Activity Activity Plan Plan Plan 2008

MAR APR MAY JUN JUL AUG


ID Description Dur Start Finish 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11
2 X 80 MW CPP - DARIBA SMELTER COMPLEX
MAJOR MILESTONES
Subtotal 761 18MAR08 17APR10

MIL001 ZERO DATE - PROJECT START 0 18MAR08 ZERO DATE - PROJECT START

MIL002 RELEASE OF LOI TO BHEL 0 18MAR08 RELEASE OF LOI TO BHEL

MIL003 KICK-OFF MEETING 0 02MAY08* KICK-OFF MEETING

MIL004 RELEASE OF LOI TO TPL 0 03JUL08* RELEASE OF LOI TO TPL

MIL006 CIVIL WORK START 0 02SEP08


MIL007 UNIT #1 - BOILER STRUCTURE ERECTION START 0 15JAN09
U2MIL007 UNIT #2 - BOILER STRUCTURE ERECTION START 0 15APR09
MIL008 UNIT #1 - BOILER DRUM LIFTING 0 30APR09
MIL010 UNIT #1 - CONDENSOR ERECTION START 0 30MAY09
MIL023 RAW WATER SYSTEM - COMMISSIONING 0 06JUL09
MIL029 DCS - FAT COMPLETION 0 20JUL09
U2MIL008 UNIT #2 - BOILER DRUM LIFTING 0 30JUL09
MIL018 UNIT #1 - STATION TRANSFORMER - CHARGING 0 16AUG09
U2MIL018 UNIT #2 - STATION TRANSFORMER - CHARGING 0 16AUG09
MIL009 UNIT #1 - TURBINE ERECTION START 0 19AUG09
MIL019 HT SWGR(STATION & UNIT) - COMMISSIONING COMPLN. 0 26AUG09
U2MIL010 UNIT #2 - CONDENSOR ERECTION START 0 30AUG09
MIL011 UNIT #1 - BOILER HYDRO-TEST COMPLETION 0 31AUG09
MIL020 LT SWGR(STATION & UNIT) - COMMISSIONING COMPLN. 0 15SEP09
MIL012 UNIT #1 - TURBINE BOX-UP 0 30SEP09
MIL028 CHIMNEY COMPLETION - BLU 0 13OCT09
MIL022 COMPRESSOR SYSTEM - COMMNG. & AIR AVAIL. TO EQPT 0 16OCT09
MIL032 UNIT #1 - TG OIL FLUSHING COMPLETION 0 24OCT09
MIL030 UNIT #1 - FUEL OIL SYSTEM - COMMISSIONING 0 25OCT09
MIL013 UNIT #1 - TURBINE ON BARRING GEAR 0 31OCT09
MIL014 UNIT #1 - BOILER LIGHT-UP 0 31OCT09
MIL027 ROADS & DRAINS - COMPLETION 0 15NOV09
U2MIL009 UNIT #2 - TURBINE ERECTION START 0 19NOV09
U2MIL011 UNIT #2 - BOILER HYDRO-TEST COMPLETION 0 30NOV09
MIL025 COAL HANDLING PLANT - COMMISSIONING 0 10DEC09
MIL031 FF , DETECTION & ALARM SYSTEMS - COMMG. COMPLN. 0 10DEC09
U2MIL012 UNIT #2 - TURBINE BOX-UP 0 30DEC09
MIL015 UNIT #1 - ROLLING & SYNCHRONIZATION 0 31DEC09

Start Date 01MAR08 DAR7 Sheet 1 of 55


Early Bar
Finish Date 17APR10 Date Revision Checked Approved
Float Bar
Data Date 18MAR08
Run Date 10SEP08 23:57 Progress Bar
2 X 80 MW CPP - DARIBA SMELTER COMPL
Critical Activity

Classic Schedule Layout


© Primavera Systems, Inc.
PDF created with pdfFactory Pro trial version www.pdffactory.com
Activity Activity Plan Plan Plan 2008
MAR APR MAY JUN JUL AUG
ID Description Dur Start Finish 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11
MIL033 UNIT #1 - BOILER COAL FIRING 0 06JAN10
U2MIL032 UNIT #2 - TG OIL FLUSHING COMPLETION 0 23JAN10
U2MIL030 UNIT #2 - FUEL OIL SYSTEM - COMMISSIONING 0 24JAN10
U2MIL013 UNIT #2 - TURBINE ON BARRING GEAR 0 30JAN10
U2MIL014 UNIT #2 - BOILER LIGHT-UP 0 31JAN10
MIL026 ASH HANDLING PLANT - COMMISSIONING 0 22FEB10
U2MIL015 UNIT #2 - ROLLING & SYNCHRONIZATION 0 31MAR10
U2MIL033 UNIT #2 - BOILER COAL FIRING 0 06APR10
MIL016 COMMISSIONING COMPLETION & PLANT HAND-OVER 0 17APR10

BASIC ENGINEERING
Subtotal 138 02MAY08 16SEP08

EN260 PREP & APPRL OF DBR - CIVIL 20 02MAY08 21MAY08 PREP & APPRL OF DBR - CIVIL
EN250 PREP & APPRL OF DBR - CHIMNEY 25 27MAY08 20JUN08 PREP & APPRL OF DBR - CHIMNEY
EN230 PREP & APPRL OF DBR - FUEL OIL SYSTEM 25 16JUN08 10JUL08 PREP & APPRL OF DBR - FUEL OIL SYSTEM
EN100 PLOT PLAN RELEASE FOR CONSTR. 50 04JUL08 22AUG08 PLOT PLAN RELEASE FOR CONSTR.
EN110 LOAD LIST FINALISATION 25 04JUL08 28JUL08 LOAD LIST FINALISATION
EN140 PREP & APPRL OF DBR - ELECTRICAL SYS 45 09JUL08 22AUG08 PREP & APPRL OF DBR - ELECTRICAL SYS
EN130 PREP & APPRL OF DBR - WATER SYSTEM 35 14JUL08 17AUG08 PREP & APPRL OF DBR - WATER SYSTEM
EN150 PREP & APPRL OF DBR - COMPRESSED AIR SYS 25 14JUL08 07AUG08 PREP & APPRL OF DBR - COMPRESSED AIR SYS
EN200 PREP & APPRL OF DBR - FIRE PROT. & DETECT SYS 45 14JUL08 27AUG08 PREP & APPRL OF DBR - FIRE PROT. & DETECT SYS
EN190 PREP & APPRL OF DBR - COAL HANDLING SYS 30 19JUL08 17AUG08 PREP & APPRL OF DBR - COAL HANDLING SYS
EN240 PREP & APPRL OF DBR - C&I 45 03AUG08 16SEP08 PREP & APPRL OF DBR - C&I
EN210 PREP & APPRL OF DBR - AC & VENTILATION 25 18AUG08 11SEP08
EN220 PREP & APPRL OF DBR - AHP 25 18AUG08 11SEP08

INTERFACE
Subtotal 652 12MAY08 22FEB10

TPL TO BHEL
TB001 UNIT #1 - BOILER FOUNDATION COMPLETION 0 25NOV08
TB002 UNIT #1 - ESP FOUNDATION COMPLETION 0 25JAN09
U2TB001 UNIT #2 - BOILER FOUNDATION COMPLETION 0 23FEB09
TB025 U#1 LP / HP HEATERS, DRAIN COOLER FOUND. COMPLN. 0 13MAR09
TB012 FUEL OIL PUMP SKID FOUNDATION READINESS 0 01APR09
U2TB002 UNIT #2 - ESP FOUNDATION COMPLETION 0 25APR09
TB020 EOT CRANE READINESS FOR EQUIPMENTS' ERECTION 0 21MAY09
TB014 UNIT #1 - BFP & CEP FOUNDATION COMPLETION 0 26MAY09
TB015 U#1 - AOP, JOP & EOP FOUNDATION COMPLETION 0 26MAY09

Start Date 01MAR08 DAR7 Sheet 2 of 55


Early Bar
Finish Date 17APR10 Date Revision Checked Approved
Float Bar
Data Date 18MAR08
Run Date 10SEP08 23:57 Progress Bar
2 X 80 MW CPP - DARIBA SMELTER COMPL
Critical Activity

Classic Schedule Layout


© Primavera Systems, Inc.
PDF created with pdfFactory Pro trial version www.pdffactory.com
Activity Activity Plan Plan Plan 2008
MAR APR MAY JUN JUL AUG
ID Description Dur Start Finish 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11
TB013 UNIT #1 CONDENSOR FOUNDATION COMPLETION 0 29MAY09
U2TB025 U#2 LP / HP HEATERS, DRAIN COOLER FOUND. COMPLN. 0 29MAY09
TB010 TG DECK READINESS FOR TG ERECTION - UNIT #1 0 05JUN09
TB016 U#1 - DEAERATOR FOUNDATION COMPLETION 0 05JUN09
U#1 - DEAERATOR FOUNDATION COMPLETION
TB026 U#1 OIL & AIR COOLER/EJECTOR SYSTEM FDN. COMPLN. 0 28JUN09
U2TB016 U#2 - DEAERATOR FOUNDATION COMPLETION 0 05JUL09
TB005 DM WATER FOR BOILER HYDRO-TEST (MANUAL MODE) 0 26JUL09
TB003 UNIT #1 - ID & FD FAN FOUNDATION COMPLETION 0 02AUG09
TB004 UNIT #1 - PA FAN FOUNDATION COMPLETION 0 09AUG09
TB011 TG BUILDING WITH SIDE & ROOF COVERING 0 09AUG09
TB027 U#1 FOUNDATION COMPLETION FOR OTHER AUX. & DUCTS 0 14AUG09
U2TB014 UNIT #2 - BFP & CEP FOUNDATION COMPLETION 0 24AUG09
U2TB015 U#2 - AOP, JOP & EOP FOUNDATION COMPLETION 0 24AUG09
TB028 HT SWITCH GEAR READINESS 0 26AUG09
U2TB013 UNIT #2 CONDENSOR FOUNDATION COMPLETION 0 29AUG09
U2TB010 TG DECK READINESS FOR TG ERECTION - UNIT #2 0 03SEP09
TB007 CHIMNEY READINESS FOR DUCT CONNECTION 0 08SEP09
TB019 ESP CONTROL ROOM READINESS 0 12SEP09
TB006 UNIT #1 - MILL FOUNDATION READINESS 0 13SEP09
TB017 LT SWITCH GEAR READINESS 0 15SEP09
TB029 READINESS OF CONTROL ROOM FOR PANEL ERECTION 0 17SEP09
U2TB026 U#2 OIL & AIR COOLER/EJECTOR SYSTEM FDN. COMPLN. 0 26SEP09
TB008 CHIMNEY READINESS FOR BOILER LIGHT-UP 0 28SEP09
TB018 AC SYSTEM READINESS 0 30SEP09
TB035 VENTILATION SYSTEM READINESS 0 13OCT09
TB024 AIR AVAILABILITY TO EQUIPMENTS 0 16OCT09
TB021 CW SYSTEM READINESS / EQUIPMENT CW AVAILABILITY 0 22OCT09
U2TB003 UNIT #2 - ID & FD FAN FOUNDATION COMPLETION 0 31OCT09
U2TB004 UNIT #2 - PA FAN FOUNDATION COMPLETION 0 07NOV09
U2TB027 U#2 FOUNDATION COMPLETION FOR OTHER AUX. & DUCTS 0 12NOV09
TB023 UNIT #1 - AHP READINESS FOR COAL FIRING 0 14NOV09
TB022 CHP READINESS FOR COAL SUPPLY TO BUNKERS 0 10DEC09
U2TB006 UNIT #2 - MILL FOUNDATION READINESS 0 12DEC09
U2TB023 UNIT #2 - AHP READINESS FOR COAL FIRING 0 22FEB10
BHEL TO TPL
BT001 I/P FOR BOILER., FAN, MILL, CHIMNEY, ESP 0 11MAY08 I/P FOR BOILER
BT003 I/P FOR ESP CONTROL ROOM 0 14MAY08 I/P FOR ESP CONTROL ROOM

Start Date 01MAR08 DAR7 Sheet 3 of 55


Early Bar
Finish Date 17APR10 Date Revision Checked Approved
Float Bar
Data Date 18MAR08
Run Date 10SEP08 23:57 Progress Bar
2 X 80 MW CPP - DARIBA SMELTER COMPL
Critical Activity

Classic Schedule Layout


© Primavera Systems, Inc.
PDF created with pdfFactory Pro trial version www.pdffactory.com
Activity Activity Plan Plan Plan 2008
MAR APR MAY JUN JUL AUG
ID Description Dur Start Finish 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11
BT004 UNIT #1 FOUNDATION BOLTS / INSERTS FOR BOILER 0 27AUG08
BT017 I/P DATA FOR PIPERACK 0 29AUG08
BT002 FUEL OIL PUMP SKID DETAILS 0 28SEP08
BT005 UNIT #1 - FOUNDATION BOLTS / INSERTS FOR ESP 0 30OCT08
U2BT004 UNIT #2 FOUNDATION BOLTS / INSERTS FOR BOILER 0 25NOV08
U2BT005 UNIT #2 - FOUNDATION BOLTS / INSERTS FOR ESP 0 28JAN09
BT015 UNIT #1 CLEARANCE FOR PA FAN FOUNDATION ABOVE GL 0 30APR09
BT009 UNIT #1 - BOILER AREA CLEARANCE FOR PAVING 0 11MAY09
BT0131 U#1 - FOUNDATION BOLTS / INSERTS FOR FD, ID FANS 0 10JUN09
BT012 UNIT #1RELEASE OF FRONT AFTER CONDENSOR ERECTION 0 21JUN09
BT0132 U#1 - FOUNDATION BOLTS / INSERTS FOR PA FANS 0 05JUL09
BT013 UNIT #1 - FOUNDATION BOLTS / INSERTS FOR MILLS 0 10JUL09
BT014 U#1CLRNCE FOR ERECT. OF CABLE TRAYS IN BLR. AREA 0 18JUL09
U2BT015 UNIT #2 CLEARANCE FOR PA FAN FOUNDATION ABOVE GL 0 30JUL09
U2BT009 UNIT #2 - BOILER AREA CLEARANCE FOR PAVING 0 10AUG09
BT011 UNIT #1COMPLETION OF PLACING OF TG ON FOUNDATION 0 17AUG09
BT016 U#1 CLRNCE.-CONST OF STG COOL AIR DUCT CONIC POR 0 18AUG09
BT006 U#1CLEARANCE FOR COMPLETION OF BOTTOM ASH HOPPER 0 31AUG09
BT008 UNIT#1 - BOILER HYDRO-TEST COMPLETION 0 31AUG09
U2BT0131 U#2 - FOUNDATION BOLTS / INSERTS FOR FD, ID FANS 0 08SEP09
BT010 UNIT #1 COMPLETION OF TG ERECTION 0 19SEP09
U2BT012 UNIT #2RELEASE OF FRONT AFTER CONDENSOR ERECTION 0 21SEP09
U2BT0132 U#2 - FOUNDATION BOLTS / INSERTS FOR PA FANS 0 03OCT09
U2BT013 UNIT #2 - FOUNDATION BOLTS / INSERTS FOR MILLS 0 08OCT09
BT007 U#1ESP/ECO/APH RELS FOR ERECT. OF FLY ASH SYSTEM 0 13OCT09
U2BT014 U#2CLRNCE FOR ERECT. OF CABLE TRAYS IN BLR. AREA 0 17OCT09
U2BT011 UNIT #2COMPLETION OF PLACING OF TG ON FOUNDATION 0 17NOV09
U2BT016 U#2 CLRNCE.-CONST OF STG COOL AIR DUCT CONIC POR 0 18NOV09
U2BT006 U#2CLEARANCE FOR COMPLETION OF BOTTOM ASH HOPPER 1 30NOV09 30NOV09
U2BT008 UNIT#2 - BOILER HYDRO-TEST COMPLETION 0 30NOV09
U2BT010 UNIT #2 COMPLETION OF TG ERECTION 0 22DEC09
U2BT007 U#2ESP/ECO/APH RELS FOR ERECT. OF FLY ASH SYSTEM 0 13JAN10

GENERAL
Subtotal 467 02MAY08 11AUG09

SITE PREPAREDNESS
SSP100 SITE CLEARENCE TO START WORK 0 01MAY08

Start Date 01MAR08 DAR7 Sheet 4 of 55


Early Bar
Finish Date 17APR10 Date Revision Checked Approved
Float Bar
Data Date 18MAR08
Run Date 10SEP08 23:57 Progress Bar
2 X 80 MW CPP - DARIBA SMELTER COMPL
Critical Activity

Classic Schedule Layout


© Primavera Systems, Inc.
PDF created with pdfFactory Pro trial version www.pdffactory.com
Activity Activity Plan Plan Plan 2008
MAR APR MAY JUN JUL AUG
ID Description Dur Start Finish 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11
SSP120 CONST. WATER AVAILABILITY 0 01MAY08 CONST. WATER AVAILABILITY
SSP170 FURNISHING LOCATION FOR CRUSHER WITH POWER POINT 0 03MAY08
SSP110 CONST. POWER AVAILABILITY 0 05MAY08 CONST. POWER AVAILABILITY
SSP122 APPROACH ROAD FROM HZL BL. TO CPP 0 30MAY08 APPROACH ROAD FROM HZL BL. TO CPP
SSP130 DISTRIBUTION OF CONST. WATER 40 01JUN08 10JUL08 DISTRIBUTION OF CONST. WATER
SSP140 READYNESS OF CONST POWER 50 01JUN08 20JUL08 READYNESS OF CONST POWER
SSP160 TPL - SITE STORE READINESS 80 11JUN08 29AUG08 TPL - SITE STORE READINESS
SSP150 TPL - SITE OFFICE READINESS 60 01JUL08 29AUG08 TPL - SITE OFFICE READINESS
SSPB001 BHEL - SITE OFFICE READINESS 60 15AUG08 13OCT08 BHEL - SITE OFFICE READINESS
SSPB002 BHEL - SITE STORE READINESS 50 21OCT08 09DEC08
SSP180 RAW WATER RESERVOIR AVAILABILITY 0 17MAR09
SSP210 SERVICE AIR AVAILABILITY 0 09MAY09
SSP190 POTABLE / FIRE WATER AVAILABILITY 0 15JUN09
SSP200 DM WATER AVAILABILITY 0 03JUL09
SSP230 SWITCHYARD AVAILABILITY 0 11AUG09
RESOURCE START-UP
RSP125 TPL -SITE MOBILIZATION 80 12MAY08 30JUL08 TPL -SITE MOBILIZATION
RSPB014 CIVIL CONTRACT FINALIZATION 45 21JUN08 04AUG08 CIVIL CONTRACT FINALIZATION
RSPB015 STRUCTURAL CONTRACT FINALIZATION 45 01JUL08 14AUG08 STRUCTURAL CONTRACT FINALIZATION
RSPB016 MOBILISATION OF CIVIL CONTRACTOR 25 05AUG08 29AUG08 MOBILISATION OF CIVIL CONTRACTOR
RSPB017 MOBILISATION STRL CONTRACTOR 30 15AUG08 13SEP08 MOBILISATION STRL CONTRACTOR
RSPB003 FINALIZATION OF BOILER ERECTION CONTRACTOR 0 16OCT08
RSPB011 FINALIZATION OF MATERIAL HANDLING AGENCY 0 16OCT08
RSP135 ORDERING OF BOP PIPING ERECTION CONTRACTOR 45 20OCT08 03DEC08
RSPB012 MOBILIZATION OF MATERIAL HANDLING AGENCY 25 01NOV08 25NOV08
RSPB005 FINALIZATION OF TG ERECTION CONTRACTOR 0 14NOV08
RSPB004 MOBILIZATION OF BOILER ERECTION CONTRACTOR 30 16NOV08 15DEC08
RSP175 BOP ELECT. ERECTION CONTRACT FINALISATION 60 28NOV08 26JAN09
RSP145 MOBILISATION OF BOP PIPING ERECTION CONTRACTOR 30 11DEC08 09JAN09
RSPB006 MOBILIZATION OF TG ERECTION CONTRACTOR 30 15DEC08 13JAN09
RSP185 MOBILISATION OF BOP ELECTRICAL ERE CONTRACTOR 45 27JAN09 12MAR09
RSP225 MOBILIZATION OF FF/FD SYSTEM ERECTION CONTRACTOR 30 14FEB09 15MAR09
RSP155 ORDERING - BOP C&I ERECTION CONTRACTOR 55 19FEB09 14APR09
RSPB007 FINALIZATION OF BTG ELECT. ERECTION CONTRACTOR 0 07MAR09
RSPB009 FINALIZATION OF BTG C&I ERECTION CONTRACTOR 0 12MAR09
RSPB008 MOBILIZATION OF BTG ELECT. ERECTION CONTRACTOR 25 23MAR09 16APR09
RSPB010 MOBILIZATION OF BTG C&I ERECTION CONTRACTOR 25 28MAR09 21APR09

Start Date 01MAR08 DAR7 Sheet 5 of 55


Early Bar
Finish Date 17APR10 Date Revision Checked Approved
Float Bar
Data Date 18MAR08
Run Date 10SEP08 23:57 Progress Bar
2 X 80 MW CPP - DARIBA SMELTER COMPL
Critical Activity

Classic Schedule Layout


© Primavera Systems, Inc.
PDF created with pdfFactory Pro trial version www.pdffactory.com
Activity Activity Plan Plan Plan 2008
MAR APR MAY JUN JUL AUG
ID Description Dur Start Finish 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11
RSP165 MOBILI OF BOP C&I ERECTION CONTRACTOR TO SITE 30 15APR09 14MAY09

UNIT I - BTG
Subtotal 739 18MAR08 26MAR10

STEAM GENERATION
BOILER FOUNDATION
ENGINEERING
EN450 BOILER FOUNDATION DRG 20 22MAY08 10JUN08 BOILER FOUNDATION DRG
BBE001 BOILER FOUNDATION ENGG 30 16JUN08 15JUL08 BOILER FOUNDATION ENGG
PROCUREMENT
BBP001 INDENTIG/ORDERING/RECEIPT OF MATERIAL-Boiler 15 16JUL08 30JUL08 INDENTIG/ORDERING/RECEIPT OF MATERIAL-Boiler
BBP002 MFG & DISPATCH OF FOUNDATION MATLS 28 31JUL08 27AUG08 MFG & DISPATCH OF FOUNDATION MATLS
CIVIL
BA100 FOUND FOR BOILER MAIN COLUMN 60 28AUG08 26OCT08
BA110 FOUND FOR BOILER AUXILIARY COLUMN 50 02OCT08 20NOV08
BA150 READINESS OF BOILER FOUNDATION 5 21NOV08 25NOV08
BOILER STRUCTURE
ENGINEERING
BSE001 ENGINEERING- BOILER STR. 30 21JUN08 20JUL08 ENGINEERING- BOILER STR.
PROCUREMENT
BSP001 RECEIPT OF BOILER STR. MATERIAL AT WORKS 10 21JUL08 30JUL08 RECEIPT OF BOILER STR. MATERIAL AT WORKS
BSP002 MANUFACTURING - BOILER STRUCTURE 128 22JUL08 26NOV08 MANUFACTURING - BOILER STRUCTURE
BSP003 DESPATCH MAIN BOILER STRUCTURE 120 29AUG08 26DEC08
BSP004 DESPATCH AUXILIARY STRUCTURE 180 31AUG08 26FEB09
ERECTION/COMMISSIONING
BSEC001 ERCN. OF MAIN BOILER STR. 90 15JAN09 14APR09
BSEC002 ERECTION OF AUX STR. 50 01MAR09 19APR09
BSEC003 STR. ERECTION BEFORE DRUM LIFTING 5 26MAR09 30MAR09
BOILER DRUM
ENGINEERING
BDE001 ENGINEERING- BOILER DRUM 30 02MAY08 31MAY08 ENGINEERING- BOILER DRUM
PROCUREMENT
BDP001 INTEND. & RECEIPT OF BOILER DRUM MTRL. AT WORKS 156 10MAY08 12OCT08
BDP002 MANUFACTURING & DISPATCH- BOILER DRUM 170 13OCT08 31MAR09
ERECTION/COMMISSIONING
BDEC001 BOILER DRUM LIFTING 0 30APR09
BOILER PRESSURE PARTS
ENGINEERING
BPE001 ENGINEERING- BOILER PRESS PARTS 30 16JUL08 14AUG08 ENGINEERING- BOILER PRESS PARTS
PROCUREMENT
BPP001 RECEIPT OF BOILER PRESS. PARTS MATERIAL AT WORKS 85 06AUG08 29OCT08 RECEIPT OF BOILER PRESS. PARTS MATERIAL AT WORKS

Start Date 01MAR08 DAR7 Sheet 6 of 55


Early Bar
Finish Date 17APR10 Date Revision Checked Approved
Float Bar
Data Date 18MAR08
Run Date 10SEP08 23:57 Progress Bar
2 X 80 MW CPP - DARIBA SMELTER COMPL
Critical Activity

Classic Schedule Layout


© Primavera Systems, Inc.
PDF created with pdfFactory Pro trial version www.pdffactory.com
Activity Activity Plan Plan Plan 2008
MAR APR MAY JUN JUL AUG
ID Description Dur Start Finish 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11
BPP002 MANUFACTURING- BOILER PRESS. PARTS 280 05SEP08 11JUN09
BPP003 DESPATCH- BOILER PRESS. PARTS 160 11JAN09 19JUN09
ERECTION/COMMISSIONING
BPEC001 BANK TUBES, WW HDR., WW PANEL & D' COMER ERECN. 90 01MAY09 29JUL09
BPEC002 SH HDR., SH TUBES ASSY. ERECN. 25 06MAY09 30MAY09
BPEC003 MAIN STEAM PIPG. ERECN 20 31MAY09 19JUN09
BPEC004 ECO.LINK,HDR & BANK ASSY., BLR. FEED PIPG. ERCN. 25 20JUN09 14JUL09
BPEC005 OTHER ACT. COMPLN. & READY FOR HT/IBR CLEARANCE 26 30JUL09 24AUG09
BPEC006 HYDRAULIC TEST OF BOILER 7 25AUG09 31AUG09
BPEC008 EDTA CLEANING / ALKALI BOIL-OUT 5 01NOV09 05NOV09
BPEC007 ACID CLEANING 4 06NOV09 09NOV09
BOILER INSULATION
ENGINEERING
BIE001 ENGINEERING FOR INSULATION- BOILER INSULATION 15 20AUG08 03SEP08
PROCUREMENT
BIP001 RECEIPT OF MATERIAL AT WORKS- BOILER INSULATION 60 27APR09 25JUN09
BIP002 MANUFACTURING- BOILER INSULATION 85 28APR09 21JUL09
BIP003 DESPATCH- BOILER INSULATION 30 22JUL09 20AUG09
ERECTION/COMMISSIONING
BIEC001 INSULATION & LINING- BOILER 45 01SEP09 15OCT09
SHEETING
ENGINEERING
BGE001 ENGINEERING-SHEETING 20 30AUG08 18SEP08
PROCUREMENT
BGP001 INDENTING & ORDERING-SHEETING 45 19SEP08 02NOV08
BGP002 DELIVERY AT SITE-SHEETING 210 17JAN09 14AUG09
ERECTION/COMMISSIONING
BGEC001 ERECTION-SHEETING 60 21OCT09 19DEC09
VALVE
ENGINEERING
BVE001 ENGINEERING - VALVES 45 31JUL08 13SEP08 ENGINEERING - VALVES
PROCUREMENT
BVP001 ORDERING - VALVES 90 14SEP08 12DEC08
BVP002 MANUFACTURING - VALVES 295 13DEC08 03OCT09
BVP003 DELIVERY AT SITE - VALVES FOR HT 150 27JAN09 25JUN09
BVP004 DELIVERY AT SITE - VALVES FOR LU 120 28MAR09 25JUL09
BVP005 DELIVERY AT SITE - VALVES FOR SYN 90 16JUL09 13OCT09
ERECTION/COMMISSIONING
BVEC001 ERECTION - VALVES FOR HT 30 15JUL09 13AUG09
BVEC002 ERECTION - VALVES FOR LU 60 17AUG09 15OCT09

Start Date 01MAR08 DAR7 Sheet 7 of 55


Early Bar
Finish Date 17APR10 Date Revision Checked Approved
Float Bar
Data Date 18MAR08
Run Date 10SEP08 23:57 Progress Bar
2 X 80 MW CPP - DARIBA SMELTER COMPL
Critical Activity

Classic Schedule Layout


© Primavera Systems, Inc.
PDF created with pdfFactory Pro trial version www.pdffactory.com
Activity Activity Plan Plan Plan 2008
MAR APR MAY JUN JUL AUG
ID Description Dur Start Finish 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11
BVEC003 ERECTION - VALVES FOR SYN 35 05NOV09 09DEC09
ELECTRICAL
ENGINEERING
TEE001 ENGINEERING - ELECTRICAL 50 30AUG08 18OCT08
PROCUREMENT
TEP001 ORDERING - ELECTRICAL 75 19OCT08 01JAN09
TEP002 MANUFACTURING - ELECTRICAL 225 18NOV08 30JUN09
TEP003 DELIVERY - ELECTRICAL 75 27APR09 10JUL09
ERECTION/COMMISSIONING
TEEC002 MCC ERECTION & COMMISSIONING 20 22AUG09 10SEP09
TEEC001 CABLE TRAY LAYING & CABLING 65 01SEP09 04NOV09
TEEC003 ERECTION & PRE-COMMISSIONING - REQD. FOR BLU 20 01SEP09 20SEP09
TEEC004 ERECTION & PRE-COMMISSIONING - REQD. FOR SYN. 50 21SEP09 09NOV09
C&I
ENGINEERING
TIE001 ENGINEERING - C&I 50 09SEP08 28OCT08
PROCUREMENT
TIP001 ORDERING - C&I 85 29OCT08 21JAN09
TIP002 MANUFACTURING - C&I 250 28NOV08 04AUG09
TIP003 DELIVERY - C&I 90 06JUN09 03SEP09
ERECTION/COMMISSIONING
TIEC001 CABLING 75 06SEP09 19NOV09
TIEC002 ERECTION & PRE-COMMISSIONING - REQD. FOR BLU 22 24SEP09 15OCT09
TIEC003 ERECTION & PRE-COMMISSIONING - REQD. FOR SYN. 55 03OCT09 26NOV09
FUEL OIL SYSTEM
ENGINEERING
FOE001 ENGINEERING - FUEL OIL SYSTEM 30 30AUG08 28SEP08
PROCUREMENT
FOP001 ORDERING - FUEL OIL SYSTEM 45 29SEP08 12NOV08
FOP002 MANUFACTURING - FUEL OIL SYSTEM 190 13NOV08 21MAY09
FOP003 DELIVERY AT SITE - FUEL OIL SYSTEM 50 12MAY09 30JUN09
ERECTION/COMMISSIONING
FOEC001 ERECTION-FUEL OIL PUMP 30 31JUL09 29AUG09
FOEC002 ERECTION-FUEL OIL PIPING 50 27AUG09 15OCT09
FOEC003 PRE-COMMISSIONING-FUEL OIL PUMP 10 16SEP09 25SEP09
FOEC0021 HT - FUEL OIL PIPING 10 16OCT09 25OCT09
BOILER FURNACE & OTHER LU ACTIVITIES (MECH.)
ENGINEERING
LUME001 ENGINEERING - BLR.FURNACE & OTHER LU ACT. (MECH) 40 16AUG08 24SEP08 ENGINEERING - BLR.FURNACE & OTHER LU ACT. (MECH)

Start Date 01MAR08 DAR7 Sheet 8 of 55


Early Bar
Finish Date 17APR10 Date Revision Checked Approved
Float Bar
Data Date 18MAR08
Run Date 10SEP08 23:57 Progress Bar
2 X 80 MW CPP - DARIBA SMELTER COMPL
Critical Activity

Classic Schedule Layout


© Primavera Systems, Inc.
PDF created with pdfFactory Pro trial version www.pdffactory.com
Activity Activity Plan Plan Plan 2008
MAR APR MAY JUN JUL AUG
ID Description Dur Start Finish 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11
PROCUREMENT
LUMP001 ORDERING - BLR.FURNACE & OTHER LU ACT.(MECH) 45 25SEP08 08NOV08
LUMP002 MANUFACTURING-BLR.FURNACE & OTHER LU ACT.(MECH) 350 25SEP08 09SEP09
LUMP003 DELIVERY - BLR.FURNACE & OTHER LU ACT.(MECH) 240 20JAN09 16SEP09
ERECTION/COMMISSIONING
LUMEC004 OTHER ACT. COMPLN. & READY FOR BLU 145 24MAY09 15OCT09
LUMEC001 BURNER ASSEMBLY 45 01SEP09 15OCT09
LUMEC002 FURNACE DOORS FIXING 45 01SEP09 15OCT09
LUMEC003 REFRACTORY & CASING/ENCLOSURE WORKS 40 01SEP09 10OCT09
LUMEC005 ERECTION - BLOWER SYSTEMS 55 01SEP09 25OCT09
BALANCE ACTIVITIES FOR CF & SYN. (MECH.)
ENGINEERING
CSME001 ENGINEERING - BAL. ACT. FOR CF & SYN. (MECH.) 30 30AUG08 28SEP08
PROCUREMENT
CSMP001 ORDERING - BAL. ACT. FOR CF & SYN. (MECH.) 45 29SEP08 12NOV08
CSMP002 MANUFACTURING - BAL. ACT. FOR CF & SYN. (MECH.) 350 29OCT08 13OCT09
CSMP003 DELIVERY - BAL. ACT. FOR CF & SYN. (MECH.) 130 21JUN09 28OCT09
ERECTION/COMMISSIONING
CSMEC002 ERECTION - COAL SYSTEM 65 11OCT09 14DEC09
CSMEC003 OTHER ACT. COMPLN. & READY FOR SYN. 55 16OCT09 09DEC09
AIR & FLUE GAS HANDLING
ESP
ENGINEERING
EN460 ESP FOUNDATION DGR 20 11JUN08 30JUN08 ESP FOUNDATION DGR
BEE001 ENGINEERING - ESP 60 18JUL08 15SEP08 ENGINEERING - ESP
PROCUREMENT
BEP002 MANUFACTURING- ESP 426 17AUG08 16OCT09
BEP001 ORDERING OF MATERIAL - ESP 150 16SEP08 12FEB09
BEP003 DELIVERY AT SITE - ESP 315 21DEC08 31OCT09
CIVIL
BA120 FOUND FOR ESP 75 11OCT08 24DEC08
BA160 READINESS OF ESP FOUNDATION 12 14JAN09 25JAN09
ERECTION/COMMISSIONING
BEEC001 ERECTION- ESP COLUMNS & PANELS 75 31JAN09 15APR09
BEEC0011 ERECTION-ESP ROOF, FUNNELS, INTERNALS & HOPPERS 195 01APR09 13OCT09
BEEC0012 ESP INSULATION 90 16JUL09 13OCT09
BEEC002 ESP BOX-UP & READINESS FOR BLU 0 13OCT09
BEEC0021 ERECTION-RECTIFIER SYSTEM & OTHER ACT. FOR CF/SY 60 14OCT09 12DEC09
BEEC003 ESP READINESS FOR CF 0 12DEC09
BEEC004 ESP READINESS FOR SYN. 0 12DEC09
Start Date 01MAR08 DAR7 Sheet 9 of 55
Early Bar
Finish Date 17APR10 Date Revision Checked Approved
Float Bar
Data Date 18MAR08
Run Date 10SEP08 23:57 Progress Bar
2 X 80 MW CPP - DARIBA SMELTER COMPL
Critical Activity

Classic Schedule Layout


© Primavera Systems, Inc.
PDF created with pdfFactory Pro trial version www.pdffactory.com
Activity Activity Plan Plan Plan 2008
MAR APR MAY JUN JUL AUG
ID Description Dur Start Finish 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11
DAMPER, GATE & ACTUATOR
ENGINEERING
BAE001 DAMPERS, GATES, ACTUATORS - ENGG. 30 22JUN08 21JUL08 DAMPERS, GATES, ACTUATORS - ENGG.
PROCUREMENT
BAP001 ORDG. OF MTRL - DAMPERS, GATES, ACTUATORS 90 22JUL08 19OCT08 ORDG. OF MTRL - DAMPERS, GATES, ACTUATORS
BAP002 MANUFACTURING - DAMPERS, GATES, ACTUATORS 330 22JUL08 16JUN09 MANUFACTURING - DAMPERS, GATES, ACTUATORS
BAP003 SITE DELIVERY - DAMPERS, GATES, ACTUATORS 36 26MAY09 30JUN09
ERECTION/COMMISSIONING
BAEC001 EREC. COMPLN. - DAMPERS, GATES, ACTUATORS 75 16JUL09 28SEP09
FAN
ENGINEERING
EN470 FAN FOUNDATION ENGG 30 01JUL08 30JUL08 FAN FOUNDATION ENGG
BRE001 FANS FD/ID/PA - ENGINEERING 30 16JUL08 14AUG08 FANS FD/ID/PA - ENGINEERING
FAME001 ENGINEERING - FAN MOTOR 35 21SEP08 25OCT08
PROCUREMENT
BRP001 ORDERING OF MATERIAL - FANS 60 15AUG08 13OCT08 ORDERING OF MATERIAL - FANS
BRP003 MANUFACTURING - FANS 400 15AUG08 18SEP09 MANUFACTURING - FANS
FAMP001 MANUFACTURING - FAN MOTOR 150 26OCT08 24MAR09
BRP002 RECEIPT OF MATERIAL AT WORKS - FAN 90 13MAR09 10JUN09
BRP005 DELIVERY AT SITE - FD FAN 150 18MAR09 14AUG09
FAMP002 DELIVERY TO SITE - FAN MOTOR 15 25MAR09 08APR09
BRP004 DELIVERY AT SITE - ID FAN 75 17MAY09 30JUL09
BRP006 DELIVERY AT SITE - PA FAN 130 22MAY09 28SEP09
CIVIL
BA130 FOUND FOR FD,PA,ID FANS - UPTO GL 60 21NOV08 19JAN09
BA133 FOUND FOR FD,ID FANS - ABOVE GL 45 11JUN09 25JUL09
BA135 FOUND FOR PA FANS - ABOVE GL 30 06JUL09 04AUG09
BA165 READINESS OF FD & ID FAN FOUNDATION 8 26JUL09 02AUG09
BA170 READINESS OF PA FAN FOUNDATION 5 05AUG09 09AUG09
ERECTION/COMMISSIONING
BREC001 ERECTION OF ID FAN 60 11JUL09 08SEP09
FAMEC001 ERECTION - FAN MOTOR 20 03AUG09 22AUG09
BREC002 ERECTION OF FD FAN 60 08AUG09 06OCT09
BREC003 ERECTION OF PA FAN 60 20AUG09 18OCT09
FAMEC002 COMMISSIONING - FAN MOTOR 1 23AUG09 23AUG09
BREC005 ID FAN - PRECOMMISSIONING 2 23OCT09 24OCT09
BREC006 FD FAN - PRECOMMISSIONING 2 23OCT09 24OCT09
BREC007 PA FAN - PRECOMMISSIONING 2 23OCT09 24OCT09

Start Date 01MAR08 DAR7 Sheet 10 of 55


Early Bar
Finish Date 17APR10 Date Revision Checked Approved
Float Bar
Data Date 18MAR08
Run Date 10SEP08 23:57 Progress Bar
2 X 80 MW CPP - DARIBA SMELTER COMPL
Critical Activity

Classic Schedule Layout


© Primavera Systems, Inc.
PDF created with pdfFactory Pro trial version www.pdffactory.com
Activity Activity Plan Plan Plan 2008
MAR APR MAY JUN JUL AUG
ID Description Dur Start Finish 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11
AIR-HEATER
ENGINEERING
BHE001 ENGG. - AIR HEATER 60 16JUL08 13SEP08 ENGG. - AIR HEATER
PROCUREMENT
BHP001 ORDERING OF MATERIAL - AIR HEATER 50 26JUL08 13SEP08 ORDERING OF MATERIAL - AIR HEATER
BHP003 MANUFACTURING - AIR HEATER 335 15AUG08 15JUL09 MANUFACTURING - AIR HEATER
BHP002 RECEIPT OF MATERIAL AT WORKS - AIR HEATER 70 02JAN09 12MAR09
BHP004 DELIVERY AT SITE - AIR HEATER 130 23MAR09 30JUL09
ERECTION/COMMISSIONING
BHEC001 ERECTION- AIR HEATER 82 20MAY09 09AUG09
BHEC002 PRE-COMMISSIONING-AIRHEATER 35 25AUG09 28SEP09
BHEC003 READINESS FOR BLU- AIR HEATER 2 29SEP09 30SEP09
DUCTING
ENGINEERING
BTE001 ENGINEERING - DUCTING 30 25AUG08 23SEP08
PROCUREMENT
BTP001 MANUFACTURING-DUCTING 360 24SEP08 18SEP09
BTP002 DESPATCH-DUCTING 162 22APR09 30SEP09
CIVIL
BA140 FOUND FOR OTHER AUX & DUCTS 45 01JUL09 14AUG09
ERECTION/COMMISSIONING
BTEC001 ERECTION - DUCTING 70 12AUG09 20OCT09
ELECTRICAL
ENGINEERING
REE001 ENGINEERING - ELECTRICAL 25 05JUN08 29JUN08 ENGINEERING - ELECTRICAL
PROCUREMENT
REP001 ORDERING - ELECTRICAL 75 30JUN08 12SEP08 ORDERING - ELECTRICAL
REP002 MANUFACTURING - ELECTRICAL 415 30JUL08 17SEP09 MANUFACTURING - ELECTRICAL
REP003 DELIVERY - ELECTRICAL 90 30JUN09 27SEP09
ERECTION/COMMISSIONING
REEC001 CABLE TRAY LAYING & CABLING 70 15JUL09 22SEP09
REEC003 ERECTION & PRE-COMMISSIONING - REQD. FOR BLU 70 09AUG09 17OCT09
REEC004 ERECTION & PRE-COMMISSIONING - REQD. FOR SYN. 80 08SEP09 26NOV09
REEC002 MCC ERECTION & COMMISSIONING 20 18SEP09 07OCT09
C&I
ENGINEERING
RIE001 ENGINEERING - C&I 45 16JUN08 30JUL08 ENGINEERING - C&I
PROCUREMENT
RIP001 ORDERING - C&I 50 31JUL08 18SEP08 ORDERING - C&I
RIP002 MANUFACTURING - C&I 420 30AUG08 23OCT09
RIP003 DELIVERY - C&I 125 03JUL09 04NOV09
Start Date 01MAR08 DAR7 Sheet 11 of 55
Early Bar
Finish Date 17APR10 Date Revision Checked Approved
Float Bar
Data Date 18MAR08
Run Date 10SEP08 23:57 Progress Bar
2 X 80 MW CPP - DARIBA SMELTER COMPL
Critical Activity

Classic Schedule Layout


© Primavera Systems, Inc.
PDF created with pdfFactory Pro trial version www.pdffactory.com
Activity Activity Plan Plan Plan 2008
MAR APR MAY JUN JUL AUG
ID Description Dur Start Finish 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11
ERECTION/COMMISSIONING
RIEC001 CABLING 72 20JUL09 29SEP09
RIEC002 ERECTION & PRE-COMMISSIONING - REQD. FOR BLU 31 16SEP09 16OCT09
RIEC003 ERECTION & PRE-COMMISSIONING - REQD. FOR SYN. 84 16SEP09 08DEC09
PULVERIZING
MILLS
ENGINEERING
MIE001 ENGINEERING- MILLS 30 06JUL08 04AUG08 ENGINEERING- MILLS
MIME001 ENGINEERING - MILL MOTOR 35 21SEP08 25OCT08
EN520 CIVIL DRG FOR MILL FOUNDATION 30 09OCT08 07NOV08
PROCUREMENT
MIP001 INDENTING OF MATERIAL-MILLS 45 05AUG08 18SEP08 INDENTING OF MATERIAL-MILLS
MIP002 ORDERING OF MATERIAL-MILLS 60 04SEP08 02NOV08
MIMP001 MANUFACTURING - MILL MOTOR 150 26OCT08 24MAR09
MIP003 RECEIPT OF MATERIAL AT WORKS-MILLS 150 03NOV08 01APR09
MIP004 MANUFACTURING-MILLS 285 03DEC08 13SEP09
MIMP002 DELIVERY TO SITE - MILL MOTOR 15 25MAR09 08APR09
MIP005 DESPATCH & DELIVERY AT SITE - MILLS 100 21JUN09 28SEP09
CIVIL
BU130 FOUNDATION OF MILLS ( UPTO GL ) 60 30JAN09 30MAR09
BU135 FOUNDATION OF MILLS ( ABOVE GL ) 40 26JUL09 03SEP09
BU150 RELEASE FRONT TO BHEL FOR MILL ERECTION 10 04SEP09 13SEP09
ERECTION/COMMISSIONING
MIEC002 MILLS ERECTION 85 14SEP09 07DEC09
MIMEC001 ERECTION - MILL MOTOR 30 14SEP09 13OCT09
MIMEC002 COMMISSIONING - MILL MOTOR 5 14OCT09 18OCT09
MIEC003 MILLS COMMISSIONING 7 08DEC09 14DEC09
POWER CYCLE
STEAM TURBINE
ENGINEERING
STE001 ENGINEERING- STEAM TURBINE 198 28MAR08 11OCT08
PROCUREMENT
STP001 ORDERING OF MATERIAL- ST 135 29APR08 10SEP08 ORDERING OF MATERIAL- ST
STP002 RECEIPT OF MATERIAL AT WORKS- ST 280 29MAY08 04MAR09 RECEIPT OF MATERIAL AT WORKS- ST
STP003 MANUFACTURING- ST 260 11SEP08 28MAY09
STP0031 AVL. SUB-ASSEMBLIES & PREPARATION FOR MRT 50 29MAY09 18JUL09
STP004 MECHANICAL RUN TEST COMPLETION 5 19JUL09 23JUL09
STP005 DESPATCH & DELIVERY AT SITE - ST 13 24JUL09 05AUG09

Start Date 01MAR08 DAR7 Sheet 12 of 55


Early Bar
Finish Date 17APR10 Date Revision Checked Approved
Float Bar
Data Date 18MAR08
Run Date 10SEP08 23:57 Progress Bar
2 X 80 MW CPP - DARIBA SMELTER COMPL
Critical Activity

Classic Schedule Layout


© Primavera Systems, Inc.
PDF created with pdfFactory Pro trial version www.pdffactory.com
Activity Activity Plan Plan Plan 2008
MAR APR MAY JUN JUL AUG
ID Description Dur Start Finish 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11
ERECTION/COMMISSIONING
STEC001 ERECTION- ST 40 19AUG09 27SEP09
STEC002 TURBINE - LIVE STEAM VALVE ERECTION 10 18SEP09 27SEP09
STEC003 TURBINE BOX UP 3 28SEP09 30SEP09
STEC0031 TURBINE - OTHER ACT. & READINESS FOR SYN. 30 01OCT09 30OCT09
GENERATOR & AUX.
ENGINEERING
GEE001 ENGINEERING- GEN. & AUX. 140 28MAR08 14AUG08
PROCUREMENT
GEP001 ORDERING OF MATERIAL- GEN. & AUX. 80 07APR08 25JUN08
GEP002 RECEIPT OF MATERIAL AT WORKS- GEN. & AUX. 280 22MAY08 25FEB09
GEP003 MANUFACTURING- GEN. & AUX. 226 27NOV08 10JUL09
GEP004 ASSEMBLY & TESTING- GEN. & AUX. 35 07JUL09 10AUG09
GEP005 DESPATCH & DELIVERY AT SITE - GEN. & AUX. 6 11AUG09 16AUG09
ERECTION/COMMISSIONING
GEEC001 GENERATOR - ERECTION 33 17AUG09 18SEP09
GEEC002 GEN AUX. ERECTION INCLUDING GCP, GRP 20 27AUG09 15SEP09
GEEC003 GENERATOR PRE- & FINAL ALIGNMENT 5 26SEP09 30SEP09
BFP & BOOSTER PUMP
ENGINEERING
BFE001 ENGINEERING- BFP & BOOSTER PUMP 120 12MAY08 08SEP08
BFME001 ENGINEERING - BFP MOTOR 35 21SEP08 25OCT08
PROCUREMENT
BFP001 ORDERING - BFP DD ITEMS 60 20MAY08 18JUL08 ORDERING - BFP DD ITEMS
BFP002 MFRG / SITE DELIVERY - BFP SUB-VENDOR & DD ITEMS 326 30MAY08 20APR09
BFMP001 MANUFACTURING - BFP MOTOR 150 26OCT08 24MAR09
BFP003 MANUFACTURING - BFP & BOOSTER PUMP 84 28JAN09 21APR09
BFMP002 DELIVERY TO SITE - BFP MOTOR 15 25MAR09 08APR09
BFP004 ASSEMBLY & TESTING - BFP & BOOSTER PUMP 28 15APR09 12MAY09
BFP005 DESPATCH & DELIVERY AT SITE- BFP & BOOSTER PUMP 14 06MAY09 19MAY09
CIVIL
TG115 BFP FOUNDATION WORKS 45 11MAR09 24APR09
TG165 READINESS FOR BFP ERECTION 0 01MAY09
ERECTION/COMMISSIONING
BFMEC001 ERECTION - BFP MOTOR 10 27MAY09 05JUN09
BFEC001 ERECTION - BFP 22 01JUN09 22JUN09
BFEC002 ERECTION - BOOSTER PUMP 10 01JUN09 10JUN09
BFMEC002 COMMISSIONING - BFP MOTOR 2 06JUN09 07JUN09
BFEC003 PRE-COMMISSIONING - BFP & BOOSTER PUMP 3 23OCT09 25OCT09

Start Date 01MAR08 DAR7 Sheet 13 of 55


Early Bar
Finish Date 17APR10 Date Revision Checked Approved
Float Bar
Data Date 18MAR08
Run Date 10SEP08 23:57 Progress Bar
2 X 80 MW CPP - DARIBA SMELTER COMPL
Critical Activity

Classic Schedule Layout


© Primavera Systems, Inc.
PDF created with pdfFactory Pro trial version www.pdffactory.com
Activity Activity Plan Plan Plan 2008
MAR APR MAY JUN JUL AUG
ID Description Dur Start Finish 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11
CEP
ENGINEERING
CEE001 ENGINEERING- CEP 120 09MAY08 05SEP08 ENGINEERING- CEP
CEME001 ENGINEERING - CEP MOTOR 35 21SEP08 25OCT08
PROCUREMENT
CEP001 ORDERING - CEP DD ITEMS 59 20MAY08 17JUL08 ORDERING - CEP DD ITEMS
CEP002 MFRG & DELIVERY AT SITE - BFP SUB-VENDOR ITEMS 194 18JUL08 27JAN09 MFRG & DELIVERY AT SITE - BFP SUB-VENDOR ITEMS
CEMP001 MANUFACTURING - CEP MOTOR 150 26OCT08 24MAR09
CEP003 MANUFACTURING- CEP 84 28JAN09 21APR09
CEMP002 DELIVERY TO SITE - CEP MOTOR 15 25MAR09 08APR09
CEP004 ASSEMBLY & TESTING- CEP 21 22APR09 12MAY09
CEP005 DESPATCH & DELIVERY AT SITE- CEP 7 13MAY09 19MAY09
CIVIL
TG160 CEP FOUNDATION WORKS 30 27APR09 26MAY09
ERECTION/COMMISSIONING
CEMEC001 ERECTION - CEP MOTOR 10 27MAY09 05JUN09
CEEC001 ERECTION- CEP 25 01JUN09 25JUN09
CEMEC002 COMMISSIONING - CEP MOTOR 2 06JUN09 07JUN09
CEEC002 PRE-COMMISSIONING - CEP 15 23OCT09 06NOV09
LUBE OIL PUMP & TANK
ENGINEERING
LOE001 ENGINEERING- LUBEOILPUMPS & TANKS 30 16JUL08 14AUG08 ENGINEERING- LUBEOILPUMPS & TANKS
PROCUREMENT
LOP001 INDENT&ORDER OF MATERIAL- LUBEOILPUMPS & TANKS 48 31JUL08 16SEP08 INDENT&ORDER OF MATERIAL- LUBEOILPUMPS & TANKS
LOP002 MANUFACTURING- LUBEOILPUMPS & TANKS 256 17SEP08 30MAY09
LOP003 RECEIPT OF MATERIAL AT SITE- LUBEOILPUMPS & TANK 11 31MAY09 10JUN09
ERECTION/COMMISSIONING
LOEC001 ERECTION- LUBEOILPUMPS & TANKS 25 11JUN09 05JUL09
LOEC002 PRE-COMMISSIONING- LUBEOILPUMPS & TANKS 9 16SEP09 24SEP09
DRAIN COOLER
ENGINEERING
DCE001 ENGINEERING - DRAIN COOLER 10 18MAR08 27MAR08
PROCUREMENT
DCP001 ORDERING - DRAIN COOLER 33 17APR08 19MAY08
DCP002 MFRG. & DELIVERY AT WORK - DRAIN COOLER MATERIAL 93 20MAY08 20AUG08
DCP003 MANUFACTURING - DRAIN COOLER 175 21AUG08 11FEB09
DCP004 TESTING - DRAIN COOLER 6 12FEB09 17FEB09
DCP005 DISPATCH & DELIVERY AT SITE - DRAIN COOLER 7 18FEB09 24FEB09
ERECTION/COMMISSIONING
DCEC001 ERECTION- DRAIN COOLERS 26 19MAR09 13APR09

Start Date 01MAR08 DAR7 Sheet 14 of 55


Early Bar
Finish Date 17APR10 Date Revision Checked Approved
Float Bar
Data Date 18MAR08
Run Date 10SEP08 23:57 Progress Bar
2 X 80 MW CPP - DARIBA SMELTER COMPL
Critical Activity

Classic Schedule Layout


© Primavera Systems, Inc.
PDF created with pdfFactory Pro trial version www.pdffactory.com
Activity Activity Plan Plan Plan 2008
MAR APR MAY JUN JUL AUG
ID Description Dur Start Finish 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11
DCEC002 PRE-COMMISSIONING- DRAIN COOLERS 2 14APR09 15APR09
AOP, JOP, EOP, OIL PURIFICATION
ENGINEERING
JEE001 ENGINEERING - STG AUX( AOP,EOP,JOP,PURFN) 30 18MAR08 16APR08
PROCUREMENT
JEP001 ORDERING - STG AUX 69 02APR08 09JUN08
JEP002 MANUFACTURING - STG AUX 120 10JUN08 07OCT08 MANUFACTURING - STG AUX
JEP003 INSPECTION - STG AUX 70 08OCT08 16DEC08
JEP004 DESPATCH & DELIVERY AT SITE - STG AUX 56 03DEC08 27JAN09
ERECTION/COMMISSIONING
JEEC001 ERECTION- STG AUX 40 01JUN09 10JUL09
JEEC002 PRE-COMMISSIONING-STG AUX 9 16SEP09 24SEP09
SURFACE CONDENSOR
ENGINEERING
CHE001 ENGINEERING - COND. & HOTWELL 90 18MAR08 15JUN08
PROCUREMENT
CHP001 ORDERING OF MATERIAL - COND. & HOTWELL 62 08APR08 08JUN08
CHP002 RECEIPT OF MATERIAL AT WORKS - COND. & HOTWELL 162 09JUN08 17NOV08
CHP003 MANUFACTURING - COND. & HOTWELL 113 18NOV08 10MAR09
CHP004 TESTING - COND. & HOTWELL 7 11MAR09 17MAR09
CHP005 DESPATCH & DELIVERY AT SITE - COND. & HOTWELL 7 18MAR09 24MAR09
CIVIL
TG111 CONDENSER FOUNDATION WORKS 30 25APR09 24MAY09
TG170 READINESS FOR CONDENSER FOUNDATION 0 29MAY09
ERECTION/COMMISSIONING
CHEC001 ERECTION - COND. & HOTWELL 23 30MAY09 21JUN09
CHEC002 PRE-COMMISSONING - COND. & HOTWELL 31 22JUN09 22JUL09
SCEC006 HP BYPASS STATION ERECTION 15 09SEP09 23SEP09
SCEC011 COMMISSIONING OF HP BYPASS SYSTEM. 1 27NOV09 27NOV09
GS CONDENSOR
ENGINEERING
GSE001 ENGINEERING - GS CONDENSOR 10 18MAR08 27MAR08
PROCUREMENT
GSP001 ORDERING OF MATERIAL - GS CONDENSOR 73 28MAR08 08JUN08
GSP002 MFRG. & RECPT. OF MTRL. AT WORKS - GS CONDENSOR 162 09JUN08 17NOV08
GSP003 MANUFACTURING - GS CONDENSOR 113 18NOV08 10MAR09
GSP004 TESTING - GS CONDENSOR 7 11MAR09 17MAR09
GSP005 DESPATCH & DELIVERY AT SITE - GS CONDENSOR 7 18MAR09 24MAR09
ERECTION/COMMISSIONING
GSEC001 ERECTION - GS CONDENSOR 45 25MAR09 08MAY09

Start Date 01MAR08 DAR7 Sheet 15 of 55


Early Bar
Finish Date 17APR10 Date Revision Checked Approved
Float Bar
Data Date 18MAR08
Run Date 10SEP08 23:57 Progress Bar
2 X 80 MW CPP - DARIBA SMELTER COMPL
Critical Activity

Classic Schedule Layout


© Primavera Systems, Inc.
PDF created with pdfFactory Pro trial version www.pdffactory.com
Activity Activity Plan Plan Plan 2008
MAR APR MAY JUN JUL AUG
ID Description Dur Start Finish 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11
GSEC002 COMMISSIONING - GS CONDENSOR 13 09MAY09 21MAY09
LP HEATERS I & II
ENGINEERING
LPE001 ENGINEERING - LP HEATERS 10 18MAR08 27MAR08
PROCUREMENT
LPP001 ORDERING OF MATERIAL - LP HEATERS 74 28MAR08 09JUN08
LPP002 MFRG. & RECPT. OF MTRL. AT WORKS - LP HEATERS 106 10JUN08 23SEP08 MFRG. & RECPT. OF MTRL. AT WORKS - LP HEATERS
LPP003 MANUFACTURING - LP HEATERS 168 24SEP08 10MAR09
LPP004 TESTING - LP HEATERS 7 11MAR09 17MAR09
LPP005 DESPATCH & DELIVERY AT SITE - LP HEATERS 7 18MAR09 24MAR09
ERECTION/COMMISSIONING
LPEC001 ERECTION - LP HEATERS 40 25MAR09 03MAY09
LPEC002 PRE-COMMISSIONING - LP HEATERS 18 04MAY09 21MAY09
HP HEATERS IV & V
ENGINEERING
HPE001 ENGINEERING - HP HEATERS 10 18MAR08 27MAR08
PROCUREMENT
HPP001 ORDERING OF MATERIAL - HP HEATERS 74 28MAR08 09JUN08
HPP002 MFRG. & RECPT. OF MTRL. AT WORKS - HP HEATERS 92 10JUN08 09SEP08 MFRG. & RECPT. OF MTRL. AT WORKS - HP HEATERS
HPP003 MANUFACTURING - HP HEATERS 175 10SEP08 03MAR09
HPP004 TESTING - HP HEATERS 14 04MAR09 17MAR09
HPP005 DESPATCH & DELIVERY AT SITE - HP HEATERS 7 18MAR09 24MAR09
ERECTION/COMMISSIONING
HPEC001 ERECTION - HP HEATERS 21 25MAR09 14APR09
HPEC002 PRE-COMMISSIONING - HEATERS 18 15APR09 02MAY09
DE-AERATOR HEADER
ENGINEERING
DHE001 ENGINEERING - DE-AERATOR HEADER 10 18MAR08 27MAR08
PROCUREMENT
DHP001 ORDERING OF MATERIAL - DE-AERATOR HEADER 74 28MAR08 09JUN08
DHP002 MFRG. & RECPT. OF MTRL. AT WORKS - DE-AER. HEAD. 78 10JUN08 26AUG08
DHP003 MANUFACTURING - DE-AERATOR HEADER 182 27AUG08 24FEB09
DHP004 TESTING - DE-AERATOR HEADER 14 25FEB09 10MAR09
DHP005 DESPATCH & DELIVERY AT SITE - DE-AERATOR HEADER 10 11MAR09 20MAR09
CIVIL
TG175 DEAERATOR FOUNDATION 25 12MAY09 05JUN09
ERECTION/COMMISSIONING
DHEC001 ERECTION - DE-AERATOR HEADER 30 06JUN09 05JUL09
DHEC002 PRE-COMMISSIONING - DE-AERATOR HEADER 2 06JUL09 07JUL09

Start Date 01MAR08 DAR7 Sheet 16 of 55


Early Bar
Finish Date 17APR10 Date Revision Checked Approved
Float Bar
Data Date 18MAR08
Run Date 10SEP08 23:57 Progress Bar
2 X 80 MW CPP - DARIBA SMELTER COMPL
Critical Activity

Classic Schedule Layout


© Primavera Systems, Inc.
PDF created with pdfFactory Pro trial version www.pdffactory.com
Activity Activity Plan Plan Plan 2008
MAR APR MAY JUN JUL AUG
ID Description Dur Start Finish 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11
DE-AERATOR STORAGE TANK
ENGINEERING
DSE001 ENGINEERING - DE-AERATOR STOR. TANK 10 18MAR08 27MAR08
PROCUREMENT
DSP001 ORDERING OF MATERIAL - DE-AERATOR STOR. TANK 74 28MAR08 09JUN08
DSP002 MFRG. & RECPT. OF MTRL. AT WORKS - DE-AR. SO. TK 78 10JUN08 26AUG08
DSP003 MANUFACTURING - DE-AERATOR STOR. TANK 182 27AUG08 24FEB09
DSP004 TESTING - DE-AERATOR STOR. TANK 14 25FEB09 10MAR09
DSP005 DESPATCH & DELIVERY AT SITE - DE-AR. SO. TK 11 11MAR09 21MAR09
CIVIL
TG175A DEAERATOR FOUNDATION 25 12MAY09 05JUN09
ERECTION/COMMISSIONING
DSEC001 ERECTION - DE-AERATOR STORAGE TANK 30 06JUN09 05JUL09
DSEC002 PRE-COMMISSIONING - DE-AREATOR STORAGE TANK 2 06JUL09 07JUL09
OIL & AIR COOLER
ENGINEERING
OAE001 ENGINEERING - OIL & AIR COOLER 10 18MAR08 27MAR08
PROCUREMENT
OAP001 ORDERING OF MATERIAL - OIL & AIR COOLER 74 28MAR08 09JUN08
OAP002 MFRG. & RECPT. OF MTRL. AT WORKS - OIL & AIR COO 113 20MAY08 09SEP08
OAP003 MANUFACTURING - OIL & AIR COOLER 190 19AUG08 24FEB09
OAP004 TESTING - OIL & AIR COOLER 28 11FEB09 10MAR09
OAP005 DESPATCH & DELIVERY AT SITE - OIL & AIR COOLER 7 11MAR09 17MAR09
ERECTION/COMMISSIONING
OAEC001 ERECTION - OIL & AIR COOLER 40 04JUL09 12AUG09
OAEC002 PRE-COMMISSIONING - OIL & AIR COOLER 1 13AUG09 13AUG09
STEAM JET AIR EJECTOR
ENGINEERING
SJE001 ENGINEERING - SJAE 17 18MAR08 03APR08
PROCUREMENT
SJP001 ORDERING OF MATERIAL - SJAE 46 04APR08 19MAY08
SJP002 MFRG. & RECPT. OF MTRL. AT WORKS - SJAE 106 20MAY08 02SEP08
SJP003 MANUFACTURING - SJAE 145 03SEP08 25JAN09
SJP004 TESTING - SJAE 9 26JAN09 03FEB09
SJP005 DESPATCH & DELIVERY AT SITE - SJAE 7 04FEB09 10FEB09
ERECTION/COMMISSIONING
SJEC001 ERECTION - EJECTOR SYSTEM 40 04JUL09 12AUG09
SJEC002 PRE-COMMISSIONING - EJECTOR SYSTEM 1 13AUG09 13AUG09

Start Date 01MAR08 DAR7 Sheet 17 of 55


Early Bar
Finish Date 17APR10 Date Revision Checked Approved
Float Bar
Data Date 18MAR08
Run Date 10SEP08 23:57 Progress Bar
2 X 80 MW CPP - DARIBA SMELTER COMPL
Critical Activity

Classic Schedule Layout


© Primavera Systems, Inc.
PDF created with pdfFactory Pro trial version www.pdffactory.com
Activity Activity Plan Plan Plan 2008
MAR APR MAY JUN JUL AUG
ID Description Dur Start Finish 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11
ELECTRICAL
ENGINEERING
HEE001 ENGINEERING - ELECTRICAL 47 18MAY08 03JUL08 ENGINEERING - ELECTRICAL
PROCUREMENT
HEP001 ORDERING - ELECTRICAL 71 04JUL08 12SEP08 ORDERING - ELECTRICAL
HEP002 MANUFACTURING - ELECTRICAL 330 24JUL08 18JUN09 MANUFACTURING - ELECTRICAL
HEP003 DELIVERY - ELECTRICAL 92 31MAR09 30JUN09
ERECTION/COMMISSIONING
HEEC001 CABLE TRAY LAYING & CABLING 166 17APR09 29SEP09
HEEC002 ERECTION & PRE-COMMISSIONING - REQD. FOR BLU 30 02MAY09 31MAY09
HEEC003 ERECTION & PRE-COMMISSIONING - REQD. FOR SYN. 119 01JUN09 27SEP09
C&I
ENGINEERING
HIE001 ENGINEERING - C&I 45 04JUN08 18JUL08 ENGINEERING - C&I
PROCUREMENT
HIP001 ORDERING - C&I 45 19JUL08 01SEP08 ORDERING - C&I
HIP002 MANUFACTURING - C&I 360 13AUG08 07AUG09 MANUFACTURING - C&I
HIP003 DELIVERY - C&I 180 11MAR09 06SEP09
ERECTION/COMMISSIONING
HIEC001 CABLING 166 22APR09 04OCT09
HIEC002 ERECTION & PRE-COMMISSIONING - REQD. FOR BLU 45 09JUN09 23JUL09
HIEC003 ERECTION & PRE-COMMISSIONING - REQD. FOR SYN. 60 24JUL09 21SEP09
PIPING & OTHER AUXILIARY SYSTEMS
P&IDs & LAYOUTs
ENGINEERING
PDE003 ENGINEERING - TG HALL EQPT. LAYOUTS & OTHER ENGG 90 01JUN08 29AUG08
PDE002 ENGINEERING - TG HOUSE PIPING/TG INTEGRAL PIPING 90 08JUN08 05SEP08
PDE001 ENGINEERING - BOILER INTERG. PIPG 90 16JUN08 13SEP08 ENGINEERING - BOILER INTERG. PIPG
BOILER INTEGRAL PIPING & UTILITY PIPING (SG)
ENGINEERING
PBE001 ENGINEERING - BLR. INTERG. & UTIL. PIPG. 90 01JAN09 31MAR09
PROCUREMENT
PBP001 MTRL. RCPT. AT WORKS-BLR. INTERG. & UTIL. PIPG. 57 25MAY09 20JUL09
PBP002 MANUFACTURING - BLR. INTERG. & UTIL. PIPG. 151 26MAY09 23OCT09
PBP003 DESPATCH & DELIVERY - BLR. INTERG. & UTIL. PIPG. 174 26MAY09 15NOV09
ERECTION/COMMISSIONING
PBEC001 ERCN.,HT&INSUL OF BI PIPG & UTIL-ACW,SA,IA - BLU 115 10JUN09 02OCT09
PBEC002 ERCN., HT & INSULATION OF BI PIPING FOR SB/SVF 80 25JUL09 12OCT09
PBEC003 ERCN., HT & INSUL. OF OTHER UTILITY PIPG 60 02OCT09 30NOV09

Start Date 01MAR08 DAR7 Sheet 18 of 55


Early Bar
Finish Date 17APR10 Date Revision Checked Approved
Float Bar
Data Date 18MAR08
Run Date 10SEP08 23:57 Progress Bar
2 X 80 MW CPP - DARIBA SMELTER COMPL
Critical Activity

Classic Schedule Layout


© Primavera Systems, Inc.
PDF created with pdfFactory Pro trial version www.pdffactory.com
Activity Activity Plan Plan Plan 2008
MAR APR MAY JUN JUL AUG
ID Description Dur Start Finish 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11
TG HOUSE PIPING & TG INTEGRAL PIPING (PCP)
ENGINEERING
PHE001 ENGINEERING- TG HOUSE & TG INTEGRAL PIPG 90 01JAN09 31MAR09
PROCUREMENT
PHP001 INDG/ORDG OF MTRL- TG HOUSE & TG INTEGRAL PIPG 54 01APR09 24MAY09
PHP002 MTRL RCPT AT WORKS - TG HOUSE & TG INTEGRAL PIPG 57 25MAY09 20JUL09
PHP003 MANUFACTURING - TG HOUSE & TG INTEGRAL PIPG 154 25MAY09 25OCT09
PHP004 DESP &DLRY AT SITE - TG HOUSE & TG INTEGRAL PIPG 175 25MAY09 15NOV09
ERECTION/COMMISSIONING
PHEC004 ERECTION OF FEED WATER PIPING 32 23JUN09 24JUL09
PHEC003 ERECTION OF CONDENSATE PIPING 38 08JUL09 14AUG09
PHEC008 HYDRO TEST OF FEED WATER PIPING 4 30JUL09 02AUG09
PHEC012 INSULATION OF FEED WATER PIPING 14 03AUG09 16AUG09
PHEC001 ERECTION OF MAIN STEAM PIPING 35 05AUG09 08SEP09
PHEC013 ERECTION OF AUX. STEAM PIPING 25 15AUG09 08SEP09
PHEC007 HYDRO TEST OF CONDENSATE PIPING 7 20AUG09 26AUG09
PHEC011 INSULATION OF CONDENSATE PIPING 7 25AUG09 31AUG09
PHEC024 PRE-BOILER FLUSHING 7 27AUG09 02SEP09
PHEC014 HYDRO TEST OF AUX. STEAM PIPING 6 09SEP09 14SEP09
PHEC022 ERCN,HT & INSUL. OF BALANCE PIPG - REQD. FOR BLU 34 12SEP09 15OCT09
PHEC005 HYDRO TEST OF MAIN STEAM PIPING 5 14SEP09 18SEP09
PHEC015 INSULATION OF AUX. STEAM PIPING 5 15SEP09 19SEP09
PHEC009 INSULATION OF MAIN STEAM PIPING 16 19SEP09 04OCT09
PHEC002 ERECTION OF EXTRACTION STEAM PIPING 38 06NOV09 13DEC09
PHEC016 ERECTION OF CONDENSOR AIR EVACUATION PIPING 35 16NOV09 20DEC09
PHEC019 ERECTION OF LUBE OIL PIPING 29 16NOV09 14DEC09
PHEC023 ERCN,HT & INSUL. OF BALANCE PIPG - REQD. FOR SYN 40 16NOV09 25DEC09
PHEC010 INSULATION OF EXTRACTION STEAM PIPING 12 14DEC09 25DEC09
PHEC018 INSULATION OF CONDENSOR AIR EVACUATION PIPING 5 21DEC09 25DEC09
HANGERS & SUPPORTS
ENGINEERING
HSE001 ENGINEERING - HANGERS & SUPPORTS 90 01JAN09 31MAR09
PROCUREMENT
HSP001 RECEIPT OF MTRL AT WORKS - HANGERS & SUPPORTS 57 25MAY09 20JUL09
HSP002 MANUFACTURING - HANGERS & SUPPORTS 154 25MAY09 25OCT09
HSP003 DESP & DLRY AT SITE - HANGERS & SUPPORTS 175 25MAY09 15NOV09
ERECTION/COMMISSIONING
HSEC002 ERECTION OF H & S - REQD. FOR BLU 62 15AUG09 15OCT09
HSEC001 ERECTION OF ACCESSIBLE PLATFORMS TO ERECT H & S 110 28AUG09 15DEC09

Start Date 01MAR08 DAR7 Sheet 19 of 55


Early Bar
Finish Date 17APR10 Date Revision Checked Approved
Float Bar
Data Date 18MAR08
Run Date 10SEP08 23:57 Progress Bar
2 X 80 MW CPP - DARIBA SMELTER COMPL
Critical Activity

Classic Schedule Layout


© Primavera Systems, Inc.
PDF created with pdfFactory Pro trial version www.pdffactory.com
Activity Activity Plan Plan Plan 2008
MAR APR MAY JUN JUL AUG
ID Description Dur Start Finish 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11
HSEC003 ERECTION OF H & S - REQD. FOR SYN. 25 01DEC09 25DEC09
HP DOSING SYSTEM
ENGINEERING
HDE001 ENGINEERING- HP DOSING STN. 90 01JAN09 31MAR09
PROCUREMENT
HDP001 INDENTING OF MATERIAL- HP DOSING STN. 24 01APR09 24APR09
HDP002 ORDERING OF MATERIAL- HP DOSING STN. 30 25APR09 24MAY09
HDP003 RECEIPT OF MATERIAL AT SITE- HP DOSING STN. 57 25MAY09 20JUL09
HDP004 MANUFACTURING - HP DOSING 90 26MAY09 24AUG09
HDP005 DESP & DLRY - HP DOSING 110 27MAY09 14SEP09
ERECTION/COMMISSIONING
HDEC001 ERECTION- HP DOSING STN. 20 15SEP09 04OCT09
HDEC002 COMMISSIONING- HP DOSING STN. 8 05OCT09 12OCT09
TANKS & VESSELS REL.
ENGINEERING
TVE001 ENGINEERING - TANKS & VESSELS 90 01JAN09 31MAR09
PROCUREMENT
TVP001 ORDERING - TANKS & VESSELS REL. 54 01APR09 24MAY09
TVP002 MANUFACTURING - TANKS & VESSELS REL. 93 25MAY09 25AUG09
TVP003 DESP & DLRY AT SITE - TANKS & VESSELS REL. 110 28MAY09 14SEP09
ERECTION/COMMISSIONING
TVEC001 ERECTION & COMMISSIONING - REQD. FOR BLU 30 15SEP09 14OCT09
TVEC002 ERECTION & COMMISSIONING - REQD. FOR SYN. 45 15SEP09 29OCT09
C&I
ENGINEERING
CIE001 ENGINEERING - CONTROL VALVES & FLOW ELEMENTS 25 06JUN08 30JUN08
PIE001 ENGINEERING - OTHER C&I 90 01JAN09 31MAR09
PROCUREMENT
CIP001 INDENTING & ORDERING - CONTROL VALVES 60 01JUL08 29AUG08 INDENTING & ORDERING - CONTROL VALVES
CIP002 INDENTING & ORDERING - FLOW ELEMENTS 45 01JUL08 14AUG08 INDENTING & ORDERING - FLOW ELEMENTS
PIP001 ORDERING - OTHER C&I 54 01APR09 24MAY09
PIP002 MANUFACTURING - OTHER C&I 154 25MAY09 25OCT09
PIP003 DESP & DLRY AT SITE - OTHER C&I 170 29MAY09 14NOV09
CIP003 RECEIPT AT SITE - CONTROL VALVES 15 01JUN09 15JUN09
CIP004 RECEIPT AT SITE - FLOW ELEMENTS 15 16JUN09 30JUN09
ERECTION/COMMISSIONING
CIEC001 ERCN. & COMMNG. - CONTROL VALVES REQD. FOR BLU 26 03OCT09 28OCT09
CIEC003 ERCN. & COMMNG. - FLOW ELEMENTS REQD. FOR BLU 22 07OCT09 28OCT09
PIEC001 ERECTION & COMMISSIONING - REQD. FOR SYN. 42 15NOV09 26DEC09
CIEC002 ERCN. & COMMNG. - CONTROL VALVES REQD. FOR SYN. 36 20NOV09 25DEC09
Start Date 01MAR08 DAR7 Sheet 20 of 55
Early Bar
Finish Date 17APR10 Date Revision Checked Approved
Float Bar
Data Date 18MAR08
Run Date 10SEP08 23:57 Progress Bar
2 X 80 MW CPP - DARIBA SMELTER COMPL
Critical Activity

Classic Schedule Layout


© Primavera Systems, Inc.
PDF created with pdfFactory Pro trial version www.pdffactory.com
Activity Activity Plan Plan Plan 2008
MAR APR MAY JUN JUL AUG
ID Description Dur Start Finish 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11
CIEC004 ERCN. & COMMNG. - FLOW ELEMENTS REQD. FOR SYN. 36 20NOV09 25DEC09
APRDS
ENGINEERING
APE001 ENGINEERING-APRDS 25 11JUN08 05JUL08 ENGINEERING-APRDS
PROCUREMENT
APP001 INDENTING & ORDERING OF MATERIAL-APRDS 55 06JUL08 29AUG08 INDENTING & ORDERING OF MATERIAL-APRDS
APP002 MANUFACTURING-APRDS 80 30AUG08 17NOV08
APP003 RECEIPT OF MATERIAL AT SITE-APRDS 20 28MAR09 16APR09
ERECTION/COMMISSIONING
APEC001 ERECTION-APRDS 84 15AUG09 06NOV09
APEC002 COMM OF APRDC 10 07NOV09 16NOV09
LP DOSING SYSTEM
ENGINEERING
LDE001 ENGINEERING- HP/LP DOSING STN. 10 13JUN08 22JUN08 ENGINEERING- HP/LP DOSING STN.
PROCUREMENT
LDP001 INDENTING OF MATERIAL- LP DOSING STN. 10 28JUN08 07JUL08 INDENTING OF MATERIAL- LP DOSING STN.
LDP002 ORDERING OF MATERIAL- LP DOSING STN. 30 08JUL08 06AUG08 ORDERING OF MATERIAL- LP DOSING STN.
LDP003 RECEIPT OF MATERIAL AT SITE- LP DOSING STN. 45 15MAR09 28APR09
ERECTION/COMMISSIONING
LDEC001 ERECTION - LP DOSING STN. 20 02AUG09 21AUG09
LDEC002 COMMISSIONING - LP DOSING STN. 8 05OCT09 12OCT09
MP
ENGINEERING
MPE001 ENGINEERING - MP 20 06JUN08 25JUN08 ENGINEERING - MP
PROCUREMENT
MPP001 INDENTING & ORDERING - ME BELLOWS 60 26JUN08 24AUG08 INDENTING & ORDERING - ME BELLOWS
MPP002 INDENTING & ORDERING - POWER CYCLE VALVES 60 26JUN08 24AUG08 INDENTING & ORDERING - POWER CYCLE VALVES
MPP003 INDENTING & ORDERING - STEAM TRAPS 45 26JUN08 09AUG08 INDENTING & ORDERING - STEAM TRAPS
MPP007 RECEIPT AT SITE - STEAM TRAPS 15 22JAN09 05FEB09
MPP004 INDENTING & ORDERING - THERMAL INSULATION 30 21FEB09 22MAR09
MPP006 RECEIPT AT SITE - POWER CYCLE VALVES 15 21FEB09 07MAR09
MPP005 RECEIPT AT SITE - ME BELLOWS 15 26FEB09 12MAR09
MPP008 RECEIPT AT SITE - THERMAL INSULATION 15 21JUN09 05JUL09
ERECTION/COMMISSIONING
MPEC004 ERECTION OF THERMAL INSULATION - REQD. FOR BLU 49 08SEP09 26OCT09
MPEC001 ERECTION OF ME BELLOWS- REQD. FOR BLU 25 17SEP09 11OCT09
MPEC002 ERECTION OF POWER CYCLE VALVES - REQD. FOR BLU 25 03OCT09 27OCT09
MPEC003 ERECTION OF STEAM TRAPS - REQD. FOR BLU 25 03OCT09 27OCT09
MPEC008 ERECTION OF THERMAL INSULATION - REQD. FOR SYN. 71 16OCT09 25DEC09
MPEC005 ERECTION OF ME BELLOWS- REQD. FOR SYN. 36 10NOV09 15DEC09
Start Date 01MAR08 DAR7 Sheet 21 of 55
Early Bar
Finish Date 17APR10 Date Revision Checked Approved
Float Bar
Data Date 18MAR08
Run Date 10SEP08 23:57 Progress Bar
2 X 80 MW CPP - DARIBA SMELTER COMPL
Critical Activity

Classic Schedule Layout


© Primavera Systems, Inc.
PDF created with pdfFactory Pro trial version www.pdffactory.com
Activity Activity Plan Plan Plan 2008
MAR APR MAY JUN JUL AUG
ID Description Dur Start Finish 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11
MPEC006 ERECTION OF POWER CYCLE VALVES - REQD. FOR SYN. 45 11NOV09 25DEC09
MPEC007 ERECTION OF STEAM TRAPS - REQD. FOR SYN. 36 20NOV09 25DEC09
LUBE OIL TRANSFER
ENGINEERING
LTE001 ENGINEERING - CLEAN OIL & DIRTY OIL PUMPS 30 18MAY08 16JUN08
PROCUREMENT
LTP001 ORDERING - CLEAN OIL & DIRTY OIL PUMPS 48 02JUN08 19JUL08 ORDERING - CLEAN OIL & DIRTY OIL PUMPS
LTP002 MANUFACTURING - CLEAN OIL & DIRTY OIL PUMPS 256 20JUL08 01APR09 MANUFACTURING - CLEAN OIL & DIRTY OIL PUMPS
LTP003 DELIVERY AT SITE - CLEAN OIL & DIRTY OIL PUMPS 11 02APR09 12APR09
ERECTION/COMMISSIONING
LTEC001 ERECTION - CLEAN OIL & DIRTY OIL PUMPS 25 13APR09 07MAY09
LTEC002 PRE-COMMISSIONNG - CLEAN OIL & DIRTY OIL PUMPS 9 16SEP09 24SEP09
HP & LP FLASH TANKS
ENGINEERING
HLE001 ENGINEERING - HP & LP FLASH TANKS 20 26JUN08 15JUL08 ENGINEERING - HP & LP FLASH TANKS
PROCUREMENT
HLP001 ORDERING - HP & LP FLASH TANKS 30 16JUL08 14AUG08 ORDERING - HP & LP FLASH TANKS
HLP002 MANUFACTURING - HP & LP FLASH TANKS 250 15AUG08 21APR09 MANUFACTURING - HP & LP FLASH TANKS
HLP003 DELIVERY - HP & LP FLASH TANKS 21 22APR09 12MAY09
ERECTION/COMMISSIONING
HLTEC001 ERECTION & COMMISSIONING - HP FLASH TANK 102 03SEP09 13DEC09
HLTEC002 ERECTION & COMMISSIONING - LP FLASH TANK 102 03SEP09 13DEC09
INSTRUMENTATION CONTROLS
TG PACKAGE
ENGINEERING
ETE001 ENGINEERING - ATRS,.. 79 19DEC08 07MAR09
PROCUREMENT
ETP001 PROCUREMENT OF MATERIALS - ATRS,.. 116 08MAR09 01JUL09
ETP002 ASSEMBLY & TESTING COMPLETION - ATRS,.. 32 02JUL09 02AUG09
ETP003 FAT, DESP & DELIVERY TO SITE - ATRS,.. 18 04AUG09 21AUG09
ERECTION/COMMISSIONING
ETEC001 ERECTION - ATRS,.. 46 17SEP09 01NOV09
ETEC002 COMMISSIONING - ATRS,.. 25 02NOV09 26NOV09
SG PACKAGE
ENGINEERING
ESE001 ENGINEERING - FLAME SCANNER, SADC, BMS 79 19DEC08 07MAR09
PROCUREMENT
ESP001 PROCUREM OF MATERIALS - FLAME SCANNER, SADC, BMS 100 08MAR09 15JUN09
ESP002 ASSEMBLY & TESTING - FLAME SCANNER, SADC, BMS 25 16JUN09 10JUL09
ESP003 FAT, DESP & DELIVERY - FLAME SCANNER, SADC, BMS 15 12JUL09 26JUL09

Start Date 01MAR08 DAR7 Sheet 22 of 55


Early Bar
Finish Date 17APR10 Date Revision Checked Approved
Float Bar
Data Date 18MAR08
Run Date 10SEP08 23:57 Progress Bar
2 X 80 MW CPP - DARIBA SMELTER COMPL
Critical Activity

Classic Schedule Layout


© Primavera Systems, Inc.
PDF created with pdfFactory Pro trial version www.pdffactory.com
Activity Activity Plan Plan Plan 2008
MAR APR MAY JUN JUL AUG
ID Description Dur Start Finish 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11
ERECTION/COMMISSIONING
ESEC001 ERECTION - FLAME SCANNER, SADC, BMS 25 17SEP09 11OCT09
ESEC002 COMMISSIONING - FLAME SCANNER, SADC, BMS 5 19OCT09 23OCT09
HMI SYSTEM
ENGINEERING
EHE001 ENGINEERING - TFT MONIT., COMPU., N/W PANEL 79 19DEC08 07MAR09
PROCUREMENT
EHP001 MTRLS. PROCUREME - TFT MONIT., COMPU., N/W PANEL 116 08MAR09 01JUL09
EHP002 ASSEMBLY & TEST. - TFT MONIT., COMPU., N/W PANEL 32 02JUL09 02AUG09
EHP003 FAT, DESP & DELI - TFT MONIT., COMPU., N/W PANEL 18 04AUG09 21AUG09
ERECTION/COMMISSIONING
EHEC001 ERECTION - TFT MONIT., COMPU., N/W PANEL 46 17SEP09 01NOV09
EHEC002 COMMISSIONING - TFT MONIT., COMPU., N/W PANEL 25 02NOV09 26NOV09
AVR SYSTEM
ENGINEERING
EAE001 ENGINEERING - AVR 79 19DEC08 07MAR09
PROCUREMENT
EAP001 PROCUREMENT OF MATERIALS - AVR 116 08MAR09 01JUL09
EAP002 ASSEMBLY & TESTING - AVR 32 02JUL09 02AUG09
EAP003 FAT, DESP & DELIVERY - AVR 18 04AUG09 21AUG09
ERECTION/COMMISSIONING
EAEC001 ERECTION - AVR 46 17SEP09 01NOV09
EAEC002 COMMISSIONING - AVR 25 02NOV09 26NOV09
OVERALL COMMISSIONING
BOILER
OLBC001 BOILER LIGHT UP 3 29OCT09 31OCT09
OLBC002 STEAM BLOWING 10 17NOV09 26NOV09
OLBC003 SAFETY VALVE FLOATING COMPLETION 3 27NOV09 29NOV09
OLBC004 BOILER COAL FIRING 6 01JAN10 06JAN10
TG
OLTC001 FINAL ALIGNMENT OF TG 9 01OCT09 09OCT09
OLTC002 TG - OIL FLUSHING 15 10OCT09 24OCT09
OLTC003 BARRING GEAR OPERATION 7 25OCT09 31OCT09
OLTC004 VACCUM PULLING- TG 2 14DEC09 15DEC09
OLTC005 STEAM DUMPING 1 16DEC09 16DEC09
OVERALL
OLOC001 ROLLING, OCC SCC OF GEN & SYNCHRONISATION 5 27DEC09 31DEC09
OLOC002 COMMG./ STABILITY RUN/TRIAL OPERATION-TG 3 29DEC09 31DEC09
OLOC003 COMMG./ 72 hrs TRIAL OPERATION-TG 3 06MAR10 08MAR10

Start Date 01MAR08 DAR7 Sheet 23 of 55


Early Bar
Finish Date 17APR10 Date Revision Checked Approved
Float Bar
Data Date 18MAR08
Run Date 10SEP08 23:57 Progress Bar
2 X 80 MW CPP - DARIBA SMELTER COMPL
Critical Activity

Classic Schedule Layout


© Primavera Systems, Inc.
PDF created with pdfFactory Pro trial version www.pdffactory.com
Activity Activity Plan Plan Plan 2008
MAR APR MAY JUN JUL AUG
ID Description Dur Start Finish 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11
OLOC004 PROV. HANDING OVER OF PLANT 0 08MAR10
OLOC005 PLANT OPTIMISATION 8 09MAR10 16MAR10
OLOC006 LOAD REJECTION & ISLANDING TESTS 5 17MAR10 21MAR10
OLOC007 RELIABILITY RUN 3 22MAR10 24MAR10
OLOC008 PG TEST 2 25MAR10 26MAR10
OLOC009 FINAL HANDING OVER OF PLANT 0 26MAR10

UNIT II - BTG
Subtotal 761 18MAR08 17APR10

STEAM GENERATION
BOILER FOUNDATION
ENGINEERING
U2EN500 BOILER FOUNDATION DRG 20 22MAY08 10JUN08 BOILER FOUNDATION DRG
U2BBE011 BOILER FOUNDATION ENGG 30 16JUN08 15JUL08 BOILER FOUNDATION ENGG
PROCUREMENT
U2BBP011 INDENTIG/ORDERING/RECEIPT OF MATERIAL-Boiler 15 16JUL08 30JUL08 INDENTIG/ORDERING/RECEIPT OF MATERIAL-Boiler
U2BBP012 MFG & DISPATCH OF FOUNDATION MATLS 28 29OCT08 25NOV08
CIVIL
U2BA200 FOUND FOR BOILER MAIN COLUMN 60 26NOV08 24JAN09
U2BA210 FOUND FOR BOILER AUXILIARY COLUMN 50 31DEC08 18FEB09
U2BA250 READINESS OF BOILER FOUNDATION 5 19FEB09 23FEB09
BOILER STRUCTURE
ENGINEERING
U2BSE011 ENGINEERING- BOILER STR. 30 21JUN08 20JUL08 ENGINEERING- BOILER STR.
PROCUREMENT
U2BSP011 RECEIPT OF BOILER STR. MATERIAL AT WORKS 10 21JUL08 30JUL08 RECEIPT OF BOILER STR. MATERIAL AT WORKS
U2BSP012 MANUFACTURING - BOILER STRUCTURE 128 19OCT08 23FEB09
U2BSP013 DESPATCH MAIN BOILER STRUCTURE 120 26NOV08 25MAR09
U2BSP014 DESPATCH AUXILIARY STRUCTURE 180 28NOV08 26MAY09
ERECTION/COMMISSIONING
U2BSEC011 ERCN. OF MAIN BOILER STR. 90 15APR09 13JUL09
U2BSEC012 ERECTION OF AUX STR. 50 30MAY09 18JUL09
U2BSEC013 STR. ERECTION BEFORE DRUM LIFTING 5 24JUN09 28JUN09
BOILER DRUM
ENGINEERING
U2BDE011 ENGINEERING- BOILER DRUM 30 02MAY08 31MAY08 ENGINEERING- BOILER DRUM
PROCUREMENT
U2BDP011 INTEND. & RECEIPT OF BOILER DRUM MTRL. AT WORKS 156 10MAY08 12OCT08
U2BDP012 MANUFACTURING & DISPATCH- BOILER DRUM 170 11JAN09 29JUN09

Start Date 01MAR08 DAR7 Sheet 24 of 55


Early Bar
Finish Date 17APR10 Date Revision Checked Approved
Float Bar
Data Date 18MAR08
Run Date 10SEP08 23:57 Progress Bar
2 X 80 MW CPP - DARIBA SMELTER COMPL
Critical Activity

Classic Schedule Layout


© Primavera Systems, Inc.
PDF created with pdfFactory Pro trial version www.pdffactory.com
Activity Activity Plan Plan Plan 2008
MAR APR MAY JUN JUL AUG
ID Description Dur Start Finish 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11
ERECTION/COMMISSIONING
U2BDEC011 BOILER DRUM LIFTING 0 30JUL09
BOILER PRESSURE PARTS
ENGINEERING
U2BPE011 ENGINEERING- BOILER PRESS PARTS 30 16JUL08 14AUG08 ENGINEERING- BOILER PRESS PARTS
PROCUREMENT
U2BPP011 RECEIPT OF BOILER PRESS. PARTS MATERIAL AT WORKS 85 06AUG08 29OCT08 RECEIPT OF BOILER PRESS. PARTS MATERIAL AT WORKS
U2BPP012 MANUFACTURING- BOILER PRESS. PARTS 280 04DEC08 09SEP09
U2BPP013 DESPATCH- BOILER PRESS. PARTS 160 11APR09 17SEP09
ERECTION/COMMISSIONING
U2BPEC011 BANK TUBES, WW HDR., WW PANEL & D' COMER ERECN. 91 31JUL09 29OCT09
U2BPEC012 SH HDR., SH TUBES ASSY. ERECN. 25 05AUG09 29AUG09
U2BPEC013 MAIN STEAM PIPG. ERECN 20 30AUG09 18SEP09
U2BPEC014 ECO.LINK,HDR & BANK ASSY., BLR. FEED PIPG. ERCN. 25 18SEP09 12OCT09
U2BPEC015 OTHER ACT. COMPLN. & READY FOR HT/IBR CLEARANCE 25 30OCT09 23NOV09
U2BPEC016 HYDRAULIC TEST OF BOILER 7 24NOV09 30NOV09
U2BPEC018 EDTA CLEANING / ALKALI BOIL-OUT 5 01FEB10 05FEB10
U2BPEC017 ACID CLEANING 4 06FEB10 09FEB10
BOILER INSULATION
ENGINEERING
U2BIE011 ENGINEERING FOR INSULATION- BOILER INSULATION 15 20AUG08 03SEP08
PROCUREMENT
U2BIP011 RECEIPT OF MATERIAL AT WORKS- BOILER INSULATION 60 27APR09 25JUN09
U2BIP012 MANUFACTURING- BOILER INSULATION 85 26JUL09 18OCT09
U2BIP013 DESPATCH- BOILER INSULATION 30 19OCT09 17NOV09
ERECTION/COMMISSIONING
U2BIEC011 INSULATION & LINING- BOILER 45 01DEC09 14JAN10
SHEETING
ENGINEERING
U2BGE011 ENGINEERING-SHEETING 20 30AUG08 18SEP08
PROCUREMENT
U2BGP011 INDENTING & ORDERING-SHEETING 45 19SEP08 02NOV08
U2BGP012 DELIVERY AT SITE-SHEETING 210 17APR09 12NOV09
ERECTION/COMMISSIONING
U2BGEC011 ERECTION-SHEETING 60 19JAN10 19MAR10
VALVE
ENGINEERING
U2BVE011 ENGINEERING - VALVES 45 31JUL08 13SEP08 ENGINEERING - VALVES
PROCUREMENT
U2BVP011 ORDERING - VALVES 90 14SEP08 12DEC08
U2BVP012 MANUFACTURING - VALVES 295 13MAR09 01JAN10
Start Date 01MAR08 DAR7 Sheet 25 of 55
Early Bar
Finish Date 17APR10 Date Revision Checked Approved
Float Bar
Data Date 18MAR08
Run Date 10SEP08 23:58 Progress Bar
2 X 80 MW CPP - DARIBA SMELTER COMPL
Critical Activity

Classic Schedule Layout


© Primavera Systems, Inc.
PDF created with pdfFactory Pro trial version www.pdffactory.com
Activity Activity Plan Plan Plan 2008
MAR APR MAY JUN JUL AUG
ID Description Dur Start Finish 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11
U2BVP013 DELIVERY AT SITE - VALVES FOR HT 150 27APR09 23SEP09
U2BVP014 DELIVERY AT SITE - VALVES FOR LU 120 26JUN09 23OCT09
U2BVP015 DELIVERY AT SITE - VALVES FOR SYN 90 14OCT09 11JAN10
ERECTION/COMMISSIONING
U2BVEC011 ERECTION - VALVES FOR HT 30 13OCT09 11NOV09
U2BVEC012 ERECTION - VALVES FOR LU 75 01NOV09 14JAN10
U2BVEC013 ERECTION - VALVES FOR SYN 35 04FEB10 10MAR10
ELECTRICAL
ENGINEERING
U2TEE011 ENGINEERING - ELECTRICAL 50 30AUG08 18OCT08
PROCUREMENT
U2TEP011 ORDERING - ELECTRICAL 75 19OCT08 01JAN09
U2TEP012 MANUFACTURING - ELECTRICAL 225 16FEB09 28SEP09
U2TEP013 DELIVERY - ELECTRICAL 75 26JUL09 08OCT09
ERECTION/COMMISSIONING
U2TEEC012 MCC ERECTION & COMMISSIONING 20 21NOV09 10DEC09
U2TEEC011 CABLE TRAY LAYING & CABLING 65 01DEC09 03FEB10
U2TEEC013 ERECTION & PRE-COMMISSIONING - REQD. FOR BLU 20 01DEC09 20DEC09
U2TEEC014 ERECTION & PRE-COMMISSIONING - REQD. FOR SYN. 50 21DEC09 08FEB10
C&I
ENGINEERING
U2TIE011 ENGINEERING - C&I 50 09SEP08 28OCT08
PROCUREMENT
U2TIP011 ORDERING - C&I 85 29OCT08 21JAN09
U2TIP012 MANUFACTURING - C&I 250 26FEB09 02NOV09
U2TIP013 DELIVERY - C&I 90 04SEP09 02DEC09
ERECTION/COMMISSIONING
U2TIEC011 CABLING 75 06DEC09 18FEB10
U2TIEC012 ERECTION & PRE-COMMISSIONING - REQD. FOR BLU 22 24DEC09 14JAN10
U2TIEC013 ERECTION & PRE-COMMISSIONING - REQD. FOR SYN. 55 02JAN10 25FEB10
FUEL OIL SYSTEM
ENGINEERING
U2FOE011 ENGINEERING - FUEL OIL SYSTEM 30 30AUG08 28SEP08
PROCUREMENT
U2FOP011 ORDERING - FUEL OIL SYSTEM 45 29SEP08 12NOV08
U2FOP012 MANUFACTURING - FUEL OIL SYSTEM 190 11FEB09 19AUG09
U2FOP013 DELIVERY AT SITE - FUEL OIL SYSTEM 50 10AUG09 28SEP09
ERECTION/COMMISSIONING
U2FOEC012 ERECTION-FUEL OIL PIPING 50 26NOV09 14JAN10
U2FOEC0031 HT - FUEL OIL PIPING 10 15JAN10 24JAN10

Start Date 01MAR08 DAR7 Sheet 26 of 55


Early Bar
Finish Date 17APR10 Date Revision Checked Approved
Float Bar
Data Date 18MAR08
Run Date 10SEP08 23:58 Progress Bar
2 X 80 MW CPP - DARIBA SMELTER COMPL
Critical Activity

Classic Schedule Layout


© Primavera Systems, Inc.
PDF created with pdfFactory Pro trial version www.pdffactory.com
Activity Activity Plan Plan Plan 2008
MAR APR MAY JUN JUL AUG
ID Description Dur Start Finish 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11
BOILER FURNACE & OTHER LU ACTIVITIES (MECH.)
ENGINEERING
U2LUME011 ENGINEERING - BLR.FURNACE & OTHER LU ACT. (MECH) 40 16AUG08 24SEP08 ENGINEERING - BLR.FURNACE & OTHER LU ACT. (MECH)
PROCUREMENT
U2LUMP011 ORDERING - BLR.FURNACE & OTHER LU ACT.(MECH) 45 25SEP08 08NOV08
U2LUMP012 MANUFACTURING-BLR.FURNACE & OTHER LU ACT.(MECH) 350 24DEC08 08DEC09
U2LUMP013 DELIVERY - BLR.FURNACE & OTHER LU ACT.(MECH) 240 20APR09 15DEC09
ERECTION/COMMISSIONING
U2LUMEC014 OTHER ACT. COMPLN. & READY FOR BLU 145 23AUG09 14JAN10
U2LUMEC011 BURNER ASSEMBLY 45 01DEC09 14JAN10
U2LUMEC012 FURNACE DOORS FIXING 45 01DEC09 14JAN10
U2LUMEC013 REFRACTORY & CASING/ENCLOSURE WORKS 40 01DEC09 09JAN10
U2LUMEC015 ERECTION - BLOWER SYSTEMS 55 01DEC09 24JAN10
BALANCE ACTIVITIES FOR CF & SYN. (MECH.)
ENGINEERING
U2CSME011 ENGINEERING - BAL. ACT. FOR CF & SYN. (MECH.) 30 30AUG08 28SEP08
PROCUREMENT
U2CSMP011 ORDERING - BAL. ACT. FOR CF & SYN. (MECH.) 45 29SEP08 12NOV08
U2CSMP012 MANUFACTURING - BAL. ACT. FOR CF & SYN. (MECH.) 350 27JAN09 11JAN10
U2CSMP013 DELIVERY - BAL. ACT. FOR CF & SYN. (MECH.) 130 19SEP09 26JAN10
ERECTION/COMMISSIONING
U2CSMEC012 ERECTION - COAL SYSTEM 65 09JAN10 14MAR10
U2CSMEC013 OTHER ACT. COMPLN. & READY FOR SYN. 55 15JAN10 10MAR10
AIR & FLUE GAS HANDLING
ESP
ENGINEERING
U2EN570 ESP FOUNDATION DGR 20 11JUN08 30JUN08 ESP FOUNDATION DGR
U2BEE011 ENGINEERING - ESP 60 18JUL08 15SEP08 ENGINEERING - ESP
PROCUREMENT
U2BEP011 ORDERING OF MATERIAL - ESP 150 16SEP08 12FEB09
U2BEP012 MANUFACTURING- ESP 426 15NOV08 14JAN10
U2BEP013 DELIVERY AT SITE - ESP 315 21MAR09 29JAN10
CIVIL
U2BA220 FOUND FOR ESP 75 09JAN09 24MAR09
U2BA260 READINESS OF ESP FOUNDATION 12 14APR09 25APR09
ERECTION/COMMISSIONING
U2BEEC031 ERECTION- ESP COLUMNS & PANELS 75 01MAY09 14JUL09
U2BEEC0041 ERECTION-ESP ROOF, FUNNELS, INTERNALS & HOPPERS 195 30JUN09 13JAN10
U2BEEC0022 ESP INSULATION 90 14OCT09 13JAN10
U2BEEC032 ESP BOX-UP & READINESS FOR BLU 0 13JAN10

Start Date 01MAR08 DAR7 Sheet 27 of 55


Early Bar
Finish Date 17APR10 Date Revision Checked Approved
Float Bar
Data Date 18MAR08
Run Date 10SEP08 23:58 Progress Bar
2 X 80 MW CPP - DARIBA SMELTER COMPL
Critical Activity

Classic Schedule Layout


© Primavera Systems, Inc.
PDF created with pdfFactory Pro trial version www.pdffactory.com
Activity Activity Plan Plan Plan 2008
MAR APR MAY JUN JUL AUG
ID Description Dur Start Finish 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11
U2BEEC0051 ERECTION-RECTIFIER SYSTEM & OTHER ACT. FOR CF/SY 60 14JAN10 14MAR10
U2BEEC013 ESP READINESS FOR CF 0 14MAR10
U2BEEC014 ESP READINESS FOR SYN. 0 14MAR10
DAMPER, GATE & ACTUATOR
ENGINEERING
U2BAE011 DAMPERS, GATES, ACTUATORS - ENGG. 30 22JUN08 21JUL08 DAMPERS, GATES, ACTUATORS - ENGG.
PROCUREMENT
U2BAP011 ORDG. OF MTRL - DAMPERS, GATES, ACTUATORS 90 22JUL08 19OCT08 ORDG. OF MTRL - DAMPERS, GATES, ACTUATORS
U2BAP012 MANUFACTURING - DAMPERS, GATES, ACTUATORS 330 20OCT08 14SEP09
U2BAP013 SITE DELIVERY - DAMPERS, GATES, ACTUATORS 36 24AUG09 28SEP09
ERECTION/COMMISSIONING
U2BAEC011 EREC. COMPLN. - DAMPERS, GATES, ACTUATORS 75 14OCT09 27DEC09
FAN
ENGINEERING
U2EN580 FAN FOUNDATION ENGG 30 01JUL08 30JUL08 FAN FOUNDATION ENGG
U2BRE011 FANS FD/ID/PA - ENGINEERING 30 16JUL08 14AUG08 FANS FD/ID/PA - ENGINEERING
U2FAME011 ENGINEERING - FAN MOTOR 35 21SEP08 25OCT08
PROCUREMENT
U2BRP011 ORDERING OF MATERIAL - FANS 60 15AUG08 13OCT08 ORDERING OF MATERIAL - FANS
U2BRP013 MANUFACTURING - FANS 400 13NOV08 17DEC09
U2FAMP011 MANUFACTURING - FAN MOTOR 150 24JAN09 22JUN09
U2BRP012 RECEIPT OF MATERIAL AT WORKS - FAN 90 13MAR09 10JUN09
U2BRP015 DELIVERY AT SITE - FD FAN 150 16JUN09 12NOV09
U2FAMP012 DELIVERY TO SITE - FAN MOTOR 15 23JUN09 07JUL09
U2BRP014 DELIVERY AT SITE - ID FAN 75 15AUG09 28OCT09
U2BRP016 DELIVERY AT SITE - PA FAN 130 20AUG09 27DEC09
CIVIL
U2BA230 FOUND FOR FD,PA,ID FANS - UPTO GL 60 19FEB09 19APR09
U2BA143 FOUND FOR FD,ID FANS - ABOVE GL 45 09SEP09 23OCT09
U2BA155 FOUND FOR PA FANS - ABOVE GL 30 04OCT09 02NOV09
U2BA175 READINESS OF FD & ID FAN FOUNDATION 8 24OCT09 31OCT09
U2BA270 READINESS OF PA FAN FOUNDATION 5 03NOV09 07NOV09
ERECTION/COMMISSIONING
U2BREC011 ERECTION OF ID FAN 60 27SEP09 25NOV09
U2FAMEC011 ERECTION - FAN MOTOR 20 01NOV09 20NOV09
U2BREC012 ERECTION OF FD FAN 60 06NOV09 04JAN10
U2BREC013 ERECTION OF PA FAN 60 18NOV09 16JAN10
U2FAMEC012 COMMISSIONING - FAN MOTOR 1 21NOV09 21NOV09
U2BREC015 ID FAN - PRECOMMISSIONING 2 26NOV09 27NOV09

Start Date 01MAR08 DAR7 Sheet 28 of 55


Early Bar
Finish Date 17APR10 Date Revision Checked Approved
Float Bar
Data Date 18MAR08
Run Date 10SEP08 23:58 Progress Bar
2 X 80 MW CPP - DARIBA SMELTER COMPL
Critical Activity

Classic Schedule Layout


© Primavera Systems, Inc.
PDF created with pdfFactory Pro trial version www.pdffactory.com
Activity Activity Plan Plan Plan 2008
MAR APR MAY JUN JUL AUG
ID Description Dur Start Finish 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11
U2BREC016 FD FAN - PRECOMMISSIONING 2 15JAN10 16JAN10
U2BREC017 PA FAN - PRECOMMISSIONING 2 17JAN10 18JAN10
AIR-HEATER
ENGINEERING
U2BHE011 ENGG. - AIR HEATER 60 16JUL08 13SEP08 ENGG. - AIR HEATER
PROCUREMENT
U2BHP011 ORDERING OF MATERIAL - AIR HEATER 50 26JUL08 13SEP08 ORDERING OF MATERIAL - AIR HEATER
U2BHP013 MANUFACTURING - AIR HEATER 335 13NOV08 13OCT09
U2BHP012 RECEIPT OF MATERIAL AT WORKS - AIR HEATER 70 02JAN09 12MAR09
U2BHP014 DELIVERY AT SITE - AIR HEATER 130 21JUN09 28OCT09
ERECTION/COMMISSIONING
U2BHEC011 ERECTION- AIR HEATER 82 18AUG09 07NOV09
U2BHEC012 PRE-COMMISSIONING-AIRHEATER 35 23NOV09 27DEC09
U2BHEC013 READINESS FOR BLU- AIR HEATER 2 28DEC09 29DEC09
DUCTING
ENGINEERING
U2BTE011 ENGINEERING - DUCTING 30 25AUG08 23SEP08
PROCUREMENT
U2BTP011 MANUFACTURING-DUCTING 360 23DEC08 17DEC09
U2BTP012 DESPATCH-DUCTING 162 21JUL09 29DEC09
CIVIL
U2BA240 FOUND FOR OTHER AUX & DUCTS 45 29SEP09 12NOV09
ERECTION/COMMISSIONING
U2BTEC011 ERECTION - DUCTING 70 10NOV09 18JAN10
ELECTRICAL
ENGINEERING
U2REE011 ENGINEERING - ELECTRICAL 25 05JUN08 29JUN08 ENGINEERING - ELECTRICAL
PROCUREMENT
U2REP011 ORDERING - ELECTRICAL 75 30JUN08 12SEP08 ORDERING - ELECTRICAL
U2REP012 MANUFACTURING - ELECTRICAL 415 28OCT08 16DEC09
U2REP013 DELIVERY - ELECTRICAL 90 28SEP09 26DEC09
ERECTION/COMMISSIONING
U2REEC011 CABLE TRAY LAYING & CABLING 70 13OCT09 21DEC09
U2REEC012 MCC ERECTION & COMMISSIONING 20 28OCT09 16NOV09
U2REEC013 ERECTION & PRE-COMMISSIONING - REQD. FOR BLU 70 28OCT09 05JAN10
U2REEC014 ERECTION & PRE-COMMISSIONING - REQD. FOR SYN. 80 27NOV09 14FEB10
C&I
ENGINEERING
U2RIE011 ENGINEERING - C&I 45 16JUN08 30JUL08 ENGINEERING - C&I
PROCUREMENT
U2RIP011 ORDERING - C&I 50 31JUL08 18SEP08 ORDERING - C&I
Start Date 01MAR08 DAR7 Sheet 29 of 55
Early Bar
Finish Date 17APR10 Date Revision Checked Approved
Float Bar
Data Date 18MAR08
Run Date 10SEP08 23:58 Progress Bar
2 X 80 MW CPP - DARIBA SMELTER COMPL
Critical Activity

Classic Schedule Layout


© Primavera Systems, Inc.
PDF created with pdfFactory Pro trial version www.pdffactory.com
Activity Activity Plan Plan Plan 2008
MAR APR MAY JUN JUL AUG
ID Description Dur Start Finish 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11
U2RIP012 MANUFACTURING - C&I 420 28NOV08 21JAN10
U2RIP013 DELIVERY - C&I 125 01OCT09 02FEB10
ERECTION/COMMISSIONING
U2RIEC011 CABLING 72 18OCT09 28DEC09
U2RIEC012 ERECTION & PRE-COMMISSIONING - REQD. FOR BLU 31 15DEC09 14JAN10
U2RIEC013 ERECTION & PRE-COMMISSIONING - REQD. FOR SYN. 84 15DEC09 08MAR10
PULVERIZING
MILLS
ENGINEERING
U2MIE011 ENGINEERING- MILLS 30 06JUL08 04AUG08 ENGINEERING- MILLS
U2MIME011 ENGINEERING - MILL MOTOR 35 21SEP08 25OCT08
U2EN590 CIVIL DRG FOR MILL FOUNDATION 30 09OCT08 07NOV08
PROCUREMENT
U2MIP011 INDENTING OF MATERIAL-MILLS 45 05AUG08 18SEP08 INDENTING OF MATERIAL-MILLS
U2MIP012 ORDERING OF MATERIAL-MILLS 60 04SEP08 02NOV08
U2MIP013 RECEIPT OF MATERIAL AT WORKS-MILLS 150 03NOV08 01APR09
U2MIMP011 MANUFACTURING - MILL MOTOR 150 24JAN09 22JUN09
U2MIP014 MANUFACTURING-MILLS 285 03MAR09 12DEC09
U2MIMP012 DELIVERY TO SITE - MILL MOTOR 15 23JUN09 07JUL09
U2MIP015 DESPATCH & DELIVERY AT SITE - MILLS 100 19SEP09 27DEC09
CIVIL
U2BU140 FOUNDATION OF MILLS ( UPTO GL ) 60 30APR09 28JUN09
U2BU145 FOUNDATION OF MILLS ( ABOVE GL ) 40 24OCT09 02DEC09
U2BU160 RELEASE FRONT TO BHEL FOR MILL ERECTION 10 03DEC09 12DEC09
ERECTION/COMMISSIONING
U2MIEC012 MILLS ERECTION 85 13DEC09 07MAR10
U2MIMEC011 ERECTION - MILL MOTOR 30 13DEC09 11JAN10
U2MIMEC012 COMMISSIONING - MILL MOTOR 5 12JAN10 16JAN10
U2MIEC013 MILLS COMMISSIONING 7 08MAR10 14MAR10
POWER CYCLE
STEAM TURBINE
ENGINEERING
U2STE011 ENGINEERING- STEAM TURBINE 198 28MAR08 11OCT08
PROCUREMENT
U2STP011 ORDERING OF MATERIAL- ST 225 29APR08 09DEC08 ORDERING OF MATERIAL- ST
U2STP012 RECEIPT OF MATERIAL AT WORKS- ST 380 29MAY08 12JUN09 RECEIPT OF MATERIAL AT WORKS- ST
U2STP013 MANUFACTURING- ST 260 12DEC08 28AUG09
U2STP0041 AVL. SUB-ASSEMBLIES & PREPARATION FOR MRT 35 05SEP09 09OCT09
U2STP014 MECHANICAL RUN TEST COMPLETION 7 10OCT09 16OCT09

Start Date 01MAR08 DAR7 Sheet 30 of 55


Early Bar
Finish Date 17APR10 Date Revision Checked Approved
Float Bar
Data Date 18MAR08
Run Date 10SEP08 23:58 Progress Bar
2 X 80 MW CPP - DARIBA SMELTER COMPL
Critical Activity

Classic Schedule Layout


© Primavera Systems, Inc.
PDF created with pdfFactory Pro trial version www.pdffactory.com
Activity Activity Plan Plan Plan 2008
MAR APR MAY JUN JUL AUG
ID Description Dur Start Finish 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11
U2STP015 DESPATCH & DELIVERY AT SITE - ST 13 17OCT09 29OCT09
ERECTION/COMMISSIONING
U2STEC011 ERECTION- ST 40 19NOV09 28DEC09
U2STEC012 TURBINE - LIVE STEAM VALVE ERECTION 10 19DEC09 28DEC09
U2STEC013 TURBINE BOX UP 2 29DEC09 30DEC09
U2STEC0041 TURBINE - OTHER ACT. & READINESS FOR SYN. 30 31DEC09 30JAN10
GENERATOR & AUX.
ENGINEERING
U2GEE011 ENGINEERING- GEN. & AUX. 140 28MAR08 14AUG08
PROCUREMENT
U2GEP011 ORDERING OF MATERIAL- GEN. & AUX. 56 29APR08 23JUN08 ORDERING OF M
U2GEP012 RECEIPT OF MATERIAL AT WORKS- GEN. & AUX. 365 10JUN08 09JUN09 RECEIPT OF MATERIAL AT WORKS- GEN. & AUX.
U2GEP013 MANUFACTURING- GEN. & AUX. 322 19NOV08 06OCT09
U2GEP014 ASSEMBLY & TESTING- GEN. & AUX. 35 07OCT09 10NOV09
U2GEP015 DESPATCH & DELIVERY AT SITE - GEN. & AUX. 6 11NOV09 16NOV09
ERECTION/COMMISSIONING
U2GEEC011 GENERATOR - ERECTION 35 17NOV09 21DEC09
U2GEEC012 GEN AUX. ERECTION INCLUDING GCP, GRP 20 27NOV09 16DEC09
U2GEEC013 GENERATOR PRE- & FINAL ALIGNMENT 5 29DEC09 02JAN10
BFP & BOOSTER PUMP
ENGINEERING
U2BFE011 ENGINEERING- BFP & BOOSTER PUMP 120 12MAY08 08SEP08
U2BFME011 ENGINEERING - BFP MOTOR 35 21SEP08 25OCT08
PROCUREMENT
U2BFP011 ORDERING - BFP DD ITEMS 60 20MAY08 18JUL08 ORDERING - BFP DD ITEMS
U2BFP012 MFRG / SITE DELIVERY - BFP SUB-VENDOR & DD ITEMS 425 30MAY08 28JUL09
U2BFMP011 MANUFACTURING - BFP MOTOR 150 24JAN09 22JUN09
U2BFP013 MANUFACTURING - BFP & BOOSTER PUMP 84 11MAR09 02JUN09
U2BFP014 ASSEMBLY & TESTING - BFP & BOOSTER PUMP 28 27MAY09 23JUN09
U2BFP015 DESPATCH & DELIVERY AT SITE- BFP & BOOSTER PUMP 14 17JUN09 30JUN09
U2BFMP012 DELIVERY TO SITE - BFP MOTOR 15 23JUN09 07JUL09
CIVIL
U2TG145 BFP FOUNDATION WORKS 45 11MAR09 24APR09
U2TG185 READINESS FOR BFP ERECTION 0 08JUL09
ERECTION/COMMISSIONING
U2BFMEC011 ERECTION - BFP MOTOR 10 25AUG09 03SEP09
U2BFEC011 ERECTION - BFP 22 30AUG09 20SEP09
U2BFEC012 ERECTION - BOOSTER PUMP 10 30AUG09 08SEP09
U2BFMEC012 COMMISSIONING - BFP MOTOR 2 04SEP09 05SEP09

Start Date 01MAR08 DAR7 Sheet 31 of 55


Early Bar
Finish Date 17APR10 Date Revision Checked Approved
Float Bar
Data Date 18MAR08
Run Date 10SEP08 23:58 Progress Bar
2 X 80 MW CPP - DARIBA SMELTER COMPL
Critical Activity

Classic Schedule Layout


© Primavera Systems, Inc.
PDF created with pdfFactory Pro trial version www.pdffactory.com
Activity Activity Plan Plan Plan 2008
MAR APR MAY JUN JUL AUG
ID Description Dur Start Finish 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11
U2BFEC013 PRE-COMMISSIONING - BFP & BOOSTER PUMP 3 23OCT09 25OCT09
CEP
ENGINEERING
U2CEE011 ENGINEERING- CEP 120 09MAY08 05SEP08 ENGINEERING- CEP
U2CEME011 ENGINEERING - CEP MOTOR 35 21SEP08 25OCT08
PROCUREMENT
U2CEP011 ORDERING - CEP DD ITEMS 59 20MAY08 17JUL08 ORDERING - CEP DD ITEMS
U2CEP012 MFRG & DELIVERY AT SITE - BFP SUB-VENDOR ITEMS 286 18JUL08 29APR09 MFRG & DELIVERY AT SITE - BFP SUB-VENDOR ITEMS
U2CEMP011 MANUFACTURING - CEP MOTOR 150 24JAN09 22JUN09
U2CEP013 MANUFACTURING- CEP 84 30APR09 22JUL09
U2CEMP012 DELIVERY TO SITE - CEP MOTOR 15 23JUN09 07JUL09
U2CEP014 ASSEMBLY & TESTING- CEP 21 23JUL09 12AUG09
U2CEP015 DESPATCH & DELIVERY AT SITE- CEP 7 13AUG09 19AUG09
CIVIL
U2TG180 CEP FOUNDATION WORKS 30 26JUL09 24AUG09
ERECTION/COMMISSIONING
U2CEMEC011 ERECTION - CEP MOTOR 10 25AUG09 03SEP09
U2CEEC011 ERECTION- CEP 25 30AUG09 23SEP09
U2CEMEC012 COMMISSIONING - CEP MOTOR 2 04SEP09 05SEP09
U2CEEC012 PRE-COMMISSIONING - CEP 15 23OCT09 06NOV09
LUBE OIL PUMP & TANK
ENGINEERING
U2LOE011 ENGINEERING- LUBEOILPUMPS & TANKS 30 16JUL08 14AUG08 ENGINEERING- LUBEOILPUMPS & TANKS
PROCUREMENT
U2LOP011 INDENT&ORDER OF MATERIAL- LUBEOILPUMPS & TANKS 48 31JUL08 16SEP08 INDENT&ORDER OF MATERIAL- LUBEOILPUMPS & TANKS
U2LOP012 MANUFACTURING- LUBEOILPUMPS & TANKS 256 16DEC08 28AUG09
U2LOP013 RECEIPT OF MATERIAL AT SITE- LUBEOILPUMPS & TANK 11 29AUG09 08SEP09
ERECTION/COMMISSIONING
U2LOEC011 ERECTION- LUBEOILPUMPS & TANKS 25 09SEP09 03OCT09
U2LOEC012 PRE-COMMISSIONING- LUBEOILPUMPS & TANKS 9 04OCT09 12OCT09
DRAIN COOLER
ENGINEERING
U2DCE011 ENGINEERING - DRAIN COOLER 10 18MAR08 27MAR08
PROCUREMENT
U2DCP011 ORDERING - DRAIN COOLER 33 17APR08 19MAY08
U2DCP012 MFRG. & DELIVERY AT WORK - DRAIN COOLER MATERIAL 184 20MAY08 19NOV08
U2DCP013 MANUFACTURING - DRAIN COOLER 175 20NOV08 13MAY09
U2DCP014 TESTING - DRAIN COOLER 7 14MAY09 20MAY09
U2DCP015 DISPATCH & DELIVERY AT SITE - DRAIN COOLER 7 21MAY09 27MAY09

Start Date 01MAR08 DAR7 Sheet 32 of 55


Early Bar
Finish Date 17APR10 Date Revision Checked Approved
Float Bar
Data Date 18MAR08
Run Date 10SEP08 23:58 Progress Bar
2 X 80 MW CPP - DARIBA SMELTER COMPL
Critical Activity

Classic Schedule Layout


© Primavera Systems, Inc.
PDF created with pdfFactory Pro trial version www.pdffactory.com
Activity Activity Plan Plan Plan 2008
MAR APR MAY JUN JUL AUG
ID Description Dur Start Finish 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11
ERECTION/COMMISSIONING
U2DCEC011 ERECTION- DRAIN COOLERS 26 04JUN09 29JUN09
U2DCEC012 PRE-COMMISSIONING- DRAIN COOLERS 2 30JUN09 01JUL09
AOP, JOP, EOP, OIL PURIFICATION
ENGINEERING
U2JEE011 ENGINEERING - STG AUX( AOP,EOP,JOP,PURFN) 30 18MAR08 16APR08
PROCUREMENT
U2JEP011 ORDERING - STG AUX 69 02APR08 09JUN08
U2JEP012 MANUFACTURING - STG AUX 254 10JUN08 18FEB09 MANUFACTURING - STG AUX
U2JEP013 INSPECTION - STG AUX 84 08JAN09 01APR09
U2JEP014 DESPATCH & DELIVERY AT SITE - STG AUX 42 19MAR09 29APR09
ERECTION/COMMISSIONING
U2JEEC011 ERECTION- STG AUX 40 30AUG09 08OCT09
U2JEEC012 PRE-COMMISSIONING-STG AUX 9 09OCT09 17OCT09
SURFACE CONDENSOR
ENGINEERING
U2CHE011 ENGINEERING - COND. & HOTWELL 90 18MAR08 15JUN08
PROCUREMENT
U2CHP011 ORDERING OF MATERIAL - COND. & HOTWELL 62 08APR08 08JUN08
U2CHP012 RECEIPT OF MATERIAL AT WORKS - COND. & HOTWELL 255 09JUN08 18FEB09
U2CHP013 MANUFACTURING - COND. & HOTWELL 112 19FEB09 10JUN09
U2CHP014 TESTING - COND. & HOTWELL 7 11JUN09 17JUN09
U2CHP015 DESPATCH & DELIVERY AT SITE - COND. & HOTWELL 7 18JUN09 24JUN09
CIVIL
U2TG121 CONDENSER FOUNDATION WORKS 30 24JUL09 22AUG09
U2TG190 READINESS FOR CONDENSER FOUNDATION 0 29AUG09
ERECTION/COMMISSIONING
U2CHEC011 ERECTION - COND. & HOTWELL 23 30AUG09 21SEP09
U2CHEC012 PRE-COMMISSONING - COND. & HOTWELL 31 22SEP09 22OCT09
U2SCEC016 HP BYPASS STATION ERECTION 15 09DEC09 23DEC09
U2SCEC021 COMMISSIONING OF HP BYPASS SYSTEM. 1 20FEB10 20FEB10
GS CONDENSOR
ENGINEERING
U2GSE011 ENGINEERING - GS CONDENSOR 10 18MAR08 27MAR08
PROCUREMENT
U2GSP011 ORDERING OF MATERIAL - GS CONDENSOR 74 28MAR08 09JUN08
U2GSP012 MFRG. & RECPT. OF MTRL. AT WORKS - GS CONDENSOR 254 10JUN08 18FEB09
U2GSP013 MANUFACTURING - GS CONDENSOR 112 19FEB09 10JUN09
U2GSP014 TESTING - GS CONDENSOR 7 11JUN09 17JUN09
U2GSP015 DESPATCH & DELIVERY AT SITE - GS CONDENSOR 7 18JUN09 24JUN09

Start Date 01MAR08 DAR7 Sheet 33 of 55


Early Bar
Finish Date 17APR10 Date Revision Checked Approved
Float Bar
Data Date 18MAR08
Run Date 10SEP08 23:58 Progress Bar
2 X 80 MW CPP - DARIBA SMELTER COMPL
Critical Activity

Classic Schedule Layout


© Primavera Systems, Inc.
PDF created with pdfFactory Pro trial version www.pdffactory.com
Activity Activity Plan Plan Plan 2008
MAR APR MAY JUN JUL AUG
ID Description Dur Start Finish 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11
ERECTION/COMMISSIONING
U2GSEC011 ERECTION - GS CONDENSOR 45 25JUN09 08AUG09
U2GSEC012 COMMISSIONING - GS CONDENSOR 13 09AUG09 21AUG09
LP HEATERS I & II
ENGINEERING
U2LPE011 ENGINEERING - LP HEATERS 10 18MAR08 27MAR08
PROCUREMENT
U2LPP011 ORDERING OF MATERIAL - LP HEATERS 74 28MAR08 09JUN08
U2LPP012 MFRG. & RECPT. OF MTRL. AT WORKS - LP HEATERS 196 10JUN08 22DEC08 MFRG. & RECPT. OF MTRL. AT WORKS - LP HEATERS
U2LPP013 MANUFACTURING - LP HEATERS 168 23DEC08 08JUN09
U2LPP014 TESTING - LP HEATERS 7 09JUN09 15JUN09
U2LPP015 DESPATCH & DELIVERY AT SITE - LP HEATERS 7 16JUN09 22JUN09
ERECTION/COMMISSIONING
U2LPEC011 ERECTION - LP HEATERS 40 23JUN09 01AUG09
U2LPEC012 PRE-COMMISSIONING - LP HEATERS 18 02AUG09 19AUG09
HP HEATERS IV & V
ENGINEERING
U2HPE011 ENGINEERING - HP HEATERS 10 18MAR08 27MAR08
PROCUREMENT
U2HPP011 ORDERING OF MATERIAL - HP HEATERS 74 28MAR08 09JUN08
U2HPP012 MFRG. & RECPT. OF MTRL. AT WORKS - HP HEATERS 184 10JUN08 10DEC08 MFRG. & RECPT. OF MTRL. AT WORKS - HP HEATERS
U2HPP013 MANUFACTURING - HP HEATERS 175 11DEC08 03JUN09
U2HPP014 TESTING - HP HEATERS 14 04JUN09 17JUN09
U2HPP015 DESPATCH & DELIVERY AT SITE - HP HEATERS 7 18JUN09 24JUN09
ERECTION/COMMISSIONING
U2HPEC011 ERECTION - HP HEATERS 21 25JUN09 15JUL09
U2HPEC012 PRE-COMMISSIONING - HEATERS 18 16JUL09 02AUG09
DE-AERATOR HEADER
ENGINEERING
U2DHE011 ENGINEERING - DE-AERATOR HEADER 10 18MAR08 27MAR08
PROCUREMENT
U2DHP011 ORDERING OF MATERIAL - DE-AERATOR HEADER 74 28MAR08 09JUN08
U2DHP012 MFRG. & RECPT. OF MTRL. AT WORKS - DE-AER. HEAD. 170 10JUN08 26NOV08
U2DHP013 MANUFACTURING - DE-AERATOR HEADER 182 27NOV08 27MAY09
U2DHP014 TESTING - DE-AERATOR HEADER 14 28MAY09 10JUN09
U2DHP015 DESPATCH & DELIVERY AT SITE - DE-AERATOR HEADER 14 11JUN09 24JUN09
CIVIL
U2TG195 DEAERATOR FOUNDATION 25 11JUN09 05JUL09
ERECTION/COMMISSIONING
U2DHEC011 ERECTION - DE-AERATOR HEADER 30 06JUL09 04AUG09

Start Date 01MAR08 DAR7 Sheet 34 of 55


Early Bar
Finish Date 17APR10 Date Revision Checked Approved
Float Bar
Data Date 18MAR08
Run Date 10SEP08 23:58 Progress Bar
2 X 80 MW CPP - DARIBA SMELTER COMPL
Critical Activity

Classic Schedule Layout


© Primavera Systems, Inc.
PDF created with pdfFactory Pro trial version www.pdffactory.com
Activity Activity Plan Plan Plan 2008
MAR APR MAY JUN JUL AUG
ID Description Dur Start Finish 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11
U2DHEC012 PRE-COMMISSIONING - DE-AERATOR HEADER 2 05AUG09 06AUG09
DE-AERATOR STORAGE TANK
ENGINEERING
U2DSE011 ENGINEERING - DE-AERATOR STOR. TANK 10 18MAR08 27MAR08
PROCUREMENT
U2DSP011 ORDERING OF MATERIAL - DE-AERATOR STOR. TANK 74 28MAR08 09JUN08
U2DSP012 MFRG. & RECPT. OF MTRL. AT WORKS - DE-AR. SO. TK 170 10JUN08 26NOV08
U2DSP013 MANUFACTURING - DE-AERATOR STOR. TANK 182 27NOV08 27MAY09
U2DSP014 TESTING - DE-AERATOR STOR. TANK 14 28MAY09 10JUN09
U2DSP015 DESPATCH & DELIVERY AT SITE - DE-AR. SO. TK 14 11JUN09 24JUN09
CIVIL
U2TG175A10 DEAERATOR FOUNDATION 25 11JUN09 05JUL09
ERECTION/COMMISSIONING
U2DSEC011 ERECTION - DE-AERATOR STORAGE TANK 30 06JUL09 04AUG09
U2DSEC012 PRE-COMMISSIONING - DE-AREATOR STORAGE TANK 2 05AUG09 06AUG09
OIL & AIR COOLER
ENGINEERING
U2OAE011 ENGINEERING - OIL & AIR COOLER 10 18MAR08 27MAR08
PROCUREMENT
U2OAP011 ORDERING OF MATERIAL - OIL & AIR COOLER 74 28MAR08 09JUN08
U2OAP012 MFRG. & RECPT. OF MTRL. AT WORKS - OIL & AIR COO 205 20MAY08 10DEC08
U2OAP013 MANUFACTURING - OIL & AIR COOLER 190 19NOV08 27MAY09
U2OAP014 TESTING - OIL & AIR COOLER 21 21MAY09 10JUN09
U2OAP015 DESPATCH & DELIVERY AT SITE - OIL & AIR COOLER 26 23MAY09 17JUN09
ERECTION/COMMISSIONING
U2OAEC011 ERECTION - OIL & AIR COOLER 40 02OCT09 10NOV09
U2OAEC012 PRE-COMMISSIONING - OIL & AIR COOLER 1 11NOV09 11NOV09
STEAM JET AIR EJECTOR
ENGINEERING
U2SJE011 ENGINEERING - SJAE 17 18MAR08 03APR08
PROCUREMENT
U2SJP011 ORDERING OF MATERIAL - SJAE 46 04APR08 19MAY08
U2SJP012 MFRG. & RECPT. OF MTRL. AT WORKS - SJAE 198 20MAY08 03DEC08
U2SJP013 MANUFACTURING - SJAE 147 04DEC08 29APR09
U2SJP014 TESTING - SJAE 7 30APR09 06MAY09
U2SJP015 DESPATCH & DELIVERY AT SITE - SJAE 7 07MAY09 13MAY09
ERECTION/COMMISSIONING
U2SJEC011 ERECTION - EJECTOR SYSTEM 40 02OCT09 10NOV09
U2SJEC012 PRE-COMMISSIONING - EJECTOR SYSTEM 1 11NOV09 11NOV09

Start Date 01MAR08 DAR7 Sheet 35 of 55


Early Bar
Finish Date 17APR10 Date Revision Checked Approved
Float Bar
Data Date 18MAR08
Run Date 10SEP08 23:58 Progress Bar
2 X 80 MW CPP - DARIBA SMELTER COMPL
Critical Activity

Classic Schedule Layout


© Primavera Systems, Inc.
PDF created with pdfFactory Pro trial version www.pdffactory.com
Activity Activity Plan Plan Plan 2008
MAR APR MAY JUN JUL AUG
ID Description Dur Start Finish 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11
ELECTRICAL
ENGINEERING
U2HEE011 ENGINEERING - ELECTRICAL 47 18MAY08 03JUL08 ENGINEERING - ELECTRICAL
PROCUREMENT
U2HEP011 ORDERING - ELECTRICAL 71 04JUL08 12SEP08 ORDERING - ELECTRICAL
U2HEP012 MANUFACTURING - ELECTRICAL 330 22OCT08 16SEP09
U2HEP013 DELIVERY - ELECTRICAL 92 29JUN09 28SEP09
ERECTION/COMMISSIONING
U2HEEC011 CABLE TRAY LAYING & CABLING 166 14JUL09 26DEC09
U2HEEC012 ERECTION & PRE-COMMISSIONING - REQD. FOR BLU 30 29JUL09 27AUG09
U2HEEC013 ERECTION & PRE-COMMISSIONING - REQD. FOR SYN. 119 28AUG09 24DEC09
C&I
ENGINEERING
U2HIE011 ENGINEERING - C&I 45 04JUN08 18JUL08 ENGINEERING - C&I
PROCUREMENT
U2HIP011 ORDERING - C&I 45 19JUL08 01SEP08 ORDERING - C&I
U2HIP012 MANUFACTURING - C&I 360 11NOV08 05NOV09
U2HIP013 DELIVERY - C&I 180 09JUN09 05DEC09
ERECTION/COMMISSIONING
U2HIEC011 CABLING 166 19JUL09 31DEC09
U2HIEC012 ERECTION & PRE-COMMISSIONING - REQD. FOR BLU 45 07SEP09 21OCT09
U2HIEC013 ERECTION & PRE-COMMISSIONING - REQD. FOR SYN. 60 22OCT09 20DEC09
PIPING & OTHER AUXILIARY SYSTEMS
P&IDs & LAYOUTs
ENGINEERING
U2PDE013 ENGINEERING - TG HALL EQPT. LAYOUTS & OTHER ENGG 90 01JUN08 29AUG08
U2PDE012 ENGINEERING - TG HOUSE PIPING/TG INTEGRAL PIPING 90 08JUN08 05SEP08
U2PDE011 ENGINEERING - BOILER INTERG. PIPG 90 16JUN08 13SEP08 ENGINEERING - BOILER INTERG. PIPG
BOILER INTEGRAL PIPING & UTILITY PIPING (SG)
ENGINEERING
U2PBE011 ENGINEERING - BLR. INTERG. & UTIL. PIPG. 90 01JAN09 31MAR09
PROCUREMENT
U2PBP011 MTRL. RCPT. AT WORKS-BLR. INTERG. & UTIL. PIPG. 57 25MAY09 20JUL09
U2PBP012 MANUFACTURING - BLR. INTERG. & UTIL. PIPG. 151 24AUG09 21JAN10
U2PBP013 DESPATCH & DELIVERY - BLR. INTERG. & UTIL. PIPG. 174 24AUG09 13FEB10
ERECTION/COMMISSIONING
U2PBEC011 ERCN.,HT&INSUL OF BI PIPG & UTIL-ACW,SA,IA - BLU 115 08SEP09 31DEC09
U2PBEC012 ERCN., HT & INSULATION OF BI PIPING FOR SB/SVF 80 23OCT09 10JAN10
U2PBEC013 ERCN., HT & INSUL. OF OTHER UTILITY PIPG 60 31DEC09 28FEB10

Start Date 01MAR08 DAR7 Sheet 36 of 55


Early Bar
Finish Date 17APR10 Date Revision Checked Approved
Float Bar
Data Date 18MAR08
Run Date 10SEP08 23:58 Progress Bar
2 X 80 MW CPP - DARIBA SMELTER COMPL
Critical Activity

Classic Schedule Layout


© Primavera Systems, Inc.
PDF created with pdfFactory Pro trial version www.pdffactory.com
Activity Activity Plan Plan Plan 2008
MAR APR MAY JUN JUL AUG
ID Description Dur Start Finish 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11
TG HOUSE PIPING & TG INTEGRAL PIPING (PCP)
ENGINEERING
U2PHE011 ENGINEERING- TG HOUSE & TG INTEGRAL PIPG 90 01JAN09 31MAR09
PROCUREMENT
U2PHP011 INDG/ORDG OF MTRL- TG HOUSE & TG INTEGRAL PIPG 54 01APR09 24MAY09
U2PHP012 MTRL RCPT AT WORKS - TG HOUSE & TG INTEGRAL PIPG 57 25MAY09 20JUL09
U2PHP013 MANUFACTURING - TG HOUSE & TG INTEGRAL PIPG 154 23AUG09 23JAN10
U2PHP014 DESP &DLRY AT SITE - TG HOUSE & TG INTEGRAL PIPG 175 23AUG09 13FEB10
ERECTION/COMMISSIONING
U2PHEC024 ERECTION OF FEED WATER PIPING 30 21SEP09 20OCT09
U2PHEC033 ERECTION OF CONDENSATE PIPING 38 22OCT09 28NOV09
U2PHEC028 HYDRO TEST OF FEED WATER PIPING 6 26OCT09 31OCT09
U2PHEC042 INSULATION OF FEED WATER PIPING 14 01NOV09 14NOV09
U2PHEC031 ERECTION OF MAIN STEAM PIPING 34 05NOV09 08DEC09
U2PHEC043 ERECTION OF AUX. STEAM PIPING 25 15NOV09 09DEC09
U2PHEC027 HYDRO TEST OF CONDENSATE PIPING 7 04DEC09 10DEC09
U2PHEC041 INSULATION OF CONDENSATE PIPING 7 09DEC09 15DEC09
U2PHEC034 HYDRO TEST OF AUX. STEAM PIPING 6 10DEC09 15DEC09
U2PHEC044 PRE-BOILER FLUSHING 7 11DEC09 17DEC09
U2PHEC052 ERCN,HT & INSUL. OF BALANCE PIPG - REQD. FOR BLU 34 11DEC09 13JAN10
U2PHEC025 HYDRO TEST OF MAIN STEAM PIPING 6 14DEC09 19DEC09
U2PHEC035 INSULATION OF AUX. STEAM PIPING 5 16DEC09 20DEC09
U2PHEC029 INSULATION OF MAIN STEAM PIPING 16 20DEC09 04JAN10
U2PHEC032 ERECTION OF EXTRACTION STEAM PIPING 38 04FEB10 13MAR10
U2PHEC036 ERECTION OF CONDENSOR AIR EVACUATION PIPING 31 14FEB10 16MAR10
U2PHEC039 ERECTION OF LUBE OIL PIPING 30 14FEB10 15MAR10
U2PHEC053 ERCN,HT & INSUL. OF BALANCE PIPG - REQD. FOR SYN 40 14FEB10 25MAR10
U2PHEC030 INSULATION OF EXTRACTION STEAM PIPING 12 14MAR10 25MAR10
U2PHEC038 INSULATION OF CONDENSOR AIR EVACUATION PIPING 5 17MAR10 21MAR10
HANGERS & SUPPORTS
ENGINEERING
U2HSE011 ENGINEERING - HANGERS & SUPPORTS 90 01JAN09 31MAR09
PROCUREMENT
U2HSP011 RECEIPT OF MTRL AT WORKS - HANGERS & SUPPORTS 57 25MAY09 20JUL09
U2HSP012 MANUFACTURING - HANGERS & SUPPORTS 154 23AUG09 23JAN10
U2HSP013 DESP & DLRY AT SITE - HANGERS & SUPPORTS 175 23AUG09 13FEB10
ERECTION/COMMISSIONING
U2HSEC012 ERECTION OF H & S - REQD. FOR BLU 62 13NOV09 13JAN10
U2HSEC011 ERECTION OF ACCESSIBLE PLATFORMS TO ERECT H & S 110 26NOV09 15MAR10

Start Date 01MAR08 DAR7 Sheet 37 of 55


Early Bar
Finish Date 17APR10 Date Revision Checked Approved
Float Bar
Data Date 18MAR08
Run Date 10SEP08 23:58 Progress Bar
2 X 80 MW CPP - DARIBA SMELTER COMPL
Critical Activity

Classic Schedule Layout


© Primavera Systems, Inc.
PDF created with pdfFactory Pro trial version www.pdffactory.com
Activity Activity Plan Plan Plan 2008
MAR APR MAY JUN JUL AUG
ID Description Dur Start Finish 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11
U2HSEC013 ERECTION OF H & S - REQD. FOR SYN. 25 01MAR10 25MAR10
HP DOSING SYSTEM
ENGINEERING
U2HDE011 ENGINEERING- HP DOSING STN. 90 01JAN09 31MAR09
PROCUREMENT
U2HDP011 INDENTING OF MATERIAL- HP DOSING STN. 24 01APR09 24APR09
U2HDP012 ORDERING OF MATERIAL- HP DOSING STN. 30 25APR09 24MAY09
U2HDP013 RECEIPT OF MATERIAL AT SITE- HP DOSING STN. 57 25MAY09 20JUL09
U2HDP014 MANUFACTURING - HP DOSING 90 25AUG09 22NOV09
U2HDP015 DESP & DLRY - HP DOSING 110 26AUG09 13DEC09
ERECTION/COMMISSIONING
U2HDEC011 ERECTION- HP DOSING STN. 20 14DEC09 02JAN10
U2HDEC012 COMMISSIONING- HP DOSING STN. 8 03JAN10 10JAN10
TANKS & VESSELS REL.
ENGINEERING
U2TVE011 ENGINEERING - TANKS & VESSELS 90 01JAN09 31MAR09
PROCUREMENT
U2TVP011 ORDERING - TANKS & VESSELS REL. 54 01APR09 24MAY09
U2TVP012 MANUFACTURING - TANKS & VESSELS REL. 93 23AUG09 23NOV09
U2TVP013 DESP & DLRY AT SITE - TANKS & VESSELS REL. 110 26AUG09 13DEC09
ERECTION/COMMISSIONING
U2TVEC011 ERECTION & COMMISSIONING - REQD. FOR BLU 30 14DEC09 12JAN10
U2TVEC012 ERECTION & COMMISSIONING - REQD. FOR SYN. 45 14DEC09 27JAN10
C&I
ENGINEERING
U2CIE011 ENGINEERING - CONTROL VALVES & FLOW ELEMENTS 25 06JUN08 30JUN08
U2PIE011 ENGINEERING - OTHER C&I 90 01JAN09 31MAR09
PROCUREMENT
U2CIP011 INDENTING & ORDERING - CONTROL VALVES 60 01JUL08 29AUG08 INDENTING & ORDERING - CONTROL VALVES
U2CIP012 INDENTING & ORDERING - FLOW ELEMENTS 45 01JUL08 14AUG08 INDENTING & ORDERING - FLOW ELEMENTS
U2PIP011 ORDERING - OTHER C&I 54 01APR09 24MAY09
U2PIP012 MANUFACTURING - OTHER C&I 154 23AUG09 23JAN10
U2PIP013 DESP & DLRY AT SITE - OTHER C&I 170 27AUG09 12FEB10
U2CIP013 RECEIPT AT SITE - CONTROL VALVES 15 30AUG09 13SEP09
U2CIP014 RECEIPT AT SITE - FLOW ELEMENTS 15 14SEP09 28SEP09
ERECTION/COMMISSIONING
U2CIEC011 ERCN. & COMMNG. - CONTROL VALVES REQD. FOR BLU 28 01JAN10 28JAN10
U2CIEC013 ERCN. & COMMNG. - FLOW ELEMENTS REQD. FOR BLU 24 05JAN10 28JAN10
U2PIEC011 ERECTION & COMMISSIONING - REQD. FOR SYN. 42 13FEB10 26MAR10
U2CIEC012 ERCN. & COMMNG. - CONTROL VALVES REQD. FOR SYN. 36 14FEB10 21MAR10
Start Date 01MAR08 DAR7 Sheet 38 of 55
Early Bar
Finish Date 17APR10 Date Revision Checked Approved
Float Bar
Data Date 18MAR08
Run Date 10SEP08 23:58 Progress Bar
2 X 80 MW CPP - DARIBA SMELTER COMPL
Critical Activity

Classic Schedule Layout


© Primavera Systems, Inc.
PDF created with pdfFactory Pro trial version www.pdffactory.com
Activity Activity Plan Plan Plan 2008
MAR APR MAY JUN JUL AUG
ID Description Dur Start Finish 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11
U2CIEC014 ERCN. & COMMNG. - FLOW ELEMENTS REQD. FOR SYN. 36 14FEB10 21MAR10
APRDS
ENGINEERING
U2APE011 ENGINEERING-APRDS 25 11JUN08 05JUL08 ENGINEERING-APRDS
PROCUREMENT
U2APP011 INDENTING & ORDERING OF MATERIAL-APRDS 55 06JUL08 29AUG08 INDENTING & ORDERING OF MATERIAL-APRDS
U2APP012 MANUFACTURING-APRDS 80 28NOV08 15FEB09
U2APP013 RECEIPT OF MATERIAL AT SITE-APRDS 20 26JUN09 15JUL09
ERECTION/COMMISSIONING
U2APEC011 ERECTION-APRDS 50 15NOV09 03JAN10
U2APEC012 COMM OF APRDC 10 04JAN10 13JAN10
LP DOSING SYSTEM
ENGINEERING
U2LDE011 ENGINEERING- HP/LP DOSING STN. 10 13JUN08 22JUN08 ENGINEERING- HP/LP DOSING STN.
PROCUREMENT
U2LDP011 INDENTING OF MATERIAL- LP DOSING STN. 10 28JUN08 07JUL08 INDENTING OF MATERIAL- LP DOSING STN.
U2LDP012 ORDERING OF MATERIAL- LP DOSING STN. 30 08JUL08 06AUG08 ORDERING OF MATERIAL- LP DOSING STN.
U2LDP013 RECEIPT OF MATERIAL AT SITE- LP DOSING STN. 45 13JUN09 27JUL09
ERECTION/COMMISSIONING
U2LDEC011 ERECTION - LP DOSING STN. 20 16NOV09 05DEC09
U2LDEC012 COMMISSIONING - LP DOSING STN. 8 03JAN10 10JAN10
MP
ENGINEERING
U2MPE011 ENGINEERING - MP 20 06JUN08 25JUN08 ENGINEERING - MP
PROCUREMENT
U2MPP011 INDENTING & ORDERING - ME BELLOWS 60 26JUN08 24AUG08 INDENTING & ORDERING - ME BELLOWS
U2MPP012 INDENTING & ORDERING - POWER CYCLE VALVES 60 26JUN08 24AUG08 INDENTING & ORDERING - POWER CYCLE VALVES
U2MPP013 INDENTING & ORDERING - STEAM TRAPS 45 26JUN08 09AUG08 INDENTING & ORDERING - STEAM TRAPS
U2MPP014 INDENTING & ORDERING - THERMAL INSULATION 30 21FEB09 22MAR09
U2MPP017 RECEIPT AT SITE - STEAM TRAPS 15 22APR09 06MAY09
U2MPP016 RECEIPT AT SITE - POWER CYCLE VALVES 15 22MAY09 05JUN09
U2MPP015 RECEIPT AT SITE - ME BELLOWS 15 27MAY09 10JUN09
U2MPP018 RECEIPT AT SITE - THERMAL INSULATION 15 19SEP09 03OCT09
ERECTION/COMMISSIONING
U2MPEC011 ERECTION OF ME BELLOWS- REQD. FOR BLU 25 05DEC09 29DEC09
U2MPEC014 ERECTION OF THERMAL INSULATION - REQD. FOR BLU 49 07DEC09 24JAN10
U2MPEC012 ERECTION OF POWER CYCLE VALVES - REQD. FOR BLU 25 01JAN10 25JAN10
U2MPEC013 ERECTION OF STEAM TRAPS - REQD. FOR BLU 25 01JAN10 25JAN10
U2MPEC018 ERECTION OF THERMAL INSULATION - REQD. FOR SYN. 71 14JAN10 25MAR10
U2MPEC015 ERECTION OF ME BELLOWS- REQD. FOR SYN. 36 04FEB10 11MAR10
Start Date 01MAR08 DAR7 Sheet 39 of 55
Early Bar
Finish Date 17APR10 Date Revision Checked Approved
Float Bar
Data Date 18MAR08
Run Date 10SEP08 23:58 Progress Bar
2 X 80 MW CPP - DARIBA SMELTER COMPL
Critical Activity

Classic Schedule Layout


© Primavera Systems, Inc.
PDF created with pdfFactory Pro trial version www.pdffactory.com
Activity Activity Plan Plan Plan 2008
MAR APR MAY JUN JUL AUG
ID Description Dur Start Finish 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11
U2MPEC016 ERECTION OF POWER CYCLE VALVES - REQD. FOR SYN. 45 05FEB10 21MAR10
U2MPEC017 ERECTION OF STEAM TRAPS - REQD. FOR SYN. 36 14FEB10 21MAR10
LUBE OIL TRANSFER
ENGINEERING
U2LTE011 ENGINEERING - CLEAN OIL & DIRTY OIL PUMPS 30 18MAY08 16JUN08
PROCUREMENT
U2LTP011 ORDERING - CLEAN OIL & DIRTY OIL PUMPS 48 02JUN08 19JUL08 ORDERING - CLEAN OIL & DIRTY OIL PUMPS
U2LTP012 MANUFACTURING - CLEAN OIL & DIRTY OIL PUMPS 256 18OCT08 30JUN09
U2LTP013 DELIVERY AT SITE - CLEAN OIL & DIRTY OIL PUMPS 11 01JUL09 11JUL09
ERECTION/COMMISSIONING
U2LTEC011 ERECTION - CLEAN OIL & DIRTY OIL PUMPS 25 12JUL09 05AUG09
U2LTEC012 PRE-COMMISSIONNG - CLEAN OIL & DIRTY OIL PUMPS 9 16SEP09 24SEP09
HP & LP FLASH TANKS
ENGINEERING
U2HLE011 ENGINEERING - HP & LP FLASH TANKS 20 26JUN08 15JUL08 ENGINEERING - HP & LP FLASH TANKS
PROCUREMENT
U2HLP011 ORDERING - HP & LP FLASH TANKS 30 16JUL08 14AUG08 ORDERING - HP & LP FLASH TANKS
U2HLP012 MANUFACTURING - HP & LP FLASH TANKS 250 13NOV08 20JUL09
U2HLP013 DELIVERY - HP & LP FLASH TANKS 21 21JUL09 10AUG09
ERECTION/COMMISSIONING
U2HLTEC011 ERECTION & COMMISSIONING - HP FLASH TANK 102 02DEC09 13MAR10
U2HLTEC012 ERECTION & COMMISSIONING - LP FLASH TANK 102 02DEC09 13MAR10
INSTRUMENTATION CONTROLS
TG PACKAGE
ENGINEERING
U2ETE011 ENGINEERING - ATRS,.. 79 19DEC08 07MAR09
PROCUREMENT
U2ETP011 PROCUREMENT OF MATERIALS - ATRS,.. 116 07MAY09 30AUG09
U2ETP012 ASSEMBLY & TESTING COMPLETION - ATRS,.. 32 31AUG09 01OCT09
U2ETP013 FAT, DESP & DELIVERY TO SITE - ATRS,.. 18 03OCT09 20OCT09
ERECTION/COMMISSIONING
U2ETEC011 ERECTION - ATRS,.. 46 21OCT09 05DEC09
U2ETEC012 COMMISSIONING - ATRS,.. 25 06DEC09 30DEC09
SG PACKAGE
ENGINEERING
U2ESE011 ENGINEERING - FLAME SCANNER, SADC, BMS 79 19DEC08 07MAR09
PROCUREMENT
U2ESP011 PROCUREM OF MATERIALS - FLAME SCANNER, SADC, BMS 100 07MAY09 14AUG09
U2ESP012 ASSEMBLY & TESTING - FLAME SCANNER, SADC, BMS 25 15AUG09 08SEP09
U2ESP013 FAT, DESP & DELIVERY - FLAME SCANNER, SADC, BMS 15 10SEP09 24SEP09

Start Date 01MAR08 DAR7 Sheet 40 of 55


Early Bar
Finish Date 17APR10 Date Revision Checked Approved
Float Bar
Data Date 18MAR08
Run Date 10SEP08 23:58 Progress Bar
2 X 80 MW CPP - DARIBA SMELTER COMPL
Critical Activity

Classic Schedule Layout


© Primavera Systems, Inc.
PDF created with pdfFactory Pro trial version www.pdffactory.com
Activity Activity Plan Plan Plan 2008
MAR APR MAY JUN JUL AUG
ID Description Dur Start Finish 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11
ERECTION/COMMISSIONING
U2ESEC011 ERECTION - FLAME SCANNER, SADC, BMS 46 25SEP09 09NOV09
U2ESEC012 COMMISSIONING - FLAME SCANNER, SADC, BMS 25 10NOV09 04DEC09
HMI SYSTEM
ENGINEERING
U2EHE011 ENGINEERING - TFT MONIT., COMPU., N/W PANEL 79 19DEC08 07MAR09
PROCUREMENT
U2EHP011 MTRLS. PROCUREME - TFT MONIT., COMPU., N/W PANEL 116 07MAY09 30AUG09
U2EHP012 ASSEMBLY & TEST. - TFT MONIT., COMPU., N/W PANEL 32 31AUG09 01OCT09
U2EHP013 FAT, DESP & DELI - TFT MONIT., COMPU., N/W PANEL 18 03OCT09 20OCT09
ERECTION/COMMISSIONING
U2EHEC011 ERECTION - TFT MONIT., COMPU., N/W PANEL 46 21OCT09 05DEC09
U2EHEC012 COMMISSIONING - TFT MONIT., COMPU., N/W PANEL 25 06DEC09 30DEC09
AVR SYSTEM
ENGINEERING
U2EAE011 ENGINEERING - AVR 79 19DEC08 07MAR09
PROCUREMENT
U2EAP011 PROCUREMENT OF MATERIALS - AVR 116 07MAY09 30AUG09
U2EAP012 ASSEMBLY & TESTING - AVR 32 31AUG09 01OCT09
U2EAP013 FAT, DESP & DELIVERY - AVR 18 03OCT09 20OCT09
ERECTION/COMMISSIONING
U2EAEC011 ERECTION - AVR 46 21OCT09 05DEC09
U2EAEC012 COMMISSIONING - AVR 25 06DEC09 30DEC09
OVERALL COMMISSIONING
BOILER
U2OLBC011 BOILER LIGHT UP 3 29JAN10 31JAN10
U2OLBC012 STEAM BLOWING 10 10FEB10 19FEB10
U2OLBC013 SAFETY VALVE FLOATING COMPLETION 3 20FEB10 22FEB10
U2OLBC014 BOILER COAL FIRING 6 01APR10 06APR10
TG
U2OLTC011 FINAL ALIGNMENT OF TG 9 31DEC09 08JAN10
U2OLTC012 TG - OIL FLUSHING 15 09JAN10 23JAN10
U2OLTC013 BARRING GEAR OPERATION 7 24JAN10 30JAN10
U2OLTC014 VACCUM PULLING- TG 2 14MAR10 15MAR10
U2OLTC015 STEAM DUMPING 1 16MAR10 16MAR10
OVERALL
U2OLOC011 ROLLING, OCC SCC OF GEN & SYNCHRONISATION 5 27MAR10 31MAR10
U2OLOC012 COMMG./ STABILITY RUN/TRIAL OPERATION-TG 3 29MAR10 31MAR10
U2OLOC013 COMMG./ 72 hrs TRIAL OPERATION-TG 3 07APR10 09APR10

Start Date 01MAR08 DAR7 Sheet 41 of 55


Early Bar
Finish Date 17APR10 Date Revision Checked Approved
Float Bar
Data Date 18MAR08
Run Date 10SEP08 23:58 Progress Bar
2 X 80 MW CPP - DARIBA SMELTER COMPL
Critical Activity

Classic Schedule Layout


© Primavera Systems, Inc.
PDF created with pdfFactory Pro trial version www.pdffactory.com
Activity Activity Plan Plan Plan 2008
MAR APR MAY JUN JUL AUG
ID Description Dur Start Finish 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11
U2OLOC014 PROV. HANDING OVER OF PLANT 0 09APR10
U2OLOC015 PLANT OPTIMISATION 2 10APR10 11APR10
U2OLOC016 LOAD REJECTION & ISLANDING TESTS 2 12APR10 13APR10
U2OLOC017 RELIABILITY RUN 2 14APR10 15APR10
U2OLOC018 PG TEST 2 16APR10 17APR10
U2OLOC019 FINAL HANDING OVER OF PLANT 0 17APR10

COMMON BOP
Subtotal 689 12MAY08 31MAR10

TG BUILDING
ENGINEERING
EN310 SPECIFICATION- EOT CRANE 25 17JUL08 10AUG08 SPECIFICATION- EOT CRANE
EN300 CIVIL DRG FOR STG BUILDING 45 03AUG08 16SEP08 CIVIL DRG FOR STG BUILDING
PROCUREMENT
PR230 ORDERING - AGGREGATE PRODUCTION CRUSHER 30 01JUN08 30JUN08 ORDER
PR240 MOBILIZATION & SET-UP OF AGGRERATE PRODN CRUSHER 60 01JUL08 29AUG08 MOBILIZATION & SET-UP OF AGGRERATE PRODN CRUSHER
PR200 ORDERING- EOT CRANE 35 11AUG08 14SEP08 ORDERING- EOT CRANE
PR210 MANUFACTURING- EOT CRANE 190 15SEP08 23MAR09
PR220 DISPATCH- EOT CRANE 25 24MAR09 17APR09
CIVIL
TG010 MAIN COLUMN FOUND 180 02SEP08 28FEB09
TG020 FABRICATION - STG BUILD STRUCTURE 240 14SEP08 11MAY09
TG110 TG FOUNDATION WORKS - UNIT #1 180 27SEP08 25MAR09
TG030 ERECTION OF STG BUILD STRUCTURE 300 24OCT08 19AUG09
TG040 CONCRETING OF BC BAY 3.5m FLOOR 60 23DEC08 20FEB09
U2TG110 TG FOUNDATION WORKS - UNIT #2 180 26DEC08 23JUN09
TG060 CONCRETING OF BC BAY 8m FLOOR 60 07JAN09 07MAR09
TG065 CONCRETING OF BC BAY 11m FLOOR 60 22JAN09 22MAR09
TG080 CONCRETING OF BC BAY 0.00m FLOOR 90 22JAN09 21APR09
TG075 CONCRETING OF BC BAY 16.5 m FLOOR 60 06FEB09 06APR09
TG125 READINESS FOR SWITCH GEAR ERECT @ 3.5 M 40 21FEB09 01APR09
TG120 UNIT BATTERY ROOM READINESS - UNIT #1 35 11MAR09 14APR09
TG100 ROOF & SIDE SHEETING 140 23MAR09 09AUG09
TG190 STATION BATTERY ROOM READINESS 45 23MAR09 06MAY09
U2TG120 UNIT BATTERY ROOM READINESS - UNIT #2 35 07APR09 11MAY09
TG015 AUX COLUMN FOUND 270 15APR09 09JAN10
TG135 READINESS FOR EOT ERECT 0 21APR09
TG050 CONCRETING OF AB BAY 5m FLOOR- PART 45 15MAY09 28JUN09
Start Date 01MAR08 DAR7 Sheet 42 of 55
Early Bar
Finish Date 17APR10 Date Revision Checked Approved
Float Bar
Data Date 18MAR08
Run Date 10SEP08 23:58 Progress Bar
2 X 80 MW CPP - DARIBA SMELTER COMPL
Critical Activity

Classic Schedule Layout


© Primavera Systems, Inc.
PDF created with pdfFactory Pro trial version www.pdffactory.com
Activity Activity Plan Plan Plan 2008
MAR APR MAY JUN JUL AUG
ID Description Dur Start Finish 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11
TG140 READINESS FOR TG FOUNDATION - UNIT #1 0 05JUN09
TG070 CONCRETING OF AB BAY 11m FLOOR - PART 45 14JUN09 28JUL09
TG113 U#1CONCRETING OF STG COOLING AIR DUCT UPTO 7.5M 45 21JUN09 04AUG09
TG340 FINISHING WORKS OF TG BUILD 250 29JUN09 05MAR10
TG130 CONTROL ROOM READINESS INCL. FINISHING WORKS 75 24JUL09 06OCT09
TG114 U#1CONCRETING OF STG COOLING AIR DUCT ABOVE 7.5M 30 18AUG09 16SEP09
TG117 ACW PUMP FOUNDATION WORKS 15 18AUG09 01SEP09
TG132 READINESS OF CON ROOM FOR PANEL ERECT 25 23AUG09 16SEP09
U2TG140 READINESS FOR TG FOUNDATION - UNIT #2 0 03SEP09
TG167 READINESS FOR ACWP ERECTION 0 11SEP09
TG172 U#1 READINESS FOR STG COOLER ERECTION 0 16SEP09
U2TG113 U#2CONCRETING OF STG COOLING AIR DUCT UPTO 7.5M 45 19SEP09 02NOV09
TG082 CONCRETING OF AB BAY 0.00m FLOOR 75 16NOV09 29JAN10
U2TG114 U#2CONCRETING OF STG COOLING AIR DUCT ABOVE 7.5M 1 18NOV09 18NOV09
U2TG172 U#2 READINESS FOR STG COOLER ERECTION 0 18NOV09
TG052 CONCRETING OF AB BAY 5m FLOOR - BALANCE 30 10JAN10 08FEB10
TG072 CONCRETING OF AB BAY 11m FLOOR - BALANCE 25 09FEB10 05MAR10
ERECTION & COMMISSIONING
EC100 ERECTION- EOT CRANE 20 22APR09 11MAY09
EC110 COMMG. OF EOT CRANE (with temp power from client 10 12MAY09 21MAY09
TG BUILD - ELE WORKS
ENGINEERING
EN370 SPEC - 6.6 kV HT SWITCH GEAR 30 29JUL08 27AUG08 SPEC - 6.6 kV HT SWITCH GEAR
EN350 SPEC - STATION BATTERY & CHARGER 25 31JUL08 24AUG08 SPEC - STATION BATTERY & CHARGER
EN360 SPEC - GEN BUS DUCT 20 20AUG08 08SEP08
EN380 SPEC - LT SWGR / MCC/ DB 30 23AUG08 21SEP08
EN410 SPEC - ELE INSTALLATION WORKS 30 30AUG08 28SEP08
EN400 SPEC - UNIT BATTERY/CHARGER & UPS 20 29SEP08 18OCT08
PROCUREMENT
PR340 ORDERING-HT SWITCH GEAR 60 28AUG08 26OCT08
PR250 ORDERING OF STATION BATTERY & CHARGER 45 04SEP08 18OCT08
PR380 ORDERING-LTSWGR/MCC.DB 60 22SEP08 20NOV08
PR410 ORDERING- GEN BUS DUCT 50 09OCT08 27NOV08
PR260 MANUF - STATION BATTERY & CHARGER 120 19OCT08 15FEB09
PR280 ORDERING- UNIT BATTERY/CHARGER & UPS 30 19OCT08 17NOV08
PR350 ENGG & MANUF - HT SWITCH GEAR 220 27OCT08 03JUN09
PR290 MANUF - UNIT BATTERY/CHARGER & UPS 120 18NOV08 17MAR09

Start Date 01MAR08 DAR7 Sheet 43 of 55


Early Bar
Finish Date 17APR10 Date Revision Checked Approved
Float Bar
Data Date 18MAR08
Run Date 10SEP08 23:58 Progress Bar
2 X 80 MW CPP - DARIBA SMELTER COMPL
Critical Activity

Classic Schedule Layout


© Primavera Systems, Inc.
PDF created with pdfFactory Pro trial version www.pdffactory.com
Activity Activity Plan Plan Plan 2008
MAR APR MAY JUN JUL AUG
ID Description Dur Start Finish 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11
PR390 MANUF - LTSWGR/MCC.DB 260 21NOV08 07AUG09
PR420 MANUFACTURING OF GEN BUS DUCT 180 18DEC08 15JUN09
PR270 DELIVERY TO SITE - STATION BATTERY & CHARGER 30 06FEB09 07MAR09
PR300 DELIVERY TO SITE - UNIT BATTERY/CHARGER & UPS 40 18MAR09 26APR09
PR391 DELIVERY AT SITE - UNIT & STATION DCDB & UPS DB 15 21MAR09 04APR09
PR393 DELIVERY AT SITE - LTSWGR (CT & PT MCC) 15 20APR09 04MAY09
PR360 DELIVERY - HT SWTCH GEAR - STATION 25 25APR09 19MAY09
PR395 DELIVERY AT SITE - BMCC, TMCC & NE SG 15 20MAY09 03JUN09
PR370 DELIVERY - HT SWTCH GEAR - UNIT 20 30MAY09 18JUN09
PR394 DELIVERY AT SITE - LTSWGR AC&VENT, FUEL OIL MCC 15 09JUN09 23JUN09
PR430 DELIVERY TO SITE - GEN BUS DUCT 30 16JUN09 15JUL09
PR396 DELIVERY AT SITE - CHP MCC, DG SG 15 08AUG09 22AUG09
ERECTION & COMMISSIONING
BATTERY/CHARGER/UPS
EC150 ERECTION - UNIT BATTERY & CHARGER - UNIT #1 20 07APR09 26APR09
EC160 COMMG.- UNIT #1 BATTERY & UPS 5 27APR09 01MAY09
U2EC150 ERECTION - UNIT BATTERY & CHARGER - UNIT #2 20 02MAY09 21MAY09
EC152 ERECTION - STATION BATTERY & CHARGER 20 07MAY09 26MAY09
EC153 ERECTION - STATION DCDB 20 07MAY09 26MAY09
U2EC160 COMMG.- UNIT #2 BATTERY & UPS 5 22MAY09 26MAY09
EC151 COMMG. - STATION BATTERY & CHARGER 5 27MAY09 31MAY09
EC154 COMMG. - STATION DCDB 5 27MAY09 31MAY09
EC190 COMM OF UPS DB 5 27MAY09 31MAY09
BUS DUCT
EC220 U#1 - ERECTION OF BUSDUCT OUTSIDE TG BUILD 30 16JUL09 14AUG09
U2EC220 U#2 - ERECTION OF BUSDUCT OUTSIDE TG BUILD 30 10AUG09 08SEP09
EC219 U#1 - ERECT OF GEN BUS DUCT INSIDE TG BUILD 20 30SEP09 19OCT09
EC240 UNIT #1 - BUSDUCT ERECTION COMPELETION. 5 20OCT09 24OCT09
EC250 PRE-COMMG.- UNIT #1 GEN BUS DUCT 10 25OCT09 03NOV09
U2EC219 U#2 - ERECT OF GEN BUS DUCT INSIDE TG BUILD 20 02JAN10 21JAN10
U2EC240 UNIT #2 - BUSDUCT ERECTION COMPELETION. 5 22JAN10 26JAN10
U2EC250 PRE-COMMG.- UNIT #2 GEN BUS DUCT 10 27JAN10 05FEB10
HT SWITCHGEAR
EC300 ERECTION - HT SWITCH GEAR - STATION 20 20MAY09 08JUN09
EC305 ERECTION - HT SWITCH GEAR - UNIT 30 19JUN09 18JUL09
EC304 COMMG./CHARGING - HT SWGR - STATION 5 17AUG09 21AUG09
EC320 COMMG./CHARGING OF HT SWRS - UNIT 5 22AUG09 26AUG09

Start Date 01MAR08 DAR7 Sheet 44 of 55


Early Bar
Finish Date 17APR10 Date Revision Checked Approved
Float Bar
Data Date 18MAR08
Run Date 10SEP08 23:58 Progress Bar
2 X 80 MW CPP - DARIBA SMELTER COMPL
Critical Activity

Classic Schedule Layout


© Primavera Systems, Inc.
PDF created with pdfFactory Pro trial version www.pdffactory.com
Activity Activity Plan Plan Plan 2008
MAR APR MAY JUN JUL AUG
ID Description Dur Start Finish 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11
LT SWITCHGEAR
EC330 ERECTION OF LT SWITCHGEAR - STATION 30 05APR09 04MAY09
EC340 ERECTION OF LT SWITCHGEAR - UNIT 30 04JUN09 03JUL09
EC355 ERECTION OF LV SWGR - BMCC, TMCC 45 04JUN09 18JUL09
EC335 COMMG./CHARGING OF LV SWGR - STATION 10 01SEP09 10SEP09
EC345 COMMG./CHARGING OF LV SWGR - UNIT 10 06SEP09 15SEP09
EC365 COMMG./CHARGING OF LV SWGR - BMCC, TMCC 20 16SEP09 05OCT09
BOILER AREA CIVIL
ENGINEERING
EN480 CIVIL DRG FOR BOILER AREA 55 23AUG08 16OCT08
EN490 ESP CONTROL BUILDING DRG 55 17SEP08 10NOV08
CIVIL
BA145 ESP CONTROL BUILDING CIVIL WORKS 210 25MAR09 20OCT09
BA190 READINESS OF ESP BUILD FOR ERECTION 5 08SEP09 12SEP09
BA180 BOILER AREA PAVING 120 08NOV09 07MAR10
MILL & BUNKER BAY
ENGINEERING
EN510 CIVIL& STRUL DRG FOR BUNKERS AREA 50 31JUL08 18SEP08 CIVIL& STRUL DRG FOR BUNKERS AREA
CIVIL
BU110 UNIT #1 - FAB. & ERN OF BUNKERS & STRUCTURE 150 03NOV08 01APR09
BU100 UNIT #1 - FOUNDATION OF BUNKER STRUCT 75 16NOV08 29JAN09
U2BU110 UNIT #2 - FAB. & ERN OF BUNKERS & STRUCTURE 150 02JAN09 31MAY09
BU120 UNIT #1 - CIVIL WORKS OF BUNKER SUPER STRUCTURE 85 11FEB09 06MAY09
U2BU100 UNIT #2 - FOUNDATION OF BUNKER STRUCT 75 14FEB09 29APR09
U2BU120 UNIT #2 - CIVIL WORKS OF BUNKER SUPER STRUCTURE 85 12APR09 05JUL09
TRANSFORMER YARD
ENGINEERING
EN530 SPEC - GENERATOR TRANSFORMER 20 12MAY08 31MAY08 SPEC - GENERATOR TRANSFORMER
EN545 SPEC - STATION TRANSFORMER 30 01JUN08 30JUN08 SPEC - STATION TRANSFORMER
EN540 SPEC - UNIT AUXILIARY TRANSFORMER 20 11JUN08 30JUN08 SPEC - UNIT AUXILIARY TRANSFORMER
EN550 SPEC - SERVICE TRANSFORMER 20 03AUG08 22AUG08 SPEC - SERVICE TRANSFORMER
EN560 FOUNDATION DRG - CIVIL 80 03AUG08 21OCT08 FOUNDATION DRG - CIVIL
PROCUREMENT
PR510 ORDERING OF GENERATOR TRANSFORMER 30 01JUN08 30JUN08 ORDERING OF GENERATOR TRANSFORMER
PR520 MANUF OF GENERATOR TRANSFORMER 400 01JUL08 04AUG09 MANUF OF GENERATOR TRANSFORMER
PR540 ORDERING- UNIT AUXILIARY TRANSFORMER 30 01JUL08 30JUL08 ORDERING- UNIT AUXILIARY TRANSFORMER
PR562 ORDERING OF STATION TRANSFORMER 40 01JUL08 09AUG08 ORDERING OF STATION TRANSFORMER
PR550 MANUF OF UNIT AUXILIARY TRANSF 240 31JUL08 27MAR09 MANUF OF UNIT AUXILIARY TRANSF
Start Date 01MAR08 DAR7 Sheet 45 of 55
Early Bar
Finish Date 17APR10 Date Revision Checked Approved
Float Bar
Data Date 18MAR08
Run Date 10SEP08 23:58 Progress Bar
2 X 80 MW CPP - DARIBA SMELTER COMPL
Critical Activity

Classic Schedule Layout


© Primavera Systems, Inc.
PDF created with pdfFactory Pro trial version www.pdffactory.com
Activity Activity Plan Plan Plan 2008
MAR APR MAY JUN JUL AUG
ID Description Dur Start Finish 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11
PR564 MANUF OF STATION TRANSFORMER 200 10AUG08 25FEB09 MANUF OF STATION TRANSFORMER
PR570 ORDERING OF SERVICE TRANSFORMER 40 23AUG08 01OCT08
PR580 MANUF OF SERVICE TRANSFORMER 250 02OCT08 08JUN09
PR560 U#1 - DELIVERY AT SITE - UNIT AUXILIARY TRANSF 15 27JAN09 10FEB09
PR566 UNIT #1 - DELIVERY AT SITE OF STATION TRANSF 15 01FEB09 15FEB09
PR590 UNIT #1 - DELIVERY AT SITE - SERVICE TRANSF 20 04FEB09 23FEB09
U2PR566 UNIT #2 - DELIVERY AT SITE OF STATION TRANSF 15 26FEB09 12MAR09
U2PR560 U#2 - DELIVERY AT SITE - UNIT AUXILIARY TRANSF 15 28MAR09 11APR09
PR530 DELIVERY AT SITE - U#1 GENERATOR TRANSFORMER 25 27APR09 21MAY09
U2PR590 UNIT #2 - DELIVERY AT SITE - SERVICE TRANSF 20 09JUN09 28JUN09
U2PR530 DELIVERY AT SITE - U#2 GENERATOR TRANSFORMER 25 05AUG09 29AUG09
CIVIL
TR100 UNIT #1 - FOUND OF GENERATOR TRANSFORMER 120 22OCT08 18FEB09
TR132 UNIT #1 - FOUND OF STATION TRANSF 120 06NOV08 05MAR09
TR140 UNIT #1 - FOUND OF SERVICE TRANSFORMER 140 01DEC08 19APR09
U2TR100 UNIT #2 - FOUND OF GENERATOR TRANSFORMER 120 21DEC08 19APR09
TR120 UNIT #1 - FOUND OF UNIT AUXILIARY TRANSF 80 20JAN09 09APR09
U2TR132 UNIT #2 - FOUND OF STATION TRANSF 120 20JAN09 19MAY09
TR110 UNIT #1 - FOUND READY FOR GT ERECTION 20 19FEB09 10MAR09
U2TR120 UNIT #2 - FOUND OF UNIT AUXILIARY TRANSF 80 19FEB09 09MAY09
U2TR140 UNIT #2 - FOUND OF SERVICE TRANSFORMER 140 01MAR09 18JUL09
TR134 UNIT #1 - FOUND READY FOR STATION TRANSF ERECT 10 06MAR09 15MAR09
TR150 U#1 FOUND READY FOR STATION SERVICE TRANSFORMER 20 21MAR09 09APR09
TR160 U#1 FDN READY FOR UNIT SERVICE TRANSFORMER 20 31MAR09 19APR09
TR130 U#1 - FOUND READY FOR UNIT AUXILIARY TRANSF 10 10APR09 19APR09
TR200 UNIT #1 - FOUND. OF ESP SERVICE TRANSFORMER 10 10APR09 19APR09
TR170 FOUND READY FOR CT & PT, CHP SERVICE TRANSFORMER 10 20APR09 29APR09
U2TR110 UNIT #2 - FOUND READY FOR GT ERECTION 20 20APR09 09MAY09
U2TR130 U#2 - FOUND READY FOR UNIT AUXILIARY TRANSF 10 10MAY09 19MAY09
TR180 MISC CIVIL WORKS LIKE FENCING, AGG FILLING 120 20MAY09 16SEP09
U2TR134 UNIT #2 - FOUND READY FOR STATION TRANSF ERECT 10 20MAY09 29MAY09
U2TR150 U#2 FOUND READY FOR STATION SERVICE TRANSFORMER 20 19JUN09 08JUL09
U2TR160 U#2 FDN READY FOR UNIT SERVICE TRANSFORMER 20 29JUN09 18JUL09
U2TR200 UNIT #2 - FOUND. OF ESP SERVICE TRANSFORMER 10 09JUL09 18JUL09
ERECTION & COMMISSIONING
EC416 UNIT #1 -ERECT OF STATION TRANSF 15 16MAR09 30MAR09
EC417 UNIT #1 - PRE-COMMG OF STATION TRANSF 5 31MAR09 04APR09

Start Date 01MAR08 DAR7 Sheet 46 of 55


Early Bar
Finish Date 17APR10 Date Revision Checked Approved
Float Bar
Data Date 18MAR08
Run Date 10SEP08 23:58 Progress Bar
2 X 80 MW CPP - DARIBA SMELTER COMPL
Critical Activity

Classic Schedule Layout


© Primavera Systems, Inc.
PDF created with pdfFactory Pro trial version www.pdffactory.com
Activity Activity Plan Plan Plan 2008
MAR APR MAY JUN JUL AUG
ID Description Dur Start Finish 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11
EC200 UNIT #1 - ERECTION OF ESP SERVICE TRANSFORMER 10 20APR09 29APR09
EC435 UNIT #1 - ERECT OF UNIT SERVICE TRANSF 15 20APR09 04MAY09
EC205 UNIT #1 - PRE-COMMG. OF ESP SERVICE TRANSF 10 30APR09 09MAY09
EC420 UNIT #1 - ERECT OF STATION SERVICE TRANSF 15 30APR09 14MAY09
EC455 ERECTION OF CT & PT SERVICE TRANSF 10 30APR09 09MAY09
EC495 ERECTION OF CHP SERVICE TRANSF 10 30APR09 09MAY09
EC400 UNIT #1 - ERECT - GENERATOR TRANSFORMER 35 22MAY09 25JUN09
U2EC416 UNIT #2 -ERECT OF STATION TRANSF 15 30MAY09 13JUN09
U2EC417 UNIT #2 - PRE-COMMG OF STATION TRANSF 5 14JUN09 18JUN09
EC410 UNIT #1 - ERECT OF UNIT AUXILIARY TRANSF 30 22JUN09 21JUL09
EC405 UNIT #1 - PRE-COMMG - GENERATOR TRANSF 30 26JUN09 25JUL09
U2EC200 UNIT #2 - ERECTION OF ESP SERVICE TRANSFORMER 10 19JUL09 28JUL09
EC415 UNIT #1 - PRE-COMMG OF UNIT AUXILIARY TRANSF 10 22JUL09 31JUL09
U2EC205 UNIT #2 - PRE-COMMG. OF ESP SERVICE TRANSF 10 29JUL09 07AUG09
U2EC420 UNIT #2 - ERECT OF STATION SERVICE TRANSF 15 29JUL09 12AUG09
U2EC435 UNIT #2 - ERECT OF UNIT SERVICE TRANSF 15 08AUG09 22AUG09
EC418 UNIT #1 - CHARGING OF STATION TRANSF 5 12AUG09 16AUG09
U2EC418 UNIT #2 - CHARGING OF STATION TRANSF 5 12AUG09 16AUG09
EC425 UNIT #1 - COMM OF STATION SERVICE TRANSF 10 22AUG09 31AUG09
EC505 COMM OF CHP SERVICE TRANSF 10 22AUG09 31AUG09
U2EC425 UNIT #2 - COMM OF STATION SERVICE TRANSF 10 22AUG09 31AUG09
EC210 UNIT #1 - CHARGING OF ESP SERVICE TRANSF 2 27AUG09 28AUG09
EC445 UNIT #1 - COMM OF UNIT SERVICE TRANSF 10 27AUG09 05SEP09
EC465 COMMISSIONING OF CT & PT SERVICE TRANSFORMER 10 27AUG09 05SEP09
U2EC210 UNIT #2 - CHARGING OF ESP SERVICE TRANSF 2 27AUG09 28AUG09
U2EC445 UNIT #2 - COMM OF UNIT SERVICE TRANSF 10 27AUG09 05SEP09
U2EC400 UNIT #2 - ERECT - GENERATOR TRANSFORMER 35 30AUG09 03OCT09
U2EC410 UNIT #2 - ERECT OF UNIT AUXILIARY TRANSF 30 22SEP09 21OCT09
U2EC405 UNIT #2 - PRE-COMMG - GENERATOR TRANSF 30 04OCT09 02NOV09
U2EC415 UNIT #2 - PRE-COMMG OF UNIT AUXILIARY TRANSF 10 22OCT09 31OCT09
EC406 COMMG - UNIT #1 GENERATOR TRANSF 1 31DEC09 31DEC09
U2EC406 COMMG - UNIT #2 GENERATOR TRANSF 1 31MAR10 31MAR10
CHIMNEY
ENGINEERING
EN600 SPECIFICATION - CHIMNEY 10 01JUL08 10JUL08 SPECIFICATION - CHIMNEY
EN610 CIVIL DRG - CHIMNEY 45 11JUL08 24AUG08 CIVIL DRG - CHIMNEY

Start Date 01MAR08 DAR7 Sheet 47 of 55


Early Bar
Finish Date 17APR10 Date Revision Checked Approved
Float Bar
Data Date 18MAR08
Run Date 10SEP08 23:58 Progress Bar
2 X 80 MW CPP - DARIBA SMELTER COMPL
Critical Activity

Classic Schedule Layout


© Primavera Systems, Inc.
PDF created with pdfFactory Pro trial version www.pdffactory.com
Activity Activity Plan Plan Plan 2008
MAR APR MAY JUN JUL AUG
ID Description Dur Start Finish 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11
PROCUREMENT
PR610 ORDERING - CHIMNEY CONSTRUCTION 45 11JUL08 24AUG08 ORDERING - CHIMNEY CONSTRUCTION
PR620 MOBILIS. OF CHIMNEY CONTRACTOR 60 25AUG08 23OCT08
CIVIL
CH100 CHIMNEY FOUNDATION 65 10AUG08 13OCT08 CHIMNEY FOUNDATION
CH110 CIVIL WORK - SHELL COMPLITION 190 24OCT08 01MAY09
CH120 CIVIL WORK - INTERNAL 160 22MAY09 28OCT09
CH122 FLUE DUCT READNESS 10 30AUG09 08SEP09
CH130 FINISHING WORKS INCLU. ELE. OF CHIMNEY 75 09SEP09 22NOV09
CH123 CHIMNEY READY FOR ID PRE COMMG. (INCLU BRICK LIN 0 16SEP09
CH125 CHIMNEY READY FOR BLU 0 28SEP09
RAW WATER SYSTEM
ENGINEERING
EN680 SPECIF - RAW WATER PUMPS 40 03AUG08 11SEP08 SPECIF - RAW WATER PUMPS
EN685 CIVIL DRG FOR RW PUMP FOUND 30 06DEC08 04JAN09
PROCUREMENT
PR830 ORDERING OF RAW WATER PUMPS 45 12SEP08 26OCT08
PR845 ORDERING OF RAW WATER PIPING 60 30SEP08 28NOV08
PR835 MANUF OF RAW WATER PUMPS 150 27OCT08 25MAR09
PR850 MANUF & DISPATCH OF RW PIPING 45 29NOV08 12JAN09
PR840 DISPATCH OF RAW WATER PUMPS 20 26MAR09 14APR09
CIVIL
RW110 CIVIL WORKS FOR RW PIPING 100 29DEC08 07APR09
RW100 CIVIL WORKS FOR RW PUMP FOUND 60 14FEB09 14APR09
ERECTION & COMMISSIONING
EC820 ERECT OF RAW WATER PIPING 60 08APR09 06JUN09
EC810 ERECT OF RAW WATER PUMPS 30 15MAY09 13JUN09
EC830 COMMG OF RW PUMPS 15 14JUN09 28JUN09
PRE-TREATMENT PLANT
ENGINEERING
EN770 SPEC FOR PT PLANT 30 17JUL08 15AUG08 SPEC FOR PT PLANT
EN790 CIVIL DRG FOR PTP 30 05OCT08 03NOV08
EN792 FDN DRG FOR DM & CS TANKS 30 05OCT08 03NOV08
PROCUREMENT
PR990 ORDERING OF PT PLANT 30 16AUG08 14SEP08 ORDERING OF PT PLANT
PR993 MNFG & DELIVERY OF PT PLANT 180 15SEP08 13MAR09
PR995 SUPPLY OF STEEL PLATES 60 30OCT08 28DEC08

Start Date 01MAR08 DAR7 Sheet 48 of 55


Early Bar
Finish Date 17APR10 Date Revision Checked Approved
Float Bar
Data Date 18MAR08
Run Date 10SEP08 23:58 Progress Bar
2 X 80 MW CPP - DARIBA SMELTER COMPL
Critical Activity

Classic Schedule Layout


© Primavera Systems, Inc.
PDF created with pdfFactory Pro trial version www.pdffactory.com
Activity Activity Plan Plan Plan 2008
MAR APR MAY JUN JUL AUG
ID Description Dur Start Finish 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11
CIVIL
PTP100 CIVIL WORKS OF CLARIFIER 120 20OCT08 16FEB09
PTP105 CIVIL CONSTN OF CHEMICAL HOUSE 180 04NOV08 02MAY09
PTP107 DM & CS TANK FOUNDATIONS 60 04NOV08 02JAN09
PTP110 CLARIFIER READY FOR MECH ERECTION 5 29DEC08 02JAN09
PTP103 CIVIL WORKS OF CWST 100 21MAR09 28JUN09
PTP130 CHEMICAL HOUSE READY FOR ERECTION 15 24MAR09 07APR09
ERECTION & COMMISSIONING
DEC955 FAB & ERE OF DM STORAGE TANK 90 29DEC08 28MAR09
EC940 ERECTION OF PT PLANT 45 14MAR09 27APR09
EC941 ERECTION OF PTP DOSING EQPT. 55 14MAR09 07MAY09
EC975 TANKS READY FOR RECEIVING DM WATER 5 29MAR09 02APR09
DEC960 ERECTION OF PTP MCC 20 05MAY09 24MAY09
EC961 PRE-COMMISSIONING OF PTP MCC 10 01JUN09 10JUN09
DEC965 CHARGING OF PTP MCC 2 11JUN09 12JUN09
EC945 COMMG OF PT PLANT 15 07JUL09 21JUL09
DEC967 DM WATER FOR BOILER HYDRAULIC TEST 5 21JUL09 25JUL09
COOLING WATER SYSTEM
ENGINEERING
EN710 SPEC - CW PUMPS 20 17JUL08 05AUG08 SPEC - CW PUMPS
EN720 SPEC - ACW PUMPS 30 06AUG08 04SEP08 SPEC - ACW PUMPS
EN730 SPEC - CW PIPING 10 06AUG08 15AUG08 SPEC - CW PIPING
EN750 CW PIPING CIVIL DRGS 25 20SEP08 14OCT08
EN740 CIVIL DRG FOR CW PUMP FOUND 45 05OCT08 18NOV08
EN780 SSF CIVIL DRGS 20 14DEC08 02JAN09
PROCUREMENT
PR860 ORDERING- C W PUMPS 30 06AUG08 04SEP08 ORDERING- C W PUMPS
PR920 ORDERING - CW PIPING 35 16AUG08 19SEP08 ORDERING - CW PIPING
PR870 MANUFACTURING - C W PUMPS 240 05SEP08 02MAY09
PR890 ORDERING OF ACW PUMPS 60 15SEP08 13NOV08
PR930 MANUFACTURING OF CW PIPING 100 20SEP08 28DEC08
PR900 MANUFACTURING OF ACW PUMPS 160 14NOV08 22APR09
PR940 DISPATCH TO SITE - C W PIPING 20 29DEC08 17JAN09
PR910 DISPATCH TO SITE - A C W PUMPS 15 23APR09 07MAY09
PR880 DISPATCH TO SITE - C W PUMPS 15 03MAY09 17MAY09
CIVIL
CW130 CIVIL WORKS FOR CW PIPING 100 19DEC08 28MAR09

Start Date 01MAR08 DAR7 Sheet 49 of 55


Early Bar
Finish Date 17APR10 Date Revision Checked Approved
Float Bar
Data Date 18MAR08
Run Date 10SEP08 23:58 Progress Bar
2 X 80 MW CPP - DARIBA SMELTER COMPL
Critical Activity

Classic Schedule Layout


© Primavera Systems, Inc.
PDF created with pdfFactory Pro trial version www.pdffactory.com
Activity Activity Plan Plan Plan 2008
MAR APR MAY JUN JUL AUG
ID Description Dur Start Finish 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11
CW100 CIVIL WORKS OF C W PUMP FOUND 90 29DEC08 28MAR09
CW140 CIVIL WORKS FOR SSF 90 03JAN09 02APR09
CW150 SSF FOUND READY FOR ERECT 10 14MAR09 23MAR09
CW110 FOUND READY FOR CW PUMPS ERECT 10 13APR09 22APR09
ERECTION & COMMISSIONING
EC890 ERECTION OF CW PIPING 100 18JAN09 27APR09
EC916 ERECTION OF SSF 45 24MAR09 07MAY09
EC900 HYDROTEST OF CW PIPING 30 18APR09 17MAY09
EC850 ERECTION OF C W PUMPS 20 28MAY09 16JUN09
EC926 COMM OF SSF 10 13JUN09 22JUN09
EC860 COMMG. OF C W PUMPS 15 30AUG09 13SEP09
EC870 ERECTION OF ACW PUMPS 15 07SEP09 21SEP09
EC880 COMM. OF ACW PUMPS 8 04OCT09 11OCT09
I D COOLING TOWER
ENGINEERING
EN760 SPEC OF INDUCED DRAFT COOLING TOWER 20 16JUN08 05JUL08 SPEC OF INDUCED DRAFT COOLING TOWER
PR980 DRG FOR COOLING TOWER 50 09SEP08 28OCT08
PROCUREMENT
PR960 ORDERING OF INDUCED DRAFT COOLING TOWER 45 06JUL08 19AUG08 ORDERING OF INDUCED DRAFT COOLING TOWER
PR970 MFG & DELIVERY OF COOLING TOWER EQPT 210 20AUG08 17MAR09
CIVIL
CT100 CIVIL CONSTN. OF IDCT 350 09OCT08 23SEP09
CT110 IDCT READY FOR MECH ERECTION 60 06JUN09 04AUG09
ERECTION & COMMISSIONING
EC922 ERECTION OF LV SWGR FOR CT 30 05MAY09 03JUN09
EC920 MECH ERECTION OF IDCT 110 26JUN09 13OCT09
EC915 BASIN READYNESS FOR WATER CIRCULATION 5 25AUG09 29AUG09
EC924 COMMG OF LV SWGR FOR CT 5 06SEP09 10SEP09
EC930 COMMG OF IDCT 25 14OCT09 07NOV09
COMPRESSOR SYSTEM
ENGINEERING
EN800 SPEC FOR COMPRESSOR / DYIER / RECEIVER 30 08AUG08 06SEP08 SPEC FOR COMPRESSOR / DYIER / RECEIVER
EN830 CIVIL DRG FOR COMPRESSOR BUILD 60 06DEC08 03FEB09
EN840 SA RECEIVER CIVIL DRG 45 16DEC08 29JAN09
PROCUREMENT
PR1050 ORDERING OF COMPRESSOR / DRIER / RECEIVER 40 07SEP08 16OCT08
PR1080 MANUF - COMPRESSOR / DRIER / RECEIVER 180 17OCT08 14APR09

Start Date 01MAR08 DAR7 Sheet 50 of 55


Early Bar
Finish Date 17APR10 Date Revision Checked Approved
Float Bar
Data Date 18MAR08
Run Date 10SEP08 23:58 Progress Bar
2 X 80 MW CPP - DARIBA SMELTER COMPL
Critical Activity

Classic Schedule Layout


© Primavera Systems, Inc.
PDF created with pdfFactory Pro trial version www.pdffactory.com
Activity Activity Plan Plan Plan 2008
MAR APR MAY JUN JUL AUG
ID Description Dur Start Finish 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11
PR1090 DISPATCH - COMPRESSOR / DRIER / RECEIVER 30 15APR09 14MAY09
CIVIL
CO100 CIVIL & STRL WORK OF COMPRESSOR BUILD 175 26DEC08 18JUN09
CO105 SA RECEIVER FOUNDATION 45 01MAR09 14APR09
CO110 COMPRESSOR FOUND READY FOR MECH ERECTION 10 10MAY09 19MAY09
CO120 AC PLANT FOUND READY FOR MECH ERECTION 5 15MAY09 19MAY09
ERECTION & COMMISSIONING
EC1030 SA RECEIVER ERECTION 30 10MAY09 08JUN09
EC1000 ERECTION OF AIR COMPRESSOR, DRIER & RECIEVER 60 09JUN09 07AUG09
EC1010 COMM OF AIR COMPRESSOR 5 12OCT09 16OCT09
EC1020 INST. AIR AVAILABLE 0 16OCT09
AC & VENTILATION SYSTEM
ENGINEERING
EN1130 SPEC- A/C & VENT SYS 30 28AUG08 26SEP08
PROCUREMENT
PR1400 ORDERING - A/C SYSTEM 50 27SEP08 15NOV08
PR1420 ORDERING - VENTILATION SYSTEM 50 27SEP08 15NOV08
PR1410 MANUF & DISPATCH - A/C SYSTEM 200 06DEC08 23JUN09
PR1430 MANUF & DISPATCH - VENT SYSTEM 190 16DEC08 23JUN09
ERECTION & COMMISSIONING
EC1401 ERECT OF VENTILATION SYSTEM 130 05MAY09 11SEP09
EC1400 ERECT OF AC SYSTEM 110 24JUN09 11OCT09
EC1403 ERECT OF LV SWGR AC & VENT SYS 25 24JUN09 18JUL09
EC1404 COMM OF LV SWGR AC & VENT SYS 10 16SEP09 25SEP09
EC1410 COMM OF VENTILATION SYSTEM 18 26SEP09 13OCT09
EC1420 COMM OF AIR CONDITIONING SYS.-BLU 5 26SEP09 30SEP09
EC1440 COMM OF AIR CONDITIONING SYS.-SYN 10 12OCT09 21OCT09
COAL HANDLING SYSTEM
ENGINEERING
EN860 SPEC FOR CHP 25 18AUG08 11SEP08
EN870 CIVIL DRG FOR CHP 120 26NOV08 25MAR09
PROCUREMENT
PR1150 ORDERING OF CHP 45 12SEP08 26OCT08
PR1160 MANUFACTURING OF CHP EQUIPMENTS 300 27OCT08 22AUG09
PR1170 DISPATCH OF CHP EQUIP 140 25APR09 11SEP09
CIVIL
CHP100 CIVIL WORKS OF CHP 350 24FEB09 08FEB10

Start Date 01MAR08 DAR7 Sheet 51 of 55


Early Bar
Finish Date 17APR10 Date Revision Checked Approved
Float Bar
Data Date 18MAR08
Run Date 10SEP08 23:58 Progress Bar
2 X 80 MW CPP - DARIBA SMELTER COMPL
Critical Activity

Classic Schedule Layout


© Primavera Systems, Inc.
PDF created with pdfFactory Pro trial version www.pdffactory.com
Activity Activity Plan Plan Plan 2008
MAR APR MAY JUN JUL AUG
ID Description Dur Start Finish 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11
ERECTION & COMMISSIONING
EC1150 FABRICATION & ERECTION OF CHP 185 15MAY09 15NOV09
EC1152 ERECTION OF LV SWGR CHP 30 02OCT09 31OCT09
EC1154 COMMISIONING OF LV SWGR CHP 5 01NOV09 05NOV09
EC1160 TRIAL RUN & COMMG OF CHP 25 16NOV09 10DEC09
ASH HANDLING SYSTEM
ENGINEERING
EN900 SPEC FOR ASH HANDLING PLANT 30 18AUG08 16SEP08
EN910 CIVIL DRG FOR ASH HANDLING PLANT 50 21DEC08 08FEB09
PROCUREMENT
PR1200 ORDERING OF AHP 45 17SEP08 31OCT08
PR1210 MNFG & DISPATCH OF ASH HANDLING SYSTEM 250 01NOV08 08JUL09
CIVIL
AHP100 CIVIL WORK FOR AHP 200 10JAN09 28JUL09
AHP110 AHP FOUND READY FOR MECH ERECTION 40 30MAY09 08JUL09
ERECTION & COMMISSIONING
EC1200 ERECTION OF ASH HANDLING SYSTEM 200 28JUL09 12FEB10
EC1202 UNIT #1 - ERECTION OF BOT ASH HOPPER 45 01SEP09 15OCT09
EC1203 ERECTION OF LV SWGR AHP 25 16SEP09 10OCT09
EC1204 COMMISIONING OF LV SWGR AHP 5 11OCT09 15OCT09
EC1205 UNIT #1 - COMPLN OF BOT ASH HOPPER - BLU 7 16OCT09 22OCT09
EC1206 UNIT #1 - TESTING OF AHS FOR CF 10 05NOV09 14NOV09
U2EC1202 UNIT #2 - ERECTION OF BOT ASH HOPPER 45 01DEC09 14JAN10
U2EV1205 UNIT #2 - COMPLN OF BOT ASH HOPPER - BLU 7 15JAN10 21JAN10
U2EC1206 UNIT #2 - TESTING OF AHS FOR CF 10 13FEB10 22FEB10
FUEL OIL SYSTEM
ENGINEERING
EN915 SPEC FOR UNLOADING SYSTEM 25 11JUL08 04AUG08 SPEC FOR UNLOADING SYSTEM
EN920 CIVIL DRAWING 60 29SEP08 27NOV08
PROCUREMENT
PR1220 ORDERING OF PLATES 45 05AUG08 18SEP08 ORDERING OF PLATES
PR1230 MANUF & DESPATCH OF PLATES 130 19SEP08 26JAN09
CIVIL
FOS120 CIVIL WORKS FOR TANK FARM AREA 75 29OCT08 11JAN09
FOS130 CIVIL WORKS FOR UNLOADING AREA 95 28DEC08 01APR09
FOS100 CIVIL WORKS FOR FUEL OIL PUMP SKID 60 07JAN09 07MAR09
FOS110 READYINESS OF SKID FOUND FOR ERECT 5 28MAR09 01APR09

Start Date 01MAR08 DAR7 Sheet 52 of 55


Early Bar
Finish Date 17APR10 Date Revision Checked Approved
Float Bar
Data Date 18MAR08
Run Date 10SEP08 23:58 Progress Bar
2 X 80 MW CPP - DARIBA SMELTER COMPL
Critical Activity

Classic Schedule Layout


© Primavera Systems, Inc.
PDF created with pdfFactory Pro trial version www.pdffactory.com
Activity Activity Plan Plan Plan 2008
MAR APR MAY JUN JUL AUG
ID Description Dur Start Finish 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11
ERECTION & COMMISSIONING
EC1220 FABRICATION & ERECT OF FUEL OIL TANK 110 27JAN09 16MAY09
EC1230 ERECTION OF UNLOADING SYSTEM 45 02APR09 16MAY09
EC1232 ERECTION OF FUEL OIL MCC 15 05MAY09 19MAY09
EC1235 COMMISSIONING OF FUEL OIL MCC 5 11SEP09 15SEP09
EC1240 COMM OF FUEL OIL UNLOADING SYS 5 16SEP09 20SEP09
LP PIPING
ENGINEERING
EN940 LAYOUT - LP PIPING - RW, SW, PW 25 05SEP08 29SEP08
EN930 LAYOUT - LP PIPING - ACW 25 13SEP08 07OCT08
EN950 LAYOUT - LP PIPING - AIR IA, SA 25 13SEP08 07OCT08
EN630 CIVIL DRGS FOR PIPE/CABLE RACK / TRENCHES / SLEE 30 08OCT08 06NOV08
PROCUREMENT
PR1270 ORDERING - LP PIPING - RW, SW, PW 45 30SEP08 13NOV08
PR1250 ORDERING - LP PIPING - ACW 45 08OCT08 21NOV08
PR1290 ORDERING - LP PIPING - AIR IA, SA 45 08OCT08 21NOV08
PR650 ORDERING OF STRL STEEL FOR PIPE RACKS 60 22OCT08 20DEC08
PR1280 MFG & DELVY - LP PIPING - RM, SW, PW 100 14NOV08 21FEB09
PR660 DELIVERY TO SITE - STRUL STEEL FOR PIPE RACK 90 21NOV08 18FEB09
PR1260 MFG & DELVY - LP PIPING - ACW 110 22NOV08 11MAR09
PR1300 MFG & DELVY - LP PIPING - AIR IA, SA 90 27NOV08 24FEB09
CIVIL
PC100 FOUNDATIONS FOR PIPE RACKS 120 18OCT08 14FEB09
PC110 FABRICATION OF PIPE RACK STRUCTURE 100 16DEC08 25MAR09
PC120 ERECTION OF PIPE RACKS 100 30JAN09 09MAY09
ERECTION & COMMISSIONING
EC1250 LP PIPING ERECTION OF COMP AIR 50 26MAR09 14MAY09
EC1290 LP PIPING ERECTION OF RW, SW, PW 50 16JUN09 04AUG09
EC1270 LP PIPING ERECTION OF ACW 45 20AUG09 03OCT09
FIRE FIGHTING & DETECTION SYSTEM
ENGINEERING
EN1000 SPEC FOR FIRE FIGHTING & DETECTION SYS 35 28AUG08 01OCT08
PROCUREMENT
PR1350 ORDERING OF FIRE FIGHTING & DETECTION SYS 45 01NOV08 15DEC08
PR1355 MANUF & DISPATCH - FIRE FIGHTING & DETECTION SYS 200 16DEC08 03JUL09
ERECTION & COMMISSIONING
EC1370 ERECTION OF FIRE FIGHTING SYS 200 26MAR09 11OCT09

Start Date 01MAR08 DAR7 Sheet 53 of 55


Early Bar
Finish Date 17APR10 Date Revision Checked Approved
Float Bar
Data Date 18MAR08
Run Date 10SEP08 23:58 Progress Bar
2 X 80 MW CPP - DARIBA SMELTER COMPL
Critical Activity

Classic Schedule Layout


© Primavera Systems, Inc.
PDF created with pdfFactory Pro trial version www.pdffactory.com
Activity Activity Plan Plan Plan 2008
MAR APR MAY JUN JUL AUG
ID Description Dur Start Finish 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11
EC1375 ERECTION OF FIRE DETECTION & ALARM SYS 75 24JUL09 06OCT09
EC1371 COMMG. OF FIRE FIGHTING SYS - REQD FOR BLU 60 13AUG09 11OCT09
EC1377 COMMISSIONING OF FIRE DETECTION & ALARM SYS 20 07OCT09 26OCT09
EC1372 COMMG. OF FIRE FIGHTING SYS - REQD FOR SYN. 60 12OCT09 10DEC09
ELECTRICAL WORKS
ENGINEERING
EN1160 SPEC - HT & LT POWER CABLING 60 22OCT08 20DEC08
PROCUREMENT
PR1480 ORDERING - HT & LT POWER CABLE 55 21DEC08 13FEB09
PR1482 MANUF & DISPATCH - HT & LT POWER CABLE 150 14FEB09 13JUL09
ERECTION & COMMISSIONING
EC1450 U#1 - LAY & TERMI - HT/LT POWER CABLE FOR BLU 120 25MAY09 21SEP09
EC1470 U#1 LAY & TERMI - HT/LT POWER CABLE FOR ROLL&SYN 120 14JUN09 11OCT09
U2EC1450 U#2 - LAY & TERMI - HT/LT POWER CABLE FOR BLU 140 18AUG09 04JAN10
U2EC1470 U#2 LAY & TERMI - HT/LT POWER CABLE FOR ROLL&SYN 150 28AUG09 24JAN10
INSTRUMENTATION
ENGINEERING
EN1210 SPEC - DCS FOR BOP 30 23AUG08 21SEP08
EN1220 SPEC - SWAS 20 17SEP08 06OCT08
EN1240 SPEC FOR C&I INSTRUMENTS 30 17SEP08 16OCT08
EN1250 SPEC - INSTRUMENTATION CABLES 30 07OCT08 05NOV08
EN1230 SPEC FOR C&I ERECTION CONTRACT 30 22OCT08 20NOV08
PROCUREMENT
PR1600 ORDERING OF DCS - BOP 65 27SEP08 30NOV08
PR1620 ORDERING - SWAS 60 07OCT08 05DEC08
PR1615 ORDERING C & I INSTRUMENTS 60 17OCT08 15DEC08
PR1632 ORDERING - INSTRUMENTS CABLE 60 06NOV08 04JAN09
PR1616 MANUF & DISPATCH TO SITE - C&I INSTRUMENTS 120 16DEC08 14APR09
PR1610 MANUF & DISPATCH TO SITE - DCS BOP 222 21DEC08 30JUL09
PR1630 MANUF & DISPATCH TO SITE - SWAS 140 05JAN09 24MAY09
PR1634 MANUF & DISPATCH TO SITE - INSTRUMENTS CABLE 120 05JAN09 04MAY09
ERECTION & COMMISSIONING
EC1720 UNIT #1 - ERECTION OF C&I INSTRUMENTS - BLU 120 13MAY09 09SEP09
U2EC1720 UNIT #2 - ERECTION OF C&I INSTRUMENTS - BLU 120 13MAY09 09SEP09
EC1726 UNIT #1 - LAYING & TER OF C&I CABLE - BLU 65 07JUL09 09SEP09
U2EC1726 UNIT #2 - LAYING & TER OF C&I CABLE - BLU 65 07JUL09 09SEP09
EC1725 U#1 - ERECTION OF C&I INSTRUMENTS - ROLL & SYNC 110 01SEP09 19DEC09

Start Date 01MAR08 DAR7 Sheet 54 of 55


Early Bar
Finish Date 17APR10 Date Revision Checked Approved
Float Bar
Data Date 18MAR08
Run Date 10SEP08 23:58 Progress Bar
2 X 80 MW CPP - DARIBA SMELTER COMPL
Critical Activity

Classic Schedule Layout


© Primavera Systems, Inc.
PDF created with pdfFactory Pro trial version www.pdffactory.com
Activity Activity Plan Plan Plan 2008
MAR APR MAY JUN JUL AUG
ID Description Dur Start Finish 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11
U2EC1725 U#2 - ERECTION OF C&I INSTRUMENTS - ROLL & SYNC 120 02SEP09 30DEC09
EC1700 ERECTION & COMM - SWAS 45 17SEP09 31OCT09
EC1705 ERECTION OF BOP DCS 25 17SEP09 11OCT09
EC1710 POWER ON - BOP DCS 2 12OCT09 13OCT09
EC1727 U#1 - LAYING & TER OF C&I CABLE - ROLL & SYNC 55 26OCT09 19DEC09
U2EC1727 U#2 - LAYING & TER OF C&I CABLE - ROLL & SYNC 65 27OCT09 30DEC09
ROADS & DRAINS
ENGINEERING
EN1350 DWG RELEASE LAYOUT- ROADS & DRAIN SYS 85 26NOV08 18FEB09
CIVIL
RD100 CIVIL WORKS OF PLANT ROADS & DRAINS 270 19FEB09 15NOV09

Start Date 01MAR08 DAR7 Sheet 55 of 55


Early Bar
Finish Date 17APR10 Date Revision Checked Approved
Float Bar
Data Date 18MAR08
Run Date 10SEP08 23:58 Progress Bar
2 X 80 MW CPP - DARIBA SMELTER COMPL
Critical Activity

Classic Schedule Layout


© Primavera Systems, Inc.