Plan been developed?
Transition • Have a Training Plan and all training manuals been developed and documented?

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-59


11-05-08
8. Stage 5: Integration and Test
The purpose of the Integration and Test Stage is to demonstrate, through testing, that
the solution developed satisfies all defined requirements and to complete the integration
of configuration items that have been readied during the Development stage. For
complex systems, the Integration and Test Stage may involve a plan to integrate
configuration items incrementally rather than all at once, allowing a staggered
development and/or deployment schedule. Projects are encouraged to use automated
testing tools, if appropriate. When complete, Stage 5 results in a fully integrated and
qualified system, to the extent that it can be verified in an Integration and Test
environment that simulates the characteristics of the target operating environment.

8.1 Integration and Test Activities


The recommended activities associated with Integration and Test include the verification
of user documentation (operators, maintenance, and user manuals), developing and
conducting Systems Testing along with the resultant reports, conducting Acceptance
Testing, generating Section 508 Assistive Technology Interoperability Test Results,
conducting Security Testing and Evaluation, preparing the Security Accreditation
Documentation, completing a PIA, and completing a System of Records Notice, if
needed. The following subsections present the details of these activities. The set of
activities actually performed for a given project in the Integration and Test Stage may
differ depending upon the approved Project Tailoring Plan.

8.1.1 Conduct System Testing and Generate Test Reports


System testing is conducted to evaluate how well the developed system satisfies the
defined and approved requirements. Components (e.g., hardware, software,
communications) are assembled, or simulated, to provide a test bed in which to validate
requirements. The system is tested to ensure that the integrated functionality delivered
meets defined mission needs. To ensure that the system is appropriately tested for
Section 508 Accessibility, the test team must also include users with disabilities or those
with the knowledge, tools, and skills necessary to emulate users with disabilities. All
tests, results, and follow up must be analyzed and documented in the System Test
Report. Failed components are migrated back to the Development stage for
rework/retest; components that pass migrated ahead for implementation. System testing
cannot be conducted by the development organization. This does not mean that the
same contractor cannot conduct the testing, but to minimize any conflict of interest, the
test organization must report directly to the PM and personnel cannot be shared
between the development organization and the test organization.
Tests conducted must address the following:
• Functional capability
• Integration of all system components
• Performance
• Security

B-60 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
• Interoperability with external components, including legacy systems
• Section 508 Accessibility
• Data conversion/loading
• Installation process
• Operational procedures
• Backup/recovery
• Disaster recovery/fail-over
To enable effective defect analysis and improvements in system design and
development, testing activities must include the collection, documentation, and reporting
of defect data. The following required characteristics of defects must be documented,
tracked, and used in test reporting.
• Defect number
• Defect description
• Date defect detected/opened
• Date defect fixed/closed
• Defect severity
• Defect priority
• Defect status
• Name of tester who detected the defect
• Name of developer assigned to correct the defect

8.1.2 Verify and Validate User Documentation


The content of the user and Operations and Maintenance manuals must be verified
against the system to be delivered. In addition, this user documentation must be
validated by a representative group of end users to ensure that the level of detail will
meet the needs of the end user community.

8.1.3 Conduct Acceptance Testing


A representative group of end users is identified to test the system in order to ensure that
the functionality delivered meets defined mission needs. The test should be conducted
by the government; test scenarios should allow for scripted and unscripted tests that
include evaluation of system documentation (e.g., user manuals, operator manuals). The
PM and Test Lead work with customers to choose a final test option and to receive
approval. Approval documentation should be kept with the Test Plan. Results are
reviewed by the PM and documented in the Acceptance Test Report.

8.1.4 Generate Section 508 Assistive Technology Interoperability Test Results


(As Applicable)
Requirements set forth in 29 U.S.C. Section 508, as amended by P.L. 105-220, August
1998, include standards that define the types of technology covered. It also provides for
standards for the minimum level of accessibility for electronic and information

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-61


11-05-08
technologies in the federal sector, including those used for communication, duplication,
computing, storage, presentation, control, transport, and production. 10 Section 508
Accessibility requirements define functional performance criteria to ensure sure that the
individual assistive technology components defined as part of a DHS solution are
interoperable and can be used to create an accessible product. Tests must be
performed and test reports generated to prove that Section 508 Accessibility
requirements for assistive technology interoperability are met by the system. These test
results must be documented in a Section 508 Assistive Technology Interoperability Test
Report. For more information on assistive technology interoperability, contact the DHS
OAST.

8.1.5 Conduct Security Test and Evaluation (IT Only)


Results of the ST&E and the Contingency Plan tests are documented in the SAR.
Additional information on the ST&E and SAR activities is provided in the Department of
Homeland Security Certification and Accreditation Guidance for SBU Systems User’s
Manual. In addition, POA&Ms must be created for any weakness that is to be mitigated
as part of the C&A process. Weaknesses that will be accepted and not mitigated are
documented in the final SAR and agreed to by the Designated Accrediting Authority
(DAA) prior to operation. POA&Ms focus on managing on-going corrective actions. 11

8.1.6 Prepare Security Certification Documentation (IT Only)


With the successful completion of the S&TE (Certification phase), the security
accreditation package is assembled and submitted to the DAA for certification signature.
The minimum acceptable accreditation package contains the following documents:
• SSP
• SAR
• POA&M
• Certifying Official Transmittal Letter
Supplemental information can be provided as requested by the DAA or Certifying
Official. This supplemental information can include items such as the Contingency Plan,
final RA, CM plan, standard operating procedures, CONOPS, and other documents.

8.1.7 Complete Privacy Impact Assessment (IT Only)


Prior to the completion of the Integration and Test stage, the PIA must be completed
and approved by the Privacy Office.

10
Summary of Section 508 Standards, General (Sub-Part A), www.section508.gov.
11
For detailed directions or guidance on the DHS POA&M process, consult the DHS 4300A Sensitive Systems
Handbook, Attachment H -- POA&M Process Guide.

B-62 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
8.1.8 Complete System of Records Notice (IT Only)
Prior to the completion of the Integration and Test stage, the SORN must be completed
and approved by the Privacy Office. See Section 6.1.10 for more information on the
SORN.

8.1.9 Complete Insertion Packages (IT Only)


The SIP consists of all the information that must be submitted by the Submitter to the
EAB for a decision to update the HLS EA SRM in order for Components to formally
state a need for an enterprise (inter-Component or inter-Agency) service or to deploy a
service on an enterprise basis. For acquisitions that are using services, the project team
must provide the appropriate supporting documentation to assist the decision process.
The SIP form has been arranged into three sections that correspond to key stages in
the process flow for the SIP review process. See the DHS EA Process Guide for more
information on SIP requirements.
The Data Insertion Package consists of the Data Asset collection worksheet,
information sharing agreements, and Information Exchange Packages. The complete
package is required for EA COE and EDMO approval and must be submitted for
registration. Updates to the Data Insertion Package by Components are key to an
effective DHS DRM and improved information sharing opportunities.
8.1.10 Operational Testing
Normally programs and projects enter formal Operational Testing (OT) and Evaluation
(OT&E) in this phase prior to production and deployment. OT is governed by Appendix
L: Test and Evaluation Master Plan (TEMP) of the Instruction/Guidebook 102-01-001.

8.2 Documents
The project team records the results of their efforts in Stage 5, Integration and Test in a
set of documents identified in Table 8-1. Documents must be traceable to the project
WBS. All documents should be placed under CM control. For a full listing of the
documents, including other items that get updated during the Integration and Test
stage, see Attachment B-5.

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-63


11-05-08
Table 8-1: Integration and Test Documents
ARP Phases
PRODUCE/
ANALYZE/ DEPLOY/
NEED SELECT OBTAIN SUPPORT
Governing SELC Stages
PRODUCT Authority

Implementation
Requirements

Development

Operations &
Integration &

Maintenance
Engineering

Disposition
Definition
Planning
Solution

Design

Test
Operators Manuals DHS SELC C F
Maintenance Manuals DHS SELC C F
User Manuals DHS SELC C F
System Test Report DHS SELC C/F
Acceptance Test Report DHS SELC C/F
Section 508 Assistive Technology Interoperability
Test Report DHS OAST C/F
Service Insertion Package (SIP) DHS EA Process C U F F
Security Assessment Report (SAR) DHS CISO C/F
Security Accreditation package DHS CISO C/F
Privacy Impact Assessment (PIA) Privacy Office C/F
DHS Periodic Reporting CPIC C U U U
Production Readiness Review Approval Letter DHS SELC C/F

8.3 Production Readiness Review and Exit Criteria


The project sponsor and the PM must conduct the PRR to review the results of the
Integration and Test Stage to validate that the system developed meets the defined
requirements, to evaluate the exit criteria to ensure that all exit criteria have been met,
and to assess system readiness for the move to production. The PRR includes the
participation of the approval authority, who confirms that all exit criteria are satisfied by
signing the PRR Approval Letter to indicate the project can proceed to the
Implementation stage. It is expected that the approval authority will rely on the
appropriate experts (e.g., EA, testing, security, budget) to evaluate the readiness of
each project to proceed. The PRR Approval Letter is countersigned by the PM. A
scanned electronic copy of the signed stage review approval letter, along with the
updated project management plan (and associated project schedule), must be emailed
to the DHS Periodic Reporting team at Periodic.Reporting@dhs.gov. Should the project
not gain PRR approval, the issues must be addressed and another PRR with
appropriate sign-offs must be conducted.

8.3.1 Exit Criteria


Table 8-2 lists the exit criteria for the Integration and Test stage.

B-64 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
Table 8-2: Integration and Test Exit Criteria
Domain Exit Criteria
Project Management • Have the risks been reviewed and are they deemed acceptable for moving
to the next stage?
• Is the project on schedule or have remediation plans been developed to
correct for schedule loss?
• Have all products defined in the approved Project Tailoring Plan been
completed and reviewed for completeness?
• Have all Action Items from the TRR been resolved?
• Have all documents from previous stages been updated as necessary to
reflect new information and decisions from the current stage?
Requirements • Has the system been user-tested by individuals with the knowledge, tools,
and ability to use assistive technologies commonly used by people with
disabilities and applicable to Section 508 requirements?
Information Security • Has the ST&E been completed?
• Has the Contingency Plan been tested?
• Has the SSP been updated?
• Has the SAR been completed?
• Have POA&Ms been completed as required?
• Has the Security Accreditation Package been assembled?
Privacy • If appropriate, has a SORN been published?
• Have all system functionalities been tested against requirements and
limitations in privacy compliance documentation?
Performance • Have all performance problems identified in system integration tests been
resolved and documented?
• Has a range of performance scenarios been tested, considering possible
peak workloads and competition for resources?
• Have all end-to-end performance tests been passed?
• Have all scalability issues been resolved?
Data Management • Has the data load been successfully tested?
• Has the Data Insertion Package been updated and submitted?
Configuration Management • Is the production system under CM control and ready to be pushed to the
production environment?
Testing • Have all integration tests been completed successfully?
• Did end users successfully complete acceptance testing?
• Does the test report identify the number of defects, their severity level, and
their expected resolution date?
• Do all defects have resolution plans?
• Have all defects, variations, problems, and known errors been recorded in
a defect repository?
• Is Section 508 acceptance testing complete?

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-65


11-05-08
Domain Exit Criteria
Enterprise Architecture • Has user acceptance testing identified any gaps in required capabilities?
• Will the system provide all of the business capability as planned?
• Are there gaps in business capability?
• Is the data required by this system already available or will it be made
available?
• Does the system include all components assigned to it for each release?
• Does the system include all technology assigned to it for each release?
• Is the EA Alignment Template complete through Section 5b?
• Are all changes required for EA Alignment Template completed for this
stage?
Software Engineering • Have all SLAs have been negotiated, agreed to, and signed by all parties?
Infrastructure • Do systems and facilities affected by the release have a current Authority
to Operate (ATO)?
• Has equipment installation been coordinated with site-specific personnel?
• Has the appropriate Help Desk been notified of impending changes?
• Have end user workstations been tested to ensure software
interoperability?
Operations and Maintenance • Have all user, operator, and maintenance manuals and procedures been
reviewed, tested, and accepted by the operations team?
• Have all operational and failover conditions been tested, if appropriate?
• Have all operations and batch processing schedules been defined in an
SLA?
Transition • Have all training manuals been reviewed and accepted by the operations
team?

9. Stage 6: Implementation
The objective of Stage 6, Implementation, is to prepare the system, operational
environment, organization, and users for the intended use of the new solution.
For information on Transition to Support and Training activities, see Appendix J:
Supportability and Sustainment, of the Instruction/Guidebook 102-01-001.

9.1 Implementation Activities


The activities associated with the Implementation stage include completing the
preparation of operational sites and deploying the solution to the production
environment; performing data extractions, transformations, and loads into production;
coordinating changes to business practices; conducting training; developing version
description documents; developing a transition-to-support document; finalizing the
identification of critical infrastructure assets; conducting pilots and/or parallel operations,
if required; publishing a SORN and acquiring Privacy Office affirmation; and obtaining
an ATO letter. The set of activities actually performed for a given project in the
Implementation stage may differ depending upon the approved Project Tailoring Plan.
The following represent the activities performed as part of the Implementation stage.

B-66 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
9.1.1 Conduct Pilot
A pilot is an initial release of a system, not a prototype or a separate project. A pilot is
developed using full SELC requirements, including those for HLS EA alignment, privacy,
security, and Section 508 Accessibility. Privacy compliance requirements do not
distinguish between the use of personally identifiable information in operations versus
its use in test activities or in pilots. Thus, in order for personally identifiable information
to be used as part of a pilot and/or as part of any parallel operations, the privacy
compliance documentation must be drafted and approved to accommodate for that
specific type of use. The privacy compliance documentation must be finalized,
approved, and published (as required) prior to the use of personally identifiable
information for testing and/or parallel operations. Compliance with all privacy
requirements is required prior to use.
Pilots are often used in parallel operation with the current system in order to provide the
opportunity to analyze pilot results through information reconciliation and data integrity
validation. Information and reports generated from the “old” system can be used as a
point of reference for the new system for analysis and results documentation. Pilot
results provide feedback on the implementation process, the "actual versus planned"
functional capability, and end-user acceptability. They can also enhance decision
making for current and future projects. More information on the use of pilots can be
found in the found in Appendix of the EA Governance Process Guide.

9.1.2 Complete Preparation of Operational Sites and Deploy Solution to


Production Environment
All stakeholders must be informed of implementation schedules and increases in
resource requirements prior to deployment. If any changes to the network and/or
systems environment have occurred since the initial design plan was submitted and
approved, the design and implementation plan should be modified to reflect those
changes. In addition, any interface and data conversion constraint(s) should be
documented, including recommended work-arounds and/or required modification to the
original plan. If the constraints will have a significant impact on resource requirements,
the revised plan should be submitted to the ARB for review and approval.
The operational sites must be prepared and all hardware must be installed. The CM
team should load the latest baseline version of the system to all hardware items and a
final regression test should be conducted to ensure that all capabilities are functioning
properly.

9.1.3 Perform Data Conversion and Load Production Data (IT Only)
Data may be extracted from legacy systems, converted or transformed, and uploaded
into the target system at multiple points within the development life cycle. Security and
privacy policies must be adhered to. It is also advisable that as each batch upload or
system interface procedure is completed, both data integrity and business function
testing procedures be applied. These procedures may include running parallel
operations testing, reconciliations, or combinations of both. Depending upon the size
and complexity of legacy data, converting legacy data and loading them to a production

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-67


11-05-08
environment may take considerable time and may need to be started before the
Implementation stage.

9.1.4 Coordinate Changes to Corresponding Business Practices


Organizational change management is primarily the responsibility of the project sponsor
and end users, but the project team must identify (or recommend) the business process
changes required to help the system and its users operate efficiently. Business practice
changes are often included in the functional business requirements, CONOPS, and/or
BIA as well as in the user training documentation developed in previous stages. This
coordination activity should be scheduled in concert with training and deployment
activities. Effective management requires that follow up evaluations be performed in
order to ensure that the business process changes are meeting the mission needs as
planned.

9.1.5 Publish System of Records Notice and Acquire Privacy Office Affirmation
(IT Only)
A SORN is a publicly published document that describes a certain type of data
collection and how that data is used. A “system of records” is a group of any records
under the control of any agency from which information is retrieved by the name of the
individual or by some identifying number, symbol, or other identifier assigned to the
individual. The Privacy Act requires each agency to publish notice of its systems of
records in the Federal Register. Prior to implementation, the project must receive an
affirmative statement from the DHS Privacy Office that all privacy compliance
requirements are met.
For more information on DHS privacy compliance requirements, contact the Privacy
Office, U.S. Department of Homeland Security, Washington, DC 20528, available via
email PIA@dhs.gov. Examples of PIAs and SORNs, as well as additional educational
materials related to compliance, are available on the DHS Privacy Office website:
www.dhs.gov/privacy.

9.1.6 Obtain Authority to Operate Letter (IT Only)


Once security testing is completed and final measures employed, an accreditation
package is prepared for obtaining approval to operate from a DAA. In order to operate
(and possibly pilot) a DHS system, an ATO letter must be signed by the DAA, finalizing
the accreditation process.

9.2 Documents
The project team records the results of its efforts in Stage 6, Implementation in a set of
documents that is presented in the Implementation Stage Document summary, shown
in Table 9-1. Documents must be traceable to the project WBS. All documents should
be placed under CM control. For a full listing of the documents, including other items
that get updated during the Implementation stage, see Attachment B-5.

B-68 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
Table 9-1: Implementation Stage Documents
ARP Phases
PRODUCE/
ANALYZE/ DEPLOY/
NEED SELECT OBTAIN SUPPORT

Governing SELC Stages


PRODUCT Authority

Implementation
Requirements

Development

Operations &
Integration &

Maintenance
Engineering

Disposition
Definition
Planning
Solution

Design

Test
Pilot Results Report ARP (DIR 102-01) C/F
Follow on Test Results ARP (DIR 102-01) C/F
Version Description Document DHS SELC C/F
Critical Infrastructure Protection Report CIP C/F
System of Record Notice (SORN) DHS Privacy C/F
Authority To Operate (ATO) Letter DHS CISO C/F
Operational Readiness Review Approval Letter DHS SELC C/F

9.3 Operational Readiness Review and Exit Criteria


An Operational Readiness Review (ORR) is conducted at the conclusion of the
Implementation Stage to review the results of the stage and to evaluate whether the
system, as implemented, continues to meet mission need and is ready to be moved into
production. The ORR requires the participation of the approval authority, who confirms
that all exit criteria have been satisfied by signing the ORR Approval Letter to indicate
the project can proceed to the Operations and Maintenance stage. It is expected that
the approval authority will rely on the appropriate experts (e.g., EA, testing, security,
budget) to evaluate the readiness of each project to proceed. The Project Manager
countersigns the ORR Approval Letter. A scanned electronic copy of the signed stage
review approval letter, along with the updated project management plan (and
associated project schedule), must be emailed to the DHS Periodic Reporting team at
Periodic.Reporting@dhs.gov. Should the project not gain ORR approval, the issues
must be addressed and another ORR with appropriate sign-offs be conducted.

9.3.1 Exit Criteria


The exit criteria for the Implementation stage are listed in Table 9-2

Table 9-2: Implementation Exit Criteria


Domain Exit Criteria
Program Management • Have the risks been reviewed and are they deemed acceptable to move to the
next stage?
• Is the project on schedule or have remediation plans been developed to correct for
schedule loss?
• Have all products defined in the approved Project Tailoring Plan been completed
and reviewed for completeness?
• Have all Action Items from the PRR been resolved?
• Have all documents from previous stages been updated as necessary to reflect
new information and decisions from the current stage?

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-69


11-05-08
Domain Exit Criteria
Information Security • Has the C&A package been signed by the DAA?
• Have all users, administrators, and operators successfully completed security
awareness training?
• Has the ATO Letter been signed by the DAA?
Performance • Have all performance problems identified in the production environment tests
been resolved?
• Has the model/simulation of the system been archived for possible future use
during operations?
Data Management • Have all data been loaded into the system and are they ready for use?
• Are all external data sources ready and available for the deployment of this
system?
Configuration • Has this system been properly placed under CM control?
Management • Does a CCB exist to evaluate and approve proposed changes to the system
baseline?
Testing • Have all production environment tests been completed satisfactorily?
• Are all continuity and recovery processes and procedures complete and tested?
Enterprise Architecture • When deployed, will the system provide all of the business capability as originally
planned?
• Have any new business capabilities been identified?
• Has user acceptance testing identified any gaps in required capabilities?
• Is it known who will be utilizing the data created by this system?
• Are the requisite Information Sharing Agreements in place?
• Are the application components being deployed as planned?
• Is the technology interoperable with the infrastructure?
• Is the technology being deployed still in alignment with the DHS TRM?
• Are all changes required for EA Alignment Template completed for this stage?
Software Engineering • Have all created services been added to the DHS Service Catalogue and
submitted to the EA PMO for registry in the service component reference model?
• Are all the availability calculations (algorithms) agreed upon and documented in
an SLA?
Infrastructure • Is the production environment ready for use?
• Can this system/enhancement be deployed into the production environment given
the current threat level or security posture (e.g., system lock-down)?
Operations and • Are all O&M staff ready to begin operations?
Maintenance • Is all scheduled downtime documented in a SLA and agreed-upon by all affected
stakeholders?
Transition • Have all users, operators, and maintenance personnel been adequately trained on
the new system?

10. Stage 7: Operations and Maintenance


The objective of Stage 7, Operations and Maintenance (O&M) is to operate the system,
make minor enhancements to the system, and conduct periodic reviews (e.g., security).
O&M personnel must monitor the current system, identify problems to be fixed, and
identify ways to improve the system.

B-70 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
10.1 Operations and Maintenance Activities
The following subsections represent the typical activities performed in the O&M stage.

10.1.1 Operate System and System Documentation


Regular maintenance (e.g., backup, archival) schedules must be documented and
adhered to in order to ensure optimum system/asset performance. Baseline
documentation (i.e., Mission Need Statement, Business Case, Security Certifications, IT
Contingency Plan, SSP, CM Plan, Incident Response Plan, Risk Assessment, POA&M,
PIA, and Section 508 Accessibility Plan) should be regularly maintained and updated,
as appropriate.

10.1.2 Identify and Make System Enhancements


Users, customers, and maintenance personnel identify modifications to the system
needed to resolve issues, enhance system performance, or provide new capabilities.
New capabilities may take the form of routine maintenance or constitute enhancements
to the system in response to user requests for new or improved capabilities. All system
changes shall be reviewed and approved by the system’s Configuration Control Board
before implementation in accordance with the system’s CM Plan. Any changes to the
system baseline must be made within the CM system and pushed into production,
according to the system’s CM Plan.
IT Only: While minor enhancements and modifications are expected during O&M,
major enhancements to a system in O&M must be treated as new IT projects and
comply with the full life cycle requirements of the SELC.
Major enhancements are any combined changes that exceed $2.5 million in cost
from planning through deployment (excluding O&M costs) unless exempted by
the Component CIO.

10.1.3 Test Disaster Recovery


Disaster recovery plans are tested during this phase. To the extent possible, all testing
should be accomplished by simulating actual conditions. Problems identified during
testing, along with optimum solutions, should be discussed and disseminated to
appropriate parties as lessons learned. Disaster recovery testing should be performed
at regular, periodic intervals in order to create and maintain a sense of awareness and
preparedness among personnel. System documentation and procedures should be
updated to reflect any corrections made to deficiencies identified during these
exercises.

10.1.4 Document Post Implementation Review Results


Within six months of deployment, the PIR should be conducted. The PIR should
document deployment/implementation and coordination issues, how they were
resolved, and how they could be prevented in future releases The results of the PIR are
documented in the PIR Results Report, which describes how the newly implemented
solution meets business requirements. The PIR focuses on three areas:

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-71


11-05-08
• Impact to stakeholders and customers
• Delivery of expected capability
• Achievement of baseline goals
The PIR is to be conducted six months after the solution is deployed, with the exception
of projects that have been cancelled. Cancelled project are to conduct a PIR
immediately.
For more information on the PIR and PIR Results Report, see the DHS CPIC Guide.

10.1.5 Conduct Operational Analyses


Operational analysis is the method to use to measure the performance and cost of an
established project in the O&M phase against baselines as defined in DHS Operational
Analysis Guidance. The objective is to measure project achievement in meeting cost,
schedule, and performance goals. Major investments that are in the steady state or
O&M phase are required to use Operational Analysis as the performance-measurement
process to measure the performance and cost of those assets against the established
baseline. Operational analyses should be conducted annually or tailored to the nature of
the asset. For more information on Operational Analysis, refer to the DHS Operational
Analysis Guidance.

10.1.6 Develop Lessons Learned Report


The Lessons Learned Report defines opportunities for improving enterprise processes
based on the experience of the acquisition team and other stakeholders during the life
cycle of the acquisition. The content for the Lessons Learned Report comes from PIR
findings, from various reviews held, or from the conduct of required activities during the
project life cycle. The objective is to make lessons learned from DHS acquisitions
available throughout the Department in order to increase the probability of success for
future acquisitions through the improvement of processes, tools, and other project-
related entities. For more information on lessons learned, refer to the DHS CPIC Guide.

10.1.7 Perform Continuous Monitoring (IT Only)


Security activities conducted during the O&M stage include security administration,
oversight and monitoring of the security controls on an ongoing basis, and informing the
DAA when changes that may impact the security of the system occur. Security
monitoring, security update, and security incident reporting activities, among others, are
presented in Table 10-1.

B-72 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
Table 10-1. O&M Security Monitoring, Security Updates, and Security Reporting

Activity Description
Security Operations and • Perform backups
Administration • Hold annual security awareness classes for all users
• Maintain current user administration and access privileges
• Hold specialized security training for security personnel
• Update security software
Configuration Management • Use DHS CM and control procedures to document proposed or actual changes
and Control to the system (including hardware, software, firmware, and surrounding
environment)
• Analyze changes to determine their security impact
Ongoing Security Control • Identify potential security-related problems in the system not identified through
Verification the security impact analysis conducted during the CM task
• Select an appropriate set of security controls and evaluate the effectiveness of
the controls through security reviews, self-assessments, security testing and
evaluation, vulnerability assessments, or security audits (selection to made by
Information Security System Engineer and project sponsor)
SSP Maintenance and • Update the SSP as changes occur (annually, at a minimum) to reflect the most
Security Incident Reports recent changes to the system and any identified or potential security impacts
• Report proposed or actual changes and identified or potential security impacts to
the authorizing official or designated representative
• Use information from status reports to determine the need for security re-
accreditation
C&A Maintenance • Validate that existing documentation meets requirements for a signed ATO letter
(operational systems must have a signed ATO letter that is good for 3 years or is
issued when a major change occurs to the system or the system environment)
• Validate that C&A documentation (defined in the Department of Homeland
Security Certification and Accreditation Guidance for SBU Systems User’s
Manual) is current and is uploaded to the CISO-approved FISMA reporting tool
NIST SP 800-53 Controls • Perform annual tests of NIST SP 800-53 controls using NIST SP 800-53A tests
Test
POA&M Updates • Develop corrective action plans for newly identified weaknesses
• Provide monthly status updates for previously identified weaknesses
Contingency Plan • Update the Contingency Plan as changes occur (annually, at a minimum)
• Perform annual tests of the Contingency Plan
Monthly Updates for • Perform monthly updates of IT system data included in the CISO-approved
Security Reports FISMA reporting tool to facilitate 1) Information Security Scorecard development,
2) quarterly FISMA report development, 3) annual FISMA report development

10.1.8 Develop Section 508 Accessibility Incident Remediation Report (IT Only)
The Accessibility Incident Remediation Report (29 U.S.C. Section 508) documents all
end-user problems with Section 508 Accessibility and describes the changes made to
remediate the problem(s). The report is included in project documentation with the
Section 508 Accessibility Plan; a copy is to be provided to DHS OAST. For more
information on the Section 508 Accessibility Incident Remediation Report, refer to DHS
OAST.

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-73


11-05-08
10.2 Documents
The project team records the evidence of its work in the set of documents listed in the
project’s tailoring plan. The determination of applicable items for a project is made
based on the approved tailoring plan for the project. For a full listing of the documents,
including others that get updated during the O&M stage, see Attachment B-5.

Table 10-2: O&M Documents


ARP Phases
PRODUCE/
ANALYZE/ DEPLOY/
NEED SELECT OBTAIN SUPPORT

Governing SELC Stages


PRODUCT Authority

Implementation
Requirements

Development

Operations &
Integration &

Maintenance
Engineering

Disposition
Definition
Planning
Solution

Design

Test
Performance Reports ARP (DIR 102-01) U
Post Implementation Review (PIR) Results CPIC U
DHS Periodic Reporting CPIC U U
Operational Analyses CPIC U
Lessons Learned CPIC U
FISMA metrics reports DHS CISO U
Security Incident reports DHS CISO U
C&A Updates (every 3 years or when major change
is made) DHS CISO U
Privacy Documentation (updated for systems
decommissioned) Privacy Office U

11. Stage 8: Disposition


Disposition is the act of eliminating all or parts of a system to include IT (e.g., shutting
down databases) and non-IT (e.g., decommissioning helicopters). The emphasis in
Disposition is to ensure that the system (or parts of the system), data, procedures, and
documentation are packaged and archived in an orderly fashion, making it possible to
reinstall and bring the system back to an operational status if necessary, and to retain
all data records in accordance with DHS and Federal policies regarding retention of
electronic records. A Disposition Plan is required to address all facets of archiving,
transferring, and disposing of all or a part of a system and its corresponding data. For IT
systems, particular emphasis is given to proper preservation of the data processed by
the system so that they are effectively migrated to another system or archived in
accordance with applicable records management regulations and policies for potential
future access. (Refer to Attachment B-2, Section B2.14, for more information on
Electronic Records Management.) For example, a common error is to dispose of legacy
tape drives without testing to verify that newer technology can read the data from the
legacy tapes or planning and maintaining an extract, transform, and load capability to
convert legacy data into a format usable by the new system.

11.1 Disposition Activities


Refer to Appendix J for a detailed discussion of Disposition Phase Activities.

B-74 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
11.2 Documents
The project team records the evidence of its work in the set of documents listed in the
project tailoring plan. The determination of applicable documents for a project is made
based on the approved tailoring plan for the project. For a full listing of the documents,
including other items that get updated during the Disposition stage, see Attachment B-5.

Table 11-1: Disposition Documents

ARP Phases
PRODUCE/
ANALYZE/ DEPLOY/
NEED SELECT OBTAIN SUPPORT
Governing SELC Stages
PRODUCT Authority

Implementation
Requirements

Development

Operations &
Integration &

Maintenance
Engineering

Disposition
Definition
Planning
Solution

Design

Test
Disposition Approval Request DHS SELC C/F
Archived Data DHS SELC C/F
Archived System DHS SELC C/F

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-75


11-05-08
Sample Template and Guidance

Attachment B-1
Systems Engineering Life Cycle
Development Methodologies
This attachment provides additional information on the DHS SELC system development methodologies
discussed in Section 2. The methodologies described are Spiral, Iterative/ Incremental, and Waterfall. Each
of the following sections discusses the advantages and disadvantages of each methodology and the
applications for which each is most suitable.

B1.1 Spiral Development Methodology


The Spiral methodology is a risk reduction-oriented development methodology that breaks a project into
multiple sequential cycles for development. It was conceived through recognition that projects are risky
and need an approach to better manage fluctuations in project direction. Each cycle sequentially
addresses one or more major risks of the project until all major risks have been addressed. Poorly
understood requirements, unfamiliar technology, changes in mission, and potential performance concerns
are examples of project risk.
Figure B1-1 depicts the Spiral methodology. The approach is to start the project on a small scale (shown
at the center of the spiral), identify a major risk facing the project, explore the risk with a prototype, refine
requirements and design based on the success of the prototype, and commit to an approach for the next
risk(s) in the sequence. Each cycle of the spiral leads the project team to a better understanding of
mission needs, user needs, technology limitations, and performance considerations. All SELC stages are
executed and most are executed multiple times. The same is true for the SELC stage reviews – all are
held and some may be held more than once.

nts
me
u ire Pla
q
Re nn
nal ing
n ctio n ts
F u me Pla
q uire nn
ing
a l Re ent
s
Pla
ion irem
ct equ nn
Fun ctional R
ess R
eq. PPR ing
Fun Busin Pl
an
ents Pl ni
irem an ng
Requ
q.

ni
Re

ng
s
es
l
na

in
io

Spiral
us
ct

B
n
Fu

SDR
Development
Model
Sy Req

Sy Req
Sy Req

Sy
st . D
S y Re q

st .

e
em

st as
st .

em

em
sC ns
st .

em

tio
Pr s i g

es ra s
em

on
e li n

Con
Pr si

in pe ati
m

s
De

cep
el gn

u O
.

P
Coroof
t B of er
im

t p
ns
De

De nc o f ep O
ep nc of tio
si

mo t
Co pt ra
gn

Pro ns Test ce
De

PDR tot trat


on
e
yp ion Op
si

ing C
De of
gn

Un velo User R
eview pt
i tTp
CDR est n ce
D Co
Un evelo TRR Integra
ti
it T p & Teston
est
Integ
ra t
TRR & Tes ion Acceptance
t Disposition
Testing Implementation O&M
PRR ORR PIR

Figure B1-1. Spiral Methodology

The strengths of the Spiral methodology are that 1) not all requirements need to be well understood at the
beginning of the project and 2) there is a heightened focus on risk reduction. Risk is accounted for early in
the project life cycle, before large-scale development activity has begun, through the use of prototypes.

B-76 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
Sample Template and Guidance

The methodology provides frequent checkpoints for risk mitigation and management oversight. If the risk
of a given cycle proves insurmountable, an alternative solution can be explored.
The assessment of the Spiral development methodology presented in Table B1-1 is adapted from the
Department of the Air Force, Guidelines for Successful Acquisition and Management (GSAM) Condensed
Version (February 2003).

Table B1-1: Spiral Methodology: Advantages vs. Disadvantages


Spiral Methodology
Advantages Disadvantages Application
• Provides better risk management • More complex and harder to The Spiral method should be
than other methodologies manage considered for projects where risks
• Requirements are better defined • Usually increases development are high, requirements must be
refined, and user needs are
• System is more responsive to user costs and schedule
important.
needs

B1.2 Iterative/Incremental Methodology


Iterative and Incremental methodologies are similar enough to be described in a single section of this
SELC Guide. Unlike the Spiral methodology, where a single project cycles through sequential iterations of
the SELC stages starting with a small group of allocated requirements and building greater
understanding/functionality and an increased number of requirements with each spiral, the Iterative and
Incremental methodologies work with segmented requirements and multiple sub-projects and process
them concurrently through the remaining stages of the SELC.
To initiate Iterative/Incremental development, a project team divides the project into smaller sub-projects
that develop a functional component or build of a system. Project requirements are allocated to each
functional sub-project. Each sub-project is then independently and concurrently managed to completion. It
is similar to the Waterfall methodology, to be described in the next section, in that each stage must be
completed before the subsequent stage can begin.
In the Iterative methodology, depicted in the diagram in Figure B1-2, each sub-project cycles through the
requirements, design, develop, and integration and test stages several times, each iteration building upon
the previous one. After all cycles are completed, the production system is implemented in the production
environment.

DHS SLC
FQT
Integration
(Dev
FQT
Integration
Test)
(Dev
FQT Test)
Integration
(Dev Test) Develop
Develop
Development
Develop
& Test& Test
& Test

Approved Implementation Operations &


Disposition
Project Support

DesignDesignDesign
Requirements
Requirements
Requirements
Planning
Planning
Planning
Requirements
Planning

Figure B1-2. Iterative Methodology

The Incremental methodology, by contrast, allocates requirements among multiple sub-projects


(increments) but cycles only once through design, development, test, and implementation, as depicted in

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-77


11-05-08
Sample Template and Guidance

the diagram in Figure B1-3. The key distinction is that each sub-project (increment) is deployed into
production as it is completed.

DHS SLC
Integration Operations &
Planning/ Design Development Implementation Disposition
& Test Support
Requirements

Approved Integration Operations &


Planning/ Design Development Implementation
Project & Test Support Disposition
Requirements

Planning/ Integration Implementation Operations &


Design Development & Test Disposition
Requirements Support

Figure B1-3. Incremental Methodology

The fundamental similarity between the Iterative and Incremental methodologies is that both require a
good understanding of the requirements at the beginning of the project. The Iterative and Incremental
methodologies are best suited to those projects with a well-defined and stable scope that need the
flexibility to divide the project into multiple parallel efforts.
Table B1-2 presents the advantages and disadvantages of Iterative/Incremental methodologies and is
adapted from the Department of the Air Force, GSAM Condensed Version (February, 2003).

B-78 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
Sample Template and Guidance

Table B1-2: Iterative/Incremental Methodology


Iterative/Incremental Methodology
Advantages Disadvantages Application
• Provides feedback, allowing later • Majority of requirements must be Good for projects:
development cycles to learn from known at beginning • Needing early delivery of
previous • Formal reviews are more complex functionality
• Allows some requirements for incremental releases as • With stable requirements at the
modification; may allow addition of opposed to single development beginning
requirements effort
• That benefit from feedback of
• Usable product is available with • Interfaces must be well-defined at earlier cycles
first release; each cycle delivers outset due to development over
functionality multiple iterations • With funding uncertainties, as
each cycle produces a working
• Project can be stopped any time • Cost and schedule overruns may system
after the first cycle and delivers a result in an unfinished system
• With low to medium levels of
working product • More frequent impact to risk
• Risk is spread over multiple cycles operations with multiple releases
• Project Management is easier for
incremental projects

B1.3 Waterfall Methodology


The Waterfall methodology is a highly structured development process and the one most commonly used.
It is referred to as Waterfall because the stages cascade from one to the next with limited, if any,
opportunity to revisit a completed stage. In the Waterfall methodology, stakeholders “sign-off” at each
stage, agreeing that the documentation is sufficient to move to the next stage of development.
Figure B1-4 depicts the Waterfall methodology and its traditional cascading of stages.
Approved
Project

PPR
PLANNING

REQUIREMENTS SDR
DEFINITION
PDR
DESIGN CDR

DEVELOPMENT TRR

INTEGRATION PRR
& TEST

IMPLEMENTATION ORR

OPERATIONS
& SUPPORT PIR

DISPOSITION

Figure B1-4. Waterfall Methodology

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-79


11-05-08
Sample Template and Guidance

The Waterfall methodology is documentation-intensive because early stages document the capability that
must be achieved and subsequent stages provide greater granularity to requirements already defined,
then define how the required capability will be achieved. The output from one stage serves as the input to
the next stage, with the project flowing from one step to the next in a cascading fashion. Stages are
typically sequential, with only localized feedback during the transition between stages. Comprehensive
reviews validate the work of one stage and require the resolution of any problems before development is
allowed to proceed to the next stage.
An important consideration for selection of the Waterfall methodology is that fixes or modifications are
often put off until the maintenance stage (after implementation). This can be costly, as the cost of error
correction is magnified in later stages. The advantages and disadvantages presented in Table B1-3 are
adapted from the Department of the Air Force, GSAM Condensed Version (February, 2003).

Table B1-3: Waterfall Methodology: Advantages vs. Disadvantages


Waterfall Methodology
Advantages Disadvantages Application
• Stages align with CPIC, • Progress and success are not observable until Useful when requirements
ARP, and typical project later stages are:
management phases • Errors or deficiencies made in earlier stages • Well understood at project
• Cost and schedule may not be discovered until implementation start
estimates may be lower • Risks are dealt with in a single development • Not expected to
and more accurate effort change/evolve over life of
• Only local feedback is available at stage project
transition points (due to sequential nature) • Project risk is relatively low
• Working product is not available until late in
project
• Corrections are addressed in maintenance
stage

B-80 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
Sample Template and Guidance

Attachment B2: Other SELC Considerations

B2.1 Index of Required Project Elements


As documented in Section 2.5 of this SELC Guide, project managers should evaluate required elements
for applicability for all DHS projects. Table B2-1 lists the sections in which these elements are discussed.

Table B2-1: Index of Required Project Elements

Element Section
Project Management B.2
Organizational Change Management (OCM) B.3
Enterprise Architecture Alignment B.4
Requirements Definition B.5
Prototyping B.6
Information Security B.7
Privacy Compliance B.8
Critical Infrastructure Protection B.9
Human Factors Engineering B.10
Section 508 EIT Accessibility B.11
Risk Management B.12
Independent Validation and Verification (IV&V) B.13
Electronic Records Management B.14
National Information Exchange Model (NIEM) B.15

B2.2 Project Management

B2.2.1 Definitions
The following paragraphs define project management-related terms found in this DHS SELC Guide for
use in DHS acquisitions.
Project Management: Project Management is the application of knowledge, skills, tools, and techniques
to a broad range of activities in order to meet the requirements of a particular project. The Project
Management Institute (PMI) groups Project Management activities into five process groups: Project
Initiation, Project Planning, Project Execution, Project Monitor and Control, and Project Close 12 (e.g.,
known collectively as the project life cycle). PMI also identifies nine supporting knowledge areas: Project
Integration Management, Project Scope Management, Project Time Management, Project Cost
Management, Project Quality Management, Project Human Resources Management, Project
Communications Management, Project Risk Management, and Project Procurement Management.
Program: A program is a group of related projects or a project that is large in scope and dedicated to a
specific purpose. In this DHS SELC Guide, for the sake of convenience, the term “project management”
will be used to mean either “program” or “project” management.
Project: PMI defines a project as a temporary endeavor undertaken to create a unique product, service,
or result.

12
PMI website, Professional Practices section, “About the Profession,” www.pmi.org.

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-81


11-05-08
Sample Template and Guidance

Program Manager: DHS Management Directive (MD) 0784 defines the role of the Program Manager and
the associated tasks as follows: 13 A Program Manager is the responsible person who, with significant
discretionary authority, is uniquely empowered to make final the scope of work, capital investment, and
performance acceptability decisions (for an assigned program[s]), and who is responsible for
accomplishing program objectives or production requirements through the acquisition of in-house,
contract or reimbursable support resources, as appropriate. The Program Manager is responsible for
management and oversight of the Integrated Project Team. In general, the Program Manager is the
manager of an acquisition program, but may be a manager of a procurement that does not rise to the
level of an acquisition program (i.e., janitorial services, HR services, bulk commodity purchases).
Project Management Methodology: A defined process (methodology) with the specific purpose of
managing a project or program through all phases of the project life cycle. The methodology is a
framework that acts as a mechanism for coordination in combining the responsibilities of managing both
an organization (Integrated Project Team – IPT) and a process (project life cycle) for the life of a project.
Integrated Project Team: A group of subject matter experts (SME) who represent the interests of their
sponsoring functional organizations in performing project activities as members of a project team under
the direction of a Project Manager for the duration of a project.
Project Life Cycle: A standardized collection of distinct phases grouped together to create the process
that a Project Manager uses to manage a project. PMI defines the set of common phases and activities in
the project life cycle (Table B2-2) as follows:

Table B2-2: Common Phases and Activities in a Project Life Cycle 14

Functional Phase High Level Description of Common Activities


Prepares a project proposal, obtains approval and reserves budget for the
Project Initiation
project, and establishes the project team.
Identifies stakeholders, defines project objectives, prepares the project
Project Planning plans for achieving the project objectives, and obtains final allocation of
budget.
Implements the project plans; coordinates people and other resources to
Project Execution
carry out the project plans.
Ensures that project objectives are met by monitoring and measuring
progress periodically to identify variances from the baselines (e.g., earned
Project Monitor & Control
value management – EVM), taking corrective action when necessary,
tracking the variances and managing changes.
Brings the project to an orderly end, formalizes and communicates the
Project Close acceptance or outcomes of a project, transfers deliverables to the clients or
the ongoing responsible area, conducts a post implementation review.

B2.2.2 Benefits
Project management conveys several benefits. It:

• Provides a standard method to ensure that projects are defined, monitored, and implemented in a
structured, consistent manner that promotes predictability and quality of outcome so that projects are
completed on time and within scope and budget.

13
Office of the Chief Procurement Officer, Department of Homeland Security, Acquisition Oversight Program
Guidebook, July 2005, p77, https://dhsonline.dhs.gov/portal/jhtml/tracking/viewdoc2.jhtml?doid=42070.
14
IEEE Std 1490-2003, IEEE Guide Adoption of PMI Standard – A Guide to the Project Management Body of
Knowledge.

B-82 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
Sample Template and Guidance

• Supports major functional processes within the life cycle, providing a uniform method to comply with
and integrate multiple life cycle requirements and tasks (e.g., strategic planning, enterprise
architecture [EA], investment planning, SELC) to ensure that projects meet stated goals.
• Uses a defined project management approach/methodology to coordinate the management of
organizational needs and expertise with the management of the project management process in order
to achieve results.

B2.2.3 Considerations
DHS Acquisition Managers, including Program Managers and Project Managers are responsible for
managing projects as “investment stewards,” ensuring compliance with MD 0784. 15 Though this DHS
SELC Guide does not define or specify a particular project management methodology to be used, it does
make the following recommendations with regard to the management of DHS IT projects:

• Program and/or Project Managers must meet the PM certification requirements as defined in MD
0784.
• Project goals and objectives should directly relate to the DHS mission.
• Key stakeholders (internal and external) should be identified early and involved throughout the life of
the project to ensure that business needs are accurately defined and met.
• Project Management Plans should identify and deliver measurable benefits to stakeholders, such as
reduced cost, improved quality, and more efficient response time.
• Project Managers are responsible for identifying and communicating risks and issues that may hinder
the successful delivery of a project.
• Project Management Plans must be flexible and should use a methodology that efficiently supports
DHS’ dynamic development environment, which is characterized by requirements and priorities that
can change due to external events.
• Project Management Plans must include program and project reviews defined in this DHS SELC
Guide in order to ensure effective reporting and management of project progression.
• Project Managers should define levels of effort and project detail relative to the level of risk to the
program, project, and/or task.
• Project Managers must develop and maintain comprehensive elements to support the project
management processes of project initiation, project planning, project execution, project monitor and
control, and project close, including a work breakdown structure, project schedule, ADEs, resource
plans, and identification of critical path, in order to ensure effective and efficient project management
and delivery to meet project objectives.
• Project Management Plans must include all appropriate standard elements found in best practice
project management methodologies to manage the project (e.g., project communication plan, project
training plan).
• Project Managers must ensure that all privacy compliance requirements (including analysis and
documentation) are met prior to implementation.

15
Department of Homeland Security, Management Directive (MD) 0784, Acquisition Oversight Program, issued
December 19,/2005, p2, https://dhsonline.dhs.gov/portal/jhtml/tracking/viewdoc2.jhtml?doid=4097002.

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-83


11-05-08
Sample Template and Guidance

B2.3 Organizational Change Management

B2.3.1 Definition
Organizational Change Management (OCM) helps organizations plan for, adapt to, and integrate change
that occurs as a result of changes in enterprise mission, IT systems, 16 or process. The implementation,
modification, or disposal of any enterprise IT system or component may result in significant change to
related business processes, organizational structure or culture, and workforce. OCM is the set of
management practices used to proactively assess and address the impact of significant organizational
change at appropriate points in the life cycle. OCM activities (e.g., reviews, assessments, tasks,
communications, and production of documents and products) should be conducted when necessary to
promote project success.
Changes to enterprise mission or IT systems can result from several types of initiatives, such as:

• Business Process Engineering/Business Process Improvement


• Business Architecture Development, Transition, and Sequencing (EA)
• Project Prioritization/Re-prioritization via IT Portfolio Management

B2.3.2 Benefits
The benefits of employing OCM include the following:

• Ownership and commitment to the enterprise change among both the leadership team and other
stakeholders
• Facilitation of new roles and responsibilities (e.g., strategy drives structure)
• Enhanced workforce readiness to support and successfully implement the mission
• Earlier identification and resolution of critical issues (e.g., unintended consequences)

B2.3.3 Considerations
• Organizational and business process improvements identified using OCM techniques should be
integrated with the Homeland Security (HLS) EA Business Architecture.
• Information Technology (IT) does not drive OCM (e.g., processes can be improved to meet mission
needs more effectively than simply by automating).
• While DHS does not mandate specific approaches to manage enterprise change, OCM is recognized
as a best practice throughout government and industry.
• OCM should be employed for all major 17 DHS development projects, especially those involving
significant change to technology, process, or organization structure.
• Project Managers should incorporate OCM concepts and activities in the project plan (e.g., Business
Impact Assessments, Outreach and Communication tasks).

16
Dr. Craig J. Petrun, The MITRE Corporation, Organizational Change Management - Practice Area Overview, Slide
1 of 27, August 3, 2006.
17
Refer to Directive 102-01 for the current investment thresholds for major projects.

B-84 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
Sample Template and Guidance

B2.4 Enterprise Architecture Alignment

B2.4.1 Definition
The domain of EA includes baseline architecture, target architecture, and a sequencing plan. 18 EAs are
essential for evolving information systems, developing new systems, and inserting emerging technologies
which optimize mission value. The existence of an EA is federally mandated by the Clinger-Cohen Act,
which makes Chief Information Officers responsible for developing, maintaining, and facilitating the
implementation of a sound and integrated IT architecture in their organizations. 19 The DHS EA is aligned
to the Federal Enterprise Architecture (FEA). The FEA is used to document, describe, and develop the
baseline architecture, the target architecture, and the sequencing plan. Component EAs are required to
align with the HLS EA. Individual projects are evaluated through the EA Governance process for
architectural alignment. The HLS EA target architecture is evolving to a Service Oriented Architecture
(SOA).

B2.4.2 Benefits
Among its benefits, an EA: 20

• Establishes the enterprise-wide roadmap to achieve the enterprise mission within the IT environment
• Acts as a “blueprint” for systematically and completely defining the current (baseline) and desired
(target) IT environment, thereby facilitating change and promoting standardization, alignment, and
integration
• Improves communication and decision making through use of a standard vocabulary, the capture of
enterprise facts, and support for enterprise analyses and decision making
• Provides a mechanism for sharing services
• Expedites the integration of legacy, migration, and new systems
• Ensures legal and regulatory compliance
• Facilitates transition to new EA concepts

B2.4.3 Considerations
• Official DHS guidance states that the role of the target architecture in the HLS EA is to establish a
cohesive and consistent view of the future in terms of the data, software, and technology required to
implement it. 21
• The HLS EA contains:
– DHS architectural principles
– A baseline inventory of “as-is” business practices and technology resources
– A four-layer target architecture (consisting of business, data, applications, and technology layers)
– A transition strategy and plan intended to move the HLS enterprise toward the evolving target
architecture

18
A Practical Guide to Federal Enterprise Architecture, version 1.0, p.1., Chief Information Officers Council, February
2001.
19
Division E – Information Technology Management Reform Act (now the Clinger/Cohen Act), s.1124, as found at
http://www.cio.gov/Documents/it_management_reform_act_Feb_1996.html.
20
Ibid, p8.
21
From HLS Target Architecture, Version 2.0, October 29, 2004.

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-85


11-05-08
Sample Template and Guidance

• DHS IT systems must align with the HLS EA. EA alignment refers to how well IT investments support
the enterprise architecture and the transition to the target architecture. To guide IT project alignment
to the HLS EA, appropriate EA-related exit criteria are defined in each DHS SELC stage.
• Project Managers and system architects are responsible for designing DHS systems that take the
following into account:
– Adherence of all IT system development efforts to the principles, standards, and processes
defined by the DHS Service Component Based Architecture
– Leverage of existing services (reuse of registered services)
– Identification of opportunities to create additional services (new services or enhancements of
existing services) for reuse throughout DHS
– Leverage of existing data assets to increase information sharing opportunities
• The EA Alignment Process is conducted:
– As part of the project approval process to ensure EA alignment of proposed projects
– Periodically, as part of the ARP, to:
– Validate alignment throughout the life of the investment (e.g., as IT investments are
defined, designed, developed, tested, implemented, maintained, and disposed of)
– Ensure that variances are identified, assessed, and either approved or rectified
• The HLS Technical Reference Model (TRM) provides technical standards for all DHS IT systems.
The TRM applies to both the development of new systems and the enhancement of existing
systems. Additionally, it applies to both pilots and prototypes. Pilots must be compliant with the
TRM; prototypes may use emerging technologies if approved by the DHS EAB.
• The EAB Governance Process Guide describes the EA Decision Request (DR) processes.
Specific types of EA DRs include the following:
– Program Alignment DR (confirm alignment of a program to the HLS EA)
– Technology Insertion DR (approve insertion of technology products/standards into the HLS
TRM)
– Service Insertion DR
– Data Insertion DR
– Performance Insertion DR
For more information on EA planning, technical insertion, and assessment processes or the DHS TRM,
contact either the EA staff in the DHS Office of the CIO’s Office of Applied Technology or the Technology
and Architecture staff of the DHS Component organization of interest.

B2.5 Requirements Definition

B2.5.1 Definition
The activities in the requirements definition phase (commonly referred to as requirements engineering by
the Software Engineering Institute [SEI]) of the systems engineering life cycle include the gathering,
analysis, specification, verification, validation, and management over time of the stakeholder-desired
capabilities and characteristics of a product and/or product component to be produced in support of
mission needs.

B2.5.2 Benefits
The benefits of effective and efficient requirements engineering include the following:

B-86 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
Sample Template and Guidance

• Greater likelihood of successful delivery that meets project cost, scope, and schedule (“requirements
development is one of three factors critical to successful acquisitions”) 22
• Improved risk management due to increased project stability
• More effective project-related communication
• Enhanced enterprise decision making via defined requirements baselines

B2.5.3 Considerations
Many of the concepts and descriptions below are adapted from the Requirements Engineering Section of
an SEI article called “A Framework for Software Product Line Practice.” 23

• Effective and efficient configuration management must be used to establish baselines from which to
manage change; requirements engineering affects all aspects of systems development and
maintenance as changes in requirements in one project may affect other related systems and/or
components (e.g., changes in requirements for a development project may affect the requirements for
maintenance of existing systems and/or components, as well as the requirements of parallel
development efforts).
• Requirements engineering is a communications exercise among the many internal and external
stakeholders it involves: citizens, executives, systems engineers, operations personnel, field
personnel, taxpayers, other “end-users” (including persons with disabilities), contractors, oversight
agencies, other projects under development, among others. Therefore, effective communication
plans, activities, and products must be established and managed with appropriate levels of detail
available for all stakeholders.
• Requirements must be defined with the appropriate level of both behavioral (e.g., the specificity to
support functional need, and the generality at appropriate points to deal with change over the lifetime
of the component) and quality characteristics (performance, reliability, security). 24
• This DHS SELC Guide recognizes a series of related activities and products that must be addressed
in requirements engineering efforts for DHS IT projects. These include the following:
– Identification of desired business capabilities from activities conducted as part of the Strategic
Planning, Enterprise Engineering, Operations, and from other appropriate components of the
enterprise life cycle
– The creation of a Concept of Operations (CONOPS), a Business Impact Assessment (BIA), and
subsequent requirements documents as defined in Section 5 Requirements Definition and
including the following:
 Operational Requirements Document (ORD)
 Functional Requirements Document (FRD)
 Requirements Traceability Matrix (RTM)
 Systems Requirements Document (SRD)
– The appropriate set of activities, products, tools, and techniques (e.g., testing, prototyping,
modeling, analyses, documentation and communication of trade-off decisions and results) as
recommended by recognized best practice organizations (e.g., SEI, PMI, IEEE) with evidence of
successful execution to support the effective and efficient development of systems and/or
components required for successful project completion in support of the DHS mission

22
Effective Acquisition Practices = Successful Government Program Management Offices (GPMO), Lisa M. De
Mello, MBA, PMP, Joseph A. Pegnato, DPA;William Sullivan, MS; Scott Webb, MS, PMP; September 2005
23
Software Engineering Institute, “A Framework for Software Product Line Practice, Version 4.2,” c.2007.
24
Ibid.

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-87


11-05-08
Sample Template and Guidance

B2.6 Prototyping

B2.6.1 Definition
Prototyping is defined as the development and implementation of a model (e.g., physical, electronic,
digital, analytical) of a product built to do the following:

• Assess the feasibility of a new or unfamiliar technology


• Assess or mitigate technical risk
• Validate requirements or a product
• Demonstrate critical features
• Verify a product
• Determine enabling product readiness
• Characterize performance or product features
• Discover physical principles 25
• Demonstrate accessibility (Section 508)
The terms “prototype” and “pilot” are often used interchangeably; from a DHS SELC perspective,
however, a prototype is not the same as a pilot. Prototypes or “proof of concepts” are initiated as a means
of demonstrating functionality, technology integration, program management, and/or business process
changes. As such, they are typically low-cost, require short development time, are not robust, and do not
follow a rigorous development methodology. They are not intended to provide operational support.
Prototypes are used to determine if a particular approach is feasible and acceptable. Based on the
prototype results, the approach may be expanded into a formal program to deliver an operational
system. 26
Unlike a prototype, a pilot is intended for operational use and, as such, follows a formal development
methodology (SELC) with full life-cycle documentation, including requirements specification, design
documents, and test plans. The pilot is required to pass security certification and, therefore, must contain
sufficient features for secure operational use. The pilot will be implemented in a much more limited
deployment than the full production system. This could mean fewer geographic sites, fewer users, and/or
more limited features. 27

B2.6.2 Benefits
In many traditional system development methodologies, prototypes were not used, were not available
during development, and/or were maintained only long enough to establish technical feasibility. It is now
recognized that prototyping can provide a variety of benefits throughout the systems development life
cycle, rather than at a single time for a single purpose:

• Prototyping is an effective technique used in product design and evaluation to accomplish the
following:
– Discover physical principles of a product
– Assess and/or confirm product feasibility, requirements, performance, and/or features
– Mitigate project and program risks
– Evaluate technical integration feasibility or alternative solutions
– Elicit user feedback and refine requirements

25
EIA 632: Processes for Engineering a System, January 1999.
26
EAB Governance Process Guide, ver. 3.0, September, 2006.
27
Ibid.

B-88 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
Sample Template and Guidance

• Prototyping is considered a best practice in commercial software development, especially as it


applies to the design of user interfaces and complex systems. 28

B2.6.3 Considerations
• Prototyping provides increased value in the use of evolutionary/Spiral development methodologies,
such as Rapid Application Development (RAD), Agile Development, and Xtreme Programming.
• All major 29 DHS IT development projects should use prototyping to facilitate requirements analysis
and technical feasibility.
• All major 30 DHS IT development projects should continue to leverage the prototype as part of the
initial build or baseline capability, where feasible.
• Privacy compliance requirements do not distinguish between pilot and prototype and instead look
purely at the data and data usage; consequently, privacy requirements must be met for both.

B2.7 Information Security

B2.7.1 Definition
The term “information security” means protecting information and information systems from unauthorized
access, use, disclosure, disruption, modification, or destruction in order to provide:

• Integrity, which means guarding against improper information modification or destruction and includes
ensuring information non-repudiation and authenticity
• Confidentiality, which means preserving restrictions on unauthorized access and disclosure, including
ways to protect personal privacy and proprietary information
• Availability, which means ensuring timely and reliable access to and use of information 31

B2.7.2 Benefits
It is DHS policy that all information systems that generate, store, process, transfer, or communicate
sensitive information shall be protected at a level commensurate with the threat. The level of protection
will be determined by the criticality and sensitivity of the information and of the mission supported by the
information system, and in compliance with national policy and standards. Information security policies,
processes, and procedures provide a variety of benefits throughout the systems development life cycle. 32

• Establish policies and procedures for the overall DHS Information Security Program and information
security in order to ensure incorporation of standards into information security technology efforts.
• Ensure that information assurance requirements are addressed by the mission areas and that
security is adequately incorporated into information system functions throughout the systems
engineering life cycle.
• Ensure that all DHS operational components can exploit the maximum advantage from information in
order to accomplish their missions while keeping residual risk to a minimum.
• Provide security policies and architecture that provide a common, interoperable, cost-effective means
of protecting DHS information resources.

28
IEEE, Guide to the Software Engineering Body of Knowledge.
29
Refer to Directive 102-01 for the current investment thresholds for major projects.
30
Ibid.
31
Federal Information Security Management Act (FISMA) of 2002, Public Law 107-347, December 17, 2007.
32
DHS Information Security Program Strategic Plan, April 4, 2004, version 1.

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-89


11-05-08
Sample Template and Guidance

• Ensure that DHS information, systems, major applications, and general support systems are
sufficiently secure to accomplish the DHS priority missions.
• Ensure compliance with Federal Information Security Management Act of 2002 (FISMA), National
Institute of Standards and Technology, Office of Management and Budget (OMB), National Security
Agency, and Central Intelligence Agency guidance as well as all applicable laws, directives, policies,
and directed actions on a continuing basis.

B2.7.3 Considerations
Government agencies are required to protect information assets against loss, theft, damage, and
unauthorized destruction, modification, and access. To fulfill this responsibility, various risk management
activities must be performed throughout the systems development life cycle. These activities include the
following:

• Identification of sensitive systems


• Performance of security risk analyses and assessments
• Development of system security plans, contingency plans, and secure operating procedures
• Testing of systems security
• Certification and accreditation of systems for operation in the assigned security mode

B2.7.3.1 Information Security Controls


FISMA requires that information security controls must be selected based on risk as determined by the
categorization of a system resulting from a Federal Information Processing Standards (FIPS) 199 review.
The FIPS 199 System Categorization availability must be synchronized with Business Continuity planning
activities by ensuring that FIPS 199 availability is consistent with the BIA Maximum Allowable Outage.
A review of the effectiveness of the controls and control testing must be performed at least annually. The
determination of the level of rigor to be used in the review is based upon the characteristics of the system,
such as the:

• Acceptable level of risk to the system and its information


• Extent to which system configurations and settings are documented and continuously monitored
• Extent to which patch management occurs
• Comprehensive nature of the past review
• Age of the most recent in-depth testing and evaluation

B2.7.3.2 Certification and Accreditation


DHS requires that all solutions using IT in any form are Certified and Accredited (C&A) in accordance with
DHS security policies before they are deployed to the operational environment. The Chief Information
Security Officer (CISO) has established a security C&A process to ensure that all DHS IT solution
development initiatives comply with DHS security policies and Federal regulations.
Key requirements of the DHS C&A process include the following:

• Identification of an Information Systems Security Officer (ISSO) to serve as the principal point of
contact for all IT security aspects of the system.
• Use of the CISO-approved tool for conducting certification and accreditation. The Office of
Information Security maintains both a classified and unclassified version of the CISO-approved C&A
tool. DHS 4300A applies to all unclassified systems and is used throughout this document as
reference. For classified systems, all references should be made to DHS 4300B. Access to the

B-90 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
Sample Template and Guidance

classified or unclassified version of the CISO-approved C&A tool should be made through the
Component’s Information System Security Manager (ISSM).
• Use of the CISO-approved tool for conducting annual self assessments and for FISMA reporting.
• Development of a Security Risk Assessment, System Security Plan (SSP), and Plan of Action and
Milestones (POA&M).
• Completion of an independent Security Test and Evaluation (ST&E) with the effort documented in the
Security Assessment Report (SAR).
• A validated Privacy Threshold Analysis reviewed and approved by the DHS Privacy Office.
• IT system C&A completed every three years except in cases where a DHS IT system or an
operational environment has experienced a “major” change. If an IT system or operational
environment is significantly changed prior to the system reaching its three year milestone, the
affected system(s) must be re-certified and re-accredited prior to being allowed to again operate in
the DHS environment.
All DHS IT projects must be in compliance with DHS Systems Security requirements; compliance is
verified throughout the systems development life cycle via exit criteria used in SELC stage reviews.
Additional information regarding the DHS IT security program is presented in DHS 4300A Sensitive
Systems Policy and Handbook, 4300B National Security Systems Policy and Handbook, and Security
Architecture Guides Volumes 1-3.

B2.7.3.3 Continuous Monitoring


The purpose of the Continuous Monitoring Phase is to provide oversight and monitoring of the security
controls in the IT system on an ongoing basis and to inform the authorizing official or designated
representative when changes occur that may impact the security of the system. The Continuous
Monitoring Phase monitors the status of the IT system to ensure that residual risk is kept within an
acceptable level. During this phase, it is necessary to identify any significant changes to the system
configuration or to the operational/threat environment that might affect system security.

B2.8 Privacy Compliance

B2.8.1 Definition
Privacy Compliance is a structured review process to ensure that all privacy compliance requirements are
met prior to final project implementation. Section 208 of the E-Government Act of 2002 requires all
Federal government agencies to conduct Privacy Impact Assessments (PIA) for all new or substantially
changed technology that collects, maintains, or disseminates personally identifiable information. The DHS
Chief Privacy Officer (CPO) is required by Section 222 of the Homeland Security Act to ensure that the
technology used by the Department sustains and does not erode privacy protections. The PIA is one
mechanism through which the CPO fulfills this statutory mandate. The CPO is also required by Section
222 to conduct PIAs for proposed rulemakings of the Department. The CPO approves PIAs conducted by
the Department’s offices and programs.

B2.8.2 Benefits
Privacy Compliance conveys the following benefits:

• Compliance with laws and regulations pertaining to the identification and protection from unlawful
disclosure and use of personally identifiable information collected, maintained, or disseminated by
DHS personnel and/or technology
• Auditable requirements, processes, and training that govern a standard approach to privacy
protection of personally identifiable information within DHS

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-91


11-05-08
Sample Template and Guidance

B2.8.3 Considerations

B2.8.3.1 Privacy Compliance Documentation

Privacy Threshold Analysis


A Privacy Threshold Analysis (PTA) is used to determine whether a full PIA is needed. The PTA template
is available on the Privacy Office website on DHS Online and www.dhs.gov/privacy. This form must be
completed and reviewed by the Privacy Office. If a PIA is required, the Privacy Office will send the project
manager (the submitter) a copy of the PIA Guidance and accompanying template to complete and return.

Privacy Impact Assessment


A Privacy Impact Assessment (PIA) is an analysis of how personally identifiable information is collected,
stored, protected, shared, and managed. The term “personally identifiable information” or “PII” refers to
any information that permits the identity of an individual to be directly or indirectly inferred, including any
other information that is linked or is linkable to that individual regardless of whether the individual is a U.S.
citizen, legal permanent resident, or a visitor to the U.S. The purpose of a PIA is to demonstrate that
project sponsors and developers have consciously incorporated privacy protections throughout the entire
life cycle of a system. This involves making certain that privacy protections are built into the system from
the beginning, when such protections are less costly and more effective. Addressing privacy issues
publicly through a PIA builds citizen trust in the operations of the Department.

System of Records Notice


A System of Records Notice (SORN) is a publicly published document that describes a certain type of data
collection and how that data is used. A “system of records” is a group of any records under the control of
any agency from which information is retrieved by the name of the individual or by some identifying
number, symbol, or other identifier assigned to the individual. The Privacy Act requires each agency to
publish notice of its systems of records in the Federal Register.

B2.8.3.2 Sources for Privacy Protection

The Privacy Act of 1974


The Privacy Act of 1974 regulates the Federal government’s use of personal information. It places
restrictions on the collection, use, maintenance, and release of information about individuals and gives
individuals the right, under certain circumstances, to see records about themselves, to obtain copies of
their records, to have records corrected or amended, and to have a statement of disagreement filed in
their records if the correction or amendment is not approved.

The E-Government Act of 2002


Section 208 mandates that all Federal Executive Branch departments and agencies and their contractors
conduct PIAs whenever they develop or procure new IT involving the collection, maintenance, or
dissemination of personally identifiable information or make substantial changes to existing technology for
managing such information.

The Homeland Security Act of 2002


Section 222 mandates the appointment of a senior-level privacy officer responsible for privacy policy. The
duties of that privacy officer include: ensuring that the use of technologies sustains, and does not erode,
privacy protections relating to the use, collection, and disclosure of personal information; ensuring that
systems of records comply with the Privacy Act of 1974; evaluating legislative and regulatory proposals
involving the collection, use, and disclosure of personal information; conducting PIAs on rules proposed
by DHS; and preparing an annual report to Congress on privacy at DHS.
For more information on DHS privacy compliance requirements, contact the Privacy Office, U.S.
Department of Homeland Security, Washington, DC 20528, available via email PIA@dhs.gov. Examples

B-92 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
Sample Template and Guidance

of PIAs and SORNs as well as additional educational materials related to the compliance are available on
the DHS Privacy Office website: www.dhs.gov/privacy.

B2.9 Critical Infrastructure Protection

B2.9.1 Definition
The USA Patriot Act of 2001 defines critical infrastructure as: 33
“Systems and assets, whether physical or virtual, so vital to the United States that the
incapacity or destruction of such systems and assets would have a debilitating impact on
security, national economic security, national public health or safety, or any combination
of those matters.”
Homeland Security Presidential Directive (HSPD)-7, passed on December 17, 2003, establishes a
national policy for Federal departments and agencies to follow in identifying, prioritizing, and protecting
critical infrastructure and key resources throughout the United States. Consistent with these acts and
directives, the DHS Critical Infrastructure Protection (CIP) Program is one of the eight programs
described in the DHS Information Security Program Strategy. It is a DHS program that reports to OMB
annually about functions and services identified and prioritized as critical infrastructure, the assets used,
and programmatic actions and efforts taken by the Component to protect the asset and ensure continuity
during or recovery after disruption. The CIP program follows the guidance of the Federal Executive Agent
(DHS Infrastructure Protection) and is responsible for identifying mission critical functions and services,
determining those which are candidates, and then making the final determination as to whether the
function and/or service is or is not national critical infrastructure.

B2.9.2 Benefits
CIP conveys the following benefits:

• Systems and assets vital to the security, economy, public health, and/or safety of the United States
are identified and prioritized, allowing the implementation of plans to protect them from incapacity,
destruction, and/or to ensure continuity or recovery after disruption.
• A national policy exists to ensure a unified approach to the identification, prioritization, and protection
of vital systems and assets.

B2.9.3 Considerations
Additional information on the CIP program can be found in the DHS Sensitive Systems Handbook
Security Program Policy. Additional information on the DHS CIP program is available from the
organization supporting Continuity Planning for Critical DHS Assets within the DHS Office of the Chief
Information Officer (DHS OCIO). For information at the Component organizational level, contact the CIP
Officer for the specific Component organization of interest.

B2.10 Human Factors Engineering

B2.10.1 Definition
Human factors engineering (HFE) is concerned with optimizing the interaction of people (often referred to
as “end users” or “users”) with the devices, applications, systems, processes, and equipment they must

33
USA PATRIOT Act of 2001 (42 U.S.C. 5195c(e))., SEC. 1016. CRITICAL INFRASTRUCTURES PROTECTION,
October 18th, 2001, from http://fl1.findlaw.com/news.findlaw.com/cnn/docs/terrorism/hr3162.pdf

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-93


11-05-08
Sample Template and Guidance

use in order to minimize errors, time spent performing a task, lost productivity, staff turn-over, and training
costs, while maximizing efficiency, clarity, ease of learning, effectiveness, and productivity. 34

B2.10.2 Benefits
Applying the principles of HFE conveys the following benefits:

• The user-centered design process creates a design that is user-evaluated and altered at several
points early in the project life cycle, resulting in an end-product or service more likely to meet user
needs.
• Cost efficiencies in service/product development can be gained because corrections are made earlier
in the development life cycle when they are less costly than those made later in the life cycle.

B2.10.3 Considerations
• User-centered design requires that project developers:
– Know the user(s), including users with disabilities, 35 and their requirements
– Involve the users early and often in the design process
– Use an iterative approach so that each iteration is targeted to improve a specific facet of the
design, with the total number of iterations determined by usability acceptance criteria and user
priority 36
• A variety of factors in the operational environment affect the importance of “usability” (or “ease of
use”) in the design of a product or service. For example, in products or services affecting human
safety or security, usability is probably a greater priority than in other applications.
• While DHS has no formal policies that specifically mandate the use of HFE by name, HFE concepts
are present in many activities related to the SELC. The user-centered design characteristics of
understanding user needs, involving the user early in design, and using an iterative design process
are analogous to activities in Strategic Planning (e.g., identify desired business capabilities), EA (e.g.,
Business Reference Models, Service Component Based Architecture), and in many facets of
Requirements Engineering (e.g., develop a CONOPS, BIA, ORD, use cases, prototyping).
• HFE should be considered in all design activities. Several standards and other resources are
available to guide designers in this area:
– ANSI/HFS 100-1988, published by the Human Factors and Ergonomics Society (HFES):
American National Standard for Human Factors Engineering of Visual Display Terminal
Workstations
– ISO 9241-Parts 1-17:1997 Ergonomic requirements for office work with visual display terminals
– ISO 9241-110:2006 Ergonomics of human-system interaction
– ISO 13407:1999 Human-centered design processes for interactive systems
– ISO/TR 16982:2002 Ergonomics of human-system interaction – Usability methods supporting
human-centered design
– ISO/TR 18529:2000 Ergonomics – Ergonomics of human-system interaction – Human-centered
lifecycle process descriptions

34
US-VISIT Human Factors Engineering Plan, May 19th, 2006, USVISIT-APMO-CONTHSSCHQ04D0096T004-
PLN060150-D
35
Note that Fitness of Duty requirements do not preclude Section 508 compliance.
36
IEC, International Engineering Consortium; http://www.iec.org/online/tutorials/hmi/topic05.html

B-94 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
Sample Template and Guidance

B2.11 Section 508 Electronic and Information Technology Accessibility

B2.11.1 Definition
In 1998, Congress amended the Rehabilitation Act to require Federal agencies to make their Electronic
and Information Technology (EIT) accessible to people with disabilities. Inaccessible technology
interferes with an individual's ability to obtain and use information quickly and easily. Section 508 was
enacted to eliminate barriers in IT, to make available opportunities for people with disabilities, and to
encourage development of technologies that will help achieve these goals. The law applies to all Federal
agencies when they develop, procure, maintain, or use electronic and information technology. Under
Section 508 of the Rehabilitation Act, as amended by the Workforce Investment Act of 1998 (P.L. 105-
220), agencies must give disabled employees and members of the public access to information that is
comparable to the access available to others. 37

B2.11.2 Benefits
The following are benefits of complying with Section 508:

• Compliance with Federal law.


• Experience with the new technologies and with the HFE used in applications to support Section 508
compliance may be reusable in other DHS design applications.
• Disabled employees and members of the public will have access to DHS information equal to that of
employees and members of the public who are not disabled.

B2.11.3 Considerations
• Each project must engage the DHS Office on Accessible Systems and Technology (OAST) or the
Component Section 508 Coordinator to ensure that it is compliant with all DHS accessibility
requirements. Accessibility reviews may require the project to prepare a plan of remediation and
additional project requirements.
• All DHS IT system development efforts must address Section 508 requirements throughout the life
cycle. Each project must have a Section 508 EIT Accessibility Plan to define its approach to meeting
Section 508 requirements.
• DHS considers accessibility to EIT a priority for all employees and external customers, including
those with disabilities. MD 4010 established OAST within the OCIO and indirectly within the Office of
Civil Rights and Civil Liberties as well as policy regarding EIT accessibility for DHS employees and
customers with disabilities. 38
• Section 508 requirements apply to all DHS Components and to all EIT developed, procured,
maintained, or used by DHS Components. Additional guidance for accessibility is provided by
numerous Public Laws, regulations, and OMB circulars, and directives:
– The Homeland Security Act of 2002, P.L. 107-296 (November 25, 2002), Section 102
– Section 508 of the Rehabilitation Act of 1973, as amended in the Workforce (65 FR 80500,
December 21, 2000; 66 FR 20894, April 25, 2001)
– Electronic and Information Technology (EIT) Accessibility Standards (36 CFR part 1194)
– Federal Acquisition Regulations (FAR) – Subpart 39.2 – Electronic and Information Technology
– OMB Circular A-130, Management of Federal Information Resources (61 FR 6428, February 20,
1996)

37
Federal Section 508 website,http://www.Section508.gov.
38
Department of Homeland Security MD 4010, Section 508 Program Management Office & Electronic and
Information Technology Accessibility

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-95


11-05-08
Sample Template and Guidance

– Clinger-Cohen Act of 1996 (40 U.S.C. 1401(3))


– Section 202(d) of the E-Government Act of 2002, Accessibility to Persons with Disabilities
– DHS MD 4010.2, Electronic Information Technology Accessibility
For further information regarding Section 508, email 508@dhs.gov, call OAST at 202-447-0476 or TTY 202-
447-5857, or visit OAST site at:
https://dhsonline.dhs.gov/portal/jhtml/community.jhtml?index=130&community=MGMT&id=2025980011.

B2.12 Risk Management 39

B2.12.1 Definition
Risk management is a process, applied on a continuous basis throughout the SELC, with the objective of
providing a repeatable process for balancing cost, schedule, and performance goals within program
funding. The process is made up of:

• Risk Identification
• Risk Analysis
• Risk Mitigation Planning
• Risk Mitigation Plan Implementation
• Risk Tracking

B2.12.2 Benefits
A properly structured and administered risk management practice will generally help to ensure a
successful acquisition program with the following benefits:

• The ability to anticipate risks before they become issues because of a planned risk management
process integral to the acquisition process, especially to the technical planning processes
• Continuous, event-driven technical reviews to help define risk areas to meet users’ needs within
acceptable risk
• An independent risk perspective because the risk management practice is independent of the Project
Manager
• A defined set of success criteria for performance, schedule, and cost elements

B2.12.3 Considerations
Risks have three components:

• A potential future event that, if it occurs, will create a programmatic issue


• A probability assessed in the present of that future event occurring
• The programmatic impact of that future event
Risk can be quantified, since it is the product of the probability of the event occurring times the
programmatic impact. An issue is an event that has occurred, and has had an impact on the program that
requires management intervention. A primary objective of risk management is to develop risk mitigation
strategies that will either prevent an event from occurring or reduce its impact. The practice of risk
management draws from many management disciplines, including but not limited to program
management, systems engineering, earned value management, production planning, quality assurance,

39
Price, Gordon, Software Testing Terminology, from http://www.stsc.hill.af.mil/crosstalk/1994/07/xt94d07l.asp.
Original citation credited to IEEE 729/610.12, Glossary of Software Engineering Terminology, New York, 1990.

B-96 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
Sample Template and Guidance

logistics, system safety and mishap prevention, and requirements definition. It establishes a process that
ensures achieving program objectives for cost, schedule, and performance. That is, risk management is a
primary practice used to ensure that the program is not a failure.

B2.13 Independent Verification & Validation

B2.13.1 Definition
Independent Verification and Validation (IV&V) is a specific certification practice. Commonly, IV&V is
performed by an individual or organization that is technically, managerially, and financially independent of
the development organization. 40

B2.13.2 Benefits
• The independent nature of IV&V provides management with insight into the project without conflict of
interest.
• IV&V provides the opportunity for more effective decision making affecting project direction.

B2.13.3 Considerations
The objectives of IV&V are to: 41

• Facilitate early detection and correction of software anomalies


• Enhance management insight into process and product risk
• Support the life cycle processes to ensure conformance to program performance, schedule, and
budget
• Provide an early assessment of software and system performance
• Provide objective evidence of software and system conformance to support a formal certification
process
• Improve the software development and maintenance processes
• Support process improvement for an integrated systems analysis model
IV&V teams analyze and review software development outputs to help to ensure that software
requirements are not in conflict with any standards or requirements applicable to other system
components. Typically, IV&V teams do not conduct tests against the system (e.g., unit, integration, user
acceptance). IV&V teams often will witness these tests to gauge the effectiveness of the testing process
in accurately and completely testing requirements and in identifying defects. While DHS does not
mandate IV&V at this time, IV&V is considered a best practice throughout government and industry. As
such, it should be employed for all major development projects.
Verification and Validation entail:

• Verifying requirements: Proving that each requirement has been satisfied. Verification can be done
by logical argument, inspection, modeling, simulation, analysis, expert review, test, or demonstration.
• Validating requirements: Ensuring that (1) the set of requirements is correct, complete, and
consistent; (2) a model can be created that satisfies the requirements; and (3) a real-world solution
can be built and tested to prove that it satisfies the requirements.

40
Price, Gordon, Software Testing Terminology, from http://www.stsc.hill.af.mil/crosstalk/1994/07/xt94d07l.asp.
Original citation credited to IEEE 729/610.12, Glossary of Software Engineering Terminology, New York, 1990
41
IEEE, Draft Standard for Software Verification and Validation, IEEE P1012/D12, September 12, 2004, p3.

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-97


11-05-08
Sample Template and Guidance

• Verifying a system: Building the system right: ensuring that the system complies with the system
requirements and conforms to its design.
• Validating a system: Building the right system: making sure that the system does what it is
supposed to do in its intended environment. Validation determines the correctness and completeness
of the end product, and ensures that the system will satisfy the actual needs of the stakeholders.
The requirement for IV&V may be placed on a high risk program by Congress as a condition of release of
funds. When this occurs, the CIO is typically required to certify that the program has an IV&V contract in
place. The DHS CIO provides this certification upon review of supporting documentation from the
program. Certification is based on the following criteria:

• An IV&V contract is in place that includes the subject program within the scope.
• The contractor’s IV&V approach meets IEEE 1012 standards.
• The contractor’s IV&V approach ensures that items are completed and are of sufficient quality and
that all outcomes will meet the needs of the user.
• The contractor’s IV&V technical approach is developed for all the necessary IV&V activities.
• The contractor’s IV&V technical approach identifies a strategy or method for determining which
activities will need to be conducted, how those activities will be performed, and when those activities
will be conducted.

B2.14 Electronic Records Management

B2.14.1 Definition
National Archives and Record Administration (NARA) regulations affecting Federal agencies and their
records management programs are found in Subchapter B of 36 Code of Federal Regulations Chapter
XII. Part 1234
establishes the basic requirements related to the creation, maintenance, use, and disposition of
electronic records. Electronic records include numeric, graphic, and text information, which may
be recorded on any medium capable of being read by a computer and which satisfies the
definition of a record. This includes, but is not limited to, magnetic media, such as tapes and
disks, and optical disks. Unless otherwise noted, these requirements apply to all electronic
information systems, whether on microcomputers, minicomputers, or main-frame computers,
regardless of storage media, in network or stand-alone configurations. This part also covers
creation, maintenance and use, and disposition of Federal records created by individuals using
electronic mail applications. 42
NARA regulations applicable to electronic records management must be considered by Project Managers
throughout all phases of the SELC. Additional resources and guidance are available at
http://www.archives.gov/records-mgmt/.

B2.14.2 Benefits
According to information from the NARA Records Management website, electronic records management:

• Contributes to the smooth operation of an agency’s acquisitions by making the information needed for
decision making and operations readily available
• Helps deliver services in a consistent and equitable manner
• Facilitates effective performance of activities throughout an agency

42
http://www.archives.gov/records-mgmt/policy/guidance-regulations.html

B-98 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
Sample Template and Guidance

• Protects the rights of the agency, its employees, and its customers
• Provides continuity in the event of a disaster
• Protects records from inappropriate and unauthorized access
• Meets statutory and regulatory requirements, including archival, audit, and oversight activities
• Provides protection and support in litigation

B2.14.3 Considerations
The Records Management (RM) Profile 43 recommends that agencies embed records management
requirements in the earliest stages of the SELC. For more information, contact the DHS records
management point of contact at NARA at http://www.archives.gov/recordsmgmt/appraisal/work-group-
all.html. Table B2-3 provides a checklist that Project Managers can use to integrate records management
into the SELC stages.

Table B2-3: Integration Checklist

Records Management Integration into the SELC


DHS SELC Checklist
Stage
Planning 1. Is the agency Records Officer included from the beginning in the system design process?
2. Are records that support the business process identified?
3. a. Do current record schedules apply to the new system?
b. Is a new record schedule required because of changes in the records?
4. Is the agency Records Officer’s signature on the agency Investment Summary Proposal?
Requirements 5. Are all records-related requirements identified and incorporated into the final CONOPS and
Definition Operational Requirements Document?
6. Are new records schedules being drafted, if needed?
7. Is the agency Records Officer’s signature on the requirements document?
Design 8. Are all records management requirements incorporated into the system design document?
9. Is the agency Records Officer’s signature on the system design document?
10. Is the agency records management staff included in project status meetings as needed?
Development 11. Is the agency records management staff included in project status meetings as needed?
12. Are proposed records schedules submitted to NARA?
Integration and 13. Are records management requirements incorporated into the system?
Test
14. Is the agency Records Officer’s signature on the Systems Test Report?
Implementation 15. Is the agency records management staff included in project status meetings as needed?
16. Is the agency Records Officer’s signature on the document approving deployment of the
system?
Operations and 17. Is the Mid-Cycle Review complete? (The review to occur three years after going to
Maintenance production to validate records management requirements and records schedules.)

43
Refer to Federal Enterprise Records Management Profile, Sections 4.1.1 through 4.1.6;
http://www.archives.gov/records-mgmt/policy/rm-profile.html.

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-99


11-05-08
Sample Template and Guidance

Records Management Integration into the SELC


DHS SELC Checklist
Stage
18. Are disposition authorities being implemented in accordance with appropriate
dispositions?
19. Is the Mid-Cycle Review report sent to the agency records management staff for review?
20. Is the agency Records Officer’s signature on the Mid-Cycle Review certification
document?
System 21. At the time of retirement or rollover of the system, are records preserved, retained, and
Disposition made fully accessible for the full retention periods in accordance with appropriate
dispositions?
22. At the time of retirement or rollover of the system, are temporary records destroyed in
accordance with appropriate dispositions?
23. At the time of retirement or rollover of the system, are permanent records transferred to
NARA in accordance with the appropriate dispositions?

B2.15 National Information Exchange Model (NIEM)

B2.15.1 Stage 1 - NIEM Scenario Planning


NIEM provides the development and life cycle processes to create and document information exchanges.
An IEPD provides users with the documentation, including business rules and use cases, for the
exchange of information, in addition to the schemas that describe the elements. The process used to
create an IEPD and maintain it through its life cycle ensures a consistent approach to sharing information
among systems across DHS and it allows for increased efficiency in deploying new services. Once
completed, the IEPDs products are stored in the DHS Information Exchange Repository to facilitate reuse
by other component agencies. They are linked to services, when applicable, that are available for
providing access to parties external to DHS. Detailed information on the IEPD development process and
products can be found in the NIEM Concept of Operations
(http://www.niem.gov//files/NIEM_Concept_of_Operations.pdf). Detailed technical documentation and
assistance is available by contacting the DHS Enterprise Data Management Office.

When Should a Program or Project Use NIEM?


If inter-component or inter-agency information exchanges (transfer of information between two parties)
will be developed, the information exchanges must be developed in accordance with the NIEM IEPD.
SELC Planning activities should address NIEM scenario planning activities. Scenario planning is a
business analysis approach to identifying information exchanges and is the first phase in the IEPD
development methodology.

B2.15.2 Stage 2 - NIEM Requirements Analysis


In the case where inter-component or inter-agency information exchanges are being developed, two
NIEM products are required:
• NIEM Exchange Model – To be documented in the NIEM IEPD main document.
• NIEM Exchange Business Requirements - To be documented in the NIEM IEPD main document.

B2.15.3 Stage 3 - NIEM Map and Model


If NIEM IEPDs are being developed as a result of inter-component or inter-agency information exchanges
the following products should be completed as part of the NIEM Map and Model Phase:
• Domain Model

B-100 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
Sample Template and Guidance

• Component Mapping Template

B2.15.4 Stage 4 - NIEM IEPD Build and Validate / Assemble and Document
If a NIEM IEPD is being developed in support of a inter-component or inter-agency information exchange,
NIEM IEPD lifecycle activities and products prescribed in the Build and Validate and Assemble and
Document phases should be performed in this SELC phase. Those products include:
• Want list
• XML Schemas – exchange, subset, and exchange schemas
• IEPD Metadata
• Main IEPD document including packaged IEPD products as specified in previous phases
Please contact the DHS EDMO for the current list of DHS required NIEM IEPD products and an IEPD
main document outline.

B2.15.5 Stage 5 - NIEM IEPD Publish and Implement


Upon completion of the Development SELC phase and the Assemble and Document NIEM IEPD lifecycle
phase, the NIEM IEPD should be packaged and uploaded to the DHS Information Exchange Repository.
Details on how to package the IEPD and how to submit the IEPD to the DHS Information Exchange
Repository can be obtained from the DHS Enterprise Data Management Office (EDMO).

B2.16 SELC and the DHS Service Oriented Architecture (IT Only)
PMs and developers also need to consider the shift in the DHS architectural strategy from one based on
traditional development of IT systems to one based on an SOA, also referred to as Service Component
Based Architecture (SCBA). The impact of this change in strategy is that as DHS transitions to an SOA,
greater emphasis will be placed on service creation, reuse, and modification for reuse of established
service, with IT acquisitions increasingly being analyzed for compliance with SOA principles,
requirements, and technology during project authorization activities.

B2.16.1 SOA Definition


The HLS-EA Target Architecture, Version 2.0, describes the DHS approach to SOA and defines the new
architectural style for developing, maintaining, and enhancing IT systems:
The Homeland Security Application and Component Architecture is based on commercial
best practices and a new paradigm promoted by the Office of Management and Budget
(OMB) and the U.S. Chief Information Officer (CIO) Council: Service/Component-Based
Architecture. The benefit of Service/Component-Based Architecture is that it defines the
functionality of the applications by the services or capabilities provided to the users.
These services are made available through reusable software components generating
significant cost savings and facilitating information sharing and commonality.
Constructing applications is a matter of assembling components into groupings that
provide the capability required to satisfy a business need.
The Service/Component Based paradigm has many advantages for the Department.
Among these advantages are reduced user training, easily modified applications (plug
and play), reuse of components in multiple applications, and better interoperability of
applications. The capabilities needed to detect and respond to new mechanisms must be
highly adaptable. The Services/Component Based paradigm provides DHS with the
needed adaptability. 44

44
HLS-EA Target Architecture, Version 2.0, October 29, 2004.

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-101


11-05-08
Sample Template and Guidance

In the new architectural environment, DHS systems will consist of a set of loosely coupled services that
will be used internally and exposed externally to other DHS applications through a service registry
mediated by the DHS Enterprise Service Bus (ESB). The requirement for communication through the
ESB does not necessarily include communication between internal components of an application (e.g.,
direct API or SQL calls). DHS SELC Guide requirements reflect DHS architectural standards as well as
those required by other enterprise life cycle processes. In its role of supporting the evolution to SOA, the
DHS SELC Guide will focus more specifically on service creation and reuse. An artifact called the Service
Reuse Plan is required as an entry criterion to the DHS SELC. This plan documents what services a
project will create, modify, or reuse. For more information on DHS’s SOA vision and plan, the DHS
Service Oriented Architecture Framework defines how DHS plans to transition to a service oriented
architecture.

B2.16.2 Multiple Track Development for Services


The SELC Guide recommends the use of a multiple track approach for acquisitions that will build or
enhance SOA services. The first track is focused on the main system development effort, which includes
the following tasks:

• Designing and developing the core system capabilities


• Analyzing and selecting existing services to reuse on the project
The other tracks are focused on:

• Defining, developing, and deploying new or enhanced services into the DHS SOA with the primary
purpose of supporting the needs of the sponsoring project
• Defining, developing, and deploying the new or enhanced services with a secondary purpose of
supporting the needs of other/future systems
Acquisitions are encouraged to reuse existing services. However, if the existing service must be
enhanced, it is the requesting project’s responsibility to provide the funding for the enhancement. It is
important to note that acquisitions may consist of one, multiple, or no service development efforts. The
number of tracks will depend on the number of services the project needs to create or enhance. The intent
is that the primary project will break out the smaller service development efforts into separate
(sub-)projects that can be independently managed. It is expected that all IT acquisitions will leverage and
build toward the SOA, which means placing more emphasis on service reuse. The overall structure of the
Program into a set of projects as described in the Directive 102-01 may consider SOA (sub-)projects as
projects to be managed separately for purposes of the APB and the ARP depending on the size, cost,
schedule, distinctness and interdependencies of the services to be reused/enhanced or newly built.

B-102 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
Sample Template and Guidance

Attachment B3: Summary of Exit Criteria


The following table lists all the exit criteria for all SELC stages.

-- Under Development --

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-103


11-05-08
Sample Template and Guidance

Attachment B4: SELC Document Matrix

Table B4-1 lists the Governing Authority that represents the DHS organization or process that mandates
the development of the artifact, the associated DHS organization to contact for more information, and a
DHS website where more information can be found.

Table B4-1: Governing Authorities, DHS Organizations, and Websites


Governing DHS Organization
Website
Authority to Contact
ARP Chief Procurement
(Directive Office’s Acquisition
102-01) Program
Management Division
DHS EA CIO’s Office of https://interactive.dhs.gov/suite/personalization/grouppage.do?groupid=847
Process Applied Technology
(OAT)
DHS OAST CIO’s Office on https://dhsonline.dhs.gov/portal/jhtml/community.jhtml?community=
Accessible Systems MGMT&index=130&id=2025980011
and Technology
(OAST)
DHS CISO CIO’s Chief https://dhsonline.dhs.gov/portal/jhtml/community.jhtml?index=10&community=
Information Security MGMT&id=2002980003
Officer (CISO)
Privacy Office DHS Privacy Office http://www.dhs.gov/privacy
DHS CPIC CIO’s Enterprise https://dhsonline.dhs.gov/portal/jhtml/community.jhtml?community=MGMT&index=0&id=1
Business
Management Office
(EBMO)
DHS SELC CIO’s EBMO https://dhsonline.dhs.gov/portal/jhtml/community.jhtml?community=MGMT&index=
141&id=2036980003

Table B4-2 depicts the SELC products and their update schedule. Each artifact is marked in the
appropriate SELC stage as Create (C), Update (U), or Finalize (F). This indicates the status of each
artifact at each SELC stage and how it should mature throughout the life cycle.

B-104 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
Sample Template and Guidance

Table B4-2: Full Document Matrix


Governing ARP Phases
Authority

OBTAIN
ANALYZE/

PRODUCE
L

SUPPORT
DEPLOY/
SELECT
NEED
i
n
e
SELC Stages
N
Documents

Implementation
u

Requirements

Operations &
Development

Integration &

Maintenance
Engineering

Disposition
Definition
Planning
m

Solution

Design

Test
b
e
r
1 Mission Need Statement ARP (Dir C F
102-01)
2 Capability Development Plan ARP (Dir C/
(CDP) 102-01) F
3 Acquisition Plan ARP (Dir C U U U U
102-01)
4 CONOPS ARP (Dir 102-01) C/F
5 Analysis of Alternatives ARP (Dir 102-01) C/F
6 Lifecycle Cost Estimate (LCCE) ARP (Dir 102-01) C U U U
7 Operational Requirements Document (ORD) C/F
8 Integrated Logistics Support Plan (ILSP) C U
9 Acquisition Program Baseline ARP (Dir 102-01) C U U
1 Project Tailoring Plan DHS SELC C/F
0
1 Service Reuse Plan DHS SELC C U U U U U U F F
1
1 HLS EA Program Alignment DHS EA Process C U U U F F
2 Decision Request
1 Program Alignment Documentation Matrix C U U U F F
3
1 Map to Business Architecture DHS EA Process C U U U F F
4
1 Map to OCIO Portfolios DHS EA Process C U U U F F
5
1 Section 508 National Security DHS OAST C/F
6 Exception Determination
1 Critical Infrastructure Protection DHS CISO C F
7 Report
1 FIPS 199 Security Categorization DHS CISO C U
8
1 Preliminary Security Risk DHS CISO C/F
9 Assessment
2 Solution Engineering Review DHS SELC C/F
0 Approval Letter
2 Project Management Plan ARP (Dir 102-01) C U U U U U F F
1 (Includes Integrated Master
Schedule) (PMP)
2 Configuration Management Plan DHS SELC C F

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-105


11-05-08
Sample Template and Guidance

Governing ARP Phases


Authority

OBTAIN
ANALYZE/

PRODUCE
L

SUPPORT
DEPLOY/
SELECT
NEED
i
n
e
SELC Stages
N
Documents

Implementation
u

Requirements

Operations &
Development

Integration &

Maintenance
Engineering

Disposition
Definition
Planning
m

Solution

Design

Test
b
e
r
2
2 Privacy Threshold Analysis (PTA) Privacy Office C/
3 F
2 Section 508 EIT Accessibility DHS OAST C U U U U U F F
4 Plan
2 Risk Management Plan ARP (Dir 102-01) C/
5 F
2 Quality Assurance Plan DHS SELC C/
6 F
2 Data Management Plan DHS SELC C F
7
2 Training Plan DHS SELC C/
8 F
2 Project Planning Review DHS SELC C/
9 Approval Letter F
3 Functional Requirements DHS SELC C U U U U F F
0 Document (FRD)
3 Requirements Traceability Matrix DHS SELC C U U U U F F
1 (RTM)
3 Test and Evaluation Master Plan ARP (Dir 102-01) C U F
2 (TEMP)
Developmental Test Plan (DTP) ARP (Dir 102-01 C U F
3 Security Requirements DHS CISO C U F
3 Traceability Matrix (SRTM)
3 Plan of Action & Milestone DHS CISO C U U F
4 (POA&M)
3 System Security Plan (SSP) DHS CISO C U U U F
5
3 Contingency Plan DHS CISO U F
6
3 Disaster Recovery Plan DHS SELC C U F
7
3 Security Risk Assessment (SRA) DHS CISO C U F
8
3 Security Test & Evaluation DHS CISO C F
9 (ST&E) Plan
4 Map to the Data Architecture DHS EA Process C U U F F
0
4 Map to the Business Architecture DHS EA Process C U U F F
1

B-106 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
Sample Template and Guidance

Governing ARP Phases


Authority

OBTAIN
ANALYZE/

PRODUCE
L

SUPPORT
DEPLOY/
SELECT
NEED
i
n
e
SELC Stages
N
Documents

Implementation
u

Requirements

Operations &
Development

Integration &

Maintenance
Engineering

Disposition
Definition
Planning
m

Solution

Design

Test
b
e
r
4 Map to Technology Standards & Products C U U F F
2
4 System Definition Review DHS SELC C/F
3 Approval Letter
4 Service Level Agreements ARP (Dir 102-01) C U F F
4
4 System Requirements Document DHS SELC C U U U F F
5
4 Interconnection Security DHS CISO C/
6 Agreement (ISA) F
4 Logical Design Document DHS SELC C/
7 F
4 Data Architecture Document DHS SELC C/
8 F
4 System Design Document DHS SELC C U U F
9
5 Technology Insertion Decision Request C/
0 F
5 Site Prep Plan DHS SELC C/
1 F
5 Deployment Plan DHS SELC C/
2 F
5 Critical Design Review Approval DHS SELC C/
3 Letter F
5 Training Materials DHS SELC C/
4 F
5 Test Case Specification DHS SELC C/
5 F
5 System Acceptance Test DHS SELC C/
6 Procedures F
5 Test Readiness Review Approval DHS SELC C/
7 Letter F
5 Operators Manuals DHS SELC C F
8
5 Maintenance Manuals DHS SELC C F
9
6 User Manuals DHS SELC C F
0
6 System Test Report DHS SELC C/F

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-107


11-05-08
Sample Template and Guidance

Governing ARP Phases


Authority

OBTAIN
ANALYZE/

PRODUCE
L

SUPPORT
DEPLOY/
SELECT
NEED
i
n
e
SELC Stages
N
Documents

Implementation
u

Requirements

Operations &
Development

Integration &

Maintenance
Engineering

Disposition
Definition
Planning
m

Solution

Design

Test
b
e
r
1
6 Acceptance Test Report DHS SELC C/F
2
6 Section 508 Assistive Technology C/F
3 Interoperability Test Report
6 Service Insertion Package (SIP) DHS EA Process C U F F
4
6 Security Assessment Report DHS CISO C/F
5 (SAR)
6 Security Accreditation package DHS CISO C/F
6
6 Privacy Impact Assessment (PIA) Privacy Office C/F
7
6 DHS Periodic Reporting CPIC C U U U
8
6 Production Readiness Review DHS SELC C/F
9 Approval Letter
7 Pilot Results Report IRP (MD 1400) C/
0 F
7 Follow on Test Results IRP (MD 1400) C/
1 F
7 Version Description Document DHS SELC C/
2 F
7 Transition To Support Document DHS SELC C/
3 F
7 Critical Infrastructure Protection CIP C/
4 Report F
7 System of Record Notice (SORN) DHS Privacy C/
5 F
7 Authority To Operate (ATO) DHS CISO C/
6 Letter F
7 Operational Readiness Review DHS SELC C/
7 Approval Letter F
7 Performance Reports IRP (MD 1400) U U
8
7 Post Implementation Review (PIR) Results U U
9
8 Disposal Plan DHS SELC C/F C/
0 F

B-108 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
Sample Template and Guidance

Governing ARP Phases


Authority

OBTAIN
ANALYZE/

PRODUCE
L

SUPPORT
DEPLOY/
SELECT
NEED
i
n
e
SELC Stages
N
Documents

Implementation
u

Requirements

Operations &
Development

Integration &

Maintenance
Engineering

Disposition
Definition
Planning
m

Solution

Design

Test
b
e
r
8 DHS Periodic Reporting CPIC U U
1
8 Operational Analyses CPIC U U
2
8 Lessons Learned CPIC U U
3
8 FISMA metrics reports DHS CISO U U
4
8 Security Incident reports DHS CISO U U
5
8 C&A Updates (every 3 years or when major U U
6 change is made)
8 Privacy Documentation (updated for systems U U
7 decommissioned)
8 Disposition Approval Request DHS SELC C/
8 F
8 Disposition Plan DHS SELC C/
9 F
9 Archived Data DHS SELC C/
0 F
9 Archived System DHS SELC C/
1 F

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-109


11-05-08
Sample Template and Guidance

Attachment B5- Acronyms

ANSI American National Standards Institute


APB Acquisition Program Baseline
API Application Programming Interface
ATO Authority to Operate
BCP Business Continuity Planning
BIA Business Impact Assessment
BRM Business Reference Model
C Create
C&A Certification and Accreditation
CCB Change Control Board
CDD Capability Development and Demonstration
CDM Conceptual Data Model
CDR Critical Design Review
CFO Chief Financial Officer
CFR Code of Federal Regulations
CI Configurable Item
CIO Chief Information Officer
CIP Critical Infrastructure Protection
CISO Chief Information Security Officer
CM Configuration Management
CMMI Capability Maturity Model Integrated
CONOPS Concept of Operations
COOP Continuity of Operations Plan
COTS Commercial Off-the-Shelf
CPIC Capital Planning and Investment Control
CPO Chief Privacy Officer
CTD Concept and Technology Development
DAA Designated Accrediting Authority
DHS Department of Homeland Security
DR Decision Request
DRM Data Reference Model
DT Developmental Test
DTP Developmental Test Plan
EA Enterprise Architecture
EAB Enterprise Architecture Board
EBMO Enterprise Business Management Office
EIA Electronic Industries Alliance
EIT Electronic Information Technology
EOA Early Operational Assessment
ESB Enterprise Service Bus
EVM Earned Value Management
F Finalize
FAR Federal Acquisition Regulation
FBRM Federal Business Reference Model
FEA Federal Enterprise Architecture
FIPS Federal Information Processing Standards
FRD Functional Requirements Document
FYHSP Future Years Homeland Security Program
GSAM Guidelines for Successful Acquisition and Management
HFE Human Factors Engineering
HFES Human Factors and Ergonomics Society
HFS Human Factors Society

B-110 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
Sample Template and Guidance

HLS Homeland Security


HR Human Resources
HSPD Homeland Security Presidential Directive
IDE Integrated Development Environment
IEC International Engineering Consortium
IEEE Institute of Electrical and Electronics Engineers
IEPD Information Exchange Package Description
IPG Integrated Programming Guidance
IPT Integrated Project Team
IRB Investment Review Board
ARP Investment Review Process
ISA Interconnection Security Agreement
ISO International Organization for Standardization
ISO/TR International Organization for Standardization/Technical Report
ISSM Information Systems Security Manager
ISSO Information System Security Officer
IT Information Technology
IV&V Independent Verification and Validation
JRC Joint Requirements Council
LCCE Life Cycle Cost Estimate
LDM Logical Data Model
MBA Masters of Business Administration
MD Management Directive
MDP Milestone Decision Point
MNS Mission Needs Statement
MOA Memorandum of Agreement
MOU Memorandum of Understanding
N/A Not Applicable
NARA National Archives and Record Administration
NCSD National Cyber Security Division
NIEM National Information Exchange Model
NIST National Institute of Standards and Technology
NPG NASA Procedures and Guidelines
O&M Operations and Maintenance
O&S Operations and Support
OAST Office on Accessible Systems and Technology
OAT Office of Applied Technology
OCIO Office of the Chief Information Officer
OCM Organizational Change Management
OGC Office of General Counsel
OMB Office of Management and Budget
OT Operational Test
ORD Operational Requirement Document
ORR Operational Readiness Review
P&D Production and Development
P.L. Public Law
PA&E Program Analysis and Evaluation
PADRT Program Assessment and Design Review Team
PAR Project Authorization Review
PART Program Assessment Rating Tool
PDM Physical Data Model
PDR Preliminary Design Review
PfM IT Portfolio Manager
PIA Privacy Impact Assessment
PII Personally Identifiable Information
PIR Post Implementation Review

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-111


11-05-08
Sample Template and Guidance

PM Project Manager
PMBOK Project Management Body of Knowledge
PMI Project Management Institute
PMO Project Management Office
PMP Project Management Plan, Project Management Professional
POA&M Plan of Action and Milestones
PPBE Planning, Programming, Budgeting and Execution
PPR Project Planning Review
PRR Production Readiness Review
PTA Privacy Threshold Assessment
QA Quality Assurance
RA Risk Assessment
RAD Rapid Application Development
RAP Resource Allocation Plan
RTM Requirements Traceability Matrix
SAR Security Assessment Report
SBU Sensitive But Unclassified
SCBA Services and Components Based Architectures
SDLC System Development Life Cycle
SDR System Definition Review
SEI Software Engineering Institute
SIP Service Insertion Package
SLA Service Level Agreement
SELC Systems Engineering Life Cycle
SME Subject Matter Expert
SO System Owner
SOA Service Oriented Architecture
SORN System of Records Notice
SP Standards Profile
SQL Structured Query Language
SRA Security Risk Assessment
SRD System Requirements Document
SRM Service Reference Model
SRTM Security Requirements Traceability Matrix
SSP System Security Plan
ST&E Security Test and Evaluation
TEMP Test and Evaluation Master Plan
TI Technical Insertion
TRR Test Readiness Review
U Update
U.S.C. U.S. Code
URL Uniform Resource Locator
V&V Validation and Verification
VDD Version Description Document
WBS Work Breakdown Structure

B-112 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
Sample Template and Guidance

Attachment B6 - Glossary

Acceptance Testing Testing conducted in a simulated operational environment to determine whether a


system satisfies its acceptance criteria (i.e., initial requirements and current needs
of its user) and to enable the customer to determine whether to accept the system.
(Per IEEE Std 1012-1998)
Acquisition The conceptualization, initiation, design, development, testing, contracting,
production, deployment, support, modification, and disposal of systems, supplies,
or services (including construction) to satisfy agency needs.
“Acquisition” means the acquiring by contract with appropriated funds of supplies
or services (including construction) by and for the use of the Federal Government
through purchase or lease, whether the supplies or services are already in
existence or must be created, developed, demonstrated, and evaluated.
Acquisition begins at the point when agency needs are established and includes
the description of requirements to satisfy agency needs, solicitation and selection
of sources, award of contracts, contract financing, contract performance, contract
administration, and those technical and management functions directly related to
the process of fulfilling agency needs by contract. [Federal Acquisition Regulation]
Acquisition Planning Preparing, developing, or acquiring the information to be used to design a project;
assess the benefits, risks, and risk-adjusted life-cycle cost of alternative solutions;
and establish realistic cost, schedule, and performance goals for the selected
alternative, before proceeding to full acquisition of the capital project or useful
segment or terminating the project. Planning must progress to the point of
commitment to achieving specific goals for the completion of the acquisition.
Information-gathering activities may include market research of available solutions,
architectural drawings, geological studies, environmental planning, environmental
and safety studies, engineering and design studies, and prototypes. Planning is a
useful segment of capital investment. Depending on the nature of the project, one
or more planning segments may be necessary [OMB Circular No. A-11].
“Acquisition planning” means the process by which the efforts of all personnel
responsible for an acquisition are coordinated and integrated through a
comprehensive plan for fulfilling the agency need in a timely manner and at a
reasonable cost. It includes developing the overall strategy for managing the
acquisition. [Federal Acquisition Regulation]
Acquisition Program The APB establishes the project’s performance requirements, schedule
Baseline (APB) requirements, and estimate of total acquisition cost. APB parameter values shall
represent the project as it is expected to be produced or deployed. In the case of
an evolutionary acquisition strategy, the APB shall include parameters for the next
phase and, if known, for follow-on phases. The APB will contain parameters that, if
not met, will require the IRB to reevaluate the project and consider alternative
project concepts or design approaches. APB parameters are typically established
for each useful segment, as well as for the program as a whole, and mirror the
objectives in the Future Years Homeland Security Program (FYHSP) and the
Program Assessment Rating Tool (PART).
Application A set of routines, protocols, and tools for building software applications. A good
Programmable API makes it easier to develop a program by providing all the building blocks. A
Interface (API) programmer puts the blocks together. (Per Services and Components Based
Architectures [SCBA], version 3.5)
Baseline A formally approved version of a configuration item, regardless of media, formally
designated and fixed at a specific time during the configuration item’s life cycle.
(Per ISO/IEC 12207)

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-113


11-05-08
Sample Template and Guidance

Baseline Goals Baseline cost, schedule, and performance goals are the standard against which
actual work is measured. They are the basis for the annual report to the Congress
required by the Federal Acquisition Streamlining Act Title V on variances of 10
percent or more from cost and schedule goals and any deviation from
performance goals. OMB must approve the goals and any changes to the goals.
The baseline cost and schedule goals should be realistic projections of total cost,
total time to complete the project, and interim cost and schedule goals. The interim
cost and schedule goals should be based on the value of work performed or a
comparable concept. The performance goals should be realistic assessments of
what the acquisition is intended to accomplish, expressed in quantitative terms if
possible.
Business Continuity Per National Institute of Standards and Technology (NIST) SP 800-34: “The
Planning (BCP) documentation of a predetermined set of instructions or procedures that describe
how an organization’s business functions will be sustained during and after a
significant disruption.”
Business Reference Per OMB Circular A-11, Business Reference Model (BRM) is a function-driven
Model framework used to describe the lines of business and sub-functions performed by
the Federal Government independent of the agencies performing them. IT
investments are mapped to the BRM to identify collaboration opportunities.
Business A requirement that outlines the procedures and information flows, the proposed
Requirement changes to those procedures, the user’s assessment of information needs, a
preliminary description of the desired system, and an outline of the user’s
acceptance requirements.
Capital Planning and A decision-making process for ensuring that investments integrate strategic
Investment Control planning, architecture, security, budgeting, procurement, and the management of
the investment in support of agency missions and business needs. The term
comes from the Clinger-Cohen Act of 1996; while originally focused on IT, it now
applies also to non-IT investments (OMB Circular No. A-11).
Certification and Per OMB Circular A-11, Certification and Accreditation (C&A) is a comprehensive
Accreditation assessment of the management, operational, and technical security controls in an
information system, made in support of security accreditation, to determine the
extent to which the controls are implemented correctly, operating as intended, and
producing the desired outcome with respect to meeting the security requirements
of the system.
Component All the entities that directly report to the Office of the Secretary, which includes the
(organizational) Secretary, Deputy Secretary and his or her staff, Chief of Staff and his or her staff,
and Counselors and their staff. See Management Directive 0010.2.
Component (as An independently deployable unit of software that exposes its functionality through
related to services) a set of services accessed via well-defined interfaces. A component is based on a
component standard, is described by a specification, and has an implementation.
Components can be assembled to create applications or larger-grained
components. (Per SCBA)
Component Based An architecture process that enables the design of enterprise solutions using pre-
Architecture manufactured components. The focus of the architecture may be a specific project
or the entire enterprise. This architecture provides a plan of what needs to be built
and an overview of what has been built already. (Per SCBA. v3.5)

B-114 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
Sample Template and Guidance

Conceptual Data An abstract representation to illustrate overall structure of organization data by


Model (CDM) identifying entity types and the relationships between them independent of any
database management system or other implementation considerations. The
Conceptual Data Model serves as the common foundation for normalizing data
access across the enterprise to support improved data sharing. The Conceptual
Data Model satisfies two main objectives: (1) to provide common vocabulary of
across the enterprise and (2) to provide understanding of the fundamental (data)
structure of the enterprise.
Configuration Item An entity within a configuration that satisfies an end use function and that can be
uniquely identified at a given reference point. (Per ISO/IEC 12207)
Configuration A management process for establishing and maintaining consistency of a
Management product’s performance, functional, and physical attributes with its requirements,
design, and operational management information throughout its life. (Per
ANSI/EIA-649)
Continuity of Per NIST SP 800-34: “A predetermined set of instructions or procedures that
Operations Plan describe how an organization’s essential functions will be sustained for up to 30
(COOP) days as a result of a disaster event before returning to normal operations.”
Control Phase Capital planning phase that requires ongoing monitoring of information technology
investments against schedules, budgets, and performance measures.
Customer An individual, organization, or enterprise that (1) commissions the engineering of a
system; (2) is a prospective purchaser of the end products of a system, or portions
thereof; or (3) is an acquirer of a product. (Per ANSI/EIA-632-1998)
Data A value or set of values, representing a specific concept or concepts in a formalized
manner, suitable for communication, interpretation, or processing by humans or by
automatic means. Data becomes “information” when analyzed and possibly
combined with other data in order to extract meaning, and provide context. The
meaning of data can vary according to its context.
Data Architecture Architectural framework for how data is stored, managed, and used in a system. It
describes how data is persistently stored, how components and processes
reference and manipulate this data, how external/legacy systems access the data,
interfaces to data managed by external/legacy systems, implementation of
common data operations. Data architecture establishes common guidelines for
data operations that make it possible to predict, model, gauge, and control the flow
of data in the system. (Carnegie Mellon Software Engineering Institute)
Data Asset A managed container for data; examples include relational database, Web site,
document repository, directory or data service. (FEA DRM 2.0)
Data Exchange Categorization of information being exchanged between one or more parties; such
as the regular exchange of environment testing data among federal, state, local,
and tribal entities. (FEA DRM 2.0)
Data Model A graphic and/or lexical representation of the data and information required to
support the operation of any set of business processes and/or the systems used to
automate them (based on FEA DRM 2.0). A description of the organization of data
in a manner that reflects an information structure; (ISO 11179-1). A representation
of data, specifying their properties, structure and inter-relationships; (ISO 11179-
3). A model that describes in an abstract way how data is represented in a
business organization, an information system, or a database management system.

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-115


11-05-08
Sample Template and Guidance

Data Reference A representational framework whose primary purpose is to enable information


Model (DRM) sharing and reuse across all levels of the government via the standard description
and discovery of common data and the promotion of uniform data management
practices. A Data Reference Model (DRM) is one of the five reference models of
the Federal Enterprise Architecture (FEA).
Acquisition Decision A predetermined point within the acquisition lifecycle phases at which the
Event investment will undergo a review prior to commencement of the next phase.
Deliverable An item agreed to be delivered to an acquirer as specified in an agreement. This
item can be a document, a hardware item, a software item, a service, or any type
of work product. (Per ANSI/EIA-632-1998)
Development The action by which a set of requirements is translated into a solution definition for
a set of products that satisfy stakeholders. (Per ANSI/EIA-632-1998)
Developmental Test Any testing used to assist in the development and maturation of products, product
elements, or manufacturing or support processes. Also any engineering-type test
used to verify that design risks are minimized, substantiate achievement of
contract technical performance, and certify readiness for Operational Testing.
Earned Value A management methodology for integrating scope of work with schedule and cost
Management elements for optimum investment planning and control.
A project (investment) management tool effectively integrating the investment
scope of work with schedule and cost elements for optimum investment planning
and control. The qualities and operating characteristics of earned value
management (EVM) systems are described in American National Standards
Institute/Electronic Industries Alliance (ANSI/EIA) Standard -748-A-1998, Earned
Value Management Systems, approved May 19, 1998. It was reaffirmed on August
28, 2002.
E-Government Per the E-Government Act of 2002, the term “electronic Government” means the
use by the Government of web-based Internet applications and other information
technologies, combined with processes that implement these technologies, to:
(a) enhance the access to and delivery of Government information and services to
the public, other agencies, and other Government entities; or
(b) bring about improvements in Government operations that may include
effectiveness, efficiency, service quality, or transformation.
Electronic Records Electronic, or machine-readable records, are records on electronic storage media
(A Glossary for Archivists, Manuscript Curators, and Records Managers, Society of
American Archivists: Chicago, 1992 p. 12). Electronic record, as defined in NARA
regulations (36 CFR 1234.2), means any information that is recorded in a form that
only a computer can process and that satisfies the definition of a Federal record per
the Federal Records Act definition supplied above. Federal electronic records are
not necessarily kept in a “recordkeeping system” but may reside in a generic
electronic information system or are produced by an application such as word
processing or electronic mail.
Electronic Records Electronic records management is using automated techniques to manage records
Management regardless of format. Electronic records management is the broadest term that
refers to electronically managing records on varied formats, be they electronic,
paper, microform, etc.
Enterprise Service An enterprise integration architecture that allows incremental integration driven by
Bus business requirements, not technology limitations. (Per SCBA, v3.5)

B-116 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
Sample Template and Guidance

Evaluate Phase Capital planning phase that requires information technology investments to be
reviewed once they are operational to determine whether the investments meet
expectations.
Evaluation A systematic determination of the extent to which an entity meets its specified
criteria. (Per ISO/IEC 12207)
Environment (1) The natural conditions (weather, climate, ocean conditions, terrain, vegetation,
dust, etc.) and induced conditions (electromagnetic interference, heat, vibration,
etc.) that constrain the design definitions for end products and their enabling
products.
(2) External factors affecting an enterprise or project.
(3) External factors affecting development tools, methods, or processes. (Per
ANSI/EIA-632-1998)
Exhibit 300 Business Exhibit 300 business cases are also referred to as capital asset plans. They are
Case required by OMB Circular A-11 and provide budget justification and reporting
requirements for investments. They provide agencies with the format to report on
the budgeting, acquisition, and management of federal capital assets.
Exhibit 53 Exhibit 53s are also referred to as agency IT investment portfolios. They are
required by OMB Circular A-11 and provide summary budget information for all
agency major and non-major IT investments.
Exit Criteria (per Project-specific accomplishments that must be demonstrated satisfactorily before a
Directive 102-01) project can either progress further in the current acquisition phase or transition to
the next acquisition phase. Exit criteria are normally selected to track progress in
important technical, schedule, or management risk areas. Exit criteria shall serve as
gates that, when successfully passed or exited, demonstrate that the project is on
track to achieve its final goals and should be allowed to continue with additional
activities within an acquisition phase or be considered for continuation into the next
acquisition phase. Exit criteria include some level of demonstrated performance
outcome (e.g., level of engine thrust), the accomplishment of some process at
some level of efficiency (e.g., manufacturing yield), the successful accomplishment
of some event (e.g., first flight), or some other criterion (e.g., establishment of a
training program or inclusion of a particular clause in the follow on contract) that
indicates that the particular aspect of the project is progressing satisfactorily.
Federal Enterprise Federal Enterprise Architecture (FEA) is a business-based framework for
Architecture government-wide improvement. It describes the relationship between business
functions and the technologies and information supporting them. The FEA is being
constructed through a collection of interrelated “reference models” designed to
facilitate cross-agency analysis and the identification of duplicative investments,
gaps, and opportunities for collaboration within and across federal agencies. More
information about the FEA reference models is available at http://www.egov.gov.
Financial System Per OMB Circular A-127, the term “financial system” means an information
system, comprised of one or more applications, that is used for any of the
following:
• collecting, processing, maintaining, transmitting, and reporting data about
financial events;
• supporting financial planning or budgeting activities;
• accumulating and reporting cost information; or
• supporting the preparation of financial statements.

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-117


11-05-08
Sample Template and Guidance

Functional A requirement that defines what system products must do and their desired
Requirement behavior in terms of an effect produced, or an action or service to be performed.
(Per ANSI/EIA-632-1998)
Independent Verification and Validation processes performed by an organization with a
Verification and specified degree of technical, managerial, and financial independence from the
Validation (IV&V) development organization. (Per IEEE Std 1012-1988)
Information Security’ Per FISMA, the term “information security” means protecting information and
information systems from unauthorized access, use, disclosure, disruption,
modification, or destruction in order to provide:
(A) Integrity, which means guarding against improper information modification or
destruction, and includes ensuring information non-repudiation and authenticity;
(B) Confidentiality, which means preserving authorized restrictions on access and
disclosure, including means for protecting personal privacy and proprietary
information; and
(C) Availability, which means ensuring timely and reliable access to and use of
information.
Information System Per OMB Circular A-130: The term “information system” means a discrete set of
information resources organized for the collection, processing, maintenance,
transmission, and dissemination of information, in accordance with defined
procedures, whether automated or manual.
Information Any equipment or interconnected system(s) or subsystem(s) of
Technology equipment/software, or any national security system, that is used in the automatic
acquisition, storage, manipulation, management, movement, control, display
(including geospatial technologies), switching, interchange, transmission (wired or
wireless telecommunications), or reception of data, voice, video, or information by
an executive agency. For purposes of this definition, equipment is used by DHS if
the equipment is used by DHS directly or is used by DHS organizational partners
(including other federal agencies, state and local governments and private
contractors) under a contract with DHS which (a) requires the use, to a significant
extent, of such equipment in the performance of a service or the furnishing of a
product. The term IT includes computers; ancillary equipment (including imaging
peripherals, input, output, and storage devices necessary for security and
surveillance); peripheral equipment designed to be controlled by the central
processing unit of a computer, software; firmware and similar procedures; services
(including support services); and related resources. The term IT does not include
any equipment that is acquired by a contractor incidental to a contract or any
equipment that contains imbedded IT that is used as an integral part of the
product, but the principal function of which is not the acquisition, storage, analysis,
evaluation, manipulation, management, movement, control, display, switching,
interchange, transmission, or reception of data or information. For example,
heating, ventilation, and air conditioning equipment, such as thermostats or
temperature control devices, and medical equipment for which IT is integral to
operation, are not IT [Federal Acquisition Regulation 2.101]. The EAB will review
all IT investments, including any investments categorized as non-IT on the E300
but that contain IT components.
Integrated Project A multi-disciplinary team led by a PM responsible and accountable for planning,
Team budgeting, procurement and life-cycle management of the investment to achieve
its cost, schedule and performance goals. Team skills include budgetary, financial,
capital planning, procurement, user, program, architecture, earned value
management, security, and other staff as appropriate. An IPT may include
members from both government (including a contracting officer) and industry, after
award.

B-118 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
Sample Template and Guidance

Integration Testing An orderly progression of testing of incremental pieces of the software program in
which software elements, hardware elements, or both are combined and tested
until the entire system has been integrated to show compliance with the program
design, and capabilities and requirements of the system. (Per IEEE Std 1012-
1988)
Integrity Per FIPS Publication 199, the term “integrity” refers to guarding against improper
information modification or destruction, and includes ensuring information non-
repudiation and authenticity. [44 U.S.C., SEC. 3542]
Interoperability Ability of systems, personnel, and equipment to provide and receive functionality,
data, information, and/or services to and from other systems, personnel, and
equipment, between both public and private agencies, departments, and other
organizations, in a manner enabling them to operate effectively together.
Investment DHS cost, outlays or expenditure to achieve goals and objectives that results in
the acquisition and/or sustainment of a needed capability (including processes) for
furthering the DHS mission. Examples of investments are expenditures for
personnel, research and development (R&D), capital assets, information
technology (IT), service, operational and maintenance, and decommissioning and
disposal of replaced systems. Investment decisions are a balance of requirements,
risks, and funding. Investment decisions spur and guide acquisition and
contracting decisions and baselines. DHS has categorized major investments as
Levels 1 and 2 and Level 3 IT.
Interoperability Per the E-Government Act of 2002, the term “interoperability” means the ability of
different operating and software systems, applications, and services to
communicate and exchange data in an accurate, effective, and consistent manner.
Life Cycle Cost The total cost to the Federal government of acquiring, operating, supporting, and,
if applicable, disposing of the items being acquired [FAR 7.101]; the sum of all
costs over the useful life of a building, system, or product; the sum total of the
direct, indirect, recurring, nonrecurring, and other related costs incurred or
estimated to be incurred in the design, development, production, operation,
maintenance, support, and final disposition of a major system over its anticipated
useful life span and salvage (resale) value, if any [FAR 52.248-2(b)]. Where
system or project planning anticipates the use of existing sites or facilities,
restoration and refurbishment costs should be included [OMB Circular A-94,
Appendix A].
Life Cycle Model A framework containing the processes, activities, and activities involved in the
development, operation, and maintenance of a software product, spanning the life
of the system from the definition of its requirements to the termination of its use.
(Per ISO/IEC 12207)
Logical Data Model A graphical representation of the information requirements of a business area at a
(LDM) more granular level than a Conceptual Data Model and includes data objects and
their interrelationships. The Logical Data Model contains objects and elements
expressed in business terms and is the basis for developing physical data models.
Major Information Per OMB Circular A-130, the term “major information system” means an
System information system that requires special management attention because of its
importance to an agency mission; its high development, operating, or maintenance
costs; or its significant role in the administration of agency programs, finances,
property, or other resources.
Major Investment At DHS, major investments include all Level 1 and 2 investments, as well as Level
3 IT investments in accordance with the investment thresholds defined in Directive
102-01.

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-119


11-05-08
Sample Template and Guidance

Metadata The information that is stored as the description of a unique piece of data and all
the properties associated with it.
Monitoring An examination of the status of the activities of a supplier and of their results by
the acquirer or a third party. (Per ISO/IEC 12207)
National Information A Federal, State, Local and Tribal interagency initiative providing a foundation for
Exchange Model seamless information exchange. It leverages the data exchange standards efforts
(NIEM) successfully implemented by the Global Justice Information Sharing Initiative
(Global) and extends the Global Justice XML Data Model (GJXDM) to facilitate
timely, secure information sharing across the whole of the justice, public safety,
emergency and disaster management, intelligence, and homeland security
enterprise. NIEM was launched on February 28, 2005, through a partnership
agreement between the U.S. Department of Justice (DOJ) and the U.S.
Department of Homeland Security (DHS) and signed by Chief Information Officers.
National Security Per OMB Circular A-130, the term “national security system” means any
System telecommunications or information system operated by the United States
Government, the function, operation, or use of which (1) involves intelligence
activities; (2) involves cryptologic activities related to national security; (3) involves
command and control of military forces; (4) involves equipment that is an integral
part of a weapon or weapons system; or (5) is critical to the direct fulfillment of
military or intelligence missions, but excluding any system that is to be
administrative and business applications (including payroll, finance, logistics, and
personnel management applications).
Non-Functional Non-functional requirements are requirements which specify criteria that can be
Requirement used to judge the operation of a system, rather than specific behaviors. This
should be contrasted with functional requirements that specify specific behavior or
functions. Typical non-functional requirements are reliability, scalability, availability,
and cost.
Operational Per OMB Circular, A-11, operational (steady state) means an asset or a part of an
asset with a delivered component performing the mission.
Operational Analysis Operational analysis is a method of examining the ongoing performance of an
operating asset investment and measuring that performance against an
established set of cost, schedule, and performance goals. An operational analysis
is, by nature, less structured than performance reporting methods applied to
developmental projects and should trigger considerations of how the investment's
objectives could be better met, how costs could be reduced, and whether the
organization should continue performing a particular function. [OMB Circular A-11]
Basically, operational analysis is used to examine whether an investment in
Operations and Maintenance still meets its intended objectives and yields
expected benefits. See the DHS Operational Analysis Guidance for more
information.
Operational Scenario A sequence of events expected during operation of system products. Includes the
environmental conditions and usage rates as well as expected stimuli (inputs) and
responses (outputs). (Per ANSI/EIA-632-1998)
Operational Test The field test performed under realistic conditions, overseen and evaluated by an
activity independent from the agency developer and user organizations, of any
system or key component of a system for the purposes of determining the
effectiveness and suitability of that system or component when used by typical
users in the expected operating environment.

B-120 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
Sample Template and Guidance

Periodic Reporting A DHS reporting process for major investments that establishes communication
among investment Program Managers, DHS Component senior leadership, and
DHS oversight entities regarding the health and status of major DHS investments.
The information provided via Periodic Reporting enables DHS to provide oversight
and to ensure compliance with Department and OMB requirements, along with
preparing required reports related to the OMB Information Technology High Risk
Template and the President’s Management Agenda e-Government initiative.
Performance A requirement that defines how well the system products are required to perform a
Requirement function, along with the conditions under which the function is performed. (Per
ANSI/EIA-632-1998)
Personally Identifiable The term “personally identifiable information” or “PII” means any information that
Information permits the identity of an individual to be directly or indirectly inferred, including
any other information which is linked or linkable to that individual regardless of
whether the individual is a U.S. Citizen, Legal Permanent Resident, or a visitor to
the U.S.
Physical Data Model A representation of a data design which takes into account the facilities and
(PDM) constraints of a given database management system. It is typically derived from
the Logical Data Model and may include all the database products required to
create relationships between tables or achieve performance goals, such as
indexes, constraint definitions, linking tables, partitioned tables or clusters. At this
level, the data modeler specifies how the logical data model will be realized in the
database schema (Conceptual, Logical, and Physical Data Models).
Planning Preparing, developing or acquiring the information used to: design the investment;
assess the benefits, risks, and risk-adjusted life-cycle costs of alternative solutions;
and establish realistic cost, schedule, and performance goals, for the selected
alternative, before either proceeding to full acquisition of the capital project
(investment) or useful segment or terminating the investment. Planning must
progress to the point where the project is ready to commit to achieving specific
goals for the completion of the acquisition before preceding to the acquisition
phase. Information gathering activities may include market research of available
solutions, architectural drawings, geological studies, engineering and design
studies, and prototypes. Planning is a useful segment of a capital project
(investment). Depending on the nature of the investment, one or more planning
segments may be necessary.
Plan of Action and As defined in OMB Memorandum 02-01, a plan of action and milestones
Milestones (POA&M), also referred to as a corrective action plan, is a tool that identifies
activities that need to be accomplished. It details resources required to accomplish
the elements of the plan, any milestones in meeting the task, and scheduled
completion dates for the milestones. The purpose of the POA&M is to assist
agencies in identifying, assessing, prioritizing, and monitoring the progress of
corrective efforts for security weaknesses found in programs and systems.
Portfolio Management The management of broad categories of investments linked by their relationship to
the mission to ensure effective performance, correspondence to the DHS EA,
minimization of overlapping functions, and proper funding.
Post-Implementation Evaluation of the investment after it has been fully implemented or terminated to
Review determine whether the targeted outcome (e.g., performance measures) of the
investment has been achieved.
Pre-Select Phase Capital planning phase that provides a process to assess whether information
technology investments support strategic and mission needs.

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-121


11-05-08
Sample Template and Guidance

Privacy Impact Per OMB Circular A-11, Privacy Impact Assessment (PIA) is a process for
Assessment examining the risks and ramifications of using information technology to collect,
maintain and disseminate information in identifiable form from or about members
of the public, and for identifying and evaluating protections and alternative
processes to mitigate the impact to privacy of collecting such information.
Program The totality of activities directed to accomplish specific goals and objectives, which
may provide new or improved capabilities in response to approved requirements
and/or sustain existing capabilities, and which may have multiple projects to obtain
specific capability requirements or capital assets. A Program is funded by one or
more Investments.
Program Manager The responsible agency customer, who, with significant discretional authority, is
uniquely empowered to make final scope-of-work, capital-investment, and
performance acceptability decisions and who is responsible for accomplishing
program objectives or production requirements through the acquisition of any mix
of in-house, contract, or reimbursable support resources. The Program Manager is
responsible for management and oversight of the IPT.
Project A planned undertaking with a definite beginning, objective and ending. A project
involves the definition, acquisition, and fielding of a unique product, service or
result in accordance with specified resources and requirements. A project may be
the whole or a part of a Program, and is funded by those Investments related to
the Program. A project is a basic building block related to a program that is
individually planned, approved, and managed. All investment elements with a start
and end date and producing a defined capability are considered projects.
Project Manager A project manager (PM) is the official assigned responsibility for accomplishing a
specifically designated unit of work effort established to achieve stated or
designated objectives, defined tasks, or other units of related effort on a schedule
and in support of the program mission. The project manager is responsible for the
planning, controlling, and reporting of the project, and for the management of a
specific function or functions, performance of the schedule, formulation of the
budget, and execution of the approved budget. The project manager works
closely with the Program Manager to ensure project objectives meet program
objectives.
Prototype A model (physical, electronic, digital, analytical, etc.) of a product built for the
purpose of a) assessing the feasibility of a new or unfamiliar technology; b)
assessing or mitigating technical risk; c) validating requirements; d) demonstrating
critical features; e) verifying a product; f) validating a product; g) determining
enabling product readiness; h) characterizing performance or product features; or
i) discovering physical principles. (Per ANSI/EIA-632-1998)
Qualification The process of demonstrating whether an entity is capable of fulfilling specified
requirements. (Per ISO/IEC 12207)
Quality Assurance All the planned and systematic activities implemented within the quality system,
and demonstrated as needed, to provide adequate confidence that an entity will
fulfill requirements for quality. (Per ISO/IEC 12207)
Registry A database providing information describing and categorizing objects, but which
does not contain the objects themselves. Registries usually provide information as
to how to access the object they describe. For example, a “Service Registry”
provides information on services. (Per SCBA, v3.5)
Release A particular version of a configuration item that is made available for a specific
purpose (for example, test release). (Per ISO/IEC 12207)

B-122 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
Sample Template and Guidance

Requirement (1) Something that governs what, how well, and under what conditions a product
will achieve a given purpose.
(2) Normative elements that govern implementation of this Standard, including
certain documents such as agreements, plans, or specifications. (Per ANSI/EIA-
632-1998)
Resource Allocation The Secretary’s formal approval of Components’ RAPs. Resource Allocation
Decision Decisions set resource allocation targets for Components for the FYHSP and
become the basis for the budget.
Resource Allocation In the programming phase of the PPBE, the Components annually develop
Plan (RAP) proposed programs consistent with the IPG. These programs, expressed in the
RAP, reflect systematic allocation of resources required to achieve missions,
objectives, and priorities, and potential alternative methods of accomplishing them.
Resource requirements reflected in RAPs are translated into time-phased funding
requirements. RAPs must account for long-term requirements and resources
including human capital, construction and investments, operating and
maintenance, and potential disposal or termination costs, and program
performance goals.
Reuse Any use of a preexisting software artifact (component, specification, etc). in a
context different from that in which it was created. (Per SCBA, v3.5)
Risk Management An organized process for identifying and assessing risks and for implementing
means to avoid them or mitigate their effect if they occur. (Per ANSI/EIA-632-
1998)
Security Category Per FIPS Publication 199, the characterization of information or an information
system based on an assessment of the potential impact that a loss of
confidentiality, integrity, or availability of such information or information system
would have on organizational operations, organizational assets, or individuals.
Security Controls Per FIPS Publication 199, the term “security controls” refers to the management,
operational, and technical controls (i.e., safeguards or countermeasures)
prescribed for an information system to protect the confidentiality, integrity, and
availability of the system and its information.
Select Phase Capital planning phase used to identify all new, ongoing, and operational
investments for inclusion into the agency’s investment portfolio(s).
Service Discrete unit of functionality that can be requested (provided a set of preconditions
is met), performs one or more operations (typically applying business rules and
accessing a database), and returns a set of results to the requester. Completion of
a service always leaves business and data integrity intact. (Per SCBA, v3.5)
Service Component A self-contained business process or service with predetermined and well-defined
functionality that may be exposed through a well defined and documented
business or technology interface.
Well-designed Service Components are “loosely coupled” and collaborate primarily
by exchanging messages. (Per SCBA, v3.5)

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-123


11-05-08
Sample Template and Guidance

Services and Services and Components Based Architecture (SCBA) leverages the Federal
Components Based Enterprise Architecture (FEA) and builds upon the concepts, principles, and
Architecture benefits of Service Oriented Architecture (SOA). SCBA represents a practical,
results-oriented, approach to modernizing enterprises. It is intended to help
organizations reduce long-term costs, improve quality of service, improve
information sharing, and help achieve a vision of flexible business processes
supported by customer-focused applications, which can be altered in a matter of
days instead of months. SCBA builds upon SOA principles in three ways:
(1) it is tightly integrated with the Federal Enterprise Architecture,
(2) it provides a description of what the architecture is (clarifying the varying
descriptions that exist), and
(3) it identifies the organizational, cultural, and process elements, as well as
technological elements, that need to exist for these architectures to be successful.
The most important aspect of SCBA is its focus on reuse of services and
components – better referred to as Service Components. (Per SCBA, v3.5)
Service Component Per OMB Circular A-11, Service Component Reference Model (SRM) is a common
Reference Model framework and vocabulary used for characterizing the IT and business
components collectively comprising an IT investment. The SRM helps agencies
rapidly assemble IT solutions through the sharing and re-use of business and IT
components. A component is a self-contained process, service, or IT capability
with pre-determined functionality that may be exposed through a business or
technology interface.
Service Level A contract or memorandum of agreement between a service provider and a
Agreement (SLA) customer that specifies, usually in measurable terms, what services the service
provider will furnish. Information technology departments in major enterprises have
adopted the idea of writing a service level agreement so that services for their
customers (users in other departments within the enterprise) can be measured,
justified, and perhaps compared with those of external (sourcing) service
providers. (Per SCBA, v3.5)
Service Oriented (1) Architecture that describes an entity (e.g., application or enterprise) as a set of
Architecture interdependent services. SOA provides for reuse of existing services and the rapid
deployment of new business capabilities based on exploiting existing assets.
(2) Representation of a system where the functionality is provided as a set of
services called by other parts of the system.
(3) Policies, practices and frameworks that enable application functionality to be
provided and requested as sets of services published at a granularity relevant to
the service Requestor, which are abstracted away from the implementation using a
single, standards based form of interface. (Per SCBA, v3.5)
Specification A document that contains specified requirements for a product and the means to
be used to determine that the product satisfies these requirements. (Per ANSI/EIA-
632-1998)
Stage A period within the life cycle of an entity that relates to the state of its description
or realization. (Per IEEE P15288/CD1)
Stakeholder An individual or organization having a right, share, claim, or interest in a system or
in its possession of characteristics that meet their needs and expectations. (Per
IEEE P15288/CD1)
Standard A document that establishes engineering and technical requirements for products,
processes, procedures, practices, and methods that have been decreed by
authority or adopted by consensus. (Per ANSI/EIA-632-1998)

B-124 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
Sample Template and Guidance

Steady State An asset or part of an asset that has been delivered and is performing the mission.
The steady state phase may also be termed “operational.”
Subsystem A grouping of items that perform a set of functions within a particular end product.
(Per ANSI/EIA-632-1998)
System An aggregation of end products enabling products to achieve a given purpose.
(Per ANSI/EIA-632-1998)
System Of Records Per OMB Circular A-11, System Of Records Notice (SORN) means a statement
Notice providing to the public notice of the existence and character of a group of any
records under the control of any agency from which information is retrieved by the
name of the individual or by some identifying number, symbol, or other identifying
particular assigned to the individual. The Privacy Act of 1974 requires this notice to
be published in the Federal Register upon establishment or substantive revision of
the system, and establishes what information about the system must be included.
System Requirement A requirement derived from one or more functional requirements and stated in
technical terms. (Per ANSI/EIA-632-1998)
System Testing The activities of testing an integrated hardware and software system to verify and
validate whether the system meets its original objectives. (Per IEEE Std 1012-
1988)
Test Case Documentation that specifies inputs, predicted results, and a set of execution
conditions for a test item. (Per IEEE Std 1012-1988)
Test Plan Documentation that specifies the scope, approach, resources, and schedule of
intended testing activities. (Per IEEE Std 1012-1988)
Total Acquisition Cost All costs for acquiring, by contract, interagency agreement (IA), and/or other
funding instruments, supplies and/or services for a designated investment through
purchase or lease, whether the supplies are already in existence or must be
created, developed, demonstrated, and evaluated, and without regard to the
type(s) of funds used, whether appropriated or non-appropriated. Service
contracts that are part of the investment must be considered part of the total
acquisition cost.
Traceability The ability to identify the relationship between various products of the development
process, i.e., the lineage of requirements, the relationship between a design
decision and the affected requirements and design features, the assignment of
requirements to design features, the relationship of test results to the original
source of requirements. (Per ANSI/EIA-632-1998)
Trade-Off Decision-making actions that select from various requirements and alternative
solutions on the basis of net benefit to the stakeholders. (Per IEEE P15288/CD1)
Use Case A use case is a technique for capturing functional requirements of business
systems and, potentially, of an IT system to support the business system.
The use case model uses “Actors” and “use cases.” An Actor is the representation
of a person or system which exists outside the system under study and who (or
which) performs a sequence of activities in a dialogue with the system.
A Use Case represents a single interaction between a primary actor (who initiates
the interaction) and other (secondary) actors, and the system itself. The interaction
is presented as a sequence of simple steps.
User An individual or organization that uses the operational system to perform a specific
function. (Per ISO/IEC 12207)

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-125


11-05-08
Sample Template and Guidance

Unit Testing Testing performed by the Development Team during the Development Stage
(Stage 4) to verify the code or changes to the code within a particular module or
subroutine. This is the lowest level of testing that can be done on a code module
or unit.
Validation Confirmation by examination and provision of objective evidence that specified
requirements have been fulfilled. (Per ISO/IEC 12207)
Verification Confirmation, through the provision of objective evidence, that specified
requirements are well defined. (Per IEEE P15288/CD1)

B-126 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008
Sample Template and Guidance

Attachment B7 - References

1. DHS Privacy Impact Assessments: The Privacy Office Official Guidance, March 2006.
2. DHS ISSM Guide to the DHS Information Security Program, Version 2.0, July 19, 2004.
3. DHS ISSO Guide to the DHS Information Security Program, Version 0.6, July 26, 2004.
4. DHS EAB Governance Process Guide, Version 3.0, September 28, 2006.
5. HLS-EA Target Architecture, Version 2.0, October 29, 2004.
6. DHS NCSD, Security in the Software Lifecycle: Making Software Development Processes—and
Software Produced by Them—More Secure, DRAFT Version 1.1, July 2006.
7. Customs and Border Protection, Systems Engineering Life Cycle Handbook, CIS HB 5500-07B,
Version 1.0, November 9, 2006.
8. ICE System Lifecycle Management, Version 1.0, February 2005.
9. TSA, Systems Development Life Cycle Guidance Document, Version 2.0.4, July 2005.
10. U.S. Coast Guard, Office of Command, Control, Communications, Computers and Information
Technology (CG-6) System Development Life Cycle (SELC), 11 February 2005.
11. CIO Council, Services and Components Based Architectures: A Strategic Guide for Implementing
Distributed and Reusable Components and Services in the Federal Government-Chapter 1:
Executive Strategy, Version 3.5, January 31, 2006.
12. IEEE, Guide to the Software Engineering Body of Knowledge, Version 1.0, May 2001.
13. IEEE. ISO/IEC IEEE P12207/CD1: Systems and Software Engineering — Software Life Cycle
Processes, June 2006.
14. IEEE, ISO/IEC IEEE P15288/CD1: Software and Systems Engineering — Systems Engineering
Life Cycle Processes, June 2006.
15. IEEE, ISO/IEC WD 27478: Systems and software engineering — Life cycle management — Guide
for Life Cycle Management, June 2006.
16. ANSI, ANSI/EIA-632-1998: Processes for Engineering a System, January 7, 1999.
17. Information Technology Infrastructure Library (ITIL) series, 2004.
18. Department of Labor, System Development Life Cycle Management Manual, Exposure Draft,
Version 2.1, December 2002.
19. Department of Defense, DoD 5000 series policy documents, 2003.
20. National Aeronautics and Space Administration, NASA Procedures and Guidelines, NPG: 7120,
November 2002.
21. Internal Revenue Service, Enterprise Life Cycle Guide, Version 2.0, May 2006.
22. Standish Group, International, The CHAOS Report, 1995.
23. Standish Group, International, 2004 Third Quarter Research Report, 2004.
24. U.S. Patent and Trademark Office, Managed Evolutionary Development Guidebook, Second
Edition, June 1993.
25. Department of the Air Force, Software Technology Support Center, Guidelines for Successful
Acquisition and Management of Software-Intensive Systems: Weapon Systems, Command and
Control Systems, Management Information Systems, Condensed Version, February 2003.

DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B B-127


11-05-08
26. Royce, Winston W., “Managing the Development of Large Software Systems,” Proceedings, IEEE
WESCON, 1970.
27. CIO Council, Services and Components Based Architectures: A Strategic Guide for Implementing
Distributed and Reusable Components and Services in the Federal Government, Version 3.5,
Chapter 1: Executive Strategy, January 2006.
28. Sensitive Systems Policy Directive DHS 4300A, June 1, 2006.
29. National Security Systems Policy Directive DHS 4300B, June 1, 2006.
30. DHS 4300A Sensitive Systems Handbook, Version 4.0, June 1, 2006.
31. DHS 4300B National Security Systems Handbook, June 1, 2006.
32. DHS Security Certification and Accreditation Guidance for SBU Systems User’s Manual, Version
2.0, May 5, 2006.
33. DHS Security Information Security Categorization Guide, Version 3.0, April 14, 2006.
34. Standards for Security Categorization of Federal Information and Information Systems; Federal
Information Processing Standards (FIPS) Publication 199, NIST, February 2004.
35. Security Considerations in the Information System Development Life Cycle, NIST Special
Publication 800-64, October 2003.
36. Contingency Planning Guide for Information Technology Systems, NIST Special Publication, 800-
34, June 2002.
37. Guide for the Security Certification and Accreditation of Federal Information Systems, NIST Special
Publication, 800-37, May 2004.
38. Guide for Developing Security Plans for Information Technology Systems, NIST Special Publication
800-18, December 1998.
39. Integrating IT Security into the Capital Planning and Investment Control Process, NIST Special
Publication 800-65, January 2005.
40. Recommended Security Controls for Federal Information Systems, NIST Special Publication 800-
53, Revision 1, December 2006.
41. Guide for Assessing the Security Controls in Federal Information Systems, Draft NIST Special
Publication 800-53A, April 2006.
42. Managing Risk from Information Systems, An Organizational Publication, Draft NIST Special
Publication 800-39, October, 2007.
43. DHS Service Oriented Architecture Framework, September October, 2006, Version 0.1.
44. NIEM Concept of Operations, NIEM Program Management Office, Revision 0.5, January 2007.

B-128 DHS Acquisition Instruction/Guidebook #102-01-001: Appendix B


Interim Version 1.9 November 7 2008