Академический Документы
Профессиональный Документы
Культура Документы
1
CHAPTER
1
2
1. INTRODUCTION TO SCHEDULING
1.1 Introduction
Sequencing and Scheduling is a form of decision-making that plays a crucial role in
manufacturing and service industries. In the current competitive environment effective
sequencing and scheduling has become a necessity for survival in the market place.
Companies have to meet shipping dates that have been committed to customers, as failure to
do so may result in a significant loss of goodwill. They also have to schedule activities in
such a way as to use the resources available in an efficient manner. Scheduling deals with the
allocation of scarce resources to tasks over time. It is a decision making process with the goal
of optimizing one or more objective functions. The resources may be machines in a
workshop, runways at an airport, crew at a construction site and so on. The tasks may be
operations in a production process, take-offs and landings at an airport, stages in a
construction project. Scheduling is the allocation of start and finish time to each particular
task. Therefore scheduling can bring productivity in shop floor by providing a calendar for
processing a set of tasks. It is nothing but scheduling various tasks on a set of resources such
that certain performance measures are optimized.
1.2 Scheduling
Scheduling decisions allocate workloads to specific work centers and determine the
sequence in which the operations are to be performed within the available capacity. Detailed
day-to-day planning of operations is called scheduling. It deals with following questions.
Which work centre will do which job?
When should an operation be started and when should it end?
On which equipment should it be done and why?
What is the sequence in which jobs are to be handled on the equipment?
Day-to-day implies a short time horizon and the literal meaning. Continuous
production system, such as assembly lines may not have much need for day to day planning
because the operations are repetitive or continuous. The production levels the necessary
production facilities inputs and man power requirements have to be planned for a long stretch
of time, as long as the production runs. In project type of production analysis helps in
planning and controlling the component jobs.
3
1.3 Scheduling Environment
Scheduling involves decisions of how to allocate and utilize limited resources to
accomplish a set of tasks. The role of scheduling in manufacturing is depicted within the flow
of information and products as shown in figure 1.1. As illustrated in the figure, scheduling
activities interface with many aspects of an organization and have a direct influence on the
company's performance. Job requirements are generated as a result of sales activities as
orders flow into an organization. A standard lead time is often quoted when accepting an
order and is used when estimating delivery dates. These standard lead time quotations may
assume infinite capacity and may neglect the processing time associated with the job. In
practice, delivery dates are in fact affected by the processing times of the jobs, available
capacity, work already scheduled and the efficiency of the operation.
Operating efficiencies are directly impacted by the performance of the scheduling
method in reducing the amount of idle time and increasing the throughput of work per unit
time. Poor scheduling decisions can strain material requirements planning, shop floor control,
capacity utilization, and working capital resources. Ultimately poor performance of a
scheduling methodology can lead to decisions that adversely affect a company's sales and
profitability.
In a manufacturing environment, several operations may be required to transform
components and fabricate items into finished products. These transformations can occur as a
result of processing operations on one or more resources. To accomplish these
transformations, manufacturing job orders are often released to perform certain tasks on these
resources in a specified sequence. Depending upon the type of operating environment, the
sequence for each job may perhaps be determined by the scheduler.
Production function encompasses the activities of procurement, allocation and
utilization of resources. The main objective of production function is to produce the goods
and services demanded by the customers in the most efficient and economical way. Therefore
efficient management of the production function is of utmost importance in order to achieve
4
Fig 1.1 Production Scheduling Interfaces
5
4. Minimize the average tardiness of the jobs.
5. Minimize the maximum tardiness of the jobs.
6. Minimize work-in-process inventory.
7. Provide for high machine utilization and
8. Minimize production costs.
In these objectives, (1) - (5) are aimed primarily at providing a high level of customer
service and (6) - (8) are aimed mainly at providing high level of plant efficiency. The
objectives mentioned above are often conflicting. One can do a better job meeting due dates
if more capacity is provided and if the work center capacity is less utilized. Similarly, more
capacity will typically reduce flow time, but at reduced capacity utilization.
1.6. Functions of scheduling:
The different Functions of Schedulling regarding the type of Operations are :
1. In process industries, such as chemicals and pharmaceuticals, scheduling might consist of
determining the mix of ingredients that goes into a vat or when the system should stop
producing one type of mixture, clean out the vat, and start producing another. Linear
programming can find the lowest-cost mix of ingredients, and the economic order quantity
with no instantaneous replenishment can determine the optimum length of a production run.
2. For mass production, the schedule of production is pretty much determined when the
assembly line is laid out. Products simply flow down the assembly line from one station to
the next in the same prescribed, nondeviating order every time. Day-to-day scheduling
decisions consist of determining how fast to feed items into the line and how many hours per
day to run the line. On a mixed-model assembly line, the order of products assembled also
has to be determined.
3. For projects, the scheduling decisions are so numerous and interrelated that specialized
project-scheduling techniques such as PERT and CPM have been devised.
4. For batch or job shop production, scheduling decisions can be quite complex.
Scheduling determines to which machine a part will be routed for processing, which worker
will operate a machine that produces a part, and the order in which the parts are to be
processed. Scheduling also determines which patient to assign to an operating room, which
doctors and nurses are to care for a patient during certain hours of the day, the order in which
a doctor is to see patients, and when meals should be delivered or medications dispensed.
6
1.7. Priority rules for scheduling
The quantities Flow Time, Lateness and Tardiness are important measures for
evaluating schedules. Often, these measures are aggregated over all the jobs in the system,
and different schedules are compared using a single performance measure, such as Average
Flow Time, Mean Tardiness, Maximum Flow Time, Maximum Tardiness or number of Tardy
Jobs. The other measure of performance of a schedule is the "MAKESPAN" which is equal
to the length of the time required to complete all jobs.
7
solution is to change automatically the weight factor of these jobs, which had to wait
longer than a specified time limit.
3. Weighted shortest processing time (WSPT) rule
The weighted shortest processing time rule is a variation of the SPT rule and is
used when the completion order of the different jobs carry different importance or
weight.
4. Last come first serve (LCFS) rule
The job that arrived at the work station last has the highest priority under a last
come , first served(LCFS) rule.
8
7. Most work remaining(MWKR)
Select the operation associated with the job having the most work remaining
to be processed.
8. Least work remaining(LWKR)
Select the operation associated with the job having the least work remaining to be
processed.
9
CHAPTER
2
10
2. TYPES OF SCHEDULING
Typical manufacturing systems produce a variety of products, each requiring a
specified set of operations on specific machines in a predetermined order. Several different
types of manufacturing environments exist in which work requires scheduling. Generally
these environments are classified as flow shops and job shops.
The flow shop environment is a product layout i.e., resources are arranged according
to the sequence of the operations. The flow shop advantages are high speed, low material
handling, short flow time and low unit processing costs. The simple example for this flow
shop is assembly line, beverage plant etc.
The job shop environment is nothing but a functional layout or process layout i.e.,
similar resources are present in the same department. It is best suited for production of low
volume and high variety customized products. The main purpose of this environment is
availability of flexible resources.
The above graph between the variety on x-axis and volume on y-axis indicates the
following two cases:
1. When the volume is high and the no of varieties produced are low, then the flow shop
environment is suitable.
2. When the volume of products to be produced is low and the numbers of varieties of
products are more, then job shop is to be opted.
11
2.1 Flow shop scheduling:
A flow shop is an environment in which there are a defined number of machines that
operate in series. The flow shop is characterized by a flow of work that is unidirectional. A
flow shop contains a natural machine order and it is possible to number the machines so that
if the jth operation of any job precedes kth operation , then the machine required for jth
operation has lower number than the machine required by the kth operation. The machines in
the flow shop are numbered 1,2...........,m; and the operations of job I are correspondingly
numbered (i, 1 ),(i,2),......(i,m).
The two-machine flow shop problem with the objective of minimizing make span
is also known as Johnson's problem. The results originally obtained by Johnson are now
standard fundamentals in the theory of scheduling. In the formulation of this problem, job j is
characterized by processing time tji required on machine 1, and tj2 required on machine 2
after the operation on machine 1 is complete. The following scheduling rules to minimize the
make span were developed by Johnson:
Step 1 : Find min (tji, te)
Step 2a : If the minimum processing time requires machine 1, place the associated
job in the first available position in the sequence. Go to step 3.
Step 2b : If the minimum processing time requires machine 2, place the associated
job in the last available position in the sequence. Go to step 3.
Step 3 : Remove the assigned job from consideration and return to step 1 until all
positions in sequence are filled.
These rules can also be applied to larger flow shop scheduling problems.
12
A job shop scheduling problem consists of a finite set J of n jobs {Jj}i=i to n to be
processed on a finite set M of m machines {Mk}k = i to n -Each job Jj must be processed on
every machine and consists of a chain of operations On, Oj2....., Ojm which have to be
scheduled in a predetermined given order (precedence constraint). There are N operations in
total, Ojk is the operation of job Jj which has to be processed on machine Mk for an
uninterrupted processing time period tjk and no operation may be preempted. Each job has its
own individual flow pattern through the machines, which is independent of the other jobs.
Each machine can process only one job and each job can be processed by only one machine
at a time (capacity constraints). The duration in which all operations for all jobs are
completed is referred to as Make span and the amount of time each job spends in a system is
known as Flow time. Many jobs in industry and elsewhere require completing a collection of
tasks while satisfying temporal and resource constraints. Temporal constraints say that some
tasks have to be finished before others can be started; resource constraints say that two tasks
requiring the same resource cannot be done simultaneously (e.g., the same machine cannot do
two tasks at a time). The objective is to create a schedule specifying when each task is being
processed and what resource it will use which satisfy all the constraints while talking as little
overall time as possible. This is Job-Shop-Schedule problem.
13
fixed duration (processing time) and tj the start time of operation i. The problem can then be
started as
Min tn
tj – ti > di, (i,j)€A
tj>0 i€N
tj – ti > di, v ti-tj>di ( i , j € Ek , k € M )
A job shop scheduling problem can be represented with the help of a disjunctive
graph as shown in the following figure.
14
Conjunctive arcs connecting nodes 0,1,2,3 and 11 represent the route for a job. The
disjunctive arcs (Dashed lines) going in opposite directions connect two operations which
belong to two different jobs and are processed on the same machine. A feasible schedule for a
job shop problem is to select a disjunctive arc between every two operations and the selected
arcs will not result in a cycle on every machine. The length of the critical path on the graph is
the Make span of the feasible schedule. Therefore, to solve a job shop problem with Make
span as the objective is to find a feasible directed graph with the minimal longest path.
15
CHAPTER
3
16
3. LITERATURE REVIEW
Like many operation research (OR) application areas the study of the scheduling
theory began in the early 1950's. Johnson's article is acknowledged as a pioneering work.
Later, several kinds of general optimization procedures were applied to scheduling problems.
These included mixed and pure integer programming formulations, dynamic programming
and branch and bound methods. Meanwhile, heuristic methods were being developed for
problems which were known to be computationally difficult. By the late 1960's, a solid body
of scheduling theory had emerged. In 1970's theoretical work on problem complexity began.
It was found that most problems are NP-hard. The last decade has seen the tendency to
emphasize the practical nature of scheduling problem and to try to bridge the gap between
theory and practice.
Blackstone et al. defined Scheduling rules as: 'rules used to select the next job to
process from jobs waiting for service'. Scheduling rules can be very simple or extremely
complex. Examples of simple rules are: 'select a job at random, or select the job that has been
waiting longest. A more complex rule might be one that selects the job with the 'closest due
date whose customer's inventory is less than a specified amount.
Pierreval, H., and Mebarki, N., Blackstone et al., Baker, Ramasesh have dealt with
many scheduling rules. A universally well accepted result of these studies is that no
scheduling rule performs globally better than any others. The scheduling rule's performance
depends on the configuration of the studied system, the operating conditions and the
performance criterion used to evaluate the scheduling rules. As a consequence, decision
makers often have difficulty in selecting the scheduling rules that are the most suited to their
problems. This has led several researchers to propose various methods for selecting the
scheduling rules best suited to given cases.
Haupt, R classified Scheduling or Dispatching rules as:
17
Due-date based rules schedule the jobs based on their due-date information. An
example of a due-date based rule is the earliest due-date (EDD) rule.
Blackstone, J.H. et al proposed Combination rules which make use of both process-
time and due-date information, e.g. Least Slack rule, Critical Ratio, etc.
Haupt, R proposed the rules which do not fall into any of the above categories and
loads the jobs depending on shop floor conditions rather than on the characteristics of jobs.
An example of this type of rule is the WINQ rule (total work-content of jobs in the queue for
the next operation on a job).
Conway et al. gave a general notation scheme for scheduling problems based on four
descriptors A/B/C/D which has since been followed by a number of researchers.
Representation of scheduling problems is as follows
A- Number of jobs (any positive integer, usually 'n')
B- Number of machines (any positive integer, frequently 'm')
C- Flow pattern and further technological and management constraints.
Possible values are:
||: single machine
J: job shop
'F': flow shop
'O': open shop
F-perm: permutation flow shop
k-parallel: k-machines in parallel
J, k-parallel: job shop with k parallel machines at each stage
D- Criteria to be optimized.
A range of methods have been developed to solve the scheduling problems which are
classified as follows.
Scheduling rules and simulation
Mathematical programming formulation and solution
(Branch and bound techniques, Dynamic programming)
18
Heuristic search methods
(Tabu search, Simulated annealing, Genetic algorithms)
While the use of heuristic algorithms is mostly resorted to in the case of static
scheduling problems, scheduling rules are made use of in the case of dynamic scheduling
problems. Scheduling rules are more popular in many real life manufacturing systems than
heuristics, mainly because scheduling rules are simple to implement and use in any shop
floor, and most real-life systems have dynamic arrivals. These rules some times called
dispatching rules or priority rules have led to a substantial amount of research in the last few
decades, especially to solve the dynamic scheduling problem of job shop systems.
Algorithms other than GAs have also been researched. Dauzere-Peres and
Paulli(1997) deal with the multi-processor job shop where every operation has more than one
machine on which it can be performed. They use the objective of minimizing makespan and
consider an integrated approach for assigning machines and scheduling the parts on those
machines using a tabu search algorithm with a new neighborhood structure.
Candido et al. (1998) considered alternative routes by dividing the routes into sub-
processes, where every sub-process is a technologically similar sequence of operations. An
alternative route must be able to perform all sub-processes. They also considered route
changes due to alternate machines that the job can go through. They created an initial for
schedule using dispatch rules such that no operation can start earlier without preempting
another operation. This technique relies on the assumption that some parts are sub-assemblies
for others and must be completed first. A simple hill climbing algorithm is then implemented
to find the local minimum makespan. Lastly, a GA is used to further minimize the makespan.
Alternative routing is only one of seven "constraints" that are used.
Kirn and Egbelu (1999) developed two local search heuristics to find alternative
routings in order to minimize makespan. The heuristics are greedy in nature and terminate at
local optima. The largest problems solved with these procedures are 10 jobs and 10 machines,
with 2-5 routings per job. It is noted that with an increase in the number of jobs or the number
of routings, the heuristic performs worse.
Chryssolouris and Subramaniam (2000) presented a scheduling method based on
extreme value theory (SEVAT) to solve the dynamic job shop problem. SEVAT, which is
traditionally used to predict rare events, in this case creates a "statistical profile of schedules
19
through random selection, and predicts the quality...of a feasible schedule. The objective is to
minimize mean job tardiness and mean job cost.
Thomalla (2001) solved the job shop scheduling problem with alternative routes using
Lagrangian relaxation. The largest problem solved is 6 jobs, 6 machines, and 10 operations
per job with the objective being to minimize the sum of the weighted quadratic tardiness of
the jobs.
Chryssolouris and Subramaniam (2001) presented a GA for scheduling a dynamic job
shop using mean job tardiness and mean job cost as performance measures. The problem they
consider has both random machine breakdowns and alternative job routings. They considered
up to 6 machines and up to 6 different resources to process an operation.
Saygin et al. (2001) presented an algorithm, the Dissimilarity Maximization Method
(DMM), to solve a real-time rescheduling problem that arises due to machine breakdowns
and other unexpected occurrences on the shop floor. The goal of the research is to maximize
the through put rate. They assume that processing times on alternate machines are the same as
on the originally scheduled machine. Alternate routes consists of changing one or two
machines on a route to a parallel alternative. DMM picks which routings to use in order to
maximize the dissimilarity between machines used in the set of routings. The algorithm is
solved on small problems; 6 parts, 7 machines and up to 8 alternate routings per part.
There has been much research involving job shop scheduling with alternative routes.
In the last few years, several papers deal with the use of genetic algorithms (GAs). Kim etal.
(2002) deal with alternative routings in the process planning stage using a co-evolutionary
algorithm in order to minimize makespan and minimize mean flow time over all the jobs.
They integrate process planning and scheduling such that a change in the process planning
stage also changes the scheduling stage. They evaluate alternative routes using all three
possibilities (operations, sequencing, and processing) as well as a network consisting of all
three together. They also assume that there are a large number of process plans for each job.
Their algorithm is tested on problems with 6-18 jobs and 8-22 operations per job.
Choi and Choi (2002) considered alternative routes and sequence dependent setups
together. They developed a mathematical programming model and a local search algorithm
using dispatching rules with an objective of minimizing makespan. Weintraub et al. (1999)
contains an extensive review of the literature up to 1997. Most of these papers, however,
20
consider the problem from a process planning viewpoint rather than that of detailed
scheduling.
21
CHAPTER
4
22
4. SCHEDULING ALGORITHM
In the present chapter, heuristics based on Maximum Work Remaining with Early
start time & Maximum Work Remaining without Early Start Time Scheduling Heuristics are
proposed. A case problem consisting of 3 jobs, 4 machines is solved using both the heuristics.
If the number of jobs as well as machines is greater than two and technological order
of the machines for all jobs are not same, scheduling problems in job shop becomes complex.
There is no readymade and well-defined methodology to solve the problems. Under such
circumstances Heuristic Approach plays an important role.
Heuristic mean serving to find out" i.e., to find out things oneself. It describes a
particular way to decision making. It utilizes commonsense, logic and above all past
experience to tackle the new problems. It provides most likely solutions, which are good
enough from practical point of view.
Problem
A job shop company got an order of three different jobs in considerable quantity.
Each job requires different machining operations on given four machines. For all jobs, the
technological orders (sequences) of machines are not same. The details are shown below:
A 4 3 2 1 ( 3,4,8,7)
B 3 4 1 2 (6,5,3,8)
C 3 4 2 1 (3,3,7,4)
23
4.1. Methodology for maximum work remaining heuristic without
earliest start time
1. Prepare a list of first unscheduled operations of each job. These are operations to be
scheduled. These are listed in column 1 of table-1, (A,1)(B,1)(C,1) indicates first
operations to be performed on each job A,B,C.
2. Calculate the remaining total process time for each job. For (A,l) (B, 1) (C, 1) the
remaining total process time can be calculated as (A, 1)= 3+4+8+7=22 hrs (B, 1)=
6+5+3+8=22 hrs (C, 1)= 3+3+7+4=17 hrs
3. These are listed in column-2. Here job-(A, B) has maximum process time remaining.
Any job can be taken up here multiple sequences occur.
4. Here first operation should be performed on job A on machine M2 and it is shown in
column-3.
5. Starting time of this operation will be zero and since it requires 3 hrs therefore
finishing time will be 3. These are shown in column 5 and 6.
6. The next list of operations is (A, 2) (B, 1) (C, 1) {since (A, 1) is already scheduled}.
Again the same procedure is repeated till all the jobs are scheduled.
7. Next job should be scheduled in such a way that the sequenced machine should be
idle and previous operation should be completed.
8. Repeat the steps above mentioned until all the jobs are scheduled
24
LIST OF PROCESS
(JOB, SCHEDULED
OPERATIONS TIME START FINISHING
OPERATION) ON
(JOB, REMAINING TIME TIME
SCHEDULED MACHINE
OPERATION) (HOURS)
25
LIST OF PROCESS
(JOB, SCHEDULED
OPERATIONS TIME START FINISHING
OPERATION) ON
(JOB, REMAINING TIME TIME
SCHEDULED MACHINE
OPERATION) (HOURS)
26
LIST OF PROCESS (JOB, SCHEDULED
OPERATIONS TIME OPERATION ON START FINISHING
(JOB, REMAINING ) MACHINE TIME TIME
OPERATION) (HOURS SCHEDULED
OUTPUT
B A C
TIME IN
1 0 0 10
6 6 13
TIME OUT
A C B
TIME IN
2 6 13 10
10 16 16
TIME OUT
B A C
TIME IN
3 12 16 18
18 22 25
TIME OUT
27
A B C
TIME IN
4 22 18 29
29 26 33
TIME OUT
28
7. If there is more than one operation with smallest early start time, then compute work
remaining for each job and select the job with maximum work remaining for
scheduling.
8. Compute the makespan and the average flow time.
LIST OF (JOB,
EARLIEST SCHEDULED
OPERATIONS OPERATION START FINISHING
START TIME ON
(JOB, ) TIME TIME
(HOURS) MACHINE
OPERATION) SCHEDULED
29
LIST OF
(JOB, SCHEDULED
OPERATIONS EARLY START START FINISHING
OPERATION) ON
(JOB, TIME (HOURS) TIME TIME
SCHEDULED MACHINE
OPERATION)
30
LIST OF
OPERATIONS EARLY (JOB, SCHEDULED FINISHING
(JOB, START TIME OPERATION) ON START TIME TIME
OPERATION) (HOURS) SCHEDULED MACHINE
(C,4) 25 (C,4) 1 25 29
Output
B A C
TIME IN
1 11 18 25
14 25 29
TIME OUT
A C B
2 TIME IN 10 18 25
18 25 29
TIME OUT
B A C
TIME IN
3 0 6 10
6 10 13
TIME OUT
4 A B C
31
TIME IN 0 6 13
TIME OUT 3 11 16
32
4.3 Critical single machine scheduling heuristic :
Problem
JOB NUMBER MACHINE SEQUENCE PROCESSING TIMES
A 4 3 2 1 3 4 8 7
B 3 4 1 2 6 5 3 8
C 3 4 2 1 3 3 7 4
∑ P1j = 3 + 4 + 8 + 7 = 22
∑ P2j = 6 + 5 + 3 + 8 = 22
∑ P1j = 3 + 3 + 7 + 4 = 17
Release times are determined by computing the earliest time the job could start (i.e.
the sum of the processing times of all proceeding jobs). Computing due dates and release
time from the date in the table provides the results listed below.
Machine 1 :-
Job A B C
Process Time 7 3 4
Earliest start Time 15 11 13
Due Date (Time) 22 14 22
Using this date L max is determined for machine 1 through enumeration of a single
machine scheduling problem. As discussed previously there are (nl)possible schedules for a
33
Job Shop problem. For the one machine case, it reduces to nl. Thus there are six possible
schedules for this machine.
Min L max = 25 – 22 = 3
The process considers the next machine (Machine 2) as a potential Critical using the
same computational processes as those used fro machine 1.
Machine 2 :-
Job A B C
Process Time 8 8 7
Earliest start Time 1 14 6
Due Date (Time) 15 22 18
34
Again there are six possible schedules, which are enumerated to determine completion
times.
Machine 3 :-
Job A B C
Process Time 4 6 3
Earliest start Time 3 0 0
Due Date (Time) 15 16 8
Again there are six possible schedules, which are enumerated to determine completion
times.
35
Job In time Out time Job In time Out time
A 3 7 A 3 7
B 7 13 C 7 10
C 13 16 B 10 16
Completion time for this schedule is 13 and the minimum L max is ZERO
The first iteration to compute L max in identifying the first critical Machine is
concluded by considering machine 4.
36
Machine 4 :-
Job A B C
Process Time 3 5 3
Earliest start Time 0 6 3
Due Date (Time) 3 11 11
Again there are six possible schedules, which are enumerated to determine completion
times.
37
Critical machine :-
The cachine with the maximum of he minimum L max ‘s for each machine is
identified as the critical machine
Max (min L max) = max {3,7,0,0} = 7
Machine 2 is Critical and the first machine to be scheduled as a result of the firs
iteration.
Based on machine 2 with sequence job C, Job B, Job A, the other critical machines
are to be determined.
Machine 1 :-
Job A B C
Process Time 7 3 4
Earliest start Time 21 11 13
Due Date (Time) 29 21 29
Again there are six possible schedules, which are enumerated to determine completion
times.
Job In time Out time Job In time Out time
A 21 28 A 21 28
B 28 31 C 28 32
C 31 35 B 32 35
38
Sequence Completion Time
Job A, Job B, Job C 35
Job A, Job C, Job B 35
Job B, Job A, Job C 32
Job B, Job C, Job A 28
Job C, Job A, Job B 31
Job C, Job B, Job A 28
Optimal schedule to minimize L max for machine 1 is Job C, Job B, Job A and
Job B, Job C, Job A
Proceeding on to the next machine and performing the same computations result in
the following data
Machine 3 :-
Job A B C
Process Time 4 6 3
Earliest start Time 3 0 0
Due Date (Time) 14 13 15
Again there are six possible schedules, which are enumerated to determine completion
times.
39
B 7 13 A 9 13
Completion time for this schedule is 13 and the minimum L max is ZERO
Machine 4 :-
Job A B C
Process Time 3 5 3
Earliest start Time 0 3 3
Due Date (Time) 10 18 18
Again there are six possible schedules, which are enumerated to determine completion
times.
Job In time Out time Job In time Out time
A 0 3 A 0 3
B 3 8 C 3 6
C 8 11 B 6 11
40
C 3 6 C 3 6
A 6 9 B 6 11
B 9 14 A 11 14
Optimal schedule to minimize L max for machine 4 are Job A, Job B, Job C and
Job A, Job C, Job B
Completion time for this schedule is 11 and the minimum L max is ZERO
The machine with the maximum of the minimum L max ‘s for each machine is
identified as the Critical :
Max (min L max) = Max {6,0,0} = 6
Based on machine 2 with sequence Job C, Job B, Job A, and machine 1 with Job C,
Job B, Job A sequence the other critical machines are to be determined.
Est & due date computations based on sequence c-b-a on machine 2 &
on sequence c-b-a on machine 1 :-
Machine 4 :-
Job A B C
Process Time 4 6 3
Earliest start Time 3 0 0
Due Date (Time) 13 12 14
Again there are six possible schedules, which are enumerated to determine completion
times.
Job In time Out time Job In time Out time
A 3 7 A 3 7
41
B 7 13 C 7 10
C 13 16 B 10 16
Optimal schedule to minimize L max for machine 3 are Job C, Job B, Job A
Job B, Job C, Job A
Job C, Job A, Job B and
Job B, Job A, Job C
Completion time for this schedule is 11 and the minimum L max is ZERO
Machine 4 :-
Job A B C
Process Time 3 5 3
Earliest start Time 0 3 3
Due Date (Time) 9 17 17
42
Again there are six possible schedules, which are enumerated to determine completion
times.
Optimal schedule to minimize L max for machine 3 are Job A, Job B, Job C and
Job A, Job C, Job B
Completion time for this schedule is 11 and the minimum L max is ZERO
The machine with the maximum of the minimum L max ‘s for each machine is
identified as the Critical :
Max (min L max) = Max {0,0} = 0
Based on machine 2 with sequence Job C, Job B, Job A, and machine 1 with Job C,
Job B, Job A and machine 3 with Job C, Job A, Job B sequence the other critical machines
are to be determined.
43
Est & due date computations based on sequence c-b-a on machine 2 &
on sequence c-b-a on machine 1 & on sequence c-a-b on machine 3 :-
Machine 4 :-
Job A B C
Process Time 3 5 3
Earliest start Time 0 13 3
Due Date (Time) 9 17 17
Again there are six possible schedules, which are enumerated to determine completion
times.
Job In time Out time Job In time Out time
A 0 3 A 0 3
B 13 18 C 3 6
C 18 21 B 13 18
Optimal schedule to minimize L max for machine 3 are Job A, Job C, Job B
Job C, Job A, Job B
44
Completion time for this schedule is 18 and the minimum L max is ZERO
45
CHAPTER
5
46
5.LEKIN SOFTWARE
Lekin is a scheduling system developed at the Stern School of Business, NYU. Major
parts of the system were designed and coded by Colombia university students. Lekin was
created as an educational tool with the main purpose of introducing the students to scheduling
theory and its applications .Lekin has an interactive scheduling system for machine
environments. Besides that, the system extensibility allows to use it in algorithm
development.
5.1 Lekin features
• Six basic workspace environments are single machines, parallel machines, flow
shop, flexible flow shop, and flexible job shop.
• A set of sample problems.
• Smooth input of user problems.
• Various dispatching rules and heuristics.
• Gantt chart with drag-and-drop support.
• Graphic tool for comparative analysis of different schedules.
• Complete graphic printouts.
• Easy attachments , import and export of external algorithm.
This soft ware helps to find solution to job shop scheduling problem .Its makes use of
dispatching rules like earliest due date, longest processing time, shortest processing time
etc,.
47
In the present thesis, 3 jobs 4 machine scheduling problem in solved with the help of
Lekin Software. The problem is solved using 3 dispatching rules namely earliest due date,
longest processing time, shortest processing time etc,.
The solution obtained using dispatching rule is compared with the three proposed
heuristics namely most work remaining (MWKR) heuristic without earliest start time (EST),
most work remaining (MWKR) heuristic with earliest start time (EST) and critical single
machine scheduling.
48
RESULTS AND CONCLUSIONS
Summary of results
Comparision of most work remaining (MWKR) heuristic without earliest start time
(EST),most work remaining (MWKR) heuristic with earliest start time (EST) and critical
single machine scheduling with the dispatching rules.
EDD 29
SPT 33
LPT 29
49
REFERENCES
50