Inspections are an integral and critical part of the exercise to ensure smooth and proper implementation of a project. Banks and Financial Institutions rely heavily on the inspection reports (as also Certificates from practising Chartered Accountants) before making disbursement of sanctioned credit limits for part financing the projects. The inspection reports emphasize more on the physical progress of the work done and the expenditure incurred but do not at times provide inclusive view of the entire project.
Исходное описание:
Оригинальное название
How to Inspect a Project Tmder Implementation by Subhash Nathuramka 4
Inspections are an integral and critical part of the exercise to ensure smooth and proper implementation of a project. Banks and Financial Institutions rely heavily on the inspection reports (as also Certificates from practising Chartered Accountants) before making disbursement of sanctioned credit limits for part financing the projects. The inspection reports emphasize more on the physical progress of the work done and the expenditure incurred but do not at times provide inclusive view of the entire project.
Авторское право:
Attribution Non-Commercial (BY-NC)
Доступные форматы
Скачайте в формате PDF, TXT или читайте онлайн в Scribd
Inspections are an integral and critical part of the exercise to ensure smooth and proper implementation of a project. Banks and Financial Institutions rely heavily on the inspection reports (as also Certificates from practising Chartered Accountants) before making disbursement of sanctioned credit limits for part financing the projects. The inspection reports emphasize more on the physical progress of the work done and the expenditure incurred but do not at times provide inclusive view of the entire project.
Авторское право:
Attribution Non-Commercial (BY-NC)
Доступные форматы
Скачайте в формате PDF, TXT или читайте онлайн в Scribd
Subhash Nathuramka, FCS, Principal Consultant, Columbus Capital Management Ltd.,
Mumbai.
Projects under implementation are subjected to procedural inspections by the officials
of lending banks and fmancial institutions to ensure that the funds advanced by e-mail: them are put to right use. Aspects which are to be considered while undertaking snathuramka@yahoo.com such inspections and to be included in the inspection reports are briefly outlined in this article.
Introductory CA Certificate needs to be distinguished from
Inspection is an integral and critical part of the exercise to Chartered Engineer's Certificate ensure smooth and proper implementation of a project. Post A Chartered Accountant is a competent accounting appraisal and post sanction of finance by Banks, financial professional to certify the expenditure incurred based on the institutions it becomes imperative that the project is basis of verification of vouchers, supporting and books of implemented as per the plan within the envisaged timeframe. account. On the other hand a Chartered Engineer is a Regular inspections are made to check whether the project is competent professional to certify the physical progress of being implemented in accordance with the approved plan/ the work done. project report and deviations are pointed out with remedial There may be following situations where the expenditure measures in the report. has actually been incurred and certified by C.A. but it does Banks and Financial Institutions rely heavily on the not provide the lending bank the right input or guidance inspection reports (as also Certificates from Practising required to take a fair view in the matter of release of credit Chartered Accountants) before making disbursement of facility - sanctioned credit limits for part financing the projects. The 1. Although the expenditure has been incurred by the inspections are made by the officials of lending banks, company it does not relate to the specific project under financial institutions or by their authorized empanelled consideration. Chartered Engineers. The inspection reports emphasize more 2. The expenditure incurred on purchase of items , on the physical progress of the work done and the equipment is not as per the approved plan. Expenditure incurred and do not at times provide inclusive view of the entire project. There are several other factors 3. The expenditure has been incurred on a head other than and aspects which need to be seen and reported along with the head envisaged in the approved plan e.g. more civil suggestions to take corrective steps. It would be a good works, higher preoperative expenses, higher soft costs, idea if an inspection report like a project report also covers less expenditure on equipment and machinery. all relevant factors having a bearing on the project be it Similarly without the verification of books of account the technical, commercial, financial or managerial to ascertain Chartered Engineer is not in a position to know the actual whether the implementation of the project is going on the expenditure incurred. He can only physically inspect the project right lines. and report the progress made in terms of percentage of work