Академический Документы
Профессиональный Документы
Культура Документы
Abstract
Voltage dips are short duration reductions in rms voltage. They are mainly caused by short circuits.
Voltage dips are one of the most troublesome power quality problems due to the interference they
cause to several types of equipment. An important issue concerning voltage dip problems is the
influence of loads on voltage dip characteristics. This paper explains in part the load influence on
voltage dip characteristics. Measurements of voltage dip, which are collected from a distribution
system under study, are presented to quantify the analysis. The voltage dip measurements show that
the remaining rms voltage present during the dip for busbars closer to the load. The measurements
also show that the load influence the voltage dip shape.
Voltage dips have become a major concern in power The distribution system under study is presented in
quality in the past decade. The cost of economical fig. 1. A main 66kV bus bar supplies the 22kV
loses and inconveniences caused by voltage dips have distribution system trough 2 66/22kV 30-MVA
triggered some studies and research activities. Many transformers and the sub-system is supplied at 415 V
experts have tried to characterise voltage dips [1,2,3]. from a 22/0.415kV 400-kVA transformer.
The existing standard on voltage dip characterises the Figure 1
voltage dips in terms of magnitude and duration. The One-line diagram of the sub-system under study
characterisation of the standard is based on the The transmission and distribution systems supply
assumption that faults will cause rectangular voltage
dips. It is also assumed that the voltage drops to a
certain low value immediately and when the fault is
cleared, the voltage recovers back to normal
immediately.
Figure 2
Summer and Winter Max Load Variation
Voltage Dip
Sub-system Max Load
260
Summer 2000 and Winter 2001
350 250
Voltage (V)
300 240
250
230
200
220
Load
150
210
100
50
200
0 0.05 0.15 0.25 0.35 0.45 0.55
6 7 8 9 10 11 12 13 14 15
Time (s)
Days
kW June01 kVA June01 kVAR June01 V1 V2 V3
kW Dec00 kVAR Dec00 kVA Dec00
Figure 3
Since, the subsystem consists of residential, Voltage dips in the subsystem
commercial and light industrial customers, the
difference of load between summer and winter in this When the fault occurred, the bus voltage decreased to
subsystem could be due to air conditioners. In a certain point and then decaying to a lower rapidly
summer, the sub-system will have more rotating voltage level during the short circuit period. After the
machines. fault is cleared, the voltage did not directly recover to
its level before fault. The voltage need a longer time to
recover back and this could be caused by air
conditioning motor loads.
5. Simulation of Post Fault Load
Behaviour
Figure 4
Voltage dip for a 3Ph-G fault
Figure 5
Load current during 3Ph-G fault
6. Conclusions