Академический Документы
Профессиональный Документы
Культура Документы
I
ate last year, oil started flowing from Total's second production reserves are estimated at close to 1 Bbbl of oil.
center in Angola's block 17. Dalia, like its forerunner Girassol, Dalia's four main reservoirs were formed over 25 million years
is being developed via one of the world's largest FP^Os linked ago following the accumulation of sediments at the mouth of the
lo an extensive network of deepwater subsea wells. Congo River. Over time, periodic subsea avalanches shifted these
There the similarities end, however. Dalia's shallower sub- sediments out to Ihe deep offshore, where they were deposited in
surface location presented greater difficulties in well design, due to and along the edges of seabed channels.
the need for a steeper drilling radius, and the field's extent would Today the turbiditic, unconsolidated and heterogeneous reser-
require twice as many wells to develop. Also, its Miocene crude is voir sands, lying at a subsurface depth of 8(K) m (2,625 ft), are sev-
much heavier than Girassol's Oligocene oil, and cooler on outflow. eral kilometers long, with varying thickness. All contain viscous and
This would necessitate more intensive flow assurance measures, both acidic crude (21-23° API), witli relatively low outflow temperatures
to saf('.iiii;ird passage nf fluids to the Fl'SO nt the cnrrt'rt trmpornltirr. of4.'"vri(l" C,
seven different completion designs for Da- The twin imperatives of heat conservation intervals with good accuracy."
lia. including two 'smart' confifiuratiotis. and hydrate formation prevention meant Technip's initial analytical program for
Qtialificalion involved individual compo- that all fluid-bearing flowiines and lisers had the Dalia IPBs involved seven tnonths of
nent and sub-systetn testing to ensure com- to be heavily insulated, to guarantee that; material (|ualitication tests, mechanical tests
pliance with Dalia's (luids specifications. The 1. During normal production periods, oil including 'crushing', bending and pulling,
completion was then assembled and run into exiting the reservoir at 46° C could not arrive and subsequent deepwater immersion per-
a horizontal test well to validate running op- at the FPSO at a temperature below 'M° C. formance tests at a location offshore Brazil
erations and functionality for workovers and 2. In tlie event of a shutdown, ihe fluids to validate the IPB's design integrity.
interventions. temperature would no( fall below 2V C be- The main puipose of the deepwaler trials
For the initial phase of development drill- fore the line's integrity had been preserved. was to provide feedback on the behavioi" of
ing. Total contracted two deepwater drill- 'ITie solution for the flowlines was a con- Ihe tensile armor layers under buckling con-
ships to work in parallel, the Pride Africa figuration of four pipe-in-pipe production line ditions. Technip submitted the pipe section
and the Pride Angola, both of which had also loops resting on the seabed. Total selected to cyclic curvature variation, as might be
served on Girassol and the subsequent tie-in Aerogel, an efficient insulation medium with induced by the FPSO's motions, while also
of Rosa/Urio. an OHTC of around 0.65, to [ill the annulus subjectitig the pipe to external pressures.
liull being launched in August that year. In tons), and we had to bring in a crane from acidic oils, the pH increases throughout the
May 2(H)5, the Dalia Mar Protuudo L-onsortiiim Japan for tbe assembly at DSME. We ended entire process when Ihe pressure decreases.
installed the topsides on the hull at DSMH's up relatively steady at the basic engineering A pressurized system maintains acidity at a
yard in Geoje Island. figure for the topsides of 30,000 metric tons level lower than pH 6.2, where equilibrium
According to Picard. the deck is not as (33,0(59 tons), but it took some ingenuity exists between the pH and the carbon diox-
-spacious as Girassol's, where room was left to stay within this weight. For instance, we ide partial pressure, inhibiting Ihe prwipila-
Ironi the outset to accommodate the later- used more sophisticated and expensive ma- tion reaction."
|)hasc tie-in ()f Kosa and Lirio. "When we terials or steel grades for the pipes than had GF Oil & Gas supplied the FPSO's power
•^larted on this project six years ago with been allowed for in the original plan." generation and compression equipment,
lbe low oil price, we had to be careful nol (")ne of the major issues affecting the top- which comprises three 24MW P(iT+25
lo over-dt'sign the lacililies. 'Hiere was some sides process design was the composition oi gas turbine generators: twci high pressure
debate at the time about leaving space for Dalia's crude, whicb brings the risk of naplv lurboconipressors (two PGT+25 turbines
future modules, but in the end we decided thenate formation during production. Under driving four compressors); and two sets of
.(gainst the extra cost of increasing the size certain conditions (temperature, pressure, low pressure and export/injection electric
ulthe hull." and acidity), the napbthetiic acids normally motor-driven compressors operating at 50
TIK' project team opied for a modular ap- dissolved in Dalia's crude are liable to pre- Mpa (.500 bars). "We are using a very fancy
proach, in contrast to Ciirassol's 'pancake' cipitation, leading to formation of deposits in coupling for the gas injection compressor,"
deck solution. '"'Iliat gave us more flexibility pipework and pressure vessels. says Picard. Sulzcr provided tbe three injec-
lor the construction. At the time, we weren't Total had conducted various studies (»f tion pumps, two driven by Solar Taurus gas
sure that all the modules could be built in this phenomenon, at times wilh the part- ttnbines, the other powered by a 5.25MW
one place. The Korean yards had a huge ners' assistance. Statoil. for instance, had electric motor.
workload at the time, so It was not easy to experience countering naphthenate forma- The seven-deck. 2.500-metric ton (2,756-
liiul slols for this project. However, SHI had tion offshore Norway. The solution for Dalia lon) living quarters module, also built by
a slot available lo assemble tbe hull and also combined anti-naphthenate injection at the SHI. is located above five levels of machin-
-;(inir module construction capacity, so In riser base, via the gas-lilt tubes, with a novel ery space in the hull, and can accommodate
(he end. we split tbe 12 modules between technique involving lirst-stage oil. water, and up to 190 personnel during shutdowns in 70
Ihem and DSMI'^, 'lliis turned out to be a gas separation under pressure. cabins. Hie quarters module also houses
good choice, as the project was not delayed. 'Tests have shown that some crude oils the control room, normally manned by just
"In our case, some of Ihe modules ended form naphthenates al higher acidic values," four staff, whose duties include monitoring
lip wfijj:hiiig over 3,,500 metric tons (3.858 Picard explains. "During the treatment of the subsea control system, lliis is one of the
Karmsund Maritime*
OFFSHORE SUPPLY AS
References;
Slatoil. Phillips, BR Amoco. Conoco. Meersk. Elf, Exxon, Canadwn
Petro Inl., Saga, Norsk Hydro, Donline. Petrovalves. Kv«mer.
world's largest, managing 17.000 underwa- the IPBs, pipe-in-pipes and injection lines, the
Sonils Base underwent extensions which in-
ter control points. It was configured from the company's Construetor managing installation cluded a new workshop to house completion
outset to eventually supervise 100 live wells, of the umbilicals, subsea manifolds, the mooi'-
and workover control systems activities.
taking into account production from possible ing foundations, and the production spools. Picard expects a final capex figure for the
future infill wells and satellite fields. Around 20 other vessels. Including tugs and Dalia development of S4 billion. It is a slighl
Dalia's oil is exported via two 610-mm barges, assisted in these various operations. increase due to external specific markel
(24-in.}, 2-km (1.2-nii) flexible pipelines to conditions (price of steel, fuel, drilling ser-
an offloading buoy, accommodating tanker Local manufacturing vices). Dalia came on stream on December
berthing. The offloading process normally As with all recenl deepwater Angolan de- 13 at 20.000 b/d of oil. "Our priority in the
lasting around 36 hours. At Girassol. the velopments. Dalia has invigorated the local early stages is to gain production experi-
SBM-designed buoy's mooring chains be- manufacturing and offshore support sector. ence." However, the development plan calls
gan to fail not long after start-up. Although The existing Sonamet yard in Lobito, for for a plateau output of 240,000 b/d of oil to
the problem was eventually resolved. Total instance, built the hull and suction anchors be reached by the end of this yean "Ques-
opted for APL's turret-moored buoy solution for the offloading buoy, and seven of the tions are being asked about how we can
for Dalia. foflowing a design competition. foundation bottom structures for tlie nine achieve this. Tlie answer is. we will know by
This 30 X 19 X 7.5 m (98 x 62 x 25 ft) struc- manifolds. It also completed assembly of the this summer But once lliere. we should stay
ture weighs 650 metric tons (717 tons), manifolds. at that level for at leasl four years."
Following onshore testing and commis- Nearby in I^jbito. Technip's new umbilical All the associated gas is being used ini-
sioning, the FPSO sailed out of South Korea plant, Angoflex, manufactured most of the tially for power generation and injection.
on March 8, 2006. arriving in block 17 early static and dynamic injection and production Some gas will be exported under Angola's
in September following a brief stopover in umbilicals, and this base was also used for proposed multi-block LNd gas-gathering
Cape Town. Fairmount. under sub-contract integration of the subsea distribution units scheme in the future.
lo Technip, provided the ocean-going tugs and umbilical termination heads. Water and gas injection should come into
for the entire voyage. In Dande. 50 km (31 mi) north of Luanda. service by the end of February or early in
The FPSO was moored at ils offshore lo- Technip found a location for a puniose-buill March. In time. Total may employ a viscosi-
cation by the Normand Installer. According spool base for the pipe-iji-pipe. injection ficalion technique in its water injection wells
to Picard, the anchor pattern was designed pipelines and offloading lines assembly, also to further boost recovery, llie company is
io take into account the effects of long swells erecting a 600-m (1,968-ft) long jetty to ac- also contemplating acquiring a 4D seismic
in this region. commodate spooling onto the two pipe reels survey over the reservoirs to monitor pro-
Earlier, Technip's Deep Blue had insUilted all onboard the Deep Blue. In Luanda itself, the duction performaiict'. O
FOR INFO OR PRICING, CONTACT RANDY HALL Email: rhall@pennenergy.com Phone: 713-499-6330 Fax: 713-963*276
£i 3007 PenilEnorgy (PEN703/01U7i