Вы находитесь на странице: 1из 74

Review of 

The Enterprise Development Fund 

Research, Evaluation and Monitoring Team 

Industry and Regional Development Branch 

MINISTRY OF ECONOMIC DEVELOPMENT 
 
 
September 2005 

 
 
 
 
 
 
 
 
 
 
 
 

 
 
 
 
 
 
 
 
  Ministry of Economic Development
Industry and Regional Development
  Research, Evaluation and Monitoring
Level 10, 33 Bowen Street
  P O Box 1473
Wellington 6140
New Zealand
 
 
Contents 
 

Acknowledgments.........................................................................................................................4 
Executive Summary.......................................................................................................................5 
PART ONE: Evaluation Goals and Methodology. ..................................................................12 
9.  Goals of the evaluation...................................................................................................12 
10.  The intervention logic.....................................................................................................12 
11.  Methodology....................................................................................................................12 
12.  Methodology of the survey............................................................................................13 
PART TWO: Policy Rationale for the Enterprise Development Fund ................................15 
1.  MED Policy ..........................................................................................................................15 
13.  Policy objectives for the Foundation Services.............................................................15 
14.  Policy objectives for the Enterprise Development Fund...........................................15 
2.  NZTE policy.........................................................................................................................17 
15.  Design of the Enterprise Development Fund .............................................................17 
16.  Criteria for projects .........................................................................................................17 
17.  Scoring of applications ...................................................................................................17 
18.  Future changes: devolvement and criteria for 05/06..................................................18 
PART THREE: Findings and Recommendations on the Implementation of Policy.........20 
19.  Programme implementation .........................................................................................20 
20.  Response by MED to the Enterprise Networks implementation.............................20 
21.  Operational implementation: the Business Evaluation Team ..................................21 
22.  Operational implementation: the Enterprise Development Team ..........................21 
23.  Design of the Enterprise Development Grants scheme.............................................22 
24.  Project activities available under EDG.........................................................................26 
PART FOUR: Findings and Recommendations on Delivery of EDG .................................28 
3.  Uptake of the fund ..............................................................................................................28 
25.  Total allocations...............................................................................................................28 
26.  Total number of applications ........................................................................................28 
27.  Total number of firms.....................................................................................................29 
28.  Approval rate...................................................................................................................29 
29.  Calls to the Business Evaluation Team ........................................................................29 
30.  Change in application numbers over time ..................................................................30 
4.  Assessment of applications................................................................................................32 
31.  Change in approval rate over time...............................................................................32 
32.  Recommendations...........................................................................................................35 
33.  Time taken to approve grants .......................................................................................36 
34.  Average time taken to approve grants over time.......................................................36 
35.  Recommendation ............................................................................................................37 
5.  Distribution of the EDG .....................................................................................................38 
36.  Summary of findings on distribution of the EDG ......................................................38 
37.  Regional spread of firms assisted .................................................................................38 
38.  Regional spread of allocations ......................................................................................39 
39.  Sectoral spread of allocations ........................................................................................40 
6.  Grant allocation and collection by firms..........................................................................42 
40.  Amounts allocated ..........................................................................................................42 
41.  Amount claimed by closed projects .............................................................................42 
7.  Analysis of applicant firms................................................................................................43 
42.  Summary of findings given below. ..............................................................................43 
43.  Overall size: turnover and FTE .....................................................................................43 
44.  Exporting ..........................................................................................................................44 
45.  Age of Firms.....................................................................................................................45 
46.  Firm Growth ....................................................................................................................45 
8.  Types of assistance funded ................................................................................................47 
47. Advice and expertise categories .................................................................................................... 47
PART FIVE: Findings and Recommendations on Outcomes ................................................49 
9.  The framework for analysis of outcomes. .......................................................................49 
48.  Goals of the EDG.............................................................................................................49 
49.  Goals of the evaluation...................................................................................................49 
50.  Specific outcomes sought by the evaluation ...............................................................50 
51.  Interpretation of the policy intent: improving management or business 
capability?..................................................................................................................................50 
52.  Interpretation of the policy intent: improving management ability or    
knowledge? ...............................................................................................................................51 
10.  Quantitative findings on accepted firms. ........................................................................53 
53.  Guide to the findings ......................................................................................................53 
54.  Numbers of firms responding.......................................................................................54 
2
55.  Numbers of firms completing projects. .......................................................................54 
56.  Overall satisfaction .........................................................................................................54 
57.  Proportions of EDG clients seeing changes in the way they manage their 
business......................................................................................................................................55 
58.  Proportions of EDG clients undertaking projects aimed at management level 
areas or business level areas ...................................................................................................56 
59.  Proportions of EDG clients seeing gains in firm activity ..........................................57 
60.  Proportions of EDG clients seeing changes in firm performance ............................58 
61.  Proportions of EDG clients gaining facts or advice ...................................................59 
62.  Do facts or advice projects impact on management practice?..................................60 
63.  Are facts or advice projects also management or business level projects?.............61 
64.  Do management level or business level projects impact on management practice?
  ............................................................................................................................................61 
65.  Do changes in management practice impact on firm performance? .......................62 
66.  Do advice or facts projects impact on firm performance? ........................................63 
67.  Do management or business level projects impact on firm performance?.............64 
11.  Quantitative findings: interpretation and conclusion ...................................................65 
68.  Overall ..............................................................................................................................65 
69.  Activity types...................................................................................................................66 
70.  Interpreting the results: improving management capability....................................66 
71.  Resolving the ambiguity between facts and advice...................................................67 
72.  Declined firms..................................................................................................................68 
73.  Recommendation ............................................................................................................68 
12.  Qualitative findings ............................................................................................................69 
74.  Guide to the findings ......................................................................................................69 
75.  Overall ..............................................................................................................................69 
76.  Business/strategic plan development and feasibility studies. ..................................69 
77.  Intellectual property protection. ...................................................................................70 
78.  Strategic Design...............................................................................................................70 
79.  Market research and marketing plans .........................................................................71 
80.  Prototype ..........................................................................................................................71 
81.  Mentoring and training ..................................................................................................72 
82.  Certification and systems evaluation ...........................................................................72 
Appendix: Survey Questions .....................................................................................................73 
3
Acknowledgments 
 
The evaluation would like to thank Dr Richard Arnold, Senior Lecturer in Statistics with 
the School of Mathematics, Statistics and Computer Science of Victoria University of 
Wellington, for his valuable and essential advice on the evaluation and data analysis, 
and for reviewing many drafts of the report.  
The evaluation would also like to acknowledge the openness with which New Zealand 
Trade and Enterprise worked with this evaluation, and the over 100 firms who gave 
their time to talk with the evaluation.  
 

4
Executive Summary 
 
1. Purpose and evaluation methodology   
1. In  accordance  with  the  New  Zealand  Trade  and  Enterprise  (NZTE)  Foundation 
papers  (EDC  (03)  54  refers)  the  Ministry  of  Economic  Development  (MED)  has 
conducted an evaluation of the Enterprise Development Fund (EDF).  
2. The focus of the evaluation was to examine: 
• Programme implementation 
• Programme delivery 
• Programme outcomes 
And  conclude  whether  the  programme  should  continue,  and  continue  unchanged  or 
with changes.    
3. NZTE  split  the  EDF  into  ‘Enterprise  Development  Grants’  and  ‘Enterprise 
Networks’.  Enterprise  Networks  has  now  been  removed  from  the  EDF.  This 
evaluation  has  examined  implementation  for  the  fund  as  a  whole,  but  examined 
delivery and outcomes for the Enterprise Development Grants only. 
4. The  evaluation  analysed  NZTE  data  and  interviewed  NZTE  staff  responsible  for 
assessing applicants to the EDG. In order to answer questions about outcomes the 
evaluation  undertook  a  telephone  survey  of  a  representative  sample  of  EDG 
recipients.  The sample was a stratified simple random sample of 132 firms with a 
response rate of 98%.  
 
2. Summary of the Enterprise Development Fund 
5. The EDF was established in 2003 (EDC (03) 54 refers) as part of NZTE foundation 
services.  Three  programmes  were  amalgamated  to  form  the  EDF:  the  Enterprise 
Awards  Scheme,  the  Export  Network  Programme  and  World  Class  New 
Zealanders. These three all delivered funding assistance to firms.   
6. The EDF was appropriated $8.613M annually (for 03/04 and 04/05). 
7. The EDF provides funding of 50% of total costs for businesses and entrepreneurs to: 
− Engage the services of a business mentor for a finite period of time 
− Undertake  more  advanced  management  and  technology  based  training  (as 
delivered through existing providers such as NZIM, Polytechnics etc) 
− Employ  specific  external  advice  and  expertise  in  a  management  area  (such  as 
feasibility studies, e‐business, market research, enhancement and uptake of new 
technologies,  human  resources,  intellectual  property,  strategic  planning, 
environmental management, production management) 

5
− Undertake  international  market  development  activities,  including  new  market 
investigation,  trade  fair  participation,  trade/business  missions,  business 
exchanges, and visiting buyers. 
 
3. Implementation of EDF 
8. MED considered the implementation of EN by NZTE sufficiently different from its 
policy  objectives  to  remove  Enterprise  Networks  from  the  EDF.  Funding  for 
Enterprise  Networks  was  moved  to  operational  expenditure  (CAB  Min  (04)  38/4 
refers). 
9. EN is now part of NZTE’s sector facilitation activities. NZTE have been invited to 
give the  policy framework for these activities, and MED is currently  in  discussion 
with NZTE on this.  
 
4. Implementation and Delivery of EDG 
10. The  design  of  the  fund  was  to  mitigate  issues  present  in  the  former  schemes  by 
improving  accessibility,  eliminating  delays  and  lack  of  clarity  in  the  application 
process, and by adhering consistently to clear criteria.   
11. Some of these issues have not been fully addressed: 
− Assessment involves a significant degree of subjective interpretation of criteria.  
− Firms  may  be  declined  at  the  end  of  the  financial  year  not  because  they  fail 
criteria but only because the fund has been fully spent.  
− NZTE does not advertise the fund widely and this reduces the chances the fund 
will  encourage  those  who  do  not  usually  seek  help  to  do  so,  and  so  limits  the 
fund’s ability to achieve the goal of changing opinions about seeking help.  
− Turnaround of applications is on average a month, from first submission to final 
decision.  
12. By Quarterly Report figures EDG was fully subscribed for the 04/05 year, and had 
an under spend in 03/04. 
13. The  numbers  of  firms  applying  to  the  EDG  has  increased  40%  over  the  two  years 
since implementation, giving a total of 684 firms applying to date. 570 applications 
were accepted. This is a small number and the fund at its current size will probably 
not have significant impacts on New Zealand SME capabilities.  
14. There  has  been  a  large  change  in  the  approval  rate.  At  inception  80%  of  all 
applicants were approved but the rate has subsequently reduced. Approvals were 
at 70% by January 2005, 60% by April 2005 and at 50% at the end of the 04/05 year.  
15. Delivery  of  the  EDG  is  even  across  regions  and  sectors.  There  is  no  significant 
difference  in  the  numbers  being  accepted  or  declined  across  regions  and  sectors, 
and the rate and size of allocations is similar across regions and sectors.  

6
16. Firms  applying  to  the  EDG  and  firms  being  accepted  include  large  numbers  of 
exporters. New criteria will be implemented in October 2005 to eliminate the export 
focus in favour of ‘net benefit to NZ.’  
 
5. Outcomes of EDG 
17. 84%  of  firms  completed  the  projects  they  had  sought  funding  for,  the  remainder 
decided not to undertake the project or stopped part‐way.  
18. 78% of firms have seen benefits from the grant, in terms of having a product ready 
for launch or launching it, understanding which segments of the market to target, 
improving the way the firm runs, gaining or clarifying a strategy for the future, or 
entering a new market. This means of the 84% of firms who complete a project, 93% 
see positive gains from it. This is a very good result for the EDG. 
19. For the final outcome of improving firm performance, 39% of EDG firms have seen 
gains  in  firm  performance,  in  terms  of  export  or  domestic  sales.  37%  said  it  is  too 
early yet to see such gains in performance. This was usually because while the grant 
was closed the project was taking longer than one year.  
20. For  the  intermediate  outcome  of  improved  management  capability,  56%  of  firms 
saw changes in the way they managed the business; 30% of firms said projects had 
no effect on management‐ but these firms typically had undertaken projects which 
were  not  geared  at  impacting  on  management.  47%  of  firms  gained  management 
level assistance and 41% gained business‐level assistance.  
21. The  management  changes  included  altering  the  internal  practices  of  the  firm, 
learning  from  the  project  about  ways  to  tackle  such  projects,  gaining  direction  for 
the firm and sometimes confirming that their own approach had been right. Firms 
also reported an improvement in their overall ability to manage the business.  
22. The  activity  types  of  intellectual  property  protection  and  prototype  development 
had  very  low  rates  of  firms  reporting  changes  in  management  practices, 
undertaking  management  level  projects,  or  gaining  advice.    Intellectual  property 
protection  and  prototype  development  are  not  well  fitted  to  the  goals  of  building 
management capability.     
23. The  evaluation  undertook  a  simple  random  sample  of  declined  firms.  However  it 
had no information on why they were declined, and so if they undertook the project 
themselves even while being declined it may be because they had the capability and 
resources to do so, and so it was appropriate that they were declined.  
24. The evaluation learnt that many were unclear on why they were declined, and this 
left  them  feeling  ‘brushed  off’  and  unwilling  to  reapply  for  assistance.  In  order  to 
not defeat the goal of improving the perception of the value of external assistance, it 
would be appropriate to give more details of why a firm was declined.  
 
 

7
Analysis of the policy goals: management and business capability 
25. The evaluation noted the fund is aimed at assisting both management and business 
capability.  At present, the fund is roughly split 50‐50 between two types of firms: 
those whose goals for the grant were to improve their business’ capability, and firms 
who  wished  to  improve  their  management  capability,  or  who  were  undertaking 
management level projects.   
26. The evaluation distinguished projects by whether they were improving business or 
management  capability,  and  looked  to  see  the  impacts  of  each  project  type.  The 
evaluation  has  found  a  significant  association  between  the  proportion  of  firms 
having  had  management  level  assistance  and  reporting  impacts  on  management. 
This  means  that  results  from  the  evaluation  show  that  firms  undertaking 
management  level  projects  will  usually  also  see  changes  in  the  way  they  manage 
their business. Firms undertaking business level projects are less likely to see such 
changes.  
27. The evaluation also found that firms undertaking projects defined as management 
level had significantly higher rates of gains in performance. This means that results 
from  the  evaluation  show  that  firms  undertaking  management  level  projects  will 
usually  also  see  gains  in  their  performance.  Firms  undertaking  business  level 
projects are less likely to see such changes.  
28. There is a caveat to this finding. Firms undertaking business level projects usually 
said  they  had  not  yet  seen  gains  as  it  was  too  early  given  the  project  they 
undertook. So time is needed to see if the above finding holds. It may not if many of 
the business level project firms see gains in performance from the project in future 
months. 
 
Analysis of the policy goals: improving capability via information or via 
building skills    
29. The evaluation found there is uncertainty in whether the fund’s objective is to be a 
channel by which managers can access information, or whether it is to assist them 
build  their  capability.  At  present,  two  types  of  firms  are  accessing  the  fund:  those 
who can themselves implement the project but need information to do so, and those 
who need assistance to gain the capability to implement their project.  
30. The  evaluation  distinguished  projects  by  whether  they  delivered  advice  to  build 
capability, or delivered information to firms, and looked to see the impacts of each 
project  type.  The  evaluation  has  found  a  significant  association  between  the 
proportion of firms having advice or not and having management level or business 
level  assistance;  and  also  seeing  changes  in  management  practice  or  not.  In 
particular,  firms  receiving  advice  had  high  rates  of  receiving  management  level 
assistance  and  seeing  changes  in  management  practice;  whereas  firms  receiving 
facts had higher rates of receiving business level assistance and not seeing changes 
in  management  practice.    This  means  that  results  from  the  evaluation  show  that 
firms having advice will usually also gain management level assistance and usually 
8
see changes in management practice. Firms gaining facts are less likely to see such 
changes.  
31. As  management  level  projects  see  higher  rates  of  gain  in  performance,  it  seems 
aiding management via advice is the best way to aid management to achieve gains 
in performance.  
32. The  evaluation  also  found  a  tentative  association  between  receiving  advice  and 
seeing gains in performance. This suggests firms receiving advice will see gains in 
performance  at  a  higher  rate  than  firms  not  receiving  advice,  but  this  relationship 
may change with time.   
 
6. Operational recommendations for EDG. 
33. Scoring  criteria  for  assessing  applications  need  to  be  defined  carefully  to  ensure 
they may be applied objectively and filter applicants appropriately. This is a crucial 
part  of  ensuring  the  goals  of  policy  are  met.  NZTE  are  currently  reviewing  their 
criteria and scoring and it would be appropriate for MED to be involved in this.   
34. Firms applying when the fund is fully subscribed or close to full subscription, and 
which  would  otherwise  pass,  should  be  held  over  to  the  beginning  of  the  next 
financial year, rather than being declined.  
35. If an application is felt to have insufficient information it should be returned with a 
request for more information. Only those applications which fail the criteria should 
be declined.  
36. Consideration  should  be  given  to  advertising  the  fund  to  extend  its  reach  and 
improve its ability to improve the perception of external advice in firms. 
37. The EDG assessment team needs a better feedback mechanism of the outcomes of 
projects to help them in assessing applicants. Currently one report is made by firms 
to  NZTE  at  the  close  of  the  grant,  and  it  has  an  optional  provision  of  sales  data 
which  most  firms  do  not  complete.  A  better  feedback  mechanism  would  be 
requiring  in  the  report  the  provision  of  information  on  difficulties  and  successes 
implementing  the  project,  and  what  was  learnt  as  a  result.  There  also  should  be  a 
request  for  a  second  outcome  report  requiring  information  on  sales  six  or  twelve 
months post end of project.  
38. An  examination  is  made  of  the  quality  of  applicants  over  2005/6,  and  the  reasons 
firms  are  declined,  as  part  of  monitoring  the  proportions  of  firms  accepted  and 
declined.  The  proportions  accepted  should  be  around  70%.  If  this  total  is 
inappropriate  given  the  overall  quality  of  applicants,  then  the  positioning  of  the 
fund can be reviewed.  
39. It  is  recommended  NZTE  establishes  a  system  of  storing  electronically  data  from 
the  application  forms  on  all  applicant  firms’  financial  and  capability  needs,  taken 
from their description in the application form of the project and their goals for the 
external advice or expertise. This should be able to be compared to final outcomes 
from  the  project  funded  by  the  grant,  and  would  place  both  an  evaluation  in  the 
9
future  and  NZTE  in  a  stronger  position  to  assess  changes  in  the  firms  post 
intervention. MED should be involved in establishing this system.   
40. The  evaluation  recommends  a  process  is  instigated  of  detailing  in  a  more 
personalized  way  the  reasons  for  a  firm  being  declined,  in  order  to  prevent  these 
firms  feeling  ‘brushed  off’  and  deciding  against  seeking  help  again,  thereby 
thwarting the goal of improving the perception of external advice.  
 
7. Policy recommendations for EDG 
41. To  target  the  fund  more  squarely  at  management  level  projects  the  assessment  of 
proposals and possibly the description of the funds goals to the market, would need 
to  be  revised.  This  would  require  a  definition  from  MED  for  NZTE  of  at  least  the 
core  of  what  ‘management  level’  is  (even  if  the  edges  of  the  distinction  with 
‘business level’ are left somewhat blurry).  
42. The fund could be weighted toward firms wishing to gain advice. This can be done 
by  adjusting  the  assessment  to  spot  these  sorts  of  firms,  and  possibly  the 
description of the fund to the market.  
43. The  evaluation  recommends  a  second  look  is  taken  at  the  sample  in  six  to  twelve 
months to re‐assess outcomes.  If the 37% who said it was too early to see benefits 
from  the  grant  see  gains  in  performance  it  will  raise  the  success  rate  of  the  fund 
significantly. The opportunity can be taken of assessing the current situation of the 
firms  who  had  reported  seeing  gains  in  performance,  to  see  if  the  gains  have 
continued.  NZTE  may  be  in  the  best  position  to  undertake  this,  as  part  of  its  on‐
going monitoring of clients.  
 
8. Overall conclusions    
44. The  evaluation  concludes  that  the  EDG  is  effective  in  delivering  intermediate 
outcomes, and thus far has achieved for nearly half  of firms the final outcomes of 
improved  firm  performance.  Further  evaluative  work  is  required  to  see  the 
outcomes for the remaining half.  
45. Determining additionality, that is, whether the fund was the cause of the changes in 
management  or  business  capability  and  in  firm  performance,  is  usually  taken  to 
require establishing that the fund is the sine qua non cause of the effects in question 
via testing the counterfactual conditional that the effect would not happen without 
the cause. The evaluation was unable to demonstrate this with the methodology at 
its disposal. A well‐designed randomized control trial is the established method of 
demonstrating  such  a  causal  link,  but  a  randomized  control  trial  takes  more  time 
than  the  evaluation  had  to  implement  and  evaluate,  and  would  conflict  with  the 
aims and implementation of the fund, since it would mean withholding grants from 
firms  thought  to  be  worthy  of  them.  The  evaluation  is  satisfied  that  the  evidence 
gathered  by  survey  has  established  a  sufficient  association  between  the  fund  and 
outcomes to merit the fund continuing.  

10
46. The evaluation concludes that the Enterprise Development Grants should continue, 
with  some  adjustments  as  specified  above.  It  recommends  that  MED  review  the 
overall size of the fund and whether it is reaching appropriate numbers of firms.  
 

11
PART ONE: Evaluation Goals and Methodology. 
 
9. Goals of the evaluation 
47. The evaluation had three overarching goals.  
48. The  first  was  to  understand  the  operational  implementation  of  both  MED  and 
NZTE  policy.  This  would  inform  the  Ministry  whether  operation  design  was 
consistent  with  policy  and  whether  the  operational  implementation  was  such  the 
goals of the fund could be achieved.   
49. The  second  was  to  understand  the  delivery  of  the  fund,  in  terms  of  numbers  of 
firms  assisted  and  declined,  regional  and  sectoral  distribution  of  funding,  and  the 
types of firms who had received funding.  
50. The  third  goal  was  to  determine  whether  the  outcomes  policy  wished  to  achieve 
were occurring for the firms undertaking the activities funded by the EDF.  
 
10. The intervention logic 
51. The intervention logic describing the EDF is given below.  
52. The  yellow  boxes  describe  the  problems  the  intervention  is  to  overcome,  the  pink 
boxes  the  activities  the  intervention  will  undertake  to  overcome  the  problems,  the 
blue boxes are the intermediate outcomes the activities should produce, and the red 
boxes  are  the  final  outcomes  that  the  intermediate  outcomes,  and  so  the 
intervention as a whole, should achieve.  
53. In  other  words,  the  activities  of  engaging  the  services  of  a  business  mentor, 
undertaking  more  advanced  management  and  technology  based  training, 
employing  specific  external  advice  and  expertise  in  a  management  area  and 
undertaking  international  market  development  activities  should  result  in 
improving  management  capability,  improving  the  perception  of  the  value  of 
external  advice,  and  improving  collaboration  between  entrepreneurs  and  existing 
firms, and this should result in improved firm performance.  
 
11. Methodology 
54. The evaluation used three different methods to meet its three goals.  
55. To understand implementation the evaluation considered the policy documents of 
MED  and  NZTE,  and  met  with  the  NZTE  teams  and  personnel  who  manage  the 
operation of the EDF, and learnt from them their processes and systems.  
56. To understand delivery the evaluation analysed the data collected by NZTE on the 
firms who apply and are granted or declined a grant.  
57. To  understand  outcomes  the  evaluation  undertook  a  survey  of  a  representative 
sample  of  accepted  and  declined  firms  and  questioned  them  on  their  reasons  for 
applying for a grant, the activities they undertook using the grant, what they learnt, 
and what outcomes had been achieved. 
58. Determining additionality, that is, whether the fund is the cause of any changes in 
management  or  business  capability  and  in  firm  performance,  is  usually  taken  to 
require establishing that the fund is the sine qua non cause of any effects in question 
via testing the counterfactual conditional that the effect would not happen without 
the cause.  
59. The  evaluation  was  unable  to  demonstrate  this  with  the  methodology  at  its 
disposal.  A  well‐designed  randomized  control  trial  is  the  established  method  of 
demonstrating  such  a  causal  link,  but  a  randomized  control  trial  takes  more  time 
than  the  evaluation  had  to  implement  and  evaluate,  and  would  conflict  with  the 
aims and implementation of the fund, since it would mean withholding grants from 
firms thought to be worthy of them.  
60. The evaluation is satisfied that the evidence gathered by survey as it has designed it 
would establish a sufficient association between the fund and outcomes to answer 
questions of outcomes and the question of whether the fund merits continuing.  
 
12. Methodology of the survey  
61. The survey was by telephone interview.  
62. The population was all firms who had completed a project by April 2005, giving a 
total of 191. The sample was a stratified simple random sample with a sample size 
chosen  to  give  a  margin  of  error  of  5%  for  estimates  of  proportions.  This  gave  a 
minimum sample of 129. The evaluation surveyed 132 firms.  
63. The  sample  was  stratified  by  the  activity  types  available  under  the  EDG,  and  the 
activities  to  be  included  were  selected  by  MED  policy.  Policy  wished  to  know  the 
outcomes  for  firms  undertaking  strategic  design,  intellectual  property  protection, 
prototype,  business  or  strategic  plans,  feasibility  studies,  certification,  systems 
evaluation, training, mentoring, market research and market plans.  
64. The  sample  was  selected  as  a  stratified  simple  random  sample  but  with  sampling 
fractions which were similar in each stratum, and also very high, the data could be 
analysed as a simple random sample.  
 

13
Enterprise Development Fund Logic Model 
 
 
 
 Problems Activities  
Intermediate outcomes Final
outcomes
 

Lack of early stage  


financing

Impediments to
  Enterprise Development Fund
provides funding to smaller
collaboration, with firms, entrepreneurs, start-ups, Improved business, management,
resultant inefficiencies   exporters and groups of
companies, after an initial
technology, international business,
exporting and leadership capability
capability assessment, to: Improved firm 
  1. Engage the services of a performance 
Lack of international  business mentor Improved perception in 
 
linkages/contacts 
  2. Undertake more
advanced management
the value of developing 
business capability  Improved 
and technology based Improved perception of the value
international 
Lack of business
  3.
training
Employ specific external
of seeking external advice
competitiveness 
management capability advice and expertise in a Increased global of 
products/services 
(including export,
international
  4.
management area
Undertake international
connectedness

management skills). and domestic market Improved collaboration between  


Also access issues.
  development activities firms

Risk aversion of firms  


 
Undervalue 
contribution of 
external advice 
PART TWO: Policy Rationale for the  
Enterprise Development Fund 
 

1. MED Policy 
 
13. Policy objectives for the Foundation Services  
65. In April 2003 Cabinet agreed to establish the Enterprise Development Fund as part 
of the Foundation Services of NZTE. (EDC (03) 54 refers)   
66. The Foundation Services are to assist small, young firms, young entrepreneurs and 
start‐ups, via information, training and financial assistance.  The rationale was that 
running a business requires skills and knowledge that small young firms may not 
yet  have  acquired.  Acquiring  them  may  be  made  difficult  by  the  expense  of 
purchasing external advice and expertise and a belief that expertise is not required 
or is not valuable. The foundation services were established to make acquiring the 
skills and knowledge easier and more attractive for firms. The rationale was given 
in EDC (03) 54 as: 
Small  businesses  and  entrepreneurs  often  lack  the  financial  ability  to 
employ  all  the  expertise  they  need  to  get  new  concepts  and  projects 
up  and  running.    They  also  tend  to  undervalue  the  potential 
contribution of expert advice on key elements of their business ideas.  
Without such advice, they are often unable to satisfy the requirements 
of  investors,  banks  and  other  financiers  for  information,  including 
business  planning,  approaches  to  preserving  the  value  of  intellectual 
property,  and  how  they  plan  to  market  their  products  and  services.  
As a result, small businesses often do not realise their full potential.   
These  barriers  could  be  overcome  if  access  to  information  was  made 
simpler  and  business  operators  were  provided  with  better 
opportunities  to  acquire  the  skills  and  knowledge  to  improve  their 
management capability. 
 
14. Policy objectives for the Enterprise Development Fund  
67. Three  Industry  New  Zealand  and  Trade  New  Zealand  programmes  were 
amalgamated to form the EDF: the Enterprise Awards Scheme, the Export Network 
programme  and  World  Class  New  Zealanders.  These  three  all  delivered  funding 
assistance to firms.   
68. The goal of the former Enterprise Awards Scheme (EAS) became the overall goal of 
the EDF. This is to assist innovative firms and entrepreneurs to build capability by 
enabling them to employ expertise and advice. 
69. Funding is for 50% of total costs up to a maximum of $20,000‐ an increase from the 
EAS  total  of  $10,000.  This  is  per  applicant  per  annum,  and  is  for  businesses  and 
entrepreneurs to: 
− Engage the services of a business mentor for a period of time 
− Undertake  more  advanced  management  and  technology  based  training  (as 
delivered through existing providers such as NZIM, Polytechnics etc) 
− Employ  specific  external  advice  and  expertise  in  a  management  area  (such  as 
feasibility  studies,  e‐business,  market  research,  enhancement  and  uptake  of  new 
technologies,  human  resources,  intellectual  property,  strategic  planning, 
environmental management, production management) 
− Undertake  international  market  development  activities,  including  new  market 
investigation, trade fair participation, trade/business missions, business exchanges, 
and visiting buyers. 
70. The  design  of  the  EDF  was  to  address  issues  with  its  predecessor  schemes.  The 
issues were: 
− Criteria:  the  EAS was  a  relative,  awards based  scheme,  where  the  top  proportion 
per  month  received  assistance,  and  the  quality  of  the  proposals  accepted  for 
funded varies from round to round as approval is relative. The EDF was to be an 
objective  criteria‐based  scheme,  where  any  firm  which  met  certain  criteria  gained 
assistance.  
− Application  turnaround:  businesses  often  did  not  know  for  up  to  two  months 
whether their application was successful.   
− Accessibility: the limited capability of small business owners to self‐appraise their 
needs limits the programmes ability to effectively address critical capability issues. 
− Overlaps:  There  were  overlaps  with  the  case  managed  Business  Growth  Fund.  
The limited funding  of the EAS lead to a  greater focus on high growth and more 
established businesses than was intended.  

16
2. NZTE policy   
 
15. Design of the Enterprise Development Fund 
71. In  a  paper  to  the  Integration  Ministers  (Paper  to  the  Integration  Ministers  4  July 
2003 refers), NZTE gave the detailed report back on its proposed operational design 
and criteria for the EDF requested in EDC (03) 54. 
72. The  paper  noted  that  the  EDF  was  an  amalgamation  of  the  three  predecessor 
programmes  and  that  it  would  remain  similar  to  them.  It  also  noted  that  grants 
were for $20,000 and for 50% costs. The activities to be funded were also the same.  
73. NZTE proposed some additional design features. These were: 
−  Criteria:  the  fund  would  adhere  to  clear  criteria  and  would  centralise  all  final 
approvals within NZTE.  
− Application  turnaround:  the  approval  processes  would  ensure  a  high  level  of 
responsiveness to clients. NZTE anticipated a fast turnaround of applications, and 
aimed for a five day turnaround from receipt of applications. 
− Overlaps: the fund would remain accessible and responsive to start‐up businesses 
and entrepreneurs not yet in business.  
− Ease  of  application:  the  application  forms  for  the  EDG  and  background  material 
would  be  as  clear  and  as  easy  to  complete  as  possible.  Being  aware  that 
applications  forms  and  the  information  required  must  still  be  reasonably 
demanding  to  ensure  accountability,  NZTE  undertook  to  provide  clients  with 
assistance in completing application forms. 
 
16. Criteria for projects   
74. NZTE established criteria for the project or activity firms wished funding for. These 
are: 
− The  project  must  have  good  commercial  potential  and  add  value  to  an  existing 
business or an entrepreneur’s current activities 
− Applicants must demonstrate that they have the capacity and capability (including 
financial and planning support) to carry the project through to commercialisation 
− The project or activity must be capable of generating high returns, or high levels of 
growth for the applicant once commercialised or undertaken. 
− The project must be consistent with relevant laws and regulations 
 
17. Scoring of applications    
75. NZTE  noted  it  expected  high  levels  of  demand  for  the  EDG,  because  it  had 
experienced high levels of demand for the Enterprise Awards Scheme, where only 
17
30% of applicants were accepted. NZTE proposed to score proposals for the EDG to 
ration demands for funding, so only those applications which best met the goals of 
the programme and of NZTE received funding. Applications were proposed to be 
scored  against  criteria  with  weightings  so  certain  criteria  were  more  important  to 
achieving the critical score. The criteria were given as: 
− Robustness of the project plan 
− financial and organisational stability 
− ability of organisation to implement project/undertake activity 
− level of innovation or additionality associated with the project or activity 
− level of growth within the organisation and likely economic benefits 
− level of need for government assistance 
 
18. Future changes: devolvement and criteria for 05/06 
76. FRST and NZTE have begun to align the delivery of EDG and Smartstart (EDC Min 
(04)  25/5  refers).  The  alignment  involves  devolving  grants  of  $5000  and  less  to  an 
agency network.  
77. This,  on  numbers  to  date,  is  15%  of  all  EDG  grants.  A  half  of  these  have  been 
strategic  development  or  product  development  grants  and  a  quarter  have  been 
mentoring or training. The last quarter are evenly spread across the activities.  
78. In  July  2005  (subsequent  to  the  evaluation’s  timeframe)  Ministers  agreed  to  revise 
the  EDG  criteria  to  make  clearer  the  distinction  between  programme,  entry  and 
assessment criteria, and to speed up assessment processes (EDC Min (04) 25/5 and 
The  coordinated  services  delivery  project  update  of  22  July  2005  refers).  NZTE  aims  to 
implement the criteria and scoring system by 1 October 2005.   
79. The revised assessment criteria are now:  
− Robustness of project plan; 
− Ability  of  business/individual  to  undertake  activity  (“previously  ability  of 
organisation  to  implement  project  or  activity  and  their  commitment  and  drive 
to  undertake  planned  work”.  This  criteria  also  picks  up  “financial  and 
organisational stability”);  
− Potential  to  improve  business  performance  (previously  “potential  for  growth 
and benefit to regional/national economies”)  
− Net  benefit  to  NZ  of  improved  business  performance  (previously  “level  of 
innovation or additionally associated with the project or activity”); and 
− Level  of  difference  the  funding  will  make  (previously  “level  of  need  for  govt 
assistance/funding assistance and a catalyst for growth”). 

18
80. NZTE  has  removed  ‘financial  ability’  as  a  criterion,  principally  because  the  firm 
must  expend  the  full  amount  prior  to  reimbursement  by  NZTE,  and  this  is  a 
sufficient step to ensure the firm is financially able to undertake the project.  

19
PART THREE: Findings and Recommendations on the 
Implementation of Policy 
 
19. Programme implementation   
81. The EDF was to be an amalgamation of the former Enterprise Awards, World Class 
New  Zealanders,  and  the  Export  Network  Programme,  delivered  by  Trade  New 
Zealand and Industry New Zealand.  
82. NZTE  has  implemented  the  Export  Networks  Programme  into  the  EDF  quite 
differently  from  its  implementation  of  the  other  two,  in  fact  it  could  be  argued  it 
was  not  implemented  into  the  EDF  at  all,  but  kept  altogether  separate.  It  was 
renamed:  ‘Enterprise  Networks’  (EN).  The  other  two  predecessors  are  renamed 
Enterprise Development Grants (EDG).  
83. NZTE split the appropriation for EDF of $8.613M between the EN and the EDG. EN 
received $4.48M, EDG the rest ($4.413M). 
84. Export Networks aided firms in their exporting efforts by assisting groups of firms 
to  target  high  quality  market  development  opportunities  offshore.  It  did  this  by 
assisting  groups  of  firms  to  take  advantage  of  market  opportunities  which 
individual  firms  could  not,  thereby  achieving  gains  in  forex  performance 
unavailable to individual firms.   
85. The  primary  issue  for  MED  with  EN  was  the  order  of  practice.  NZTE  selected 
offshore  opportunities  and  requested  interest  from  firms  in  those  activities;  rather 
than  establishing  a  process  whereby  firms  applied  for  funding  to  attend  offshore 
activities they had selected.  
86. The selection of offshore activities by NZTE was sector‐led: events were ranked by 
their  degree  of  fit  to  NZTE’s  sector  priorities,  and  those  which  fitted  best  were 
chosen  for  the  year’s  EN  activity.  Client  managers  were  notified  and  they  invited 
firms  on  their  books  whom  they  deemed  appropriate  to  apply.  Firms  not  selected 
could  not  apply.  Offshore  activities  which  were  not  selected  by  NZTE  were  not 
available for firms   
87. The  design  principles  of  the  EN  contradicted  CER.  Targeting  export  education 
breaches the EDF criteria of no common ownership. A number of firms larger than 
criteria for EN have accessed the fund.  
 
20. Response by MED to the Enterprise Networks implementation  
88. MED considered the implementation of EN  sufficiently different from their  policy 
objectives  to  remove  Enterprise  Networks  from  the  EDF.  Funding  for  Enterprise 
Networks was moved to operational expenditure (CAB Min (04) 38/4 refers). 
89. EN is now part of NZTE’s sector facilitation activities. NZTE have been invited to 
give the  policy framework for these activities, and MED is currently  in  discussion 
with NZTE on this.  
20
 
 
The report ends its evaluation of EN here. The rest of the report is on the 
evaluation of the remainder of the EDF: the Enterprise Development Grants 
scheme.  
 
 
21. Operational implementation: the Business Evaluation Team 
90. The  client  managers  for  most  firms  using  the  EDG  are  those  of  the  Business 
Evaluation  Team.  The  Business  Evaluation  Team  is  also  the  ‘frontline’  team  who 
handle the calls to the NZTE hotline phone number. There are 14 members of the 
team. 
91. As client managers, each member of the team has large numbers of EDF and other 
NZTE  clients.  As  they  have  so  many,  they  are  not  expected  to  have  a  proactive 
relationship  with  all  their  clients.  Individual  client  managers  may  choose  to  ring 
firms on their books, but this is not obligatory. Hence EDF clients are called ‘light 
touch’ firms. They are not closely watched by NZTE.  
 
22. Operational implementation: the Enterprise Development Team 
92. The  Enterprise  Development  Team  is  the  central  point  of  assessment  for 
applications for the fund. There are four members.  
93. Firms  can  apply  for  the  fund  directly  to  the  team  using  applications  from  the 
NZTE  website,  or  can  be  guided  to  the  team  by  the  business  evaluation  team.  If 
firms apply directly to the enterprise development team and do not have a client 
manager,  the  team  finds  them  a  suitable  client  manager,  usually  one  from  the 
business evaluation team. 
94. The  team  has  two  hats.  They  have  a  pre‐assessment  role,  where  the  team  assists 
firms with the filling out of firms, reviews applications and may personally advise 
firms  on  whether  the  applications  are  sufficiently  complete  and  what  additional 
information  is  required.  There  is  potential  tension  between  these  two  roles,  but 
careful use of advice on potential is also of benefit to firms who are clearly outside 
the criteria. The assessment process is discussed further in paragraphs 102‐133 
95. The team’s other hat is assessment. Their process is to divide applications among 
team members, and then assess them. The team then meets, usually once a week, 
but  more  frequently  as  necessary,  to  discuss  their  assessment  of  applications.  At 
this point they either confirm the assessment, or reassess them.   
96. Firms are notified by letters if they are accepted or declined. From December 2004 
letters  to  declined  firms  were  changed  to  include  details  on  why  the  application 
was declined. If firms were declined only because they lacked information but are 

21
felt  to  have  potential  they  are  encouraged  to  re‐apply  with  the  additional 
information.  
97. The team is encouraged to become familiar with business, by allowing members to 
visit other NZTE client managers based across New Zealand.  
 
23. Design of the Enterprise Development Grants scheme 
98. The  evaluation  examined  whether  design  issues  and  proposed  design  (given  in 
part two) have been met and implemented.  
 
Assessment against criteria  
99. Firms  are  assessed  against  criteria.    However  there  are  some  issues  with 
assessment which means it is not as objective as it might be, and assessment does 
not always adhere to criteria in ways clear to firms (even if the criteria themselves 
are clear to firms).  
100. Firms who apply late in the financial year are declined only because the funding 
year is finished, and not because they do not qualify. At the end of the 04/05 year 
the  score  firms  had  to  achieve  was  raised  in  order  to  prevent  an  over  spend, 
suggesting firms applying later in the year were disadvantaged. See section 31 for 
further details.  
Recommendation 
101. It  would  be  more  consistent  with  a  criteria‐based  scheme  if  firms  applying  very 
late were held over and approved against the criteria in the first weeks of the new 
financial year.  
102. Scoring should not be raised only to prevent an over‐spend apparent towards the 
end of the financial year, as this unfairly disadvantages firms applying late in the 
financial year. Having raised the scoring NZTE intends to leave it at this level, but 
should not raise it again before the end of the 05/06 year.  
 
Turnaround of applications 
103. NZTE  aims  for  a  fast  turnaround  of  applications  once  they  are  complete.  NZTE 
stated the turnaround would be 5‐days from receipt of application, and there are 
some issues in meeting this. NZTE does not on average make a 5‐day turnaround 
from receipt of application.  
104. Instead,  because  it  assists  firms  fill  out  their  applications,  and  sends  applications 
back  when  they  need  more  information,  NZTE  counts  its  turnaround  from  the 
date the application form is sufficiently complete. NZTE says it maintains a seven 
day turnaround from this point. See section 33 for further details.  
 
 
22
Recommendation 
105. It may be preferable to resolve the inconsistency of returning applications for more 
detail  and  declining  applications  but  with  an  invitation  to  reapply  with  more 
detail.  The  evaluation  recommends  declining  applications  only  when  the  firm 
actually  fails  the  criteria,  and  not  when  there  is  insufficient  information  to  tell 
whether it ought to pass or fail. The latter leaves firms in considerable uncertainty.    
 
Accessibility 
106. The  accessibility  of  the  fund  is  limited  by  its  being  advertised  to  economic 
development  agencies  and  other  consultants,  because  only  firms  already  seeking 
assistance  or  advice  will  learn  about  it.  This  lessens  the  chances  the  fund  will 
encourage  those  firms  who  don’t  usually  seek  external  advice  to  do  so.  It  also 
limits the fund to those who have already decided they have a capability gap.  
Recommendation 
107. Advertising the fund more broadly may solve this issue, however advertising the 
fund broadly must be balanced against the potential resulting problem of the fund 
selling out very quickly in the year.  
 
Overlaps 
108. The delivery of the fund by NZTE has been successful in avoiding overlaps with 
the  Growth  Services  Fund.  NZTE  have  added  to  the  eligibility  criteria  the 
requirement that firms have a turnover of less than NZ$5M and/or 20 FTEs or less.  
109. EDG  clients  are  typically  low  growth,  low  turnover  and  fairly  young.  However 
there was no definition of what ‘young’ meant, or whether it was to be interpreted 
in terms of age, or, for example, growth, or capability. See sections 45 and 46 for 
further details.  
 
Ease of application process  
110. The  evaluation  asked  the  sample  of  firms  it  surveyed  about  the  length  of 
application  time  and  whether  firms  were  satisfied  with  the  time  it  took  them  to 
apply.  The  majority  of  firms  said  that  given  what  resulted  from  the  grant  it  was 
worth the time and effort.   
111. Most firms did go on to say the process was long‐winded and took a great deal of 
time‐ for some days, others hours. On the whole however, having received funds 
and seen a benefit, they were felt the grant was worth the time it took to apply.   
112. Many  also  noted  that  the  process  of  writing  out  their  business  plan  and  plan  for 
the project for the application form was beneficial for their own clarity of business 
goals and current situation.  

23
113. The evaluation can not tell how many 
firms  did  give  up  in  filling  out  the  Satisfaction with the time taken to apply
forms and never applied. Some firms 
told  the  evaluation  they  nearly  gave  Sample of closed projects 1/10/2003 to 4/2005
up.  If  there  were  ways  of  shortening 
120

the  application  forms,  it  may  be 


worth considering.   100

80
114. Some  firms  commented  that  they 

Number
wished  for  more  flexibility  in  60

adjusting  the  project  once  it  had  40

started.  NZTE  will  not  reimburse 


20
firms  for  additional  tasks  on  the 
project  to  those  in  the  original  0
worth it Not worth it

application.  The  claims  must  match  Worth of time taken

the  tasks  laid  out  in  the  original 


application form. The only variation which is permitted is to change the external 
provider. Many firms find as the project develops that they need to add tasks to it, 
and  firms  have  explained  to  the  evaluation  that  they  cannot  predict  the  project 
exactly one year out, and often things eventuate which they didn’t anticipate. The 
firms argued that this is the nature of undertaking early‐stage projects.  
115. To  get  around  this,  firms  try  to  have  applications  accepted  with  minimal 
information,  to  give  them  the  freedom  to  add  tasks  later,  and  yet  still  have  the 
project fit the original broad application.  
116. NZTE  notes  it  must  balance  flexibility  in  process  with  the  time  it  must  spend 
evaluating whether a change in a project is appropriate and whether it changes the 
project sufficiently it as a whole no longer qualifies for funding. It feels the costs of 
this will outweigh the benefits to firms.  
 
Recommendation 
117. With  devolvement  it  may  be  that  issue  of  adjusting  projects  mid‐way  can  be 
ameliorated  with  the  greater  degree  of  contact  between  firms  and  the  delivery 
agents. This issue might best be considered when the devolvement is evaluated.  
 
Criteria and scoring of proposals 
118. From  implementation  until  October  2005  the  criteria  which  have  been  used  to 
assess  firms  were  as  initially  proposed.  (The  changes  made  subsequent  to  the 
time‐frame of the evaluation were given above).  
119. The categories for the criteria for the time‐frame of the evaluation were:  
− robustness of proposal 
− financial and organisational stability 

24
− ability  of  organisation  to  implement  project  or  activity  and  their  commitment 
and drive to undertake planned work 
− potential for growth and benefit to regional/national economies 
− level  of  need  for  government  assistance/funding  assistance  as  a  catalyst  for 
growth 
− level of innovation or additionality of the product/service of the value added to 
existing 
120. Under  each  category  have  been  added  descriptions  and  corresponding  scores, 
ranging from poor to good.  
121. The team is to match the application to the description and score accordingly. For 
example  under:  ‘ability  of  organisation  to  implement  project  or  activity’  the 
descriptions and scores are:  
1‐3   Lack of or limited experience in the industry  
  Lack of or limited experience in business 
Management depth appears light in some areas 
4‐6  Demonstrated level and depth of management experience 
Demonstration of drive to succeed 
Evidence of transferable skills 
Mentors/support work engaged as needed 
7‐10  Demonstrated depth of management experience 
Experience in industry 
Obtains external advice or mentoring 
122. The higher the score the better an applicant does by that criterion. The scores are 
then  weighted.  The  scores  an  applicant  receives  under  ‘growth  potential’  and 
‘innovativeness of product’ are multiplied by 20. The others are multiplied by 15.  
123. An  applicant  must  obtain  a  minimum  of  4  out  of  10  for  ‘growth  potential’  and 
‘innovativeness of product’ and 3 out of 10 for each of the others to be approved. 
Multiplied, that is 80 out of 100 and 45 out of 100 respectively.  
124. An applicant must get a total of 570 overall to be approved. 
125. The  team  meets  regularly  to  confirm  assessment  scoring,  however  they  have 
reported  to  the  evaluation  that  there  is  close  consistency  in  scoring  by  the 
members,  and  so  they  have  decided  to  cease  meeting  regularly  to  check 
consistency of scoring. 
 
Recommendation 
126. The  evaluation  has  noted  that  there  is  some  ambiguity  between  the  criterion 
addressing  ability  of  the  firm  to  implement  the  project  they  seek  funding  for, 
25
which is measured by management experience, and the capability‐building goal of 
the fund.  
127. Firms gain higher scores and thereby are more likely to be granted an award the 
more  experience  they  have.    They  gain  between  7  and  10  points  if  they  have: 
‘demonstrated  depth  of  management  experience’  or  ‘experience  in  industry’  or 
‘obtains external advice or mentoring.’ They will fail the criteria if they have: ‘lack 
of  or  limited  experience  in  the  industry’  or  ‘lack  of  or  limited  experience  in 
business’ or ‘management depth appears light in some areas.’ 
128. It  seems  inconsistent  with  building  capability  if  a  lack  of  or  limited  amount  of 
experience fails a firm. It may help if the criterion and scoring refer specifically to 
the minimum kind of experience firms should have, to qualify, and not the degree 
of experience (measured, say, by years). The EDG can then be more easily aimed 
at those firms with certain basic skills who lack more sophisticated skills.  
129. The  tests  for  net  benefit  to  NZ  are  improved  productivity  and  efficiency,  limited 
displacement  (displacement  would  result  from  funding  firms  with  significant 
domestic  focus  and  significant  domestic  competition)  and  presence  of  spillovers. 
These  are  still  high  level  concepts  requiring  variables  which  can  identify  in  a 
project description when and to what degree productivity would be improved, or 
when and where a spillover would occur.  
130. Translating  high  level  concepts  into  concrete  variables  (operationalising  the 
concepts)  is  a  crucial  part  of  ensuring  the  goals  of  policy  are  met.  For  example, 
‘level of difference’ must be operationalised in such a way that the variables which 
are  to  indicate  funding  will  make  a  level  of  difference,  really  do  indicate  the 
funding  makes  the  required  difference.  If  they  don’t,  firms  are  not  truly  being 
assessed against that criteria. 
131. The  evaluation  recommends  MED  is  involved  in  assisting  with  development  of 
the scoring criteria for the EDG assessments. 
 
24. Project activities available under EDG 
132. The  full  range  of  project  activities  available  to  firms  through  the  EDG  is  broader 
than first proposed. The activities currently available are: 
− strategic business development (including business/strategic plan development, 
human  resource  strategic  plan  development,  financial  viability  planning, 
strategic design advice) 
− feasibility studies 
− product  development  (including  prototype  design,  development  and  testing, 
intellectual property protection) 
− business  and  operational  excellence  (including  international  quality  standards 
certification, systems evaluation and development, environmental management 
system) 

26
− e‐commerce and e‐business strategies (including development of a e‐strategy) 
− Market  strategy  development  (including  market  research  or  new  market 
investigation, marketing plans).  
133. These  activities  cover  a  very  broad  range  of  possible  activities,  but  are  not  all 
equally popular, and some are rarely taken up by firms. The most popular, and so 
most  of  the  allocations  have  gone  to:  intellectual  property  protection,  prototype 
development,  strategic  business  development,  and  strategic  design  advice.  See 
section 47 for further details.   

27
PART FOUR: Findings and Recommendations on  
Delivery of EDG 
 
Note:  NZTE  has  some  problems  with  its  data  system  and  has  difficulties  extracting  data  from  it.  The 
evaluation is aware that details on at least 153 applications are missing from its data set.  This is 17.4% of 
the total grant data for EDF. The evaluation has no details on these applicants and so has not included them 
in  its  analysis.  The  evaluation  is  confident  the  data  it  has  is  sufficient  to  give  an  accurate  picture  of  the 
delivery of the EDG to date. 
 
134. There are possible impacts of delivery that the evaluation is unable to determine 
exactly;  for  example,  the  development  of  a  network  of  consultants  able  to  help 
businesses and willing to encourage businesses to seek their help. Conversely, for 
example,  it  is  possible  that  the  fund  stimulates  consultants  to  adjust  their  fees 
upward to take advantage of the 50:50 funding.  
 

3.  Uptake of the fund 
 
Note: for section 3 and 4 only the evaluation reports on data for 20 Months, that is, from October 2003 to 
end June 2005. This covers the time from implementation until the end of the 04/05 year.  
 
25. Total allocations  
135. NZTE allocated $4.133M to EDG.  
136. The total appropriated to the EDG for 03/04 and 04/05 is $8.266M 
137. The evaluation has a total allocation for 03/04 and 04/05 of $6,424,798.11.  
138. By NZTE quarterly report figures there was an under spend in 03/04 but 04/05 was 
fully  subscribed.  Quarterly  report  figures  have  a  total  allocation  for  EDG  of 
$M7.253.  
 
26. Total number of applications 
139. In 20 months NZTE has received 809 applications for the Enterprise Development 
Grants capability building component.  
140. In the 2003/2004 year there were 320 applications.   
141. In  the  2004/2005  year  there  were  489  applications.  This  is  a  53%  increase  from 
03/04 to 04/05.  
 
 
28
27. Total number of firms 
142. Note  that  firms  reapply,  and  so  there  Firms returning for a second grant
have  been  more  applications  for  the 
grant than there are firms applying  1/10/2003 to 30/6/2005

143. Over 20 months from October 2003 to 30  $20,000.00

June 2005 684 firms have applied for the 

2004/2005 Amount claimed


EDG. The small size of the EDG limits its  $15,000.00
impact on SMEs.  
144. 285 firms applied in 03/04.   $10,000.00

145. 399 firms applied in 04/05. This is a 40% 
increase from 03/04 to 04/05.   $5,000.00

146. The  graph  right  shows  firms  who 


$0.00
reapplied. Firms claiming two grants are 
$0.00 $5,000.00 $10,000.00 $15,000.00 $20,000.00 $25,000.00
represented by dots in the middle of the  2003/2004 Amount claimed
graph.  Those  who  did  not  receive  two 
grants are the dots on $0 on both axes.  
147. 136  firms  (16%)  have  reapplied  for  the  EDG.  68  (8%)  reapplied  for  the  same 
project,  with  20  of  those  declined  again,  and  34  accepted.  Three  were  declined 
twice  then  accepted.  The  evaluation  has  recommended  earlier  that  a  clear 
distinction  be  made  in  assessment  processes  between  returning  applications  for 
more information and declining applications.  
 
28. Approval rate  
148. In  the  period  October  2003  to  June  2005  EDF  has  approved  570  applications  and 
declined 216 applications.  
149. This is 786 in total, and the difference from the earlier total given of applications 
(809)  is  that  that  was  number  of  applications  handled.  Some  of  these  have  been 
returned to firms who did not reapply.   
150. In  the  2003/2004  year  251  applications  were  accepted  (81%)  and  57  declined 
(18.5%).   
151. In the 2004/2005 year 319 applications were accepted (68%) and 159 were declined 
(33%). 
 
29. Calls to the Business Evaluation Team 
152. EDG inquiries can be made to the business evaluation team who run the ‘frontline’ 
NZTE hotline number, and the team may recommend firms to apply for an EDG 
grant. The data from the call centre does not give a picture of the interest in EDG 
going via the centre.  

29
153. The  call  centre  does  not  tally 
distinctly  the  various  NZTE  grants,  Inquiries to the hotline team

so  all  grant  inquiry  by  telephone  is 


under  ‘grants.’  From  03/04  to  March  1/17/2003 to 30/4/2005
04/05 (see graph right) the number of  3000 Total calls
requests  for  grants  handled  by  the  Web inquiries
Grant advice
2500
hotline call centre looks steady.  
2000
154. The  data  on  web  hits  does  not 

Number
1500
exclude  hits  generated  by  spam,  so 
the web data does not show whether  1000

genuine  hits  have  increased  or  500

decreased. NZTE is working  to build 
0
firewalls,  and  notes  that  this  will 

DEC 2003

DEC 2004
SEP 2003

SEP 2004
FEB 2004

FEB 2005
JUN 2004
OCT 2003

OCT 2004
MAR 2004

MAR 2005
JUL 2003

JUL 2004
NOV 2003

NOV 2004
APR 2004

APR 2005
JAN 2004

JAN 2005
AUG 2003

AUG 2004
MAY 2004
show  as  a  marked  decrease  in  hits, 
but will not be a decrease in genuine  Month
hits. 
 
30. Change in application numbers over time 
155. There has been an increase in the numbers applying to the EDG over the two years 
of  its  operation.  After  a  small  beginning,  the  interest  in  EDG  grew.  Numbers 
applying  jumped  in  April  2004  to  roughly  fifty  a  month  and  have  remained 
around that total.  
156. The  graphs  below  show  applications  lodged  (graph  below  left)  and  applications 
assessed (graph below right). Note the surge in numbers lodged in June and July 
2004,  with  the  corresponding  surge  in  assessments  in  June  and  August  2004  and 
carrying over through September and October 2004.  

Applications lodged Applications assessed

1/10/2003 to 7/4/2005 1/10/2003 to 30/5/2005

80 80
Number of assessments
Number of applications

60 60

40 40

20 20

0 0
DEC 2003

DEC 2004
DEC 2003

DEC 2004
SEP 2004

SEP 2004
FEB 2004

FEB 2005
FEB 2004

FEB 2005

OCT 2003

OCT 2004
JUN 2004

JUN 2005
OCT 2003

OCT 2004
JUN 2004

MAR 2004

MAR 2005
MAR 2004

MAR 2005
JUL 2004

JUL 2004
NOV 2003

APR 2004

NOV 2004

APR 2005
NOV 2003

APR 2004

NOV 2004

JAN 2004

JAN 2005
JAN 2004

JAN 2005

AUG 2004
AUG 2004

MAY 2004

MAY 2005
MAY 2004

Month Month

30
157. There  was  a  drop  in  decisions  in  July,  presumably  as  a  result  of  yearend  03/04 
activities,  and  many  applications  lodged  in  July  look  to  have  been  assessed  in 
August.  
 
 

31
4. Assessment of applications 
 
31. Change in approval rate over time 
158. From  03/04  to  04/05  the  number  of  applications  which  have  been  declined  has 
increased from 57 to 159, which is an increase of 179%. The number of applications 
accepted has increased from 251 to 319, which is an increase of 27%. 
 
159. This  shows  that  over  the  two  years  of  delivery  there  has  been  a  change  in  the 
approval  rate.  The  graphs  below  show  the  numbers  accepted  and  declined  over 
time, with the dark line added to show the trend.  
160. The  graph  below  left  shows  that  the  numbers  of  accepted  applications  are  in 
decline. The graph below right shows that the numbers declined are increasing. 
 

Declined applications over time Accepted applications over time

1/10/2003 to 30/5/2005 1/10/2003 to 30/5/2005

60 Declined 60 Accepted
applications applications
Moving Moving
50 average of average of
50
declined accepted
applications applications
40
Number

Number

40

30

30
20

20
10

0 10
DEC 2003

DEC 2004

DEC 2003

DEC 2004
SEP 2004

SEP 2004
FEB 2004

FEB 2005

FEB 2004

FEB 2005
JUN 2004

OCT 2004

JUN 2004

OCT 2004
MAR 2004

MAR 2005

MAR 2004

MAR 2005
JUL 2004

JUL 2004
NOV 2003

APR 2004

NOV 2004

APR 2005

NOV 2003

APR 2004

NOV 2004

APR 2005
JAN 2004

JAN 2005

JAN 2004

JAN 2005
AUG 2004

AUG 2004
MAY 2004

MAY 2005

MAY 2004

MAY 2005

Month Month

 
 
 
161. As  another  way  of  viewing  this  change,  consider  the  ratio  of  acceptances  to 
declines.  
162. If  the  numbers  accepted  and  declined  over  the  total  number  of  applications  is 
examined  (graph  below  right)  it  can  be  seen  that  the  proportion  of  applications 
accepted  has  steadily  declined  from  80%  (0.80)  in  November  2003  to  60%  in 
August 2004 and 50% (0.50) in May 2005.  

32
163. Put another way, the number of 
applications  declined  has  risen 
Proportion of applications accepted and declined over time
from below 20% (0.20) to around 
50% (0.50).  
1/10/2003 to 30/5/2005
164. This  is  a  large  change.  It  has 
Accepted
resulted  in  a  very  large  decline  applications
0.8 Moving
rate.   average of
accepted
applications

165. The  change  in  the  proportions  Declined

Proportion
0.6
applications
Moving
accepted and declined may have  average of
declined
a number of explanations.   0.4 applications

166. First,  demand  for  the  fund  may  0.2

be  higher  than  the  EDG  can 


currently  accommodate,  and  so 

DEC 2003

DEC 2004
SEP 2004
FEB 2004

FEB 2005
JUN 2004

OCT 2004
MAR 2004

MAR 2005
JUL 2004
NOV 2003

APR 2004

NOV 2004

APR 2005
JAN 2004

JAN 2005
AUG 2004
MAY 2004

MAY 2005
the  EDG  team  is  forced  to  fail 
more  applications  than  they  can  Month

pass.  Second,  it  might  be  that 


over time the applications are lowering in standard. Third, there may have been a 
change in assessment methods. Fourth, the there may be an issue with the criteria 
themselves.  
167. Examining  the  expenditure  of  the  fund  (the  data  the  evaluation  has  will  be 
sufficiently accurate to allow this) shows it was not in serious danger of being over 
subscribed  early  in  the  03/04  year  when  acceptance  numbers  first  declined,  nor 
even toward the end of the 04/05 year when declines reached over 40% (see table 
right).  In  March  2005  the  fund  still  had  ¾  of  a  million  Date Allocation
dollars  left  to  spend.  Decreasing  numbers  of  accepted 
October-03 $183,604.23
applications  seems  inconsistent  with  an  effort  to  prevent  November-03 $236,002.47
oversubscription.   December-03 $383,350.52
January-04 $247,223.25
168. The  second  possible  explanation  was  a  change  in  the  February-04 $115,889.17
standard  of  applications.  This  may  be  due  to  a  change  in  March-04 $225,215.89
April-04 $404,186.75
the types of firms applying. Perhaps a truly representative 
May-04 $456,915.74
standard of applicable firms is now being seen by the team;  June-04 $703,380.07
because better than average firms applied early in the life of  Total $2,955,768.09
the fund.  
July-04
$117,510.73
169. As  NZTE  does  not  advertise  the  fund  widely,  in  its  early  August-04 $593,816.55
September-04 $468,432.43
days  only  those  firms  who  are  proactive  about  seeking  October-04 $465,113.12
assistance  would  have  known  about  it.  These  firms  may  November-04 $334,250.10
have also been better than average.   December-04 $361,215.81
January-05 $307,229.22
170. If this is the case, the score to pass the criteria is higher than  February-05 $391,522.81
the average firm can manage, and perhaps is too high.  March-05 $347,920.68
Total $3,387,011.45
171. Conversely,  the  change  in  standards  may  have  arisen 
because  without  advertising,  only  those  firms  who  approach  economic 
development agencies or other consultants discover the fund. These firms may be 
33
less  able  than  average.  If  this  is  the  case,  advertising  may  raise  the  standard  of 
firms applying.  
172. NZTE has recently raised the maximum score firms had to achieve to be awarded 
the grant, from 570 to 585. This was in March 2005 and was said to be in order to 
prevent an over spend in the 04/05 year. However as shown above there was a fair 
bit  of  money  still  available  in  March,  and  the  decline  in  proportions  accepted 
began  earlier  than  March,  so  this  cannot  be  the  explanation  for  the  trend  as  a 
whole.  If  the  standards  of  firms  applying  have  declined,  raising  the  score  will 
compound the issue. This will be able to be seen in the approval rates next year. 
173. Finally,  the  standard  of  applications  may  explain  increasing  levels  of  declines  if 
sufficient numbers are declined for poor quality applications, but are subsequently 
approved. However the numbers in this situation are too small for this. Only 8% 
were declined and then reapplied for the same project.  
174. The third possible explanation was a change in assessment methods.  
175. NZTE  has  told  the  evaluation  that  their  assessment  has  become  more  thorough 
with  expanded  assessment  instructions  implemented  in  January  2005.  The 
expanded  assessment instructions contained detailed instructions for the existing 
scoring requirements to help the EDG team score applications. These might have 
made  it  easier  to  determine  the  standard  of  the  applications,  causing  higher 
numbers  to  be  declined,  or  they  may  have  made  it  tougher  for  firms  to  pass 
assessment and be approved. Again, this change was implemented too late to be 
the cause of the decline.  
176. The final possible cause was an issue with the criteria and their application.  
177. In assessing applications by applying criteria the team makes a decision, and the 
evaluation  has  looked  at  the  information  the  team  has  at  its  disposal  to  make  its 
decisions, and how that is translating into decisions. Understanding this may help 
in understanding why there is a trend of increasing declines.  
178. Considering  first  the  reasons  for  declining  firms,  after  December  2004  (which  is 
the  date  from  which  NZTE  kept  detailed  records  on  their  reasons  for  declining 
firms),  75%  are  failed  on  ‘potential  for  growth  and  benefit  to  the  economy’,  62% 
are  failed  on  ‘level  of  innovation  of  the  product  or  service,  or  value‐add  to  the 
firm’s activities’.  
179. Less  than  10%  are  failed  on  ‘level  of  need  for  government  assistance’,  ‘ability  of 
firm  to  implement  the  project’  or  on  ‘proof  of  funding’.  A  third  is  failed  on 
‘financial  stability’.  There  is  a  fairly  even  split  on  pass  or  fail  on  ‘robustness  of 
proposal.’ This criterion is general‐ the overall feel for the application itself. 
180. The  main  reasons  for  failure  then  are  that  the  applications  show  low  or  poor 
potential for growth, from the idea, product or service proposed; or show low or 
no  benefit  to  the  economy.  This  suggests  that  the  EDG  has  not  had  firms  with 
lower ability, as was speculated above; else firms would be being failed on ‘ability 
to implement the project’ or ‘financial stability’.  

34
181. Rather,  the  team  is  rejecting  firms  because  they  feel  they  have  low  or  poor 
potential for growth and low benefit to the national economy.  
182. Looking  next  to  the  information  the  team  has  available  to  make  these  decisions, 
the team has the information from the story woven by the firm in their application, 
information  from  other  NZTE  client  or  sector  managers,  and  information  from 
their own experience of assessing applications.  
183. The  team  is  limited  in  information  from  assessing  previous  applications  because 
there is very little feedback for them on their previous decisions. The final reports 
firms file usually have no information in them on sales. There is no request in the 
forms  for  information  on  issues  faced  by  the  firm  in  implementing  the  project. 
There is no other process of follow up. As a result, the team is not learning from 
the outcomes of their decisions which of their decisions were right or wrong.  
184. So with limited information, the team must make one of the hardest decisions to 
make about firms‐ the potential of a small and young business and a new product. 
This  decision  is  genuinely  uncertain.  As  the  EDG  team  noted  to  the  evaluation, 
‘it’s a real punt’.  
185. Furthermore,  with  the  fund  going  to  young  inexperienced  firms,  NZTE  faces 
genuine risk that funds go to firms who will fail anyway. NZTE may feel it needs 
to  be  risk  averse  in  order  to  best  fulfill  its  obligations  to  Government.  This  may 
have  translated  into  pressure  on  the  EDG  team  to  be  conservative  in  their 
assessments.   
186. It  may  be  that  the  reason  firms  are  being  declined  in  increasing  numbers  is 
because  without  good  experience  in  spotting  and  acknowledging  potential,  and 
perhaps  with  an  overly  strong  concern  of  risk,  the  team  has  become  too 
conservative in its decisions.  
 
32. Recommendations 
187. The evaluation recommends a mechanism for more detailed feedback to the team 
on  the  results  of  projects  and  grants,  so  the  team  may  learn  the  results  of  their 
decisions, and so learn about making these sorts of decisions.  
188. It recommends a careful look at the data for the year 2005/2006, to see whether the 
trend in application decisions continues. It also recommends that NZTE comes to 
an  opinion  on  application  quality  and  whether  standards  are  declining  overall, 
and  watches  the  quality  over  the  next  year.  This  will  inform  NZTE  on  whether 
scoring levels and overall positioning of the fund are appropriate. 
189. If standards are not declining and the trend continues, the evaluation recommends 
further  resources  be  provided  to  the  EDG  team  in  terms  of  at  least  one  highly 
experienced case manager or former business person, perhaps temporally to assist 
the  team  adjust  their  scoring,  or  permanently.  The  evaluation  suggests  NZTE 
consider  approving  a  random  sample  of  applications  to  counter  conservatism  in 
the assessment.  

35
190. It  recommends  that  MED  and  NZTE  agree  that  given  the  EDG  is  to  help  young, 
inexperienced  firms,  which  are  therefore  a  higher  risk,  a  percentage  of  firms 
failing  in  spite  of  EDG  assistance  is  likely  and  acceptable.  In  turn,  NZTE  can 
encourage its assessment team to be risk‐taking.   
 
33. Time taken to approve grants 
191. The  EDG  Team  aims  to  assess  a  proposal  within  7  days.  The  team  has  told  the 
evaluation that it has been successful in keeping to this timeframe this year. 
192. The  graph  right  shows  the 
distribution  of  time  taken  to 
Days taken for a grant decision
assess  applications.  Durations  lie 
mostly between 7 and 30 days, but  30

can  stretch  out  to  90  days  and 


longer.   Number of applications 25

193. The  team  has  explained  to  the  20

evaluation  that  its  turnaround  of 


seven days is once the application  15

is  complete.  An  application  may 


not  be  considered  complete  first  10

time,  and  so  the  team  must  send 


them  back.  So  the  length  of  time  5

taken  to  assess  applications  is  a 


0
function  of  many  firms  not 

101
111
10
13
16
19
1

70
77
31
34
37

52
55
58
62
66

84
90
22
25
28
7

40
43
46
49
4

sending  in  applications  with  Days

enough  information  for  a  proper 


assessment.  
194. The added work for the team to reassess applications and the inconvenience to the 
firm in delays makes it worth considering whether the application forms are clear 
enough. 
 
34. Average time taken to approve grants over time 
195. The evaluation looked to see if the assessment time changed over time. A look at 
the  average  time  taken  for  each  decision  per  month  shows  that  the  average 
number of days have fallen since the large averages of March, April and May 2004 
(see  graph below).  The  average  is  currently  a  month,  indicated  by  the  horizontal 
line at 30 days.  
196. Either  the  team  is  improving  in  its  ability  to  assess  applications,  or  firms  are 
submitting more complete assessments. NZTE has decided not to provide data to 
the  evaluation  on  time  taken  from  initial  lodgment  to  decision  date  post  March 
2005, so the evaluation does not know whether the team has improved further.  

36
197. There  was  a  very  large  spike  in  time 
taken in March, April and  May  2004. 
It  was  a  500%  shift  in  the  average.  Days taken to decide on grant, over time
This  was  due  to  the  spike  in  the 
numbers  of  applications  lodged  1/12/2003 to 30/3/2005
causing  very  high  workloads  for  the 
180
team. This shows the level of interest 

Average number of days


the  team  at  its  current  size  can  150

accommodate‐  around  40  120

applications a month.   90

  60

35. Recommendation  30

198. NZTE is adjusting its assessment and  0

DEC 2003

DEC 2004
SEP 2004
FEB 2004

FEB 2005
JUN 2004

OCT 2004
MAR 2004

MAR 2005
JUL 2004
APR 2004

NOV 2004
JAN 2004

JAN 2005
AUG 2004
MAY 2004
approval  processes  to  shorten  their 
duration;  this  may  be  sufficient  to 
Month Grant Allocated
reduce  the  time  taken  to  revue  and 
decide  on  applications.  Reducing  the  workload  by  15%  (the  proportion  being 
devolved)  may  also  help.  However  the  evaluation  recommends  NZTE  record 
three  dates  per  application‐  submission,  start  of  assessment  and  decision  date  so 
time taken can be more easily determined and tracked.  

37
5. Distribution of the EDG 
 
Note: For the sections 5,6,7,8 the data is for 18 months: October 2003 to April 2005. This reduces 
the totals of applications to 723, with 517 accepted and 178 declined.  
 
36. Summary of findings on distribution of the EDG 
199. The  evaluation  has  found  the  distribution  is  similar  across  regions  and  sectors, 
and there is no significant difference in acceptance rate for any region or sector.1 
 
37. Regional spread of firms assisted  
200. Auckland has had higher numbers of applications for the EDG than other regions 
(see  graph  below  left).  Wellington  and  Canterbury  have  the  second  largest 
numbers of applications.   
201. Controlling  for  numbers  of  firm  per  region2  shows  that  the  rate  of  grant 
applications per region is fairly similar, shown on the graph below right by bars of 
more even height.  
 
 

Number of grant applications per region Rate of grant applications per region
1/10/2003 to 7/4/2005 1/10/2003 to 7/4/2005

250 0.50

200 0.40
Application rate %
Applications

150 0.30

100 0.20

50 0.10

0 0.00
anganui/Ruapehu/Rangitikei
anganui/Ruapehu/Rangitikei

Chatham Islands

Nelson/Tasman
Chatham Islands

Nelson/Tasman

Northland
Northland

Rotorua

Wellington
Taranaki
Rotorua

Otago

Waikato
Wellington

Marlborough

Southland

Taupo
Taranaki
Otago

Taupo

Waikato
Marlborough

King Country
Southland
King Country

Thames Valley
Tararua
Tararua

Thames Valley

Canterbury

Wairarapa

West Coast
Canterbury

Wairarapa

Eastern Bay of Plenty


Eastern Bay of Plenty

West Coast

Manawatu

Tairawhiti
Manawatu

Tairawhiti

Auckland

Kapiti/Horowhenua
Auckland

Kapiti/Horowhenua

Hawke's Bay
Hawke's Bay

Western Bay of Plenty


Western Bay of Plenty

Region Region

1
For regional spread a chi-square test of independence gives a p-value of .282 and for sectoral spread a chi-square test
of independence gives a p-value of .229.
2
Using Statistics New Zealand 2003 data on firms per region.
38
202. Controlling  further  for  the  numbers  of 
firms  applying  per  region,  it  can  be 
seen that the proportion of applications  Rate of acceptances per region
1/10/2003 to 7/4/2005
accepted per region that the acceptance 
rate per region is very similar. The bars 
on  the  graph  right  are  all  of  similar 
100
height. 

Acceptance rate %
80
203. From  the  above  analysis  it  can  be 
concluded  that  the  EDF  is  assisting  60

firms in all regions evenly.  40

  20

  0

Auckland

Waikato
Wairarapa
Wanganui/Ruapehu/Ra
Wellington
West Coast
Western Bay of Plenty
Tairawhiti
Taranaki
Tararua
Taupo
Thames Valley
Southland
Canterbury
Chatham Islands

Otago
Kapiti/Horowhenua
King Country
Manawatu
Marlborough
Nelson/Tasman
Northland
Eastern Bay of Plenty
Hawke's Bay

Rotorua
 
 
Region
 
38. Regional spread of allocations 
204. Auckland has had the highest total allocations of grants from the EDF to date (see 
graph below left).  
205. Controlling for the number of firms in the region3 shows the amount of allocations 
per region varies, but not in favour of the larger regions (see graph below right).  
 
 

Allocation per region Allocation per firm in region


1/10/2003 to 7/4/2005 1/10/2003 to 7/4/2005

2500000 60

50
2000000
Allocation per firm $
Amount allocated

40
1500000

30

1000000
20

500000
10

0 0
anganui/Ruapehu/Rangitikei

anganui/Ruapehu/Rangitikei
Nelson/Tasman

Nelson/Tasman
Northland

Northland
Rotorua

Rotorua
Wellington

Wellington
Taranaki

Taranaki
Otago

Waikato

Otago

Waikato
Marlborough

Marlborough
Southland

Southland
King Country

King Country
Thames Valley

Thames Valley
Canterbury

Wairarapa

Canterbury

Wairarapa
Eastern Bay of Plenty

West Coast

Eastern Bay of Plenty

West Coast
Manawatu

Manawatu
Tairawhiti

Tairawhiti
Auckland

Auckland
Kapiti/Horowhenua

Kapiti/Horowhenua
Hawke's Bay

Hawke's Bay
Western Bay of Plenty

Western Bay of Plenty

Region Region

3
Using Statistics New Zealand 2003 data on firms per region.
39
206. Controlling  for  the  number  of 
Allocation per assisted firm per region
applicants per region shows allocations  1/10/2003 to 7/4/2005
do  not  vary  much  across  region  (see 
20,000.00
graph right). 
207. The  evaluation  has  found  there  is  no  15,000.00

significant  difference  in  the  rate  of 

Allocation $
acceptance for different regions.4  10,000.00

208. The EDF is assisting firms in all regions 
fairly evenly.     5,000.00

 
0.00

anganui/Ruapehu/Rangitikei
Nelson/Tasman
Northland

Rotorua

Wellington
Taranaki
Otago

Waikato
Marlborough

Southland
King Country

Thames Valley
Canterbury

Wairarapa
Eastern Bay of Plenty

West Coast
Manawatu

Tairawhiti
Auckland

Kapiti/Horowhenua
Hawke's Bay

Western Bay of Plenty


 
 
 
Region
 
 

39. Sectoral spread of allocations 
209. NZTE  divides  firms  into  seven  sectors:  manufacturing;  information, 
communication  and  technology;  creative  and  services;  food  and  beverage,  bio‐
technology; wood processing, building and interiors and education.  
210. Data  received  from  NZTE  without  a  firm’s  sector  nominated  have  been  called 
‘uncoded’. 
211. The manufacturing sector has made the largest number of applications, with 206. 
See graph below right. 
212. The  next  two  highest  are  information, 
communication  and  technology  and  Number of firms and applications per sector
creative  and  services.  Both  had  130 
applications.  
1/10/2003 to 7/4/2005
213. The  manufacturing  has  also  had  the  250 No.of firms
assisted
highest  number  of  grants  allocated,  Applications
200
with 160 accepted, or 31% of all grants. 
The  information  sector  had  76%  of  150
Sum

applications  accepted  and  creative  and  100

services had 60% accepted.  
50

214. Manufacturing has received the largest 
0
total  allocations:  $2,095,555,  but  this 
munication & Technology
Education

Uncoded
Food & Beverage

Manufacturing
Bio-technology

sing Building & Interiors


Creative & Services

reflects  the  larger  number  of  grants 


applied  for  (see  graph  bottom  left  and 
table bottom left).  sector

4
A chi-square test of independence gives a p-value of .282
40
215. The evaluation has found there is no significant difference in the rate of acceptance 
for  different  sectors.5  The  average  amount  allocated  to  a  firm  is  also  similar,  no 
matter the sector (graph below right). 
216. From  this  analysis  the  evaluation  can  conclude  that  there  is  no  bias  toward  any 
sector in the approval or decline of applications.  
 

Allocation per sector Average allocation per sector


1/10/2003 to 7/4/2005 1/10/2003 to 7/4/2005

2000000 15000.00

Amount allocated
Allocatio ns ($)

1500000
10000.00

1000000

5000.00
500000

0 0.00

Information, Communication & Technology

Wood Processing Building & Interiors


Manufact uring

Uncoded
Information, Communication & Technology

Wood Processing Building & Interiors


Manufact uring

Uncoded

Bio-technology

Creative & Services

Education

Food & Beverage


Bio-technology

Creative & Services

Education

Food & Beverage

Sector Sector

 
 
Total
  Sector Allocation $
1 Manufacturing 2,095,557.51
2 Information, Communication &
  Technology
1,247,433.88

3 Creative & Services 816,522.33


 
4 Food & Beverage 767,636.13
5 Bio-technology 657,563.62
 
6 Wood Processing Building & Interiors 445,792.3
  7 Uncoded 281,061.84
8 Education 46,126.44
 

5
A chi-square test of independence gives a p-value of .229
41
6. Grant allocation and collection by firms 
 

40. Amounts allocated 
217. 50%  of  grants  are  for  $12000  and  less. 
Distribution of amounts allocated
20% are for $5000 and less. 
218. The  graph  right  shows  a  peak  of  48 
1/10/2003 to 7/4/2005
grants  of  $3000.  This  is  caused  by  the 
$3000 cap on two categories of activity.  
150

219. The  most  frequent  single  amount 


allocated  is  the  maximum,  $20,000.  120

There  have  been  three  grants  above 

Frequency
90
$20,000, but as of April 2005 these were 
not claimed in full.   60

  30

 
0

41. Amount claimed by closed projects  $0.00 $5,000.00 $10,000.00 $15,000.00 $20,000.00


Amount Allocated

220. Firms  have  one  year  from  date  of 


acceptance  of  their  application  to  claim  the  approved  costs  from  the  project  and 
thereby their grant from NZTE. At one year the grant and project is closed. There 
have been 193 projects closed to date. They have had allocated to them a total sum 
of $2.165M.  
221. Of  this  $1.79M  has  been  claimed  and  paid.  This  is  a  shortfall  of  $366,462.43 
(16.9%). The shortfall is due to not all clients claiming their full amount. 
222. 15%  of  grants  have  less  than  60% 
claimed. See graph right. 
223. The  evaluation  spoke  with  many  of  Distribution of proportions claimed

these firms and found that for most a 
change in plans, either for the project  1/10/2003 to 7/4/2005
or  for  the  firm  as  a  whole,  saw  their 
project  alter  or  not  go  ahead,  and  so  100

they did not claim.  
80

224. As  this  sort  of  thing  seems  likely  to 


Frequency

happen  to  firms  in  the  future,  the  60

EDG  will  probably  have  some 


40
amount left over each year which was 
allocated but not claimed.   20

0
0.0000 0.2000 0.4000 0.6000 0.8000 1.0000
Proportions

42
7. Analysis of applicant firms 
 
42. Summary of findings given below. 
225. EDG  clients  are  typically  small,  with  less  than  10FTEs  and  less  than  $200,000 
turnover. 
226. Over half of all applicants are exporters, and firms who export show significantly 
higher rates of acceptance into the fund. 
227. It is not clear whether the policy criteria of ‘young start‐up’ refers to age, and not, 
for  example,  to  growth.  If  it  applies  to  age,  and  if  ‘young’  means  firms  less  than 
five  years  old,  40%  of  EDG  firms  are  not  young  start‐ups;  if  ‘young’    means  less 
than 10 years old, nearly a quarter of firms funded are not young start‐ups.  
 
43. Overall size: turnover and FTE 
228. Most  EDG  clients  are  small,  with  less  than  10  FTEs  and  a  turnover  of  less  than 
$200,000.  
229. One goal of the EDG as a foundation service is to move its clients through to more 
advanced  services,  such  as  the  growth  services  range.  Almost  none  of  the  EDG 
clients to date have accessed the growth services range. This may be because the 
gap  in  capability  between  EDF  clients  and  GSR  clients  is  broader  than  can  be 
improved via the EDF. Certainly the GS Range is targeted at high growth potential 
firms and this is likely to be a small percentage of the firms eligible for the EDF. 
230. Looking  at  the  graph  right,  the  line  on  the  y  axis  is  at  20  FTEs,  which  is  the 
maximum  allowed  by  the  fund’s  eligibility  criteria,  and  shows  that  NZTE  will 
over‐ride  that  restriction  on  occasion. 
The  lack  of  dots  in  the  upper  right 
FTE and Turnover of accepted firms
quadrangle shows that it is overridden 
only  if  the  firms  are  also  smaller  than 
$5M turnover.   1/10/2003 to 7/4/2005

231. The  line  on  the  x  axis  is  at  the  $5M  50
maximum,  and  shows  that  NZTE  will 
override  that  restriction  on  occasion  40

also,  but  again,  it  seems  only  if  the 


Full Time Staff

30
firms are smaller than 20FTEs. 
20

10

$0 $2,000,000 $4,000,000 $6,000,000 $8,000,000 $10,000,000 $12,000,000


Last full year total turnover

43
232. The  graph  right  shows  that  declined 
firms  tend  to  be  smaller  than 
FTE and Turnover of declined firms
accepted  firms,  but  firms  have  been 
accepted  who  have  very  low 
1/10/2003 to 7/4/2005
turnover.  
  60

44. Exporting  50

233. Based  on  whether  they  report  an 

Full Time Staff


40

export  turnover,  over  half  of  all  EDF 


30
applicants  are  exporters,  and  almost 
half  of  all  accepted  firms  are  20

exporting.   10

234. Only about 4% of New Zealand SME  0

firms  export.  If  firms  applying  to  the  $0 $2,000,000 $4,000,000 $6,000,000 $8,000,000 $10,000,000 $12,000,000
Last full year total turnover
EDG  were  typical  of  New  Zealand 
firms, only 4% would be exporting. 
235. The  table  right  shows  the  numbers 
All applicants
exporting  who  apply  to  the  EDG 
(40.9%).  This  indicates  that  the  EDG  Frequency Percent
Not Exporting 427 59.1
firms  are  not  a  typical  population  of  Exporting 296 40.9
firms,  perhaps  because  it  is  a  self‐ Total 723 100.0
selecting sample of New Zealand firms.  
236. Examining  the  rate  of  acceptance  and  declined  for  exporting  and  non  exporting 
firms shows that there is a bias in favour of exporting. The evaluation has found 
there is a significant difference between the rates of acceptance for firms who are 
exporting and those who are not.6  
237. More  firms  are  being  declined  when  they  are  not  exporting  than  would  be 
expected  if  there  were  no  relationship,  and  fewer  are  being  accepted.  Firms  who 
are exporting are showing somewhat higher rates of being accepted, and firms not 
exporting somewhat lower rates.  
238. It may be that firms who are already exporting are also firms who tend to pass all 
the EDG criteria more easily. 
However  the  EDG  has  been  All applicants
included  in  NZTE’s  overall  Status of Project Frequency Percent
focus  on  exporting,  and  the  Declined Not Exporting 120 67.4
Exporting 58 32.6
criteria ‘potential for growth’ 
Total 178 100.0
was defined to be national or  Accepted Not Exporting 291 56.3
export.  If  firms  failed  this  Exporting 226 43.7
they would fail the criteria as  Total 517 100.0
a whole, and be declined the 

6
A chi-square test of independence gives a p-value of .027
44
EDG.  So  firms  who  are  ‘not  exporting’  had  at  least  to  be  those  who  had  the 
potential for export.  
239. The  criteria  for  the  EDG  have  been  revised  and  the  focus  on  exporting  has  been 
shifted  to  a  focus  on  improved  business  performance  and  net  benefit  to  NZ  of 
improved business performance. The tests for the latter are improved productivity 
and  efficiency,  limited  displacement  (displacement  would  result  from  funding 
firms  with  significant  domestic  focus  and  significant  domestic  competition)  and 
presence of spillovers.  
 

45. Age of Firms 
240. Data was provided on the year firms accepted into the EDG were established.   
241. 21%  of  firms  were  established 
before 1995.  
Year established for accepted firms
242. 79%  of  firms  were  established  in 
1995 and after.  
1/10/2003 to 30/6/2005
243. 322  firms  (62%)  were  established 
in 2000 and after.  100

244. It  is  not  clear  whether  the  policy 


80
criteria  of  ‘young  start‐up’  refers 
to  age,  and  not,  for  example,  to 
Number

60
growth. If it applies to age, and if 
‘young’ means firms less than five  40
years  old,  40%  of  EDG  firms  are 
not  young  start‐ups;  if  ‘young’   20

means  less  than  10  years  old, 


nearly  a  quarter  of  firms  funded  0
2000
2002
2004
1914
1946
1953
1964
1968
1970
1973
1975
1978
1980
1982
1984
1986
1988
1990
1992
1994
1996
1998

are not young start‐ups.  
Year firm established
 
46. Firm Growth 
245. The evaluation calculated the growth of firms in the years prior to applying to the 
EDG from data included in applications forms.  
246. Growth was calculated as the change in total full year turnover from 2 years prior 
to applying, to 1 year prior to applying.   
247. The  graph  below  right  shows  the  average  growth  rate  of  accepted  and  declined 
firms for the calendar years 2003, 2004, and 2005 to April. The average growth for 
accepted firms is between 0 and l.5%. If, as discussed above, ‘young’ is in terms of 
growth, then most EDG clients are young.  

45
248. For 2003 and 2004 accepted firms had 
higher  average  growth  than  declined 
Change in turnover for accepted and declined firms
firms.  
249. The  2005  data  is  a  function  of  low  1/10/2003 to 7/4/2005
application  numbers.  The  data  the 
Status of Project
evaluation  received  ended  in  April  Declined
Accepted
2005,  so  the  data  for  that  year  is  3.00

Mean change in turnover


incomplete.  
2.00
250. The  graphs  below  of  applications  by 
month show that for declined firms a 
few  had  applied  with  high  turnover,  1.00

and only a few had applied who had 
low  turnover.  So  a  few  applications  0.00

with  high  growth  have  skewed  the 


2003 2004 2005
average.  With  further  data  on  Year grant awarded
turnover  for  declined  firms  for  the 
calendar year 2005, it may be seen whether the 2005 intake is similar to previous 
years.  
251. The graphs also show that most firms have growth of less than 5%.  
 
 
 
 
 

Change in turnover of accepted firms Change in turnover of declined firms

1/10/2003 to 7/4/2005 1/10/2003 to 7/4/2005

20.00 20.00

15.00 15.00
Change in turnover

Change in turnover

10.00 10.00

5.00 5.00

0.00 0.00

-5.00 -5.00

-10.00 -10.00

Jul/03 Oct/03 Jan/04 Apr/04 Jul/04 Oct/04 Jan/05 Apr/05 Oct/03 Jan/04 Apr/04 Jul/04 Oct/04 Jan/05 Apr/05
Month grant allocated Month grant allocated

46
8. Types of assistance funded 
 

252. Firms  apply  to  the  EDG  for  assistance  for  activities  they  wish  to  undertake.  The 
activities  must  be  within  specified  categories  and  types  of  activities.  These  are 
described further below.  
253. Firms may undertake within one grant as many categories and types of activities 
as  they  wish,  so  activity  numbers  given  in  this  section  do  not  match  firm  or 
application numbers.  
 
47. Advice and expertise categories 
254. The  types  of  activities  which  may  be  funded  with  the  EDG  are divided  first  into 
advice and expertise categories. The categories are strategic business development, 
feasibility  studies,  product  development,  business  and  operational  excellence,  e‐
commerce and e‐business strategies, market strategy development.  
255. The  largest  categories  are  strategic  business  development,  product  development 
and  market  development.  35%  of  total  allocations  went  to  product  development, 
27% to strategic development, 17% to market development.   
256. Within each category are areas of activity. The areas are: 
− strategic business development 
− business/strategic plan development 
− human resource 
strategic plan 
development  Distribution of funding by activity type

− financial viability 
planning  1/10/2003 to 7/4/2005

− strategic design  Category
e-business
advice  category
Feasibility studies

− feasibility studies  Market
development
Mentoring
− product development  Operational
excellence

− prototype  design,  Product


development categ
Strategic
development  and  developme
Training
testing 
− intellectual  property 
protection 
− business  and  operational 
excellence 
 
− international quality standards certification 
− systems evaluation and development 
− environmental management system 
− e‐commerce and e‐business strategies 
− development of a e‐strategy 
− Market strategy development 
− Market research or new market investigation 
− Marketing plans 
 
257. The  largest  activity  areas  are  intellectual  property  protection,  prototype 
development,  strategic  business  development,  and  strategic  design  advice  (see 
graph below right). 
258. The graph below left shows totals allocated to date. The activities within product 
development,  prototype  development  and  intellectual  property  protection  have 
absorbed a large proportion of funding to date, at around $3.5M total allocations. 
Roughly one million has gone to each per annum.  
 

Funding totals per activity type Areas of activity undertaken by accepted firms

1/10/2003 to 7/4/2005 1/10/2003 to 7/4/2005

150
3,000,000.00
Total allocated $

120
Number

2,000,000.00
90

60
1,000,000.00

30

0.00
0
Mentoring
Market development

Training
Feasibility studies

prototype devlpmt
Operational excellence

strategic design
intellectual property

strategic planning
e-business category

Tr ring

St

S y a ti

e-
C
M

M t inv

Bu t pla ati

Fi

Fe ic

Pr ility n a

In

En s e
er ual
um s/st
en

ar

ar

na eso ic p elo

te e d

bu
ai

ra l pla str

ot

st
as des g
si

vi
tif
ni

lle
ke

ke est

te

ot Stu

em n
to

ne

nc

ro

si nta
an rate d d rch

ib

ic
ng

yp

ct

ne
n
i
s

m
r

ss ma d d
o

e
va
nn on

pr me

st
ev
ur

nn

lu
in

ra age
ig

o
g

el

l
dy ice
c

a
p e n t,
g

in egi op
g

op

tio
an sea

rty de
dv

n
n
a
,r

an
la

pr sig
t
n
e

ev

ot

Category
de e

ec
c

ev
ve

pl

tio
pm

el
an
l

n
n

48
PART FIVE: Findings and Recommendations on Outcomes 
 

9. The framework for analysis of outcomes.   
  

48. Goals of the EDG  
259. The  goal  of  the  EDG  was  to  assist  innovative  firms  and  entrepreneurs  to  build 
capability  to  test  early  stage  business  concepts  and  projects  by  enabling  them  to 
employ expertise and advice. 
260. Funding was to enable firms to: 
− Engage the services of a business mentor for a period of time 
− Undertake  more  advanced  management  and  technology  based  training  (as 
delivered through existing providers such as NZIM, Polytechnics etc) 
− Employ  specific  external  advice  and  expertise  in  a  management  area  (such  as 
feasibility studies, e‐business, market research, enhancement and uptake of new 
technologies,  human  resources,  intellectual  property,  strategic  planning, 
environmental management, production management) 
− Undertake  international  market  development  activities,  including  new  market 
investigation,  trade  fair  participation,  trade/business  missions,  business 
exchanges, and visiting buyers. 
 
49. Goals of the evaluation 
261. The  evaluation  sought  to  learn  whether  the  outcomes  policy  wished  to  achieve 
were occurring for the firms undertaking the activities funded by the EDF.  
262. Achieving  this  goal  enables  the  evaluation  to  report  on  whether  the  intervention 
designed  by  policy  was  successful.  It  would  be  successful  if  the  issues  identified 
by  policy  were  overcome  by  the  activities  firms  undertook,  and  if  the  outcomes 
identified by policy resulted from these activities. 
263. To  achieve  its  goals  the  evaluation  held  interviews  with  a  sample  of  firms.  The 
population was all firms who had completed a project by April 2005, giving a total 
of  191.  The  sample  was  a  stratified  simple  random  sample  with  a  sample  size 
chosen  to  give  a  margin  of  error  of  5%  for  estimates  of  proportions.  This  gave  a 
minimum sample of 129. The evaluation surveyed 132 firms.  
264. The sample was stratified by the activity types the EDG is broken into by NZTE, 
and those to be included were selected by MED policy. Further details are given in 
section 10. 
 
 
50. Specific outcomes sought by the evaluation  
265. The evaluation sought to understand the objectives for firms in undertaking their 
projects.  
266. It  wished  to  know  whether  the  projects  undertaken  by  firms  had  improved 
business  or  management  capability  and  whether  firms  had  experienced  gains  in 
performance as a result.  
267. It  wished  to  know  the  rate  at  which  projects  had  gains  in  activity  (such  as 
launching  a  product  or  entering  a  market)  and  performance  (in  terms  of  sales) 
with and without a change in management practice.  
268. It  wished  to  determine  any  differences  between  the  different  project  activities  in 
the rate at which they improved business or management capability, and the rate 
at which they led to gains in performance.  
269. It  wished  to  understand  the  nature  of  the  projects  being  undertaken  in  each 
activity type. 
270. It wished to know whether firms intended pursuing further assistance, and what 
their opinion was on the time it took to fill out the applications.    
 
51. Interpretation of the policy intent: improving management or business 
capability? 
271. Attempting to determine the improvements to business 
and  management  capability  by  the  projects  undertaken  Numbers of firms wanting business or management level
assistance
with  funding  gave  rise  to  a  definitional  issue:  the 
difference  between  ‘business  capability’  and 
‘management capability’.   80

75

272. The statement of policy intent says the goal of the fund  70
Number

is to build: “basic business capability” but describes this  65

as the capability to handle: “day‐to‐day management of  60

the many different functions of a firm, as well as longer‐ 55

term strategic issues.”   50
Business Management

Business or management level


273. Day‐to‐day business and long‐term strategic issues may 
well be separate tasks requiring different types of skills. Improving them may give 
different kinds of outcomes.  
274. The  evaluation  categorised  projects  into  management  level  and  business  level.  If 
the project was on an activity of the firm considered to be a function of the firm, 
such as building a prototype or the design of marketing material for a product, or 
identification of distributors in a market, it was ‘business level.’ If it were strategic, 
such  as  improving  production  methods  or  developing  a  marketing  plan  or  a 
branding strategy, or it was taking an overview of all firm activities and strategy, 
it was considered to be ‘management level’.  

50
275. The  evaluation  looked  to  see  whether  firms  wished  for  help  with  day‐to‐day 
business  matters,  or  with  strategic  matters,  or  for  help  with  taking  a  broad 
overview  of  the  fund  and  its  overall  strategy,  and  if  there  is  a  difference  in  the 
outcomes for each.  
 
52. Interpretation of the policy intent: improving management ability or    
knowledge?  
276. Attempting to determine how and whether external expertise gave improvements 
to business and management capability gave rise to a second definitional issue: the 
difference  between  projects  delivering  advice,  and  projects  delivering  facts.  The 
difference  is  also  a  difference  in  the  situations  and  objectives  of  firms  for  their 
projects. 
277. The ability to manage a firm can be improved by learning ways or better ways of 
performing the tasks required of managers. It can also be improved by getting the 
information  managers  need  to  make  management  decisions  and  ensure  firms 
move  ahead  not  with  guesswork  but  with  strategy.  So  via  the  provision  of 
information  required  to  achieve  a  project,  and  via  the  provision  of  the  skills 
required, management’s ability can be improved.     
278. However, there is quite a difference between a firm who needs advice on an issue 
or situation that is, advice on how to tackle a situation; and a firm who needs only 
facts to make their own decisions on what to do. The latter has abilities the former 
does not; the latter knows what information it needs and knows how to act on it.  
279. So the distinction between gaining knowledge and gaining ability is really  about 
types of firms‐ one sort will have higher capability than another because it has the 
capability to implement a project just not the information it needs to do so.  
280. The  distinction  can  be  seen  in  a  situation  where,  for  example,  a  firm  already 
knows  how  to  enter  a  market,  but  just  does  not  have  the  facts  on  a  particular 
market  to  know  whether  they  should  do  it.  This  is  a  different  type  of  firm  from 
one who does not know how to enter a market, nor what information they need to 
make a decision on entering.  
281. The distinction also shows in situations where a firm needs to purchase work from 
externals, such as a report, because the firm needs it to be independent, or where a 
firm  needs  external  people  with  manufacturing  machinery  in  order  to  produce  a 
product  or  prototype.  Neither  of  these  are  situations  where  the  problem  for  the 
firm is a lack of ability in the sense of skills; rather it is ability in the sense that they 
are unable to complete a project until they get the external information or technical 
assistance they need.   
282. The  policy  statement  is  not  clear  on  which  sort  of  firm  it  was  intended  that  the 
EDG  assisted  (if  not  both)  because  it  described  assisting  firms  with  both 
information and skills. The policy states that (italics added): 

51
Foundation services aim to build basic business capability…through the 
provision  of  generic  business  information,  advice  and  training…If 
entrepreneurs and managers have difficulties in accessing or developing 
the  necessary  skills,  this  could  lower  economic  efficiency  and  national 
productivity. Small businesses and entrepreneurs often lack the financial 
ability  to  employ  all  the  expertise  they  need  to  get  new  concepts  and 
projects  up  and  running…As  a  result,  small  businesses  often  do  not 
realise their full potential.  
283. The  issue  then  is  whether  the  goal  of  capability  building  is  to  include  firms who 
can themselves implement the project or is to be restricted to those firms who need 
to learn the skills to gain capability in order to implement the project. Is the fund a 
channel for information to managers or is it only to build their actual capability? 
284. With the possibility that the distinction does make a difference in outcomes, and in 
order to aid policy resolve the question of whether the fund ought to be a channel 
for information, the evaluation has looked to see whether facts and information or 
advice was sought by firms, and what the difference is in outcomes.   
 

52
10.   Quantitative findings on accepted firms. 
 

53. Guide to the findings 
285. This  section  lays  out  all  the  findings  from  the  research  on  outcomes  for  those 
interested  in  the  evidence  itself.  The  evaluation’s  conclusions  based  on  the 
evidence  are  laid  out  in  the  next  section  (13).  Those  who  just  wish  to  read  the 
summary of findings and conclusions may skip this section.  
286. The survey was undertaken by telephone interview. The population was all firms 
who had completed a project by April 2005, giving a total of 191. The sample was 
a stratified simple random sample with a sample size chosen to give a margin of 
error of 5% for estimates of proportions. This gave a minimum sample of 129. The 
evaluation surveyed 132 firms.  
287. The  sample  was  stratified  by  the  Stratum Population Sample size
activity  types  the  EDG  is  broken  Mentoring/Training 21 21
into  by  NZTE,  and  those  to  be  Market research and
investigation 32 21
included  in  the  evaluation  were 
selected  by  MED.  The  Prototype 36 22
stratification  was  to  ensure  by  Systems evaluation 28 22
chance the sample did not exclude  Intellectual property
protection 26 12
firms  undertaking  activities  the  Business and strategic
evaluation wished to sample.   development 30 19

288. With  sampling  fractions  which  Strategic Design 18 15


were  similar  in  each  stratum,  and  Total 191 132
also  very  high,  the  data  could  be  analysed  as  a  simple  random  sample.  No 
corrections for the finite population size were made.  
289. The high sampling fraction and response rate enables the sample to be generalized 
to  all  EDG  firms  undertaking  the  same  activities  as  the  strata.  The  results  have 
only limited generalisability to the population of firms in NZ as a whole due to the 
fact  that  the  population  of  firms  applying  for  grants  is  self  selecting.  If  the  firms 
who  apply  for  the  fund  in  the  future  are  different  in  character  or  if  the  numbers 
accepted  increase  to  a  large  degree,  the  results  on  outcomes  found  here  may  not 
continue to apply.  
290. The  findings  are  of  two  sorts:  proportions  of  firms  in  the  EDG  who  saw  various 
outcomes  subsequent  to  completing  their  project,  and  relationships  between 
certain activities or project types and outcomes. The graphs are the count of firms 
reporting the outcomes. 
291. The  relationship  is  found  using  the  statistical  test:  ‘chi‐square  test  of 
independence’.  The  Chi‐square  test  is  a  statistical  procedure  to  test  for  the 
existence of an association between two categorical variables. An example of such 
a comparison would be the variable ‘advice was given’ (possible answers are yes 
and no) and ‘changes in management were made (possible answers are also yes or 
53
no).  The  Chi‐square  test  provides  a  significance  or  p‐value  for  the  comparison: 
small values of the p‐value mean that a significant association has been found. For 
the  purposes  of  this  evaluation  a  significance  level  of  5%  (p=.05)  is  used  (this 
corresponds  to  the  standard  95%  confidence  level),  and  any  test  with  a  p‐value 
less than 0.05 as taken as evidence for an association.  
292. Where  there  is  evidence  for  an  association  caution  should  be  exercised  in  the 
interpretation  of  the  result:  the  test  cannot  establish  whether  the  relationship  is 
causal  or  not.  Lack  of  evidence  for  an  association  may  mean  there  is  no 
association, or that the association is too weak to detect with the given sample size.  
 
54. Numbers of firms responding. 
293. For  two  firms  the  appropriate  people  have  not  been  able  to  be  reached  for 
interview.  One  firm  refused  an  interview.  The  firm  is  reasonably  high‐profile,  so 
the  refusal  was  not  due  to  any  poor  performance  overall.  This  gives  a  response 
rate of 98% 
 
55. Numbers of firms completing projects. 
294. Of  the  sample  124  (94%)  of  firms  are  still  in  business.  The  7  considered  not  in 
business  were  unreachable  on  details  provided  by  NZTE  and  are  unlisted  with 
Telecom NZ.  
295. Not all firms completed their projects. 111 (84%) had completed their projects. 13 
firms cancelled their projects part‐way through either because of changes in their 
plans or because the project never quite got off the ground.  
296. Both  numbers  completing  projects  and  those  deemed  exited  indicate  that 
expecting  a  100%  rate  of  impact  of  the  fund  is  unreasonable.  There  is  likely  to 
always be firms whose plans change and who do not undertake the project.  
297. Instead, expecting an 80% completion level seems reasonable; and this entails the 
proportion of success in achieving outcomes will be less than 80%.  
 
56. Overall satisfaction 
298. 90% of firms were happy with the EDG and NZTE. Many wanted to make clear to 
the  evaluation  how  grateful  they  were  for  the  assistance.  These  firms  also 
mentioned  the  length  of  the  application  process  but  felt  it  was  justifiable  given 
they were seeking public funds. 
299. 10%  of  firms  had  some  specific  issue  with  NZTE  or  the  EDG  process  which  left 
them disgruntled.  For the majority it was either the length of the applications or 
the inflexibility of the EDG process in its position on alterations to the project mid‐
way.  Some  had  tried  to  get  such  changes  allowed  and  found  the  process 
exhausting. 

54
300. Being  disgruntled  with  the  process  often  coincided  with  disappointment  in  the 
project  they  had  undertaken.  When  the  gains  were  small  firms  minded  the  time 
they had spent applying.  
301. The overall satisfaction level is a good result for the EDG and NZTE.  
 
57. Proportions of EDG clients seeing changes in the way they manage their 
business. 
302. The  evaluation  looked  at  the  proportions  of  firms  reporting  changes  in  the  way 
they manage the business.  
303. 56% of firms saw changes in the way they managed the business (see graph right, 
note it gives counts of respondents not overall percentage).  
304. 30% of firms said projects had no effect on management. These firms typically had 
undertaken  projects  which  were  not  geared  at 
Numbers of firms with changes in the way they manage
impacting on management.  
305. The  changes  described  by  those  who  had  seen 
80

changes  included  altering  the  internal  practices  of 


the  firm,  learning  from  the  project  about  ways  to  60

Number
tackle  such  projects,  gaining  direction  for  the  firm  40

and  sometimes  confirming  that  their  approach  had 


been  right.  Firms  also  reported  an  improvement  in  20

their overall ability to manage the business.   0

Yes No

306. No  firms  reported  projects  having  detrimental  Change

impacts on the way the firm was managed.  
307. The  evaluation  found  significant  differences  between  the  rates  of  effect  on 
management for different activity types. A chi‐square test of independence gives a 
p‐value of p=.004. Mentoring, training, marketing and business planning had high 
rates of effect. Prototype had especially low rates.  This means that usually firms 
undertaking  mentoring,  training,  marketing  and  business  planning  projects  will 
see impacts from these projects on their management.  
 
 
 
 
 
 
 

55
 
activity * Firm on whether it affected management Crosstabulation
 
Firm on whether it
affected management
  Yes No Total
activity Business/strategic plan Count 12 4 16
  Expected Count 10.5 5.5 16.0
% within activity_cded 75.0% 25.0% 100.0%
  Intellectual property Count 5 6 11
protection Expected Count 7.2 3.8 11.0
  % within activity_cded 45.5% 54.5% 100.0%
Marketing Count 16 2 18
  Expected Count 11.8 6.2 18.0
% within activity_cded 88.9% 11.1% 100.0%
Mentoring/Training Count 15 2 17
  Expected Count 11.1 5.9 17.0
% within activity_cded 88.2% 11.8% 100.0%
  Prototype Count 7 13 20
Expected Count 13.1 6.9 20.0
  % within activity_cded 35.0% 65.0% 100.0%
Strategic Design Count 7 4 11
  Expected Count 7.2 3.8 11.0
% within activity_cded 63.6% 36.4% 100.0%
  Systems Evaluation Count 12 8 20
Expected Count 13.1 6.9 20.0
  % within activity_cded 60.0% 40.0% 100.0%
Total Count 74 39 113
Expected Count 74.0 39.0 113.0
  % within activity_cded 65.5% 34.5% 100.0%

 
58. Proportions of EDG clients undertaking projects aimed at management level 
areas or business level areas 
308. The evaluation categorised projects by whether they were focused on management 
level  activities  or  on  business  level  activities  and  looked  at  the  proportions 
undertaking each.   
Numbers of firms wanting business or management level
309. 47% of firms were undertaking projects which were at  assistance

management  level  and  41%  were  undertaking 


business‐level projects.   80

75

310. Of  those  firms  who  undertook  management  level 


70

projects,  82%  said  they  had  seen  changes  in 


Number

65

management,  and  17%  said  they  had  not.  Of  those 


60

who  were  undertaking  business  level  projects,  42% 


55

said  they  had  seen  changes  to  management  practices, 


50

and 51% said they had not.   Business Management

Business or management level

311. The  evaluation  found  a  significant  association  between  the  proportions  of  firms 
undertaking  business‐level  or  management  level‐projects,  and  activity  type 
undertaken by firms. A chi‐square test of independence gives a p‐value of p<.001. 
Mentoring  and  training,  business  planning,  systems  evaluation  and  strategic 
design  had  high  rates  of  management  level  projects.  Intellectual  property  and 
prototype had low rates.   
312. This  means  that  one  can  be  confident  that  some  activities‐  intellectual  property 
and  prototype‐  will  usually  not  be  undertaken  by  firms  who  want  management 
level  assistance,  but  instead  business  level.  The  other  activities  will  usually  be 
56
undertaken  by  firms  who  want  management  level  assistance.  Whether  these 
activities  fit  in  the  EDG  depends  on  whether  the  goals  of  the  fund  are  building 
ability in the sense of management ability, or in the sense of business ability.  

Level of assistance * activity_cded Crosstabulation

activity_cded
Business/ Intellectual
strategic property Mentoring/ Strategic Systems
plan protection Marketing Training Prototype Design Evaluation Total
Level of assistance Business Count 6 11 9 1 15 4 8 54
Expected
7.9 5.1 8.8 7.9 9.3 5.1 9.8 54.0
Count
% within
Level of 11.1% 20.4% 16.7% 1.9% 27.8% 7.4% 14.8% 100%
assistance
Management Count 11 0 10 16 5 7 13 62
Expected
9.1 5.9 10.2 9.1 10.7 5.9 11.2 62.0
Count
% within
Level of 17.7% .0% 16.1% 25.8% 8.1% 11.3% 21.0% 100%
assistance
Total Count 17 11 19 17 20 11 21 116
Expected
17.0 11.0 19.0 17.0 20.0 11.0 21.0 116.0
Count
% within
Level of 14.7% 9.5% 16.4% 14.7% 17.2% 9.5% 18.1% 100%
assistance

 
 
59. Proportions of EDG clients seeing gains in firm activity  
313. The  evaluation  looked  at  the  proportions  of  firms  reporting  changes  or  gains  in 
such  activities  as  getting  a  product  ready  to  launch  or  launching  it,  or 
understanding  the  firm’s  market  better,  or  gaining  a  strategy,  or  entering  a  new 
market.  
314. 78%  of  firms  achieved  the  results  described  above,  so  it  is  estimated  that  78%  of 
EDG  clients  have  used  the  grant  to  make  positive  effects  on  their  firm.  This  is  a 
good result for the EDG and NZTE.   
315. Furthermore,  firms  who  report  changes  in  management  and  firms  who  do  not 
both see effects on firm activity.  
 
 
 
 
 
 
 
 
 

57
 
  Gains in activity
  Frequency Percent
Valid Developing product 7 5.3
  Assists with
targeting/gaining 39 29.5
  customers/investors
Basic business
2 1.5
requirement now in place
Improved performance 18 13.6
Entering Market 28 21.2
Gave firm clear strategy 9 6.8
Total 103 78.0
Total 132 100.0

60. Proportions of EDG clients seeing changes in firm performance  
316. The  evaluation  looked  at  the  proportions  of  firms  reporting  changes  in 
performance in terms of domestic or export sales.  
317. 39%  of  firms  saw  changes  in  their  firm’s 
performance,  with  increased  domestic  or  foreign  Numbers of firms with changes in firm performance

revenue.  37%  said  it  was  too  early  to  see  any 
results  in  revenue.  2%  said  the  project  had  80

increased productivity.  
60

318. As  84%  of  firms  undertook  the  project,  gains  in 
Number

40

performance  for  39%  entails  nearly  half  of  firms 


who  make  use  of  the  grant  have  seen  gains  in  20

performance to date.   0

Increased Expanded Not yet


productivity domestic/export
319. The  evaluation  found  no  significant  association  sales
Change
between  the  proportions  with  effects  on 
performance  and  different  types  of  activity.  A  chi‐square  test  of  independence 
gives a p‐value of p=.090 
320. The  table  shows  intellectual  property  protection  had  very  high  rates  of  firms 
reporting gains were yet to eventuate, and market research and investigation were 
high  also.  Intellectual  property  protection  is  a  long  and  expensive  process,  and 
does not directly lead to gains in performance but for many firms is necessary for 
them.  Market  research  and  investigation  also  takes  time  to  result  in  gains,  and 
many firms received the advice or information they need but were yet to enter the 
market or were yet to see sales.  
321. Systems evaluation and strategic design had high rates of reporting gains in terms 
of sales, with business planning and mentoring being fairly high. Typically these 
firms  were  undertaking  projects  which  they  were  able  to  get  to  market  more 
quickly  or  see  gains  more  quickly.  Prototype  was  evenly  split  between  reporting 
gains and reporting gains were yet to eventuate, as firms were fairly evenly split 
in stages of prototype development. 
58
 
 

Effect on the firm performance * activity_cded Crosstabulation

activity_cded
Business/ Intellectual
strategic property Mentoring/ Strategic Systems
plan protection Marketing Training Prototype Design Evaluation Total
Effect on the firm Increased Count 0 0 0 0 1 0 2 3
performance productivity/strengthened Expected Count .4 .3 .5 .5 .6 .2 .5 3.0
position % within Effect
on the firm .0% .0% .0% .0% 33.3% .0% 66.7% 100%
performance
Expanded Count 8 2 6 9 9 5 12 51
domestic/export sales Expected Count 7.4 5.4 8.4 7.9 9.4 4.0 8.4 51.0
% within Effect
on the firm 15.7% 3.9% 11.8% 17.6% 17.6% 9.8% 23.5% 100%
performance
Not yet Count 7 9 11 7 9 3 3 49
Expected Count 7.1 5.2 8.1 7.6 9.0 3.8 8.1 49.0
% within Effect
on the firm 14.3% 18.4% 22.4% 14.3% 18.4% 6.1% 6.1% 100%
performance
Total Count 15 11 17 16 19 8 17 103
Expected Count 15.0 11.0 17.0 16.0 19.0 8.0 17.0 103.0
% within Effect
on the firm 14.6% 10.7% 16.5% 15.5% 18.4% 7.8% 16.5% 100%
performance

 
61. Proportions of EDG clients gaining facts or advice 
322. The  evaluation  looked  at  the  proportions  of  firms 
who  gained  advice  or  assistance  and  at  the 
proportions gaining information (such as facts on a 
market) or the use of specialist facilities.   Numbers of firms wanting facts, advice or specialist skills

323. 50%  of  firms  gained  advice.  38%  gained  facts  or 
specialist facilities.   80

60

324. The  evaluation  found  a  significant  association 


Number

between  the  proportion  of  firms  gaining  facts  or  40

advice  and  the  activity  type  undertaken  by  the  20

firm.  A  chi‐square  test  of  independence  gives  a  p‐ 0

Advice Facts Legal Grant used Specialist


value  of  p<.001.  Mentoring,  training  and  strategic  for internal technical
costs skills or
facilities
design  had  high  rates  for  advice;  intellectual  Type of assistance sought

property and prototype had  high rates for  facts or 


specialist skills such as manufacturing skills or legal skills (patent attorneys).  

59
Whether firm wanted advice on what to do, or not. * activity_cded Crosstabulation

activity_cded
Intellectual
Business/str property Mentoring/ Strategic Systems
ategic plan protection Marketing Training Prototype Design Evaluation Total
Whether firm Advice Count 10 0 10 17 4 11 14 66
wanted advice on Expected Count 9.7 6.3 10.8 9.7 11.4 6.3 11.9 66.0
what to do, or not. % within Whether
firm wanted advice 15.2% .0% 15.2% 25.8% 6.1% 16.7% 21.2% 100.0%
on what to do, or not.
No Count 7 11 9 0 16 0 7 50
Expected Count 7.3 4.7 8.2 7.3 8.6 4.7 9.1 50.0
% within Whether
firm wanted advice 14.0% 22.0% 18.0% .0% 32.0% .0% 14.0% 100.0%
on what to do, or not.
Total Count 17 11 19 17 20 11 21 116
Expected Count 17.0 11.0 19.0 17.0 20.0 11.0 21.0 116.0
% within Whether
firm wanted advice 14.7% 9.5% 16.4% 14.7% 17.2% 9.5% 18.1% 100.0%
on what to do, or not.

 
62. Do facts or advice projects impact on management practice? 
325. The evaluation looked at whether there was any association between having facts 
or advice and seeing changes in the way firms managed their business, or whether 
these two things are independent of each other.  
326. The evaluation has found a significant association between the proportion of firms 
with  an  effect  on  management,  and  having  had  advice.  A  chi‐square  test  of 
independence gives a p‐value of p<.001. 
327. An association was found between advice and changes in management practice, in 
particular  the  rate  of  reporting  the  project  affected  management  was  higher  for 
groups  receiving  advice.  This  means  that  one  can  be  confident  that  firms  having 
advice will usually also see changes in the way they manage their business. Firms 
asking for facts will usually not see any changes.  
 
  Whether firm wanted advice on what to do, or not. * Firm on whether it affected
management Crosstabulation
  Firm on whether it
affected management
  Yes No Total
Whether firm Advice Count 52 14 66
wanted advice on Expected Count
  what to do, or not.
43.2 22.8 66.0
% within Whether
firm wanted advice 78.8% 21.2% 100.0%
  on what to do, or not.
No Count 22 25 47
  Expected Count 30.8 16.2 47.0
% within Whether
  firm wanted advice 46.8% 53.2% 100.0%
on what to do, or not.
  Total Count 74 39 113
Expected Count 74.0 39.0 113.0
  % within Whether
firm wanted advice 65.5% 34.5% 100.0%
on what to do, or not.
 
 

60
 
328. One  can  be  confident  that  firms  reporting  impacts  on  management  will  usually 
have also received advice. Firms reporting no impacts will usually have used the 
project to purchase information or specialist skills.  
 
63. Are facts or advice projects also management or business level projects? 
329. The evaluation looked at whether there was any association between gaining facts 
or  advice  and  gaining  management  or  business  level  assistance.    The  evaluation 
has found a significant association between the proportion of firms having advice 
or  not  and  having  management‐level  or  business‐level  assistance.  A  chi‐square 
test of independence gives a p‐value of p<.001. In particular firms receiving advice 
had  high  rates  of  undertaking  management  level  assistance;  whereas  firms 
receiving facts had higher rates of undertaking business‐level projects.   
330. This  means  that  one  can  be  confident  that  firms  having  advice  will  usually  also 
have management level assistance. Firms gaining facts will usually not.  
 
 
Whether firm wanted advice on what to do, or not. * Level of assistance Crosstabulation
 
Level of assistance
  Function Strategic Total
Whether firm Advice Count 8 58 66
  wanted advice on Expected Count 30.7 35.3 66.0
what to do, or not. % within Whether
  firm wanted advice 12.1% 87.9% 100.0%
on what to do, or not.
  No Count 46 4 50
Expected Count 23.3 26.7 50.0
  % within Whether
firm wanted advice 92.0% 8.0% 100.0%
  on what to do, or not.
Total Count 54 62 116
  Expected Count 54.0 62.0 116.0
% within Whether
  firm wanted advice 46.6% 53.4% 100.0%
on what to do, or not.
 
 
64. Do management level or business level projects impact on management practice? 
331. The evaluation categorised projects by whether they were focused on management 
level  activities  or  on  business  level  activities,  and  then  looked  at  whether  there 
was any association between the two types of projects and seeing changes in the 
way firms managed their business, or whether they are independent of each other.  
332. The evaluation has found a significant association between the proportion of firms 
having had management‐level or business‐level assistance and reporting  impacts 
on  management.  A  chi‐square  test  of  independence  gives  a  p‐value  of  p<.001.  In 
particular firms receiving management‐level assistance had high rates of reporting 

61
impacts  on  management;  whereas  business‐level  had  high  rates  of  reporting  no 
impacts on management.  
333. This  means  that  one  can  be  confident  that  firms  undertaking  management  level 
projects  will  usually  also  see  changes  in  the  way  they  manage  their  business. 
Firms undertaking business level projects usually will not.  
 
 
Level of assistance * Firm on whether it affected management Crosstabulation
  Firm on whether it
affected management
  Yes No Total
Level of assistance Business Count 23 28 51
  Expected Count 33.4 17.6 51.0
% within Level of
  45.1% 54.9% 100.0%
assistance
management Count 51 11 62
  Expected Count 40.6 21.4 62.0
% within Level of
82.3% 17.7% 100.0%
  assistance
Total Count 74 39 113
  Expected Count 74.0 39.0 113.0
% within Level of
65.5% 34.5% 100.0%
  assistance

 
65. Do changes in management practice impact on firm performance? 
334. The  evaluation  has  found  no  significant  association  between  firms  who  reported 
management  changes  and  those  who  did  not  and  those  reporting  effects  on 
performance  (in  terms  of  domestic  or  export  performance).  A  chi‐square  test  of 
independence gives a p‐value of p=.170. Firms seeing changes in management and 
firms seeing no changes had similar rates of gains in firm performance (Note that 
this  is  rate  of  gain  not  degree  of  gain.  The  evaluation  does  not  have  data  on 
turnover  subsequent  to  the  project’s  implementation  with  which  to  calculate 
actual turnover change). 
335. This  means  that  gains  in  firm  performance  are  seen  both  by  firms  who  changed 
management practice and by firms who did not. Projects deliver benefits to firms 
in  terms  of  gains  in  performance  independently  of  whether  they  deliver  gains  in 
management practice.  
 
 
 
 

62
 
  Effect on the firm performance * Firm on whether it affected management Crosstabulation

Firm on whether it
  affected management
Yes No Total
  Effect on the firm Increased Count 3 0 3
performance productivity/strengthened Expected Count 2.0 1.0 3.0
  position % within Effect on
100.0% .0% 100.0%
the firm performance
  Expanded Count 37 14 51
domestic/export sales Expected Count 34.2 16.8 51.0
  % within Effect on
the firm performance
72.5% 27.5% 100.0%

Not yet Count 29 20 49


  Expected Count 32.8 16.2 49.0
% within Effect on
  the firm performance
59.2% 40.8% 100.0%

Total Count 69 34 103


  Expected Count 69.0 34.0 103.0
% within Effect on
67.0% 33.0% 100.0%
  the firm performance

 
 
66. Do advice or facts projects impact on firm performance? 
336. The evaluation has found an association very close to significant between projects 
delivering facts or advice and those reporting effects on performance (in terms of 
domestic  or  export  performance).  A  chi‐square  test  of  independence  gives  a  p‐
value of p=.053. This means that the association is tentative, and may differ with 
further  evidence  in  time.      The  table  shows  that  firms  undertaking  projects 
delivering  advice  have  high  proportions  of  firms  also  seeing  either  increased 
productivity  or  expanded  sales.  Projects  delivering  facts  show  lower  proportions 
of firms of increased productivity or expanded sales.  
 
 
Whether firm wanted advice on what to do, or not. * Effect on the firm's performance Crosstabulation

  Effect on the firm's performance


Increased
  productivity/ Expanded
strengthene domestic/ex
d position port sales Not yet Total
  Whether firm Advice Count 2 34 21 57
wanted advice on Expected Count 1.7 28.2 27.1 57.0
what to do, or not.
  % within Whether
firm wanted advice 3.5% 59.6% 36.8% 100.0%
on what to do, or not.
  No Count 1 17 28 46
Expected Count 1.3 22.8 21.9 46.0
  % within Whether
firm wanted advice 2.2% 37.0% 60.9% 100.0%
  on what to do, or not.
Total Count 3 51 49 103
  Expected Count 3.0 51.0 49.0 103.0
% within Whether
firm wanted advice 2.9% 49.5% 47.6% 100.0%
  on what to do, or not.

 
 
63
67. Do management or business level projects impact on firm performance? 
337. The  evaluation  found  a  significant  association  between  the  proportion  of  firms 
where  there  was  an  effect  on  firm  performance  and  projects  assisting  with 
management or business type projects. A chi‐square test of independence gives a 
p‐value of p=.023. In particular, projects assisting with management‐level activities 
showed a higher rate of gains in firm performance in terms of export and domestic 
revenue and improved productivity.  
338. Business‐level  projects  had  higher  rates  of  revenue  gains  being  yet  to  eventuate, 
and  consistent  with  this  had  a  significantly  higher  rate  of  firms  subsequently 
launching  products,  and  enabling  firms  to  target  market  segments  and  attract 
prospective investors. A chi‐square test of independence gives a p‐value of p<.001. 
339. This  means  that  one  can  be  confident  that  firms  undertaking  management  level 
projects  will  usually  also  see  gains  in  their  performance.  Firms  undertaking 
business level projects will not.  
340. Note, however, there is a caveat to this finding. Firms undertaking business level 
projects usually said they had not yet seen changes in gains as it was too early for 
this  given  the  project  they  undertook.  Time  is  needed  to  see  if  the  result  above 
holds.  It  may  not  if  many  of  the  business  level  project  firms  see  gains  in 
performance in, say, the next six months. 
 
 

Effect on the firm performance * Level of assistance Crosstabulation

Level of assistance
Business Management Total
Effect on the firm Increased Count 1 2 3
performance productivity/strengthened Expected Count 1.4 1.6 3.0
position % within Effect on
33.3% 66.7% 100.0%
the firm performance
Expanded Count 17 34 51
domestic/export sales Expected Count 23.8 27.2 51.0
% within Effect on
33.3% 66.7% 100.0%
the firm performance
Not yet Count 30 19 49
Expected Count 22.8 26.2 49.0
% within Effect on
61.2% 38.8% 100.0%
the firm performance
Total Count 48 55 103
Expected Count 48.0 55.0 103.0
% within Effect on
46.6% 53.4% 100.0%
the firm performance

64
11. Quantitative findings: interpretation and conclusion 
 

341. The evaluation was interested in seeing whether the EDG had resulted in changes 
and  gains  in  management  practice  and  in  activities  of  the  firm;  whether  these 
resulted  in  gains  in  performance,  and  whether  there  was  any  difference  in 
outcomes  for  activity  type,  and  for  firms  undertaking  projects  delivering  advice, 
facts, management level, or business level assistance.  
 
68. Overall 
342. 84%  of  firms  went  ahead  with  the  project;  the  remainder  saw  changes  in  plans 
which meant they no longer wished to undertake the project.  
343. 78% of firms have seen benefits from the grant, in terms of having a product ready 
for launch or launching it, understanding which segments of the market to target, 
improving the way the firm runs, gaining or clarifying a strategy for the future, or 
entering  a  new  market.  This  means  that  of  the  84%  of  firms  who  complete  a 
project, 92% see positive gains from it. This is a very good result for the EDG.  
344. 56% of firms saw changes in the way they managed the business; 30% of firms said 
projects  had  no  effect  on  management‐  but  these  firms  typically  had  undertaken 
projects which were not geared at impacting on management. 47% of firms gained 
management level assistance and 41% gained business‐level assistance.  
345. 39%  of  firms  have  seen  gains  in  firm  performance.  37%  said  it  is  too  early  yet  to 
see gains in performance. This was usually because while the grant was closed the 
project  was  taking  longer  than  one  year.  The  evaluation  recommends  a  second 
look  at  the  sample  in  six  to  twelve  months,  for  if  the  37%  also  see  gains  in 
performance it will raise the success rate of the fund significantly. 
346. The  difference  between  the  roughly  50%  of  firms  who  gained  in  terms  of 
management  capability  and  the  nearly  80%  who  have  gained  in  terms  of  the 
activities  they  used  the  fund  for  is  due  to  ambiguities  in  the  original  policy 
statement resulting in a  broad interpretation by NZTE of building ‘management 
capability’. 
347. Firms are undertaking projects which in a broad sense improve their management 
capability; but not in a narrow sense. Roughly 50% of firms had no intention when 
undertaking  the  projects  for  it  to  have  any  changes  to  or  have  any  effects  on 
management. So in terms of the fund’s capability objectives the success rate of the 
EDG  is  47%  for  self‐reported  changes  and  56%  for  changes  which  have  been 
categorised as at a management level.  
348. 50% of firms use the fund to gain advice, and 38% use it to gain facts or specialist 
facilities.  
 

65
69. Activity types 
349. All  activity  types  were  equal  in  their  rates  of  subsequent  gains  in  firm 
performance in terms of domestic or export sales.  
350. The  types  of  activity  differ  in  the  rates  at  which  they  result  in  change  in 
management  practice.  Mentoring,  training,  marketing  projects,  and  business 
planning  showed  significantly  higher  rates  of  change  in  the  way  firms  manage 
their  business.  This  means  one  can  be  confident  that  these  activities  will  usually 
have firms changing their management practice.  
351. Activity type was also related to undertaking management level projects. All but 
intellectual property and prototype had high rates of being used for management 
level projects, with mentoring and training being especially high. This means one 
can be confident that these activities will usually have firms gaining management 
level assistance.  
352. The  activity  types  of intellectual  property  protection  and  prototype  development 
had  very  low  rates  of  firms  reporting  changes  in  management,  undertaking 
management level projects or gaining advice.  It seems these are not well fitted to 
the goals of the EDG.  
 
70. Interpreting the results: improving management capability 
353. The  goal  of  the  EDG  is  improve  firm  performance  via  an  improvement  in 
management and business capability.  
354. The  evaluation  defined  projects  as  business  or  management  level,  and  looked  to 
see  the  impacts  of  each  project  type.  The  evaluation  has  found  a  significant 
association  between  the  proportion  of  firms  having  had  management‐level  or 
business‐level assistance and reporting impacts on management. This means that 
one  can  be  confident  that  firms  undertaking  management  level  projects  will 
usually  also  see  changes  in  the  way  they  manage  their  business.  Firms 
undertaking business level projects usually will not.  
355. The evaluation also found that firms undertaking projects defined as management 
level  had  significantly  higher  rates  of  gain  in  performance.  This  means  that  one 
can  be  confident  that  firms  undertaking  management  level  projects  will  usually 
also see gains in their performance. Firms undertaking business level projects will 
not.  
356. Note the caveat to this finding. Firms undertaking business level projects usually 
said they  had not  yet  seen changes in gains as it was too early for this given the 
project they undertook. Time is needed to see if the result above holds. It may not 
if  many  of  the  business  level  project  firms  see  gains  in  performance  in,  say,  the 
next six months. 
357. Currently the proportions of firms using the EDG to undertake management level 
or  business  level  projects  are  fairly  even.  To  target  the  fund  more  squarely  at 
management  level  projects  the  assessment  of  proposals  and  possibly  the 
66
description of the funds goals to the market, would need to be revised. This would 
require a definition from MED for NZTE of at least the core of what ‘management 
level’ is (even if the edges of the distinction with ‘business level’ are left somewhat 
blurry).  
358. As  the  fund  is  undergoing  change  with  its  devolution,  due  for  piloting  1 
December 2005, there is time to assess the sample again, to coordinate any changes 
with final implementation of the devolved model in mid 2006.   
 
71. Resolving the ambiguity between facts and advice.    
359. The  evaluation  found  there  is  an  issue  in  whether  the  fund  is  a  channel  for 
information to managers or whether it is to build their capability. At present, two 
types  of  firms  are  accessing  the  fund:  those  who  can  themselves  implement  the 
project but need information to do so, and those who need to gain the capability to 
implement  their  project.  It  may  be  that  the  fund’s  goal  of  capability  building  is 
achieved best by including firms who can themselves implement the project or by 
being  restricted  to  those  firms  who  need  to  learn  the  skills  to  gain  capability  in 
order to implement the project. 
360. The  evaluation  defined  projects  as  delivering  advice  to  build  capability,  or 
delivering information to firms with the requisite capability, and looked to see the 
impacts  of  each  project  type.  The  evaluation  has  found  a  significant  association 
between  the  proportion  of  firms  having  advice  or  not  and  having  management‐
level  or  business‐level  assistance  and  seeing  changes  in  management  practice  or 
not. In particular firms receiving advice had high rates of receiving management 
level  assistance  and  seeing  changes  in  management  practice;  whereas  firms 
receiving  facts  had  higher  rates  of  receiving  business‐level  assistance  and  not 
seeing changes in management practice.  This means that one can be confident that 
firms  having  advice  will  usually  also  gain  management  level  assistance  and 
usually see changes in management practice. Firms gaining facts will usually not 
see such changes.  
361. As  management  level  projects  see  higher  rates  of  gain  in  performance,  it  seems 
aiding management via advice is the best way to aid management to achieve gains 
in performance.  
362. The  evaluation  also  found  a  tentative  association  between  receiving  advice  and 
seeing  gains  in  performance.  Firms  undertaking  projects  delivering  advice  have 
high  proportions  of  firms  also  seeing  either  increased  productivity  or  expanded 
sales. Projects delivering facts show lower proportions of firms gaining increased 
productivity or expanded sales. 
363. Thus  the  fund  could  be  at  least  weighted  toward  firms  wishing  to  gain  advice. 
This  can  be  done  by  adjusting  the  assessment  to  spot  these  sorts  of  firms,  and 
possibly the description of the fund to the market.  
364. The evaluation must still make the same caveat as before, that time may eliminate 
these differences. Again, with the final implementation of changes to the fund due 
67
mid  2006,  there  is  time  to  test  these  possibilities  by  assessing  the  sample  again, 
before any further changes are made to the fund.  
 
72. Declined firms 
365. The  evaluation  rang  a  simple  random  sample  of  declined  firms.  The  sample  size 
was  58.  The  evaluation  contacted  70%  of  the  sample.  All  who  were  contacted 
spoke to the evaluation, giving a 70% response rate. The remainder of the sample 
was not able to be located. 
366. 38% of the declined EDG firms went on and did the project. 33% did not.  
367. It  may  be  that  the  firms  who  were  declined  but  undertook  their  projects 
nonetheless did so because they had the resources to do so and this was the reason 
for them being declined. The evaluation has no information on why the firms were 
declined  with  which  to  confirm  this  supposition  because  many  were  declined 
prior to those records being kept.   
368. The firms who had been declined and had not undertaken the project viewed that 
as a real loss.  
369. Many who were declined felt they had been brushed off, could not understand it, 
and were left unhappy with NZTE and the grant process. Many said they would 
not  reapply.  This  suggests  that  the  goal  of  the  fund  to  encourage  firms  to  seek 
assistance must be considered a goal for those firms who are declined as well, and 
the  process  of  declining  firms  should  not  discourage  firms  from  seeking  further 
assistance.  More  personalized  and  encouraging  explanations  of  the  reasons  for 
being declined will help prevent the feeling of being ‘brushed off.’   
 
73. Recommendation  
370. The evaluation recommends that a process of detailing more fully the reasons for 
declining firms is instigated.  
371. It is recommended NZTE establishes a system of storing electronically data from 
the application forms on all applicant firms’ financial and capability needs, taken 
from their description in the application form of the project and their goals for the 
external advice or expertise. This should be able to be compared to final outcomes 
from the project funded by the grant, and would place both an evaluation in the 
future  and  NZTE  in  a  stronger  position  to  assess  changes  in  the  firms  post 
intervention. MED should be involved in establishing this system.   

68
12. Qualitative findings 
 
74. Guide to the findings 
372. The findings in this section are qualitative. They are drawn from the sample of 132 
firms.  They  are  not  statistically  representative  of  outcomes  of  the  EDG,  or  the 
activities  occurring,  that  is,  one  cannot  generalize  from  these  statements  to  the 
EDG  as  a  whole.  The  findings  are  to  give  an  understanding  of  the  range  of 
situations, goals and experiences of the firms in the sample.       
 
75. Overall 
373. Firms  said  that  the  fund  was  a  significant  leg‐up  to  achieving  their  goals,  and 
often  gained  them  the  results  they  were  after  in  a  very  much  shorter  time  frame 
than  they  felt  they  could  have  done  on  their  own.  So  while  it  is  not  certain  that 
firms would not have done the project and achieved their goals without the grant, 
the firms were sure they achieved them faster. Many also said they were able to do 
the project to a much higher standard than otherwise.  
 
76. Business/strategic plan development and feasibility studies. 
374. The  situations  of  firms  undertaking  this  type  of  activity  were  mainly  a  wish  to 
expand into new markets, advice on the firm and its performance, or to have help 
commercialising a product.  
375. The  projects  were  mostly  genuine  efforts  at  tackling  skill‐gaps,  that  is,  the  firms 
did not have the skills to the plans for the business themselves. Those not genuine 
included a firm using the grant to fund a report it needed written by an external, 
independent  party,  in  order  to  secure  investors.    Another  firm  needed  help  in 
gaining  FDA  approval:  they  needed  agents  in  the  US  who  were  proficient  at 
organising  and  managing  that  process,  as  well  as  an  independent  chemical 
analysis of their product.  
376. The  latter  is  a  grey  case,  because  without  agents  who  know  the  process  a  firm 
would be lost in the FDA bureaucracy and the firm did not have that knowledge. 
They said they now know how to pull together the necessary documentation, and 
who the right people in the US, and could help other companies in NZ do it. 
377. Seven firms needed facts with which to decide how and whether to proceed with 
their  plans.    Three  needed  assessments  of  markets  in  order  to  decide  whether  to 
launch in that market, and two successfully launched as a result. 
378. Firms  who  requested  and  received  management  capability  help  included  a  firm 
who  wished  for  a  long‐term  strategy  after  a  few  roller‐coaster  years  with  major 
international  clients.  They  felt  they  were  a  small  company  who  had  struck  gold 
early on but didn’t know what business planning was or how they should handle 

69
down‐times  between  clients.  As  a  result  of  their  project  they  have  developed  a 
global plan as well as having analysed their company’s strengths and potential.  
379. Other  firms  wished  for  help  in  improving  their  performance.  They  gained  new 
ways of thinking about their firm as well as specific things to work on to improve 
performance.  For  one  firm  the  outcome  was  a  fundamental  restructure‐  in 
direction, branding, and new relationships with external researchers, as well as by 
gaining a board of directors and shareholders. The former manager now operates 
the business and leaves its management to his new board.   
 
77. Intellectual property protection.  
380. Protecting i.p varied in its importance for firms. I.T and bio‐tech firms view it as 
essential.  Software  is  easily  copied  once  it  is  launched  as  a  product,  so  software 
firms  must  have  i.p  protection.  Firms  in  the  pharmaceutical  industry  cannot  get 
partners  or  investors  without  them  being  assured  they  have  rights  over  any 
product  they  make,  for  development  costs  so  much,  rights  at  the  end  of 
development must be assured. In that regard firms say they don’t have a business 
without i.p protection. Other firms view i.p as only as useful as they are capable of 
affording  to  defend  it.  Firms  said  i.p  was  also  useful  for  letting  them  know  that 
their idea really was original and that they were right to pursue it.  
381. Two  firms  explained  that  the  volumes  they  need  to  produce  their  products  at, 
either to meet the volume of product demanded by the market, or to meet the low 
costs demanded by the market, means they cannot manufacture in New Zealand. 
The  manufacturing  industry  is  both  too  small  and  too  expensive.  They  said 
manufacturing offshore entails they must have global patents, else they will loose 
their product to rival offshore manufacturing firms.  
382. Gaining  global  patents  usually  costs  firms  more  than  one  hundred  thousand 
dollars, and the EDG does not go far toward that, although firms were grateful for 
any and all assistance they had with such large costs.  
383. I.p protection is not something which easily fits with the policy goals of improving 
management  skills  or  abilities.  Firms  already  knew  whether  they  wanted  or 
needed  I.p  For  some  i.p  lay  within  a  larger  strategy  of  selling  or  manufacturing 
offshore, but this strategy was already developed.  
 
78. Strategic Design 
384. Projects under this type of activity included projects with a narrow focus, such as 
on aspects of product design, and a broader focus, on branding for the company as 
a whole.  
385. Product design projects included such things as developing owner’s manuals and 
instructional  DVDs,  assistance  with  design,  logos,  wording  and  marketing 
material  for  the  product.  Projects  also  included  technical  advice  on  technology 

70
projects, and in these cases the difference between strategic design and prototype 
development is slim. 
386. Branding projects include one undertaken by a new firm still getting their product 
into  production  but  who  believed  their  product  would  sell  on  image,  and  so 
wanted the ‘feel’ of the company to be right. The firm had already spent money on 
this  but  the  grant  gave  work  a  leg‐up  and  meant  the  firm  moved  ahead  more 
quickly. It had a product ready for production in 12 months.  
387. Another  firm  had  been  to  a  branding  seminar  and  decided  to  re‐brand  their 
existing firm, and said they would never start a firm again without going through 
a branding exercise first. They felt it was very important for marketing and success 
in general.  
 
79. Market research and marketing plans 
388. Some  of  the  marketing  projects  were  done  by  firms  who  did  not  know  how  to 
approach  entering  a  new  market,  and  needed  someone  who  knew  what 
information  to  gather  and  what  the  firm  would  need  to  do.  Some  of  these  firms 
felt  they  had  learnt  what  to  do  from  these  projects  and  could  now  enter  any 
market on their own.  
389. Other firms knew the specific information on a market they needed, but many of 
these firms said they would not try to do that sort of research on their own.  
390. Firms  who  knew  what  sort  of  information  they  needed  said  they  would  not  feel 
comfortable researching a market themselves. It is a skill that some managers said 
they  will  continue  to  access  externally  while  they  remain  too  small  to  have  an 
employee with such skills. One firm said for a small business it is better to contract 
the  task  out  to  huge  experience  in  profiling  a  market,  and  so  not  be  gobbled  up 
and spat out by big players in the U.S. To not do this is false economy. 
391. Firms who did not know how to develop a plan to enter a market felt they could 
learn  such  a  skill.  Many  of  these  firms  were  also  undertaking  marketing  work 
under mentoring. 
 
80. Prototype 
392. Most  of  the  firms  developing  prototypes  used  the  grant  to  purchase  facilities  for 
production they did not have or the technical skills needed to build the prototype 
their  firm  did  not  have.  Two  firms  used  the  grant  to  fund  internal  costs  and  did 
not use external providers.  
393. Only  three  of  the  firms  used  the  grant  to  purchase  advice  on  developing  their 
prototype. 

71
 
81. Mentoring and training 
394. This type of activity is the one most geared to building management ability, and so 
has seen the greatest impact on it. Some firms have had a complete turnaround in 
performance and described the results as ‘mind‐blowing.’ 
395. Firms  have  also  decided  to  keep  the  mentor  on,  or  have  established  a  board  of 
directors for ongoing help.   
396. There is some overlap with the marketing activities, some firms used the training 
or  mentoring  to  develop  marketing  plans,  but  the  difference  is  that  via  training 
and  mentoring  they  learn  both  how  to  develop  a  plan  and  develop  one  for  their 
firm.  
 
82. Certification and systems evaluation 
397. Certification was of two different types‐ compulsory and optional certification for 
a  product,  which  required  an  assessment  of  the  product,  and  compulsory  and 
option  certification  of  the  firm,  which  required  an  analysis  of  procedure  and 
documentation.  
398. Some firms knew how to prepare the firm for the certification, and the grant went 
to  their  costs  or  the  costs  of  the  evaluation  of  the  firm.  Others  did  not,  and  the 
grant went to the costs of the consultants used. 
399. Systems  evaluation  ranged  from  a  review  of  the  systems  of  the  firm  to 
development  of  products.  One  firm  in  fact  built  a  prototype:  the  firm  needed 
funding  for  the  project  but  due  to  the  requirement  for  external  assistance  they 
hired  consultants  to  build  the  prototype  when  they  had  the  skills  in  house.  The 
results were not as good as they would have liked and they had to do a fair bit of 
re‐development. 
400. A  firm  who  had  systems  reviewed  had  the  ‘seat‐of‐the‐pants’  systems  they  had 
built  over  the  years  reviewed  and  altered.  The  consultants  documented 
responsibilities and removed uncertainty on roles and procedures. As a result the 
firm improved its performance, especially delivery time and saw revenue growth 
as a result.  
 
 
 
 
 

72
 

Appendix: Survey Questions  
 
401. These  are  the  questions  used  for  the  survey,  and  all  firms  were  asked  these 
questions,  but  all  the  interviews  involved  asking  further  questions  to  better 
understand  the  situation  of  the  firm,  the  project  and  the  outcomes.  These  varied 
from firm to firm as required. 
 

1.  OK. to begin with, if you could think back to before the _______assistance was        
decided upon, when you were originally thinking to seek help, what sort of help were 
you after, and how did you arrive at  _________? 
 
2. So thinking about the project itself, what were your specific goals for it?  
 
 
3. So you had received approval for the grant, and called in the external people you 
had chosen, what happened next? what did the external people do? 
 
4. Can you describe what sort of effects the project has had on your business, if any? 
 
 
5. Have you seen any impact of this on your business’ performance 
 

6. Can you think of any ways in which the project has influenced the way you manage    
your business? 
 

7. Do you think you will seek any more assistance for your business? 
 

8. On balance, do you think what has resulted from this, then, was worth the time 
spent on applying? 
 

73

Вам также может понравиться