Академический Документы
Профессиональный Документы
Культура Документы
Fredericksburg plant was initially planned to be closed down by GM after a history of exceeding
budget instead saving and United Auto Workers strike took place. But Joe Henrich, a young and
new plant manager, was able to exploit different opportunities and implemented several process
improvements one after the other. With his great interpersonal and leadership skills, he was able
to regain the trust of the union and senior workers started to take part in the process improvement
he implemented. With the Application for QS 9000 and ISO 9000 the plant I taking a huge step
By February 1997, the 1500 ton press broke down and the production of TCC, a special
press is the first process in the production and will limit the plant productivity if not addressed
immediately.
After analysis of several options, the team recommends to repair the old press with new parts and
install a new die that will cover 3 activities of the current operation all at the same time. This
recommendation has the highest cost amounting to $592,000 but with savings as high as
$666,000. The expected return of the expenses is 10.68 months. In order to be successful, the
team laid out an implementation plan because an execution without a proper plan is nevertheless
February 1997 break-down of the 1500-ton press where the shafts were broken due to excessive
wear over time. Productivity downtime is high and budget attainment of the plant may not be
achieved.
Supporting Arguments:
The 1500 ton press was the first step in the production process and it is the process bottleneck.
breakdown will have a big effect on the operation cost because the press had already depreciated
over 18years in the production arena; in short, the useful life is almost at its end, which will only
Alternative Strategies
Option A: Hire skilled tradesmen from outside the company to repair the broken press using its
old parts. It would cost $75,000 for the service fee assuming the Union accepts the solution. It is
the lowest possible cost among the 3 options and would only take one day downtime. However,
the repair cannot guarantee machine reliability. The 1500 ton press almost reached its salvage
Option B: Vendor will repair the press by using new parts as replacement to the old ones. This
will require four days of downtime and will cost $210,000. Additional $2 will be incurred for the
job for trouble shooting. (Refer to Appendix 1 for the detailed computation)
Option C: Repair the press with old or new parts and install a more complex new die. The new
die would eliminate another two steps in the process allowing 1500 ton press to accomplish three
steps at once. The new operation would eliminate three operators each shift. However, it needs a
two week downtime and at least three months for the whole new operation to be fully operable.
The old die would remain to operate in case of malfunction of the new die. This option is the
most expensive and ambitious in terms of introducing new operation for the workers but can
deliver savings for long term operations. The total cost for this option is $592,000 for old
equipment to be replaced by new parts or $457,000 for old equipment to be repaired and the
expected wage savings is around $666,000. (Refer to Appendix 1 for the detailed computation)
Recommendation:
Base on the strategies presented, below is the summary of cost and benefit analysis:
implementation. Taking into consideration the current status of the plant, we can say that to
minimize financial loss we should eliminate option A because the press is almost reached its
salvage value. Although it has the lowest cost, investing on this will only mean that there will be
higher maintenance and operation cost for the succeeding breakdowns. Reliability is an issue
when longer-term goals are at hand. On the other side, choosing option B will have a longer
1
return on investment (ROI) . The Fredericksburg plant cannot afford savings from other
improvements to suffice the 4.62 years ROI of the press. Therefore, we choose option 3 where
the old equipment will be replaced by new parts. It may have a higher cost than the counterpart
(replacing with old parts), but since there is only 2 months difference between the two there will
be a great advancement in terms of production capacity if new parts are installed. The return on
investment will happen after 10.68 months from starting day of full operation. In case the new
die will not function as expected, the old press, which will be repaired, will suffice the needed
Implementation
The current month is February 1997, they still have 4 months before the accreditation. By the
time June has come, the operation should be fully operable as well as processes are already in
months to be fully operable and of course is expected to have a higher capacity. Before the
installation of the new die, the old press must be repaired first with new parts. Four days is
expected for the downtime but with one day WIP, 3 days of inventory will be outsourced. After
the repair, the new die will then be installed for about 2 weeks and within this duration, the
production will depend on the repaired press output. Trainings must be done for the workers who
will be retained in the operation during the installation of new die because 3 activities are
expected to be done all at the same time by the new die, thus, new process operation will soon
govern. Reassignment of work, reorientation of job description and other related activities should
be done ahead. By the time the new die is ready for full operation, workers who will be involved
in the new operation are also ready. Since there is uncertainty whether the new die will function
as expected, the repaired press can always suffice the needed TCC for daily production. The
good thing about the repaired press is that it will last longer and has higher reliability than just
Going back to Joe’s vision for the company, we can say that the best strategy to withstand the
challenges of the plant continually is to maintain the pace of slowly adapting the new culture of
continuous improvement. This culture must be embedded in Fredericksburg plant and the
management had been highly effective in doing this. The opportunity to improve and qualify for
the QS9000 and ISO9000 certifications will come smoothly as they continue to solve issues and
Option B:
Cost to repair with new parts $210,000
Cost for outsourcing $2/TCC
Number of TCC needed per day 22,000 units
Number of days to be sufficed with outsourced TCC: 3 days Note: 4 days downtime; 1 day WIP
Per year average base wages $42,000 Note: Overtime are eliminated
Benefit Cost $32,000
Total Cost
= $210,000 (Cost to repair with new parts) + $132,000 (Cost during downtime)
= $342,000
Return on investment
= $342,000(Total Cost) / $74,000 (Annual Potential Savings)
= 4.62 years
Option C:
Cost to repair with new parts $250,000
Cost to repair with old parts $210,000
Cost for outsourcing $2/TCC
Number of TCC needed per day 22,000 units
Number of days to be sufficed with outsourced TCC: 3 days Note: 4 days downtime; 1 day WIP
Per year average base wages $42,000 Note: Overtime are eliminated
Benefit Cost $32,000
Number of shifts 3 shifts
Number of workers per shift to be omitted 3 workers
New Parts:
Cost during downtime
= 22,000 (Number of TCC produced) * $2 (TCC additional cost) * 3days (Number of days downtime)
= $132,000
Total Cost
= $250,000 (Cost for new die) +$132,000 (Cost during downtime) + $210,000 (cost to repair with new parts)
= $592,000
Return on investment
= $592,000(Total Cost) / $666,000 (Annual Potential Savings)
= 0.89 years or 10.68 months
Old Parts:
Cost during downtime
= 22,000 (Number of TCC produced) * $2 (TCC additional cost) * 3days (Number of days downtime)
= $132,000
Total Cost
= $250,000 (Cost for new die) +$132,000 (Cost during downtime) + $75,000 (cost to repair with old parts)
= $457,000
Return on investment
= $457,000(Total Cost) / $666,000 (Annual Potential Savings)
= 0.69 years or 8.28 months
Reference:
1
computation used only depends on the available data