Вы находитесь на странице: 1из 3

Sharing Control & Safety Instruments

Are your layers overlapping?

Dirk Schreier
Functional Safety Consultant
HIMA Australia Pty Ltd
L3, 37 St Georges Terrace
Perth WA 6000
Australia

INTRODUCTION

Since its release as an Australian standard in July of 2004, AS61511 is rapidly being
accepted and applied on Safety Instrumented Systems throughout the process industry.
Principles such as independence between control and protective instruments have existed
for many years, however they continue to often be overlooked even with the introduction of
this standard.

Older prescriptive standards particularly in burner / boiler applications recognize the need for
independence between control & safety. With older technology it was more difficult to share
signals. Separate switches were often used to provide the shutdown function and alarming
function.

Today’s improved technology has made it easier to share signals. Signal isolators and
splitting devices are often used to share transmitter signals between control and safety
instrumented systems (SIS). Splitters are also available with certain SIL ratings thereby
giving the impression that signals can be safely shared.

AS61511 requires an assessment to be made that considers the independence of protection


layers. This is particularly important when a failure in the control function can cause a
demand on the safety function. This is the critical aspect often overlooked; a further
examination of the problem will clarify the issue.

WHAT’S THE PROBLEM?

The problem is generally not so much the splitting device itself, as we are able to obtain
failure data for these devices and include them in our calculations. The problem is generally
the lack of understanding the methods used and the assumptions made during the Layer Of
Protection Analysis (LOPA) and SIL Assignment.

Simplistically, two aspects are considered during this analysis; (1) Consequence and (2)
Likelihood. A Consequence analysis will estimate the damage that will be done should the
hazardous event occur. Likelihood analysis will estimate how likely it is that this event might
take place given the current controls that are in place. The product of these two aspects is
effectively the risk.

Sharing Control & Safety Instruments – Page 1 of 3 March 2005


Are your layers overlapping?
The next step is to compare the risk with the tolerable risk. If the risk is higher than the
tolerable risk, further risk reduction is required. The magnitude of this difference is
represented by a Safety Integrity Level (SIL).

TRANSMITTERS

Consider the following scenario. A pressure transmitter provides a BPCS (basic process
control system) with a process variable, which is used for control purposes. The BPCS along
with the transmitter keeps the process under control.

A SIL selection team considers this control loop during a layer of protection analysis, and
gives credit for reducing the likelihood of the hazardous occurrence. The SIL selected for this
loop demonstrates a requirement for further risk reduction, and a Safety Instrumented
System is suggested to achieve this. A signal splitter is introduced to provide the ESD
system with a repeat of this variable, in order for it to detect and act upon pressure
excursions beyond the process limits.

The layer of protection analysis is repeated, now considering also the SIS protection, the
required risk reduction appears to have been met however credit for the pressure transmitter
has been taken twice, once in the BPCS, and once in the SIS protection layer. A failure of the
transmitter circumvents the control provided by the BPCS and the protection layer provided
by the SIS; a serious common mode failure!

This problem is not isolated to the use of splitters, but also when re-transmitting a signal from
a SIS analogue output for use in the control system. Separate pressure transmitters must be
provided to ensure independent layers of protection.

VALVES

The independence criterion is also just as important when considering final elements such as
valves. Consider the scenario where a protective function removes the air supply from a
control valve. Once again the SIL Selection team considers the control loop when estimating
the likelihood and is thereby taking credit for the valve.

A stuck open control valve causing a hazard will produce a demand on the safety function.
However, in this scenario the safety function will fail to protect against the hazard as it only
has the same ‘stuck’ valve available to remove the hazard.
Once again credit has been taken for the valve twice. Once as reducing the likelihood by
controlling the process and thereby the demand on the safety function and secondly as
reducing the likelihood as part of the SIS protection layer.

Separate control and shutdown valves must be provided to ensure independent layers of
protection.

Sharing Control & Safety Instruments – Page 2 of 3 March 2005


Are your layers overlapping?
OPERATORS

Another common mistake made with regards to independent layer of protection deals with
taking credit for operator intervention. Operator intervention is often considered during a
LOPA. The operator acts on an alarm generated by the process control system and performs
some action to get the process back into control. The problem here is that the signal, from
which the alarm is generated, could be the same signal that is used for controlling the
process.

Credit is taken for the transmitter twice. Once for reducing the likelihood by controlling the
process and thereby the demand on the safety function, and once as a layer of protection
provided by the operator alarm. A dangerous failure of the transmitter circumvents the control
provided by the BPCS and the layer of protection provided by the operator intervention.

If the transmitter is stuck at a healthy value then control is lost, and an alarm would never be
raised.

CONCLUSIONS

It is therefore very important to understand the assumptions made during the LOPA before
introducing these devices. Double dipping is a common mistake made when applying these
methods and may contribute heavily to common cause failures.

Following AS61511 will ensure your layers don’t overlap because it includes a balance of
processes and competence, however companies regularly overlook the competence element
hence jeopardizing the possibility of compliance to the standard. Following just the processes
laid down in the standard is not enough to comply, nor is a strategically placed CFSE at
defined intervals.

The biggest issue that leads to instances such as the “double dipping” scenario is a lack of
competence in the project. This is not to be confused with age or general experience of the
instrument or control engineer in charge. More importantly it is the specific safety systems
experience and knowledge the engineer has with the application, the consequences, legal &
regulatory framework and acumen for considering the pessimistic view of “what could
possibly go wrong”

This is why 44% of errors occur in the specification stage of a project and is a major factor
why independence is overlooked by double dipping.

Sharing Control & Safety Instruments – Page 3 of 3 March 2005


Are your layers overlapping?

Вам также может понравиться