Вы находитесь на странице: 1из 5

VAV Box Reheat Guidelines Revised 05/01/02

VAV BOX
REHEAT
SELECTION

KRUEGER
EXCELLENCE IN AIR DISTRIBUTION

Page # 1
VAV Box Reheat Guidelines Revised 05/01/02

VAV terminals provide a measured quantity of The need to rapidly warm a space following a
conditioned air to a space, in response to a night setback has another set of requirements.
control signal from a thermostat or room sensor. Air needs to be heated as rapidly as possible,
This air may be tempered with a reheat coil, with a maximum of mixing, without too much
plenum air, or both. The means and selection of regard for occupant comfort. This requires both a
parameters for this reheat leads to much of the high delta-t and a high airflow. Note: The hotter
complexity and questions in selecting and the air temperature, the longer it will take to heat
specifying VAV terminals. Selection of the reheat the room, for a given heat delivery rate!
design parameters requires both an
understanding of the limitations of the reheat coil This is due to stratification of hot air at the
(hot water or electric) and the means of air ceiling. The maximum design discharge
distribution, if problems in the installation are to temperature is probably 120F. This is the limit for
be avoided. electric heater units, set by the National Electric
Code. In addition, insulation adhesives are
Overview: typically designed around this expected air
Reheat is provided to terminal VAV units temperature. If fan powered units have a plenum
primarily to allow for individual room controlled inlet located water coil, caution must be used to
heat to perimeter zones. With fan terminals, this not overheat the downstream fan motor, limiting
concept uses heated plenum air, supplied coil discharge temperatures to less than 110F.
through ceiling diffusers, to offset skin load The engineer therefore needs to ensure that both
heating demands. Single duct terminals, occupied heating and morning warm-up
however, reheat cooled primary air to offset situations are covered in his design with proper
perimeter heating requirements, which may be stages of electric heat or proportional water coil
wasteful of energy, especially when the same air valves.
handler is using chilled air for interior zones
which require year round cooling. Fan terminals The reheating of cold primary air seems, on the
require some energy to run the fans, however, so surface, to be a wasteful practice in terms of
the use of fan powered units is not without some optimum utilization of energy resources. There
penalties. In mild climates, the trade-off between are many situations, however, where it is not
equipment first costs and operating costs may only necessary, but also beneficial to do so, and
lead to the selection of single duct reheat units can save considerable energy. These include:
as the most economical solution.
1.) Providing comfort with a great diversity
The ASHRAE Fundamentals Handbook of loads: When both heating and cooling is
(Chapter 31) states that discharging air at a required from a single air handler, due to
temperature more than 15F above the room (90F climate and building design factors, reheat is
in a 75F room) will likely result in significant often an economical solution. As it is only
unwanted air temperature stratification. In used in a few locations, and only part of the
addition, ASHRAE Standard 62 (Indoor Air time, the energy penalty for reheat is
Quality) is being modified to require increased minimal.
outside air when heating from the ceiling. This is 2.) Supplementing baseboard perimeter heat:
because hot air tends to stay at the ceiling, and Baseboard heating systems can be the most
may 'short-circuit' directly back to the room effective means of offsetting perimeter
exhaust without mixing in the room. Indeed, heating demand loads. At times, however,
using the newly released ASHRAE 129 test peak heating demand loads may exceed the
procedure for Air Change Effectiveness, mixing installed baseboard capacity and
effectiveness values as low as 20% (or lower) supplemental overhead heat can be
have been observed, when the supply to room supplied.
differential exceeds 15F. Calculations will show 3.) Maintaining minimum ventilation rates:
that in most cases, it only requires 85F air to The benefit of an installed re-heat coil in non-
handle a typical winter design perimeter load at 1 perimeter zones becomes apparent when
cfm/SqFt. air supply rate (the airflow rate we minimum ventilation rates exceed the cooling
recommend for both good ventilation mixing and demand. This happens when the quantity of
comfort). supply air to a space required to provide
proper ventilation exceeds that required to

Page # 2
VAV Box Reheat Guidelines Revised 05/01/02

offset local heat sources, such as when the method #2). This often requires adjusting the
ratio of occupants to equipment (which heating CFM to achieve the desired room BTUH
requires little ventilation air) shifts towards at a discharge air temperature that will promote
occupants, as in conference rooms. In these good room air distribution and ventilation mixing.
cases, the required quantity of ventilation air This action is seldom performed, but should be.
may sub-cool the zone. The user inputs the room temperature and the
room load (not coil load), and the program
A slight amount of controlled reheat can calculates the necessary airflow at the selected
prevent this sub cooling. The alternative, leaving air temperature. With today’s DDC
reducing supply air temperature at the air controls, or with a parallel fan terminal, this
handler, may result in other spaces that reheat airflow setting is easy to establish.
cannot be cooled at design maximum
airflows, and also tends to increases space
relative humidity. Water coil issues:
4.) Controlling Humidity with sub cooling:
Humidity control can be enhanced using
Mixed air temperature: Mixed air temperature
reheat coils, just as for ventilation
(the combination of primary and induced air
requirements. When the local humidity is too
temperatures) is dependent on the coil location.
high, then drier cooler air can be added, and
The KSelect calculates the entering air
then slightly reheated to avoid sub cooling.
temperature for water coils. It also uses a
calculation to determine unit leaving air
Hot Water Heat: temperature on parallel boxes with a plenum inlet
The Krueger selection programs (The Krueger located coil (See below).
stand alone VAV box coil selection program and
the KSelect VAV terminal selection program) are Series Fan boxes: As the coil is always on the
very powerful tools, with many options, but discharge, the mixed air quantity (and the coil
cannot defy the basic laws of physics, entering air temperature) is based on the fan
(regardless of what is specified). Unlike custom cfm. The coil entering air temperature is
air handlers, the fin spacing, circuiting, and tube calculated based on the minimum primary at one
spacing are fixed for VAV box coils. This means temperature and the induced airflow (which is the
that there is only one solution for a given gpm, # fan cfm less the minimum primary) at another
of rows and airflow rate, for a given coil size. temperature. With series flow units, the coil
leaving air temperature and the box leaving air
When selecting a coil, one can pick only one are the same.
independent variable, with different parameters
for increasing the number of rows, gpm, etc. Parallel fan boxes: With some parallel fan
There are 6 different calculation paths included powered units, the coil location may be on the
in both programs. The selection of the best path plenum inlet so the coil entering air is always the
almost always requires a discussion with the plenum air temperature. There is mixing after the
engineer. If given a schedule to meet that is coil, however. The units discharge air
based on a coil other than Krueger’s it is temperature is therefore a mix of primary air,
necessary to know which item on the provided typically at the minimum primary air flow rate,
schedule is to be met. While this should probably and plenum air heated by the coil, at the fan air
be the BTUH, it is often the gpm (which is flow rate.
apparently set in concrete due to prior pump
selection), etc. Both scheduled gpm and BTUH Most parallel units have the coil on the
cannot be met, unless the Krueger coil is the discharge. This may be required when the
basis of design. Pick one! required coil leaving temperature exceeds 120F,
and there is a danger of ‘cooking’ the fan motor,
As discussed earlier, the coil leaving air and is usually the result of a relatively high
should be fixed so as to not exceed ASHRAE’s primary air minimum combined with a high
recommended 90F maximum (Chapter 31, heating demand. In this case, the coil acts like a
Fundamentals Handbook) except in unoccupied series fan box, except the air flow in heating
morning warm-up, for effective air distribution in mode is the sum of the primary (typically at a
the room (this is the default calculation method, minimum setting), plus the fan cfm.

Page # 3
VAV Box Reheat Guidelines Revised 05/01/02

sometimes becomes a static pressure sensor.


Leaving Water Temperature: A method has been At low flows, there may be insufficient velocity, or
provided (#5) for solving for leaving water static pressure, in the unit to ‘make’ the contactor
temperature. This was included primarily for a in the flow switch. This may be due to probe
design evaluation tool, and should NOT be used location, damper position, low discharge static
in selection. Cooling coils are often selected on pressure or likely, a combination of all. (Note: for
the basis if water coil delta-t, where the fan powered terminals, the minimum fan setting
discharge temperature is controlled. This is sufficient to operate the electric heat)
technique, however, is not recommended for
Electric Heat Controller
heating coils in VAV boxes, where the discharge
InletSize Min Max Min Max
temperature is seldom controlled. It is 04 100 230 50 230
recognized that many boiler manufacturers 05 100 360 75 360
require a high entering water (return water) 06 100 520 110 520
temperature to avoid ‘shocking’ the system. This 07 200 710 140 710
should be accomplished through three-way 08 200 925 185 925
valves, secondary loops, or other means, not 09 400 1200 240 1200
through coil selections. At part load, when the 10 400 1450 290 1450
water valve is throttled, coil leaving water 12 730 2100 420 2100
temperatures will ALWAYS be less than 14 1030 2900 580 2900
recommended by the boiler suppliers! 16 1350 3700 740 3700
24x16 1600 7100 1400 7100

Fluid Type: Three hot fluids are commonly used:.


Water, Ethylene and Propylene Glycol. The use As a manufacturer, we are limited by the ETL
of Glycol will significantly increase the minimum (Fan boxes) or UL (Single Duct) listing on the
gpm allowed for turbulent flow. Most programs heater as to what we can do to solve this
compute a Reynolds number, which must be problem. The rating of the heater itself, however,
greater than 5000 for a valid selection, and which is independent of the installation and does not
increases the minimum gpm as the percentage allow much latitude in installing the heater. The
of glycol increases. table here lists the minimum flows currently
required for electric heat with Krueger LMH units.
Coil Load vs. Room Load: A water coil is often A second, reheat minimum is selectable with
selected based on a given BTUH. There are, most DDC controls
however, two loads that can be used for this
calculation. One is the coil load, which is based Besides the minimum flow to activate the heater
on the air flow rate and the supply to discharge safety circuits, there is an issue of the diffuser
temperature differential. The other is the room performance. All diffusers have a specific
load, which is the difference between the room performance envelope. With VAV systems,
temperature and the discharge temperature, and diffusers should be selected so that at full flow
may be calculated from skin losses less internal they are near the limit of objectionable sound, so
loads. Often, it is not clear which is being as to allow for optimum performance at reduced
specified. Most software assumes the BTUH flows. VAV boxes are also selected at as high an
load is the coil load. inlet velocity as possible, for the same reason.
When heated air is being discharged form a
Electric Heat: ceiling diffuser, the outlet velocity needs to be as
high as possible, to prevent stratification.
The electric heater provided with Krueger LMH
Airflows below the electric heating minimum
series (Single Duct) VAV box is essentially a shown in the above table are unlikely to be
rated duct heater installed in an elongated single
satisfactory from an air distribution standpoint,
duct unit. This longer unit provides for developed
and short circuiting of ventilation air and
flow, after the damper, and a relatively uniform excessive temperature stratification are likely,
airflow across the coil elements. At low flows,
regardless of the resultant discharge
however, there is a minimum flow consideration.
temperature.
The heater has a safety switch that prevents the
heater from engaging unless there is a minimum
With fan boxes, the fan’s minimum flow rate is
sensed pressure in the duct. Normally, this is a
sufficient to permit electric heater operation, so
velocity pressure, although in practice, it there is no minimum setting or requirement. See

Page # 4
VAV Box Reheat Guidelines Revised 05/01/02

the above table for VAV damper minimum flows Summary:


as a function of control type and inlet size. The
Electric and Hot water reheat coils are
heater, moreover, is rated as a part of the unit
provided on many types of VAV terminals. There
assembly, instead of a separate listing.
are selection criteria for each that should be
considered both to ensure proper unit
Finally, it should again be noted that ASHRAE
performance and to distribute the heated air
recommends a maximum discharge temperature
properly into the space. With all, however, the
of 90F with overhead heating to avoid excessive
engineer should assure that the discharge
stratification, except in morning warm-up
temperatures would provide a comfortable
(Fundamentals, Chapter 31). Many times, simple
space, and provide ventilation mixing as well. It
logic can be applied to select suitable conditions
will often be necessary to discuss these issues
of airflow and re-heat which maintain room air
with the design engineer before making a final
mixing, diffuser performance and air change
selection to ensure that everyone is making the
effectiveness, within the factory airflow and kW
same assumptions
limitations for units with electric heaters. We
recommend 1cf/sqft as a heating flowrate in
perimeter zones to achieve optimum air
distribution when heating.

Wiring Issues: The allowable kW is a function


of unit size, voltage and phase of the electric
power supplied. Notice that only 4-wire 480
three-phase is available for power hook-up, as a
standard option. No manufacturer makes a
fractional HP 3-phase motor, so a fan box unit
must connect one leg of the 480 3-phase to
neutral to get a 277 VAC power tap for the
motor. A three-wire connection to a fan box
requires a very large transformer for the motor.
With single ducts, the lead times are increased,
and the unit is a special order. (Note: none of this
is easily accomplished in the field!)

The allowable kW is not infinite, but must be


selected from the table built into K-Select (and
shown in the price pages). K-Select only allows
selections of valid kW’s. K-Select electric heat
selection screen will calculate selection
parameters based on the last input variable
entered before the ‘Calculate’ button is pressed.
Selecting stages of heat is also important. If
large capacity heaters are required, as many
stages as possible should be selected to avoid
temperature set-point overshoot. Note that
smaller size heaters, and some control
sequences, often have only 2 stages available.
An SCR electric heater controller is not currently
available on Krueger VAV terminals.

Page # 5

Вам также может понравиться