Академический Документы
Профессиональный Документы
Культура Документы
of ICT
3 You are responsible for the update the web site for your organization.. Your
current assignment is:
A. Project management
B. Functional management
C. Facility management
D. Program management
4 At what point in the project would stakeholders have the most ability to influence
the final outputs of the project product?
A. Implementation
B. Development
C. Concept
D. Close out
5 Phase exits, kill points and stage gates are used for what purpose?
A. Planning the next stage in the project
B. Communicating milestones to stakeholders
C. Determining if the project should continue into the next phase
D. Measuring earned value
14 It is critical for your company to offer its products on the Internet to increase its
market share. The company has no previous experience in this area, but it
believes that knowledge is needed rapidly. As you have shown an interest in the
Internet, you are asked to start planning for this project. The first step to take as
you begin planning is to:
a. identify the risks.
b. plan the scope.
c. prepare a schedule.
d. negotiate a budget.
18 Based on the life cycle model of the typical project, which stage is expected to
experience the highest resource usage?
A. Initial phase(s)
B. Intermediate phase(s)
C. Closing phase(s)
D. Staffing phase(s)
20 Core processes:
A. Can interact differently with one-another, depending on the nature of the
project
B. Have clear dependencies
C. Must be preformed simultaneously
D. Are managed by the same staff members throughout the project
A. Project charter
B. Constraints
C. Alternatives identification
D. Assignment of the PM
26 Project alternatives are examined during the _____ phase of the project
A. conceptual
B. finish
C. development
D. implementation
E. A and C
27 Project leadership requires that the project manager pay attention simultaneously
to the:
A. Tasks to be performed and needs of the team
B. Quantity and quality of the work to be performed
C. Efficiency and effectiveness of the team
D. Time, cost and performance deliverables
E. All of the above
28 The primary source document for establishing the content of the Project Status
Report is:
A. The project charter
B. The Project Plan
C. The ASTM Project Document Guide
D. The summary work breakdown structure
29 Project life cycles are very useful for _____ and _____ .
A. Configuration management, termination
B. Objective setting, information gathering
C. Standardization, control
30 Interfacing with the customer after project go-ahead is the responsibility of: C
A. Project sponsor
B. Project team
C. Project manager
D. Functional manager
E. All of the above are possible, based upon the size and complexity of the
project
- end -