Академический Документы
Профессиональный Документы
Культура Документы
Unit
Item of work Access Road, 4m wide
lm
I Description Quantity Unit Unit cost
M
A
T
E
R
I
A
L
S
Direct Material Cost
11 Description Quantity Duration Unit cost
L Engineer 1 0.5 250
A Work Permit Receiver 1 4 180
B Safety Supervisor 1 4 180
O Laborer 4 4 120
R
Direct Labor Cost
111 Description Quantity Duration Unit cost
E Minor Tools 5%
Q Accomodation 2 4 200
U Vehicle 2 4 200
I Bulldozer 1 2 850
P Dumptruck 1 2 650
M Loader 1 2 650
E trailer 2 3 850
N
T
Direct Equipment Cost
Direct Cost
COST OF WORK
Unit Cost/lm
Quantity
568
Total cost
-
-
-
-
-
-
-
125.00
720.00
720.00
1,920.00
3,485.00
174.25
1,600.00
1,600.00
1,700.00
1,300.00
1,300.00
5,100.00
-
-
12,774.25
16,259.25
2,438.89
18,698.14
32.92
Detailed cost estimate
Unit
Item of work Fencing
ls
I Description Quantity Unit Unit cost
M
A
T
E
R
I
A
L
S
Direct Material Cost
11 Description Quantity Duration Unit cost
L Engineer 1 0.5 250
A Work Permit Receiver 1 4 180
B Safety Supervisor 1 4 180
O Laborer 4 4 120
R
Direct Labor Cost
111 Description Quantity Duration Unit cost
E Minor Tools 5%
Q Accomodation 2 4 200
U Vehicle 2 4 200
I Boom Truck 1 1 650
P JCB 1 1 650
M Compactor 1 2 150
E
N
T
Direct Equipment Cost
Direct Cost
COST OF WORK
Unit Cost/lm
Quantity
1
Total cost
-
-
-
-
-
-
-
125.00
720.00
720.00
1,920.00
3,485.00
174.25
1,600.00
1,600.00
650.00
650.00
300.00
-
-
-
4,974.25
8,459.25
1,268.89
9,728.14
9,728.14
Detailed cost estimate
Unit
Item of work Drilling for pole foundation
ea
I Description Quantity Unit Unit cost
M
A
T
E
R
I
A
L
S
Direct Material Cost
11 Description Quantity Duration Unit cost
L Engineer 1 0.25 250
A Work Permit Receiver 1 2 180
B Safety Supervisor 1 2 180
O Laborer 4 2 120
R
Direct Labor Cost
111 Description Quantity Duration Unit cost
E Minor Tools 5
Q Accomodation 2 2 200
U Vehicle 2 2 200
I Drilling Rig, 1000 mm dia 9 2.5 450
P water tank 1 2 450
M mud pump 1 450
E
N
T
Direct Equipment Cost
-
-
-
-
-
-
-
62.50
360.00
360.00
960.00
1,742.50
8,712.50
800.00
800.00
10,125.00
900.00
-
-
-
-
21,337.50
23,080.00
3,462.00
26,542.00
2,949.11
Detailed cost estimate
Drilling for anode and anode bed Unit
Item of work installation lm
I Description Quantity Unit Unit cost
M
A
T
E
R
I
A
L
S
Direct Material Cost
11 Description Quantity Duration Unit cost
L Engineer 1 0.375 250
A Work Permit Receiver 1 3 180
B Safety Supervisor 1 3 180
O Laborer 4 3 120
R
Direct Labor Cost
111 Description Quantity Duration Unit cost
E Minor Tools 5
Q Accomodation 2 3 200
U Vehicle 2 3 200
I Drilling Rig 80 1 450
P water tank 1 3 450
M mud pump 1 2 450
E water pump 1 1 100
N
T
Direct Equipment Cost
-
-
-
-
-
-
93.75
540.00
540.00
1,440.00
2,613.75
13,068.75
1,200.00
1,200.00
36,000.00
1,350.00
900.00
100.00
-
-
53,818.75
56,432.50
8,464.88
64,897.38
811.22
Detailed cost estimate
Concrete works includes rebars , Unit
Item of work casing fabrication & instalation,
pouring, curing and capping m3
19
Total cost
6,650.00
3,325.00
42.00
2,340.00
-
-
-
-
-
12,357.00
156.25
900.00
900.00
360.00
1,000.00
1,200.00
1,200.00
2,880.00
8,596.25
429.81
4,000.00
2,000.00
150.00
2,600.00
-
-
-
-
9,179.81
30,133.06
4,519.96
34,653.02
1,823.84
Detailed cost estimate
Pole installation complete with Unit
Item of work
dressings ea
I Description Quantity Unit Unit cost
M
A
T
E
R
I
A
L
S
Direct Material Cost
11 Description Quantity Duration Unit cost
L Engineer 1 0.375 250
A Work Permit Receiver 1 3 180
B Safety Supervisor 1 3 180
O Electrician 2 3 180
R laborer 4 3 120
Direct Labor Cost
111 Description Quantity Duration Unit cost
E Minor Tools 5%
Q Accomodation 3 3 200
U Vehicle 2 3 200
I boom truck 1 3 650
P backhoe 1 3 650
M
E
N
T
Direct Equipment Cost
93.75
540.00
540.00
1,080.00
1,440.00
3,693.75
184.69
1,800.00
1,200.00
1,950.00
1,950.00
-
-
-
-
7,084.69
10,778.44
1,616.77
12,395.20
1,377.24
Detailed cost estimate
Unit Quantity
Power line installation single
Item of work
phase two wires 13.8 kv lm 568
I Description Quantity Unit Unit cost Total cost
M -
A -
T -
E -
R -
I -
A -
L -
S -
Direct Material Cost -
11 Description Quantity Duration Unit cost
L Engineer 1 0.625 250 156.25
A Work Permit Receiver 1 5 180 900.00
B Safety Supervisor 1 5 180 900.00
O Electrician 2 5 180 1,800.00
R Helper 2 5 120 1,200.00
Laborer 4 5 120 2,400.00
Direct Labor Cost 7,356.25
111 Description Quantity Duration Unit cost
E Minor Tools 5% 367.81
Q Accomodation 2 5 200 2,000.00
U Vehicle 2 5 200 2,000.00
I
P boom truck 1 3 450 1,350.00
M Bucket truck 1 3 450 1,350.00
E -
N -
T -
Direct Equipment Cost 7,067.81
14,424.06
62.50
360.00
360.00
720.00
960.00
2,462.50
123.13
800.00
800.00
700.00
900.00
-
-
-
-
3,323.13
8,460.63
1,269.09
9,729.72
54.05
Detailed cost estimate
Excavation for underground CP Unit
Item of work
cable(positive and negative) m3
I Description Quantity Unit Unit cost
M
A
T
E
R
I
A
L
S
Direct Material Cost
11 Description Quantity Duration Unit cost
L Engineer 1 0.06375 250
A Work Permit Receiver 1 0.51 180
B Safety Supervisor 1 0.51 200
O Laborer 2 0.51 120
R
Direct Labor Cost
111 Description Quantity Duration Unit cost
E Minor Tools 5%
Q Accomodation 2 0.51 200
U Vehicle 2 0.51 200
I Backhoe 125 1 0.51 650
P Trailer 1 2 850
M
E
N
T
Direct Equipment Cost
Direct Cost
15.94
91.80
102.00
122.40
332.14
16.61
204.00
204.00
331.50
1,700.00
-
-
-
-
2,456.11
2,788.24
418.24
3,206.48
50.60
ACTIVITIES UoM Quantity
Fencing ls 1
Access Road
lm 568.00
Mark Up 15%
Cost/wellhead
Number of Wells 4
Total Cost
Notes:
1. LABOR & EQUIPMENTS ONLY…
Unit Cost Cost
50.60 3,206.78
54.05 9,729.00
2,949.11 26,542.00
1,377.24 12,395.20
29.20 16,587.67
811.22 64,897.38
1,823.84 34,653.02
9,728.14 9,728.14
18,698.14
32.92
196,437.32
785,749.29