Вы находитесь на странице: 1из 12

<Company Logo>

<Company Name>

<Project Name>

Prepared May 8, 2011

Proprietary and confidential

R E Q U E S T F O R P R O P O S A L
Table of Contents
USING THIS TEMPLATE........................................................................................3
TEMPLATE CONTENTS.....................................................................................3
INTRODUCTION AND BACKGROUND...................................................................5
PURPOSE OF THE REQUEST FOR PROPOSAL...................................................5
ADMINISTRATIVE.................................................................................................6
TECHNICAL CONTACT......................................................................................6
CONTRACTUAL CONTACT................................................................................6
DUE DATES.....................................................................................................6
SCHEDULE OF EVENTS....................................................................................6
GUIDELINES FOR PROPOSAL PREPARATION........................................................8
PROPOSAL SUBMISSION..................................................................................8
DETAILED RESPONSE REQUIREMENTS................................................................9
EXECUTIVE SUMMARY.....................................................................................9
SCOPE, APPROACH, AND METHODOLOGY.......................................................9
DELIVERABLES................................................................................................9
PROJECT MANAGEMENT APPROACH................................................................9
DETAILED AND ITEMIZED PRICING..................................................................10
APPENDIX: REFERENCES.................................................................................10
APPENDIX: PROJECT TEAM STAFFING..............................................................10
APPENDIX: COMPANY OVERVIEW....................................................................10
EVALUATION FACTORS FOR AWARD...................................................................11
CRITERIA.........................................................................................................11
SCOPE OF WORK.................................................................................................12
REQUIREMENTS...............................................................................................12
DELIVERABLES................................................................................................12

Confidential 2
USING THIS TEMPLATE
Foundstone has developed this Request For Proposal (“RFP”) template to help
organizations identify and select a quality security vendor to perform professional
services work. It also lists questions organizations should consider asking potential
vendors to ensure that a thorough and comprehensive approach to the project will be
taken. This template should apply for a variety of information security projects
including:

• External Network Vulnerability Assessment and Penetration Testing


• Internal Network Vulnerability Assessment and Penetration Testing
• Web Application Penetration Testing
• Dial-In / RAS Security Testing
• DMZ or Network Architecture Designs / Reviews
• Wireless Network Assessment and Penetration Testing
• Virtual Infrastructure Security Assessment
• Server Configuration Reviews
• Firewall and Router Configuration Reviews
• VPN Configuration Reviews
• Voice over IP Assessments
• Social Engineering Assessments
• Physical Security Reviews
• Software Source Code Reviews
• Application Threat Modeling and Design Reviews
• Information Security Policy and Procedure Development or Review
• Information Security Risk Assessment
• Security Awareness Program Development or Review
• Incident Response Program Development or Review
• Secure SDLC Program Development or Review
• PCI Quarterly Scans
• PCI Report on Compliance Assessment or Gap Analysis

TEMPLATE CONTENTS
The template contains a number of different sections that provide the vendor with a
better understanding of the business and technical objectives of the effort. The major
sections of the RFP template are:

• Introduction and Background: A description of the project’s objectives plus


any additional background about the organization or business objectives that
may provide the vendor with additional useful perspective.

• Administrative Information: Contact information that the vendors will need


to prepare and submit their proposal as well as major dates associated with
the RFP submission, evaluation and award process.

• Guidelines for Proposal Preparation: Guidelines for vendor


communication with the organization are provided in this section and a
preferred proposal format is described for the vendor.

Confidential 3
• Evaluation Factors for Award: Outlines the criteria that will be used to
evaluate the various proposals.

• Statement of Work and Deliverables: This section provides sufficient


technical details about the environment to allow a vendor to understand the
scope of the effort and price it appropriately. In addition, the deliverables or
work products required from the project are described.

Confidential 4
INTRODUCTION AND BACKGROUND

PURPOSE OF THE REQUEST FOR PROPOSAL


ABC Company is a provider of specific products or services to types of customers in
the industry. It has facilities in approximately number locations within the United
States, as well as several other locations in Europe and Asia.

ABC Company is interested in conducting a security assessment that will allow it to:

• Provide line items that summarize the scope of the work required. Examples
are:

• Gain a better understanding of potential corporate network vulnerabilities that


may be visible from the Internet.

• Determine if the current wireless network is configured securely.

• Evaluate the security associated with public self service web applications that
are used by ABC Company’s customers.

These activities are part of ABC Company’s ongoing risk management program and
are focused on identifying the risk level ABC Company is currently exposed to so that
an appropriate set of responses to those threats can be developed.

ABC Company is seeking to identify and select an outside independent organization


to perform the activities listed above. The remainder of this document provides
additional information that will allow a service provider to understand the scope of
the effort and develop a proposal in the format desired by ABC Company.

Confidential 5
ADMINISTRATIVE

TECHNICAL CONTACT

Any questions concerning technical specifications or Statement of Work (SOW)


requirements must be directed to:

Name
Address

Phone
FAX
Email

CONTRACTUAL CONTACT

Any questions regarding contractual terms and conditions or proposal format must be
directed to:

Name
Address

Phone
FAX
Email

DUE DATES
A written confirmation of the Vendor’s intent to respond to this RFP is required by
XX/XX/XX. All proposals are due by time am/pm on XX/XX/XX. Any proposal received
at the designated location after the required time and date specified for receipt shall
be considered late and non-responsive. Any late proposals will not be evaluated for
award.

SCHEDULE OF EVENTS

Confidential 6
Event Date

1. RFP Distribution to Vendors

2. Written Confirmation of Vendors with Bid


Intention
3. Questions from Vendors about scope or
approach due
4. Responses to Vendors about scope or
approach due
5. Proposal Due Date

6. Target Date for Review of Proposals

7. Final Vendor Selection Discussion(s)--Week of

8. Anticipated decision and selection of Vendor(s)

9. Anticipated commencement date of work

Confidential 7
GUIDELINES FOR PROPOSAL PREPARATION

PROPOSAL SUBMISSION
Award of the contract resulting from this RFP will be based upon the most responsive
Vendor whose offer will be the most advantageous to ABC Company in terms of cost,
functionality, and other factors as specified elsewhere in this RFP.

ABC Company reserves the right to:

• Reject any or all offers and discontinue this RFP process without obligation or
liability to any potential Vendor,
• Accept other than the lowest priced offer,
• Award a contract on the basis of initial offers received, without discussions or
requests for best and final offers, and
• Award more than one contract.

Vendor's proposal shall be submitted in several parts as set forth below. The Vendor
will confine its submission to those matters sufficient to define its proposal and to
provide an adequate basis for ABC Company’s evaluation of the Vendor’s proposal.

In order to address the needs of this procurement, ABC Company encourages


Vendors to work cooperatively in presenting integrated solutions. Vendor team
arrangements may be desirable to enable the companies involved to complement
each other's unique capabilities, while offering the best combination of performance,
cost, and delivery for the Penetration Test being provided under this RFP. ABC
Company will recognize the integrity and validity of Vendor team arrangements
provided that:

• The arrangements are identified and relationships are fully disclosed, and
• A prime Vendor is designated that will be fully responsible for all contract
performance.

Vendor’s proposal in response to this RFP will be incorporated into the final
agreement between ABC Company and the selected Vendor(s). The submitted
proposals are suggested to include each of the following sections:

1. Executive Summary
2. Approach and Methodology
3. Project Deliverables
4. Project Management Approach
5. Detailed and Itemized Pricing
6. Appendix: References
7. Appendix: Project Team Staffing
8. Appendix: Company Overview

The detailed requirements for each of the above-mentioned sections are outlined
below.

Confidential 8
DETAILED RESPONSE REQUIREMENTS

EXECUTIVE SUMMARY
This section will present a high-level synopsis of the Vendor’s responses to the RFP.
The Executive Summary should be a brief overview of the engagement, and should
identify the main features and benefits of the proposed work.

SCOPE, APPROACH, AND METHODOLOGY


Include detailed testing procedures and technical expertise by phase. This section
should include a description of each major type of work being requested of the
vendor. All information that is provided will be held in strict confidence. The proposal
should reflect each of the sections listed below (examples of the types of sections
that could appear are listed below – select or modify them as appropriate):

• External Network Vulnerability Assessment and Penetration Testing


• Internal Network Vulnerability Assessment and Penetration Testing
• Web Application Penetration Testing
• Dial-In / RAS Security Testing
• DMZ or Network Architecture Designs / Reviews
• Wireless Network Assessment and Penetration Testing
• Virtual Infrastructure Security Assessment
• Server Configuration Reviews
• Firewall and Router Configuration Reviews
• VPN Configuration Reviews
• Voice over IP Assessments
• Social Engineering Assessments
• Physical Security Reviews
• Software Source Code Reviews
• Application Threat Modeling and Design Reviews
• Information Security Policy and Procedure Development or Review
• Information Security Risk Assessment
• Security Awareness Program Development or Review
• Incident Response Program Development or Review
• Secure SDLC Program Development or Review
• PCI Quarterly Scans
• PCI Report on Compliance Assessment or Gap Analysis

DELIVERABLES
Include descriptions of the types of reports used to summarize and provide detailed
information on security risk, vulnerabilities, and the necessary countermeasures and
recommended corrective actions. Include sample reports as attachments to the
proposal to provide an example of the types of reports that will be provided for this
engagement.

PROJECT MANAGEMENT APPROACH


Include the method and approach used to manage the overall project and client
correspondence.

Confidential 9
Briefly describe how the engagement proceeds from beginning to end.

DETAILED AND ITEMIZED PRICING


Include a fee breakdown by project phase and estimates of travel expenses.

APPENDIX: REFERENCES
Provide three current corporate references for which you have performed similar
work.

APPENDIX: PROJECT TEAM STAFFING


Include biographies and relevant experience of key staff and management personnel.
Describe the qualifications and relevant experience of the types of staff that would
be assigned to this project by providing biographies for those staff members.
Describe bonding process and coverage levels of employees. Affirm that no
employees working on the engagement have ever been convicted of a felony.

APPENDIX: COMPANY OVERVIEW


Provide the following for your company:
• Official registered name (Corporate, D.B.A., Partnership, etc.), Dun &
Bradstreet Number, Primary and secondary SIC numbers, address, main
telephone number, toll-free numbers, and facsimile numbers.
• Key contact name, title, address (if different from above address), direct
telephone and fax numbers.
• Person authorized to contractually bind the organization for any proposal
against this RFP.
• Brief history, including year established and number of years your company
has been offering Information Security Testing.

Confidential 10
EVALUATION FACTORS FOR AWARD

CRITERIA
Any award to be made pursuant to this RFP will be based upon the proposal with
appropriate consideration given to operational, technical, cost, and management
requirements. Evaluation of offers will be based upon the Vendor’s responsiveness to
the RFP and the total price quoted for all items covered by the RFP.

The following elements will be the primary considerations in evaluating all submitted
proposals and in the selection of a Vendor or Vendors:

1. Completion of all required responses in the correct format.


2. The extent to which Vendor’s proposed solution fulfills ABC Company’s stated
requirements as set out in this RFP.
3. An assessment of the Vendor’s ability to deliver the indicated service in
accordance with the specifications set out in this RFP.
4. The Vendor’s stability, experiences, and record of past performance in
delivering such services.
5. Availability of sufficient high quality Vendor personnel with the required skills
and experience for the specific approach proposed.
6. Overall cost of Vendor’s proposal.

ABC Company may, at their discretion and without explanation to the prospective
Vendors, at any time choose to discontinue this RFP without obligation to such
prospective Vendors.

Confidential 11
SCOPE OF WORK

REQUIREMENTS
The following information should be used to determine the scope of this project and
provide pricing for this engagement: (Fill in the appropriate information for the
scope of this project, providing as many details as possible about the targets of the
assessment. The rows in the table below provide a few examples for various types of
assessments.)

External Network Vulnerability Assessment


• Number of IP addresses in target space: XX
• Number of live hosts: XX
Internal Network Vulnerability Assessment
• Number of servers in target space: XX
• Number of network devices in target space: XX
• Number of workstations in target space: XX
Server Configuration Reviews
• Number and type (operating system and function) of servers to be reviewed:
XX
Firewall Reviews
• Number of type of firewalls to be reviewed: XX
• Number of rules in each firewall rule set: XX
Web Application Assessment
• Name and description of each application to be assessed: XX
• Number of user input pages for each application: XX
• Number of user roles / privilege levels for each application: XX
Application Code Review
• Name and description of each application to be assessed: XX
• Number of lines of code in the application: XX
• Language(s) the application is written in: XX

DELIVERABLES
At the conclusion of the assessment, ABC Company requires written documentation
of the approach, findings, and recommendations associated with this project. A
formal presentation of the findings and recommendations to senior management
may also be required. The documentation should consist of the following:

DETAILED TECHNICAL REPORT


A document developed for the use of ABC Company’s technical staff which discusses:
the methodology employed, positive security aspects identified, detailed technical
vulnerability findings, an assignment of a risk rating for each vulnerability, supporting
detailed exhibits for vulnerabilities when appropriate, and detailed technical
remediation steps.

EXECUTIVE SUMMARY REPORT


A document developed to summarize the scope, approach, findings and
recommendations, in a manner suitable for senior management.

Confidential 12