This report is about powering up a thruster panel step by step. With this method every
step is under control.
Because drives have not been used during transportation of the vessel this method
gains confidence of operation. This method must be performed by an experienced
technician.
Cooling system
-. Check for flow and temperature of ships cooling water for both drive cabinets and
main motor.
-. Check pre-pressure of both secondary cooling systems of each thruster system.
(must be at least 1,5 Bar)
-. Check supply (3x440Vac) and power up heat exchangers.
Power up
-. Check external supply(230Vac) 10F2. Power up and check consumers.
-. Open 5F15. Switch 23S2 'OPERATION' to Emergency.
-. Check main supply (3x690Vac). Power up main supply. Check voltage at 5F15.
-. Power up 5F15. Check lamp 'MAIN POWER SUPPLY AVAILABLE'.
-. Check EM-STOP functionality. (complete thruster system) Check Maintenance-
switch. Check lamp test.
-. DC voltage on display's of both AFE's (inside cabinet) should drop slowly after last
step.