A. If a risk is identified in a risk response plan, then that means that risk has already
happened.
B. Once a risk has happened, you refer to the risk management plan to determine what
action needs to be taken.
C. A risk that was not planned but has happened is called a trigger.
D. Risk identification happens in all the phases of the project.
9. Which of the following is an output of the Risk identification process.
A. Lessons Learned
B. Checklists
C. Risk Register
D. SWOT Analysis
10. In which process of Project Risk Management knowledge area are numeric values are
assigned to probabilities and impact of risks
A. Qualitative Risk Analysis
B. Quantitative Risk Analysis
C. Numeric Risk Analysis
D. Risk Response Planning
11. Which is least risk phase of a project?
A. Planning
B. Closing
C. Execution
D. Control
12. You are the project manager of a Project. Which of the following techniques will you use to
create the risk management plan?
A. Planning meetings
B. Status meetings
C. Variance meetings
D. Risk tolerance
13. A risk trigger is also called __________?
A. A warning sign
B. A delay
C. A cost increase
D. None of the above
14. A risk is _________occurrence that has a positive or a negative effect on a project
A. Known
B. Uncertain
C. Known
D. Potential
15. The Risk Register is initiated during __________phase?
A. Risk Identification
B. Risk Management Planning
C. Qualitative Risk Analysis
D. None of the above