Subject BPR

Internal I

Name
Roll Number

I Answer the following Questions 10X1/2=5

1. __is senior executive who authorizes and motivates the overall Reengineering effort [ ]
a) Reengineering b) Process c) Leader d) steering
team owner committee
2. Task drawn in __ are performed simultaneously [ ]
a) Rectangle b) Triangle c) Circle d) Parallel
3. Equation of Throughput Rate = [ ]
a) WP/CT b) TH * FT c) 1/CT d) both a and c
4. The amount of production capacity that can be made available in the short term [ ]

a) Immediate b) Effective c) Potential d) None of the above


5. Sometimes resources are forced to be idle simplicity because necessary inputs are [ ]
unavailable
a) Resource b) Starvation c) Blockage d) None of these
Breakdown
6. ___can be defined on different levels within the Organization [ ]
a) Strategy b) People c) Technology d) Process
7. __are the most valuable of all the resource in the Organization [ ]
a) Quantitative b) Leadership c) Human resources d) Qualitative
8. Benefits of Reengineering [ ]
a) Lower costs b) Lower risk c) Better use of d) all the above
existing staff
9. BPR is often concerned with__cost of the existing process [ ]
a) Increasing b) Reducing c) Constant d) Equity
10. __is end to end delay in business process [ ]

a) Cycle time b) Process time c) Setup time d) Working time

II Answer the following (Fill In the blanks) 10X1/2=5


1. _________spent doing a task over, even it seems like natural part of process.
2 BPR is a method of improving the __________ and ___________of Organization.
3. ______ and _______ of the firm are not confined to top management
4. The first emphasis in reengineering a process is to eliminate all ___________.
5. _______________is powerful tool for identifying process improvement potential.
6. _________________must provide strong leadership for reengineering to be successful.
7. Managers are uncertain about their performance when the process are ______________.
8. A business process begins with ________________ and ends with __________________.
9. ________________is critical process to the entire reengineering effort.
10. ____________ spent for the other processing time to be done during the step.

III Answer the following (Descriptive Questions ) 5X1=5


1. Write a definition for Business Process Reengineering(BPR)?
2. What is a cycle time?
3. Write a equations of work in process, throughput and flow time?
4. Write a few sentence for a redesign of business process?
5. Difference between total quality management and business process reengineering?