Академический Документы
Профессиональный Документы
Культура Документы
qualification protocols
2
qualification protocols
2 Overview
2.1 Objective
To assure that the system will consistently produce_______
of predictable quality when operated in prescribed manner:
all physical aspects, related procedures, process monitoring
and control all function as per specifications.
2.2 Purpose
To demonstrate that the design, construction,
commissioning and operation of the system is suitable for
the intended purpose and possesses the quality attributes to
render it cGMP compliant and meets regulatory
obligations.
2.3 Reasons for validation
* To demonstrate that system design (with all
components) is compatible with system functions
* To demonstrate that system has the capacity to achieve
specified quality levels
* To verify that operation, cleaning, sanitation, and
maintenance procedures for system are acceptable
* To establish that sampling plan has the capacity to
determine whether or not the system is under control
* To establish that operating and maintenance people are
adequately trained
* To verify that a proper system of documentation and
record maintenance exists
2.4 Responsibility
* Production Manager
* QA Manager
* Validation Manager
* Engineering Manager
* Process Development Manager
2.5 Revalidation
System to be revalidated on:
* Substitution of existing system or sub-system with
new system or sub-system
3
qualification protocols
2. Purpose
To provide an outline for the design of the equipment/system to be
procured and ensure that it meets cGMP and Regulatory expectations
3. Design input
* Overview of system, sub-assemblies, and components – how they
function and recommended materials of construction; raw material
data; finished material expectations
* Special concerns, if any, and recommended care during
manufacture and installation
4. Design basis
* Specifications in terms of bill of materials
5. Acceptance criteria
* Parametric definitions with tolerances
6. System description
* Sketch or line diagram
7. Reference documents
* SOPs for operation, regeneration, maintenance, cleaning,
sanitation, testing etc for system/sub- systems/components
8. Manufacturer’s communication
* Description of system offered
4
qualification protocols
2. Purpose
To verify that
1 System is installed as per approved drawings
2 System meets cGMP and Regulatory expectations
3 SOPs have been identified, drafted and listed
4 Instruments have been identified for calibration of system
5 Support utilities properly connected
6 Peripherals and electricals properly connected
7 Safety features and aspects accounted
3. Recording instructions
1 Record requested information in ink.
2 Use separate data sheet for separate components/systems, even
if there are more than one of a type, so that identity of each is
preserved
3 Sign and assign date in ink
4. System description
1 Name of system/Model/Serial No/
Manufacturer’s name, address and contact nos/
Supplier’s name, address and contact nos
2 Identification number/location
3 Use of the system/equipment and its capacity
4 Components
Component DQ specs Manufacturer’s specs Actual observation
5
qualification protocols
5. SOPs
S/N Function SOP Date of Revn No Title Next revn
No issue and date due on
a Operating
b Cleaning & sanitizing
c Calibration
d Preventive maintenance
e Testing & requalification
f Comments & observations
6. Calibration review
a. Process Instruments
S/N Instrument Location Date of Calibrated Checked Next calibrn
calibrn by by due on
b. Test Instruments
S/N Instrument Location Date of Calibrated Checked Next calibrn Component
calibrn by by due on to be calibrtd
6
qualification protocols
8. Drawings
Category: Piping and Instrumentation
General arrangement/ schematic line diagram
Utility
Isometric
Other
S/N Title of Drawing Category Location Drawing No Date
7
qualification protocols
8
qualification protocols
2. Purpose
1 To demonstrate that the equipment/system performs
reproducibly and consistently
2 To document performance of the equipment/system for future
reference
3 To assure that the equipment /system performance is adequate
to support the process for which the system is intended
4 To develop SOPs for start-up, operation, shut-down and
sanitisation of the equipment/system
5 To document test procedures and criteria for acceptance
6 To define parameters that should be reproducible
7 To verify performance across full range of operation from
minimal to maximal loads, with special evaluation at upper
and lower limits
3. SOP verification
1 Is current version in use?
2 Do operating personnel understand and follow SOP
methodology and requirements?
3 Does SOP provide adequate direction and control to ensure
uniform equipment/system performance?
(Comments if answer to above is negative)
Final Remarks: SOP verification result: Pass/Fail?
4. Control panel functionality
Purpose
To demonstrate that the control panel provides proper
functionality as per description
Testing
1 Verify that all controls on the panel are properly labeled and
identified
2 Verify functionality of each component on the panel against its
stated function
3 Observe and record responses with control panel in use
Functionality test results:
Identification:Eqpmnt No/Make/Serial No/ Location of eqpmnt
Control panel serial no/ location of control panel
S/N Component of Described Description matches function
control panel function Yes No
Comments:
Reviewed and inspected by: Name/signature/date
9
qualification protocols
10
qualification protocols
11
qualification protocols
MR KISHOR DATAR
Early in design, the owner and designer should discuss who will be
responsible for as-built drawings, setting up maintenance files, and
training. They should create a qualification plan for the HVAC,
including:
1 a functional description of what the systems will do;
2 maps of room pressures, airflow diagrams, and cleanliness zones
served by each air handler;
3 a list of critical components to be qualified, including the
computer controlling the HVAC;
4 a list of owner’s procedures that must be followed for qualification
of equipment and systems that affect critical variables;
5 a list of qualification procedures (IQ/OQ/PQ protocols) written
especially for the project; and
6 a list of needed commissioning equipment.
The approval procedure should also be defined in the QP. It is
important to measure and document the critical variables of a system
(such as room pressure), but it is also important to document
performance of components that affect that critical variables (e.g.,
room pressure sensors, temperature sensors, airflow volume monitor)
for GMP as well as business records. Documentation helps ensure
that replacement parts (e.g., motors) can be specified, purchased, and
installed to satisfy critical variables.
Critical components must be determined (including instruments) that
could affect critical parameters and could, through an undetected failure,
lead to product corruption. If performance data are in the qualification
records, replacement parts of different manufacture can be installed
without major change control approvals, as long as they meet
performance requirements. Owner approvals for the qualification plan
should be obtained while proceeding with detailed design.
Design Qualification
1. Prepare User Requirement, Specifications & Functional
Specifications
Include System ID, Rooms covered, Class to be maintained,
Temperature & RH conditions to be maintained within area,
12
qualification protocols
13
qualification protocols
Installation Qualification
The installation qualification (IQ) protocol records construction
inspection to verify compliance with contract documents, including
completion of punch list work, for critical components. It may
include material test reports, receipt verification forms, shop
inspection reports, motor rotation tests, and contractor-furnished
testing and balancing. It also includes calibration records for
instrumentation used in commissioning and for installed
instrumentation (e.g., sensors, recorders, transmitters, controllers, and
actuators) traceable to National Institute of Standards and Technology
(NlST) instruments.
Control software should be bench tested, and preliminary (starting)
tuning parameters should be entered. Control loops should be dry-
loop checked to verify that installation is correct. Equipment and
instruments should be tagged and wiring labeled. Commissioning
documentation must attest to the completion of these activities and
include as-built drawings and installation-operation-maintenance
(IOM) manuals from contractors and vendors.
1. Preparing for Installation Qualification
Making copy of following documents approved during DQ phase for
cross- verification of Installation, Detailed duct layout, Detailed heat
load calculations, Air flow with level of filtration & control system
schematics, AHU data sheet with fan selection, Dehumidifier/
Recovery wheels etc. data sheets & selections (If applicable), Design
specifications for control & monitoring system with selection of
control system & components, Typical P & ID for near coil piping of
AHU / Dehumidifier etc., Filter selection & data sheets of filters, Data
sheets of all major items etc. Simultaneously prepare Installation
Check Sheet giving ref. of drawings, details etc. approved during DQ,
Include items to be checked as per GEP like Flange gaskets,
tightening of bolts etc., SOP’s - duct leak test, Hydro test, loop check,
etc.
14
qualification protocols
Operational Qualification
The operational qualification (OQ) protocol documents startup,
including critical components. This includes individual performance
testing of control loops under full operating pressure performed in a
logical order (i.e., fan control before room pressure control). The
commissioning agent must verify that operating parameters are within
acceptance criteria.
The HVAC may be challenged under extremes of design load (where
possible) to verify operation of alarms and recorders, to determine
(and correct, if significant) weak points, and to verify control and
door interlocks. Based on observations, informal alert values of
critical parameters, which might signify abnormal operation, may be
considered.
Files should include an updated description of the HVAC system,
describing how it operates, schematics, airflow diagrams, and room
pressure maps that accompany it. Copies should be readily accessible
and properly filed. Operating personnel should be familiar with the
data in these records and be able to explain it to an agency inspector.
GMP documents should also include test reports for HEPA filters
(efficiency or pinhole-scan integrity tests) at final operating velocities.
15
qualification protocols
If the filter installer performed the tests, the data should have been
part of the IQ package.
1. Prepare Operation Qualification Protocol
Includes checking all the operational parameters like Interlocks, Input
Utilities, Fan Performance, Actuations of control system for their
correctness.
Carry out these checks using protocol & prepare report with any
deviations, corrective actions taken & acceptance.
Completion of Report with supporting documents like printouts etc.
will complete “Operation Qualification.”
Performance Qualification
Performance qualification (PQ) is proof that the entire HVAC
performs as intended under actual production conditions. PQ is the
beginning of the ongoing verification that the system meets
acceptance criteria of the product (often called validation). This
includes documentation of
· Maintenance record keeping and final operating and maintenance
procedures in place, with recommended frequency of maintenance,
and (at the owner’s option) a procedure for periodic challenge of
the controls and alarms
· Logs of critical parameters that prove the system maintains
acceptance criteria over a prescribed time
· Training records of operators and maintenance personnel
· Final loop tuning parameters
After accepting PQ, the owner’s change control procedure should
limit further modifications to critical components (as shown on IQ
and OQ forms) that affect the product.
Once the system is operational, pharmaceutical product trial lots are
run in the facility (process validation) and the owner should regularly
monitor viable (microbial) and nonviable particles in the room.
1. Preparing for Performance Qualification:
Vendor to submit following SOPs, to be approved by Client/Consultant:
1. Measuring Velocity, Volume & calculating ACH,
2. DOP test if HEPA filter is used,
3. Particle count measurement,
4. T & RH measurement & recording,
5. Recovery, Fall Out (if applicable),
6. Any additional as per guideline & applicable for specific system.
* Client to have SOPs required for Viable checking, approved & effective.
16
qualification protocols
17
qualification protocols
Machinery
1. Component specifications. To be stated for all types and size(s) of
components to be handled.
2. Parametric range(s)
3. Filling or packaging rate.
4. Whether regular changes to different components sizes are
required (this is important if the change-over takes a long time
for a machine).
5. The location and environment in which the machine is to be
used, e.g., sterile area, clean room, etc.
6. The filling or packaging- line layout if the equipment is to
connect to other machinery. The infeed and outfeed positions on
equipment forming a long packaging line need to be considered.
This should include a layout drawing of the line.
7. Careful consideration by production staff is required to determine
what monitoring gauges and devices are required to help ensure
that product quality is maintained. These are classed as critical
devices. When the requirements have been defined, the accuracy
limits (or acceptable limits) must be determined for each device.
9. Consideration must be given to safeguards to prevent products or
components from becoming trapped in the equipment. It is better
to design out the areas for rogue entrapment rather than have
packaging machine operators search dozens of locations for
rouges at the end of each batch produced. with inevitable missed
rogue items due to human error .
10. Easy cleaning of equipment should be possible. The ability to
easily completely dismantle filling equipment to ensure effective
cleaning and sterilizing will help reduce the risk of
bacteriological continuation and minimize the batch/product
change- over time.
11. Easy access for maintenance and calibration is required
12. Lubrication
13. If the equipment available is computer controlled, define exactly
what type of computer system is required (try to standardize)
18
qualification protocols
Reaction vessels
Before design of the equipment following requirements shall be
considered:
o Reaction Volume
o MOC of the contact parts
o Maximum and Minimum Temperature
o Stirring Speed
o Need for vacuum distillation facilities
o Need for reflux facilities
o Need for slow charging of one of the reactant
o Need for protection of the content from moisture
o Need for maintaining inert gas environment in the vessel.
o Need for handling hazardous materials in the reactor
o Need for handling hazardous gaseous eflfluents from the reaction
vessel
o Need for scrapping the reaction product after the reaction is over
o Need for phase separation after the reaction is over
o Need for precise control of temperature and pressure during the
reaction
o Need for transfer of all inputs via vacuum and transfer all the
reaction products by vacuum
o Need for safeguarding against the accidental explosion .
o Need for observation for change in colour and state
o Need for continous monitoring of pH
19
qualification protocols
Analytical instruments
Steps in Design Qualification of Analytical Equipment
• Description of the analysis problem
• Selection of the analysis technique
• Description of the intended use of the equipment
• Description of the intended environment
• Preliminary selection of the functional and performance
specifications (technical, environmental, safety)
20
qualification protocols
21
qualification protocols
22
qualification protocols
23
qualification protocols
24
qualification protocols
25