Академический Документы
Профессиональный Документы
Культура Документы
Declaration
I declare that this assignment is my individual work. I have not copied
from any other student’s work or from any other source except where due
acknowledgment is made explicitly in the text, nor has any part been written for
me by another person.
Prototype Model: when the customer requirements are not clear ambiguous or
our project team is following this model with sample first.
But iterative waterfall models give us more flexibility through giving chance
to revisit early phases.
Spiral model is an adaptive model. When the requirements of the customer are
enhausing:
1. Plan
2. Analyze and Design
3. Construct prototype
4. Test and integrate
these steps iterate till completion of the project.
Q3:-What incentive is there for the team to go through the task of creating
a WBS? It looks like a lot of work and some of them won't see why it
needs their involvement.
Ans: - Who wants to commit to a project timeline only to find out later that the
work was misunderstood and grossly underestimated? The WBS can actually be
used as a crucial component of protecting team morale. There is nothing worse
for team members starting a project than the sinking feeling that once again
their management does not understand the work at the team members' level.
Once again, management will set incorrect expectations based on a coarse and
insufficient understanding of what actually has to get done at the team members'
desks and benches. Once again, management will ask them to do the
impossible. Work breakdown structures are simply a way of organizing the
work activities necessary to implement the project into a numbered outline
form. This helps ensure nothing is lost in the cracks. Notice I said traceability
between requirements and implementation work in the WBS.
PART B
Q1:-how the waterfall model and prototyping model can be accommodated
in the spiral process model?
Ans: - 1. Spiral model can be accommodating in prototyping and waterfall
model. It is a model of iterative process as prototyping and also a systematic
approach to solve a problem as in waterfall model.
2. Spiral model take problem as a series of step to solve a problem as in
waterfall, and take the contribution of users or customers in each phase as in
prototyping model.
Q2:- How much detail and how many levels should my work breakdown
structure go to and how do I know if I'm done?
Ans:-The general answer to this question is to go far enough down in levels and
details to be sure your schedule estimates will have a good degree of
accuracy. One rule of thumb is to take the WBS down to activity blocks of
no more than 2-weeks' duration. But the level of detail, and what
constitutes the right degree of accuracy, is ultimately a judgment call for
the project manager.
When deciding how specific and detailed to make your work packages, you
must be careful to not get too detailed. This will lead to the project manager to
have to micromanage the project and eventually slow down project progress. On
the other hand, work packages whose details are too broad or large become
impossible for the project manager to manage as a whole.
The WBS should contain a list of broken down deliverables. In other words,
what the customer/stakeholder will get when the project is complete. It is NOT
a list of specific activities and tasks used to accomplish the deliverables. How
the work is completed (tasks and activities) can vary and change throughout the
project, but deliverables cannot without a change request, so you do not want to
list activities and tasks in the WBS.
The risk planning, analysis, and response planning efforts are rarely integrated
into the overall project plan. As a result, risk management is not a priority for
the project team, and adequate resources (budget and people) are not allocated
to address issues caused by risk events. This "we will deal with those events if
and when they occur" mentality leaves little or no room for error on the project.
The project risk management plan is a mix of all the plans developed on earlier
stages of a project. To create such a plan, the project manager together with the
project team needs to use the project scope statement, the cost management
plan, the schedule management plan, and the communications management
plan. By means of group meetings and discussions, the project manager collects,
filters out, and analyzes information in order to build the project risk
management plan considering existing environmental factors. The project team
helps collect and analyze necessary information.