Вы находитесь на странице: 1из 13

Land Contamination & Reclamation, 9 (4), 2001 © 2001 EPP Publications

DOI 10.2462/09670513.600

In situ bioremediation of groundwater


contaminated with phenols, BTEX and
PAHs using nitrate as electron acceptor
Richard J.F. Bewley and Graham Webb

Abstract
This paper describes the implementation of an in situ bioremediation scheme to
address historical groundwater contamination at the site of a former oil works, now
occupied by an operating facility manufacturing bitumen-related products. Site investi-
gations had indicated that groundwater beneath the facility was contaminated with up to
20 600 µg/L phenols, 169 µg/L polyaromatic hydrocarbons (PAHs) and 440 µg/L ben-
zene, toluene, ethylbenzene and xylenes (BTEX). The site was mostly covered by
hardstanding so that the key risks posed by the contamination were to an adjacent river
located 50 m from the site boundary. The remedial scheme involved the installation of
four abstraction wells located towards the site boundary with the river from which
groundwater was abstracted at a typical rate of 40–50 m3/day and conveyed via reticu-
lation pipework to two sets of three reinjection wells located hydraulically upgradient of
the source area. Prior to reinjection, the groundwater was supplemented with a continu-
ous source of sodium nitrate as an oxygen source, together with nutrients, these being
supplied in the form of a commercial mixture of urea and diammonium phosphate. A
commercial mixture of phenol-degrading bacteria, PHENOBAC, was also applied peri-
odically in batch mode as point source injections to the most contaminated area, and to
the reinjected groundwater. Over the 2.5 years that the scheme was operating, mean
concentrations of phenols were reduced from 1100 µg/L at the start to 12 µg/L, PAHs
from 11 µg/L to 0.9 µg/L and BTEX from 58 µg/L to 19 µg/L. Following termination of
the scheme, ongoing monitoring of the groundwater indicated an initial increase in con-
centrations assumed to be due to ‘bounce-back’, followed by a further decline. Mean
concentrations of contaminants two years after termination were 93 µg/L phenols,
0.7 µg/L PAHs and 11 µg/L BTEX. Monitoring of groundwater indicated a general
increase in viable counts of bacteria, declining after termination, and a transient
increase in nitrite, indicative of biological dentifrication.

Key words: BTEX, in situ bioremediation, nitrate, PAHs, phenols

INTRODUCTION AND SITE DESCRIPTION in the UK which currently produces a range of flooring,
damp proofing and roofing materials based on bitumen
This paper presents the results of a groundwater reme- and synthetic resins. The site is located on an industrial
diation programme undertaken at an operating facility estate in the north-west Midlands between a railway
line to the south and a major river approximately 50 m
to the north.
Received March 2001; accepted June 2001 At the beginning of the 20th century, oil shale
extraction took place in the area. According to histori-
Authors cal maps an ‘oil works’ formerly occupied the present
Richard J.F. Bewley1 and Graham Webb2 site and on a 1: 2600 Ordnance Survey map dated 1934,
1. Dames & Moore, 5th Floor, Blackfriars House, St. Mary’s
Parsonage, Manchester M3 2JA, UK (author for correspond-
the presence of a gasometer indicated potential coal
ence). gasification processes. Prior to its current use part of the
2. Dames & Moore, Iveagh Court, 4th Floor, 6-8 Harcourt site had also been occupied by a rail wagon repair yard.
Road, Dublin 2, Ireland

335
Land Contamination & Reclamation / Volume 9 / Number 4 / 2001

A series of investigations concerning soil and of fine to medium-grained sands. These were further
groundwater quality within the site boundary were fol- underlain by glacial clays as proved in borehole 401, on
lowed by some localised remediation of soil contami- the northern boundary.
nated by volatile organic compounds in an area In summary, the following sequence was inferred:
adjacent to a Low Flash products building. This
involved excavation and disposal of contaminated soil
to a licensed landfill, reinstatement with clean fill and (1) Fill: predominantly granular but with some clay
construction of protective measures for underlying soil. and silt content up to 1.8 m thick;
An additional area of excavation and disposal involved (2) Clay: soft, firm and stiff, silty and occasionally
a former railway sleeper pit and adjacent contaminated described as silt up to 1.2 m thick with a base at 2.0
soil which was also removed to a licensed landfill, and – 2.8 m depth;
reinstated with clean granular fill. (3) Sand: loose to medium dense, black, very silty and
Whilst these areas were both localised in nature and fine-grained becoming light grey, silty and fine –
accessible for soil remediation, much of the remainder medium and occasionally coarse-grained below
of the site was covered by hardstanding and buildings. 7 m and red/brown below 11 m, having a thickness
A series of boreholes were excavated over the site area, of approximately 10 m and a depth to base of
to evaluate soil and groundwater quality, as shown in 12.3 m (in BH401 on the northern boundary (Fig-
Figure 1. ure 1);
These indicated that the geological succession (4) Clay: stiff red brown, silty, slightly sandy and
beneath the site consisted of granular fill materials gravelly, thickness or depth not proved but the lat-
overlying a thin natural clay, underlain by a succession ter is in excess of 13.5 m.

R I V E R

SEP 93 NOV 93 NOV 92 DEC 93 3.5-7.0m 9.2-12.0m


PHENOLS 815µg/l 7090µg/l PHENOLS NA PHENOLS 20600µg/l 1660µg/l DEC 92
PAHs 37µg/l 45µg/l PAHs NA PAHs 24µg/l 26µg/l PHENOLS 5µg/l
BTEX 440µg/l 137µg/l BTEX 4.5µg/l BTEX 305µg/l 60g/l PAHs 68µg/l
305
BTEX NA

105
401
304
SEP 93 NOV 93
202
PHENOLS 502µg/l 5930µg/l
PAHs 146µg/l 169µg/l
BTEX 88µg/l 55g/l
SEP 93
PHENOLS 2.3µg/l
PAHs 6.4µg/l
203 BTEX 0.3µg/l

DEC 92
PHENOLS 10300µg/l
PAHs 140µg/l 301
BTEX NA

SEP 93 NOV 93
PHENOLS 3.3µg/l 0.08µg/l
PAHs 1.8µg/l 4.7µg/l
302 BTEX 1.9µg/l 1.5µg/l
204
303
KEY
PHASE I SAMPLING LOCATIONS (GRAB SAMPLES)

250mm GROUNDWATER MONITORING WELL


DEC 92 150mm GROUNDWATER MONITORING WELL
DEC 92
PHENOLS 1357µg/l
PHENOLS 0.2µg/l
PAHs 3.9µg/l 75mm GROUNDWATER MONITORING WELL
PAHs 0.6µg/l
BTEX NA
BTEX 2.3µg/l 34mm GROUNDWATER MONITORING WELL

PAHs POLYAROMATIC HYDROCARBONS (16 USEPA LISTED)

BTEX BENZENE, TOLUENE, ETHYLBENZENE, XYLENES

USEPA TARGET COMPOUNDS


0 10 20 30 40 50m
NA NOT ANALYSED
APPROXIMATE SCALE

Figure 1. Site plan showing concentrations of key contaminants detected in groundwater

336
In situ bioremediation of groundwater contaminated with phenols, BTEX and PAHs using nitrate as electron acceptor

Generally, the fill materials were found to be dry culatory approach was therefore selected as represent-
and groundwater was encountered at shallow (2 – 3 ing the most appropriate method of introducing
metres) depth within the superficial sands. The sands nutrients and an electron acceptor into the groundwater
beneath the site formed a shallow aquifer, believed to to enhance in situ microbial activity. However, whereas
be in hydraulic continuity with the river, the bed level hydrogen peroxide had previously been used in treat-
of which was reportedly at 2 m AOD. The river was ment of a sandy gravel aquifer (Bewley et al. 2001), the
tidal adjacent to the site with a tidal range of approxi- prolonged travel time and assumed half-life of this rea-
mately 5 m. Groundwater levels at the site were mar- gent were considered to represent serious limitations at
ginally above mean water levels in the river and this site.
inferred a net flow of groundwater towards the river. A Nitrate, on the other hand, represented a soluble
hydraulic gradient of 1:260 was estimated. electron acceptor (when present as the sodium or potas-
The soil and groundwater investigations identified sium salt for example) that could be injected in poten-
the occurrence of significant contamination in the tially high quantities into the aquifer. Under anaerobic
groundwater, specifically arising from benzene, tolu- conditions, nitrate will undergo denitrification, with
ene, ethylbenzene and o-, m-, and p-xylenes (BTEX), reduction to gaseous oxides of nitrogen and nitrogen
phenols, particularly phenol itself, cresols (methylphe- gas. Additionally, it has been shown (primarily through
nols) and xylenols (dimethylphenols), and polyaro- laboratory microcosms or studies of intrinsic biodegra-
matic hydrocarbons (PAHs). dation) to be suitable as an electron acceptor during the
Concentrations of the above determinands identi- degradation of aromatics such as phenols (e.g. Bossert
fied in the groundwater during the various phases of and Young 1986; Lerner et al. 2000), naphthalene
investigation are depicted on Figure 1. (Al-Bashir et al. 1990) and BTEX compounds,
On the basis that off-site migration of such contami- although in the case of the latter, the evidence for ben-
nation could potentially impact the adjacent river, the zene degradation has often been negative (Häner et al.
site owners retained Dames & Moore to design and 1995; Krumholz et al. 1996; Bewley 1996).
implement a volunteered remedial strategy with the The nitrate reduction process for phenol can be sum-
objective of minimising the potential risk to this recep- marised thus:
tor.
28 28 + 14 29
C 6 H 6 O + ------ NO 3 + ------ H → 6CO 2 + ------ N 2 + ------ H 2 O
5 5 5 5
SELECTION OF REMEDIAL APPROACH
Reports of nitrate having been used in active in situ
Whereas potentially historic soil contamination existed bioremediation projects have largely been confined to
under the operational areas and other covered parts of clean-up of BTEX and petroleum hydrocarbons (Bat-
the site (as confirmed by the soil investigations), it termann et al. 1993; Hutchins et al. 1991; Werner
would not have been possible to have addressed this 1985) although there is also a report of its use in treat-
without significant demolition of above ground struc- ment of pentachlorophenol (Campbell et al. 1989).
tures and disruption of site activities. However, The proposed scheme therefore involved abstract-
because the majority of the site area was covered by ing groundwater from an area hydraulically down-gra-
buildings and hardstanding then the amount of infiltra- dient of the site, supplementing with nutrients and
tion over such an area (with the potential to leach con- nitrate as an oxygen source and re-injecting the
tamination into the groundwater) was likely to be very amended groundwater up-gradient of the contaminated
limited. The focus of the remedial scheme was there- area. The nitrate as oxygenating agent and nutrients
fore to address contamination in the saturated zone. would then accelerate the natural biodegradation proc-
A review of potential remedial options was under- esses taking place within the saturated zone (normally
taken and it was considered that the best practicable limited by sub-optimal levels of these factors). Dia-
approach involved in situ bioremediation. This was grammatic representation of the scheme is provided in
based on the fact that the contamination was present as Figure 2.
dissolved rather than free phase. Also, given the poten- The feasibility of using bioremediation was con-
tial for sorbed phase to be present it was considered that firmed by a bench-scale laboratory test. This demon-
an in situ approach offered significant advantages over strated that in a sample of groundwater from the most
pump-and-treat, especially given the relatively contaminated area, concentrations of the key contami-
fine-grained nature of the aquifer. The fine-grained nant groupings (BTEX, phenols and PAHs) could be
nature of the aquifer also indicated that a passive in situ reduced to below 50 µg/L, albeit using an inoculum
approach would be of very limited effectiveness due to and under aerobic conditions. A constant discharge
the reduced radius of influence of dosing wells. A recir- (pump) test was also undertaken to assess the hydraulic

337
Land Contamination & Reclamation / Volume 9 / Number 4 / 2001

characteristics of the fine sand aquifer beneath the site. (ii) for BTEX, with benzenes, toluene, ethylben-
Groundwater computer modelling was then carried out zene and each xylene isomer not to exceed
to optimise the number and locations of abstraction and 20, 50, 60 and 60 µg/L respectively and not
re-injection wells, together with appropriate abstrac- to exceed 100 µg/L;
tion and re-injection rates.
(iii) for polyaromatic hydrocarbons (PAHs) as the
The target concentrations for switch-off of the
sum of 16 US EPA target list priority pollut-
scheme were:
ant compounds not to exceed 75 µg/L.
(i) for phenols (as the sum of phenol, cresols and
xylenols on the US EPA Target List, i.e. phe- These targets were based on what was considered
nol, 2-methylphenol (o-cresol), 4-methylphe- practicably achievable from the bench-scale testing
nol (p-cresol) and 2,4-dimethylphenol and were broadly consistent with the Dutch guidelines
(2,4-xylenol)) not to exceed 100 µg/L; at the time, where applicable.

PLAN

R I V E R

NUTRIENT/NO3 RETICULATION
INJECTION POINT PIPEWORK

AW401 AW404
AW402
AW403

IW407
IW406
KEY
IW405
ABSTRACTION BOREHOLE (AW)
INJECTION BOREHOLE (IW)
DIRECTION OF INOCULUM INJECTION WELLS
GROUNDWATER BH302
BH303 FLOW MONITORING WELLS (BH)
IW410

IW408 0 20 40 60 80 100m
IW409 APPROXIMATE SCALE

SECTION 12m DEPTH OXYGEN


9m DEPTH
ABSTRACTION INOCULUM NUTRIENTS SOURCE: INJECTION
WELLS (AW) NITRATE WELL (IW)

NORTH SITE RETICULATION PIPEWORK


BOUNDARY
CONCRETE
RIVER CLAY
FILL
SAND
? CLAY CLAY
? ? SANDY CLAY
MEAN FINE WITH FILL
WATER SAND
LEVEL MEDIUM
SAND
DYNAMIC
GROUNDWATER
LEVEL
ZONE OF IN-SITU SAND BECOMING
BIOREMEDIATION COARSER

SUBMERSIBLE
PUMP

CLACIAL CLAY

Figure 2. Diagrammatic representation of remedial scheme

338
In situ bioremediation of groundwater contaminated with phenols, BTEX and PAHs using nitrate as electron acceptor

Following termination of the active recirculatory installed between 5 September 1994 and 30 September
scheme, a monitoring period of up to two years was to 1994.
be carried out to take account of potential Following initial pump testing of the abstraction
‘bounce-back’ and intrinsic biodegradation. wells commencing during the week of 6 October 1994
(week 1) it was found that unacceptable amounts of silt
were migrating from the aquifer, through the well con-
METHODOLOGY struction and into the system pipework. To mitigate this
problem, each abstraction well was lined with a
Installation of remediation system 100 mm nominal diameter well screen wrapped with an
A schematic of the remediation system is shown in Fig- 80 micron nominal pore size geotextile. This work was
ure 2. undertaken during week 3. Siltation problems were
A series of four abstraction wells (AW401 – also encountered within the injection wells, due to
AW404) were located along the down-gradient bound- materials in the aquifer being more fine-grained and
ary of the site. Each well was installed to the base of the looser than expected. As a result of the siltation, it was
aquifer, a depth of approximately 12 m below ground found during initial testing of the remediation system
level and comprised 150 mm diameter well casing that a number of the injection wells were unable to
screened from 2 m to 11 m below ground level, accept the design flows from the abstraction wells. To
installed within a 300 mm diameter borehole. The reduce this problem, and hence to increase the flow
annulus between the borehole wall and well casing was capacity of the injection wells, each well was lined with
filled with a sand filter pack across the screened sec- 150 mm casing and the resulting annulus was filled
tions of well casing, with a bentonite grout seal with a finer grained filter pack. This work was under-
installed above the filter pack. A submersible borehole taken during weeks 8 to 9.
pump was installed within each of the four wells. For In addition to the wells utilised in the abstrac-
each well location, a brickwork chamber was con- tion/re-injection system, four inoculum injection wells
structed to a depth of l m to house a flow control valve were installed in the vicinity of well AW401, using
and a sampling tap to enable collection of groundwater ‘window sampling’ equipment. The wells were drilled
samples directly from the rising main. A rising main at 75 mm nominal diameter to a depth of 4 m bgl. A
network comprising 75 mm diameter PVC pipe com- piezometer comprising 38 mm PVC screen, a sur-
bined the flows from the four abstraction wells into a rounding filter pack and a bentonite seal was installed
single discharge pipeline. Connected to the latter was a at each location. Stop-cock covers were installed at
nutrient dosing facility that enabled addition of nutri- each location to protect the installations. Monitoring
ents from a 500-litre mixing tank and pump (in batch boreholes (BH302 and BH303) had previously been
form), and continuous dosing of sodium nitrate and installed on site in September 1993 as part of the inves-
Purisol 100 from 1000-litre IBCs. tigation works. The boreholes had been advanced to
The nutrient dosing facility also housed the electri- between 3 and 4 m depth with the installation of
cal supply and control panel for each of the abstraction 150 mm and 75 mm ID piezometers in BH302 and
well pumps and dosing pumps. Discharge pipework led BH303 respectively.
from the facility to a series of six re-injection wells,
located as shown on Figure 2. These injection wells Commissioning and operation
were installed to depths varying from 9 to 11 m bgl. Commissioning trials of the remediation system
Each hole was drilled at 460 mm nominal diameter and included stepped discharge pump tests and a constant
single wall, screened PVC well casing of 250 mm nom- discharge pump test which were performed during
inal diameter was installed from the base of each well weeks 9 to 10. The pumping trials indicated the follow-
to 2 m bgl. Blank casing was installed above the ing operational characteristics of the system:
screened section, from ground level to 2 m bgl. A filter
pack was installed from the base of each well across the (i) the maximum potential abstraction rate from
screened section with a bentonite seal from 0.5 m to any one abstraction well was of the order of 4
2 m bgl. – 5 m3/hr;
The installation of three of the abstraction wells (ii) the maximum potential injection rate into any
(AW402, AW403 and AW404) and the six injection one of the injection wells was of the order of
wells (IW405 to IW410) was undertaken between 15 0.6 m3/hr (wells 408, 409, 410) to 0.8 m3/hr
August 1994 and 16 September 1994. A fourth abstrac- (wells 405, 406, 407);
tion well, AW401, had been installed in November (iii) the results of the test indicated a steady-state
1993 during a previous phase of work at the site. The draw-down of the water table at the abstrac-
remaining components of the remediation system were tion wells of the order of 1.0 – 1.5 m at the

339
Land Contamination & Reclamation / Volume 9 / Number 4 / 2001

Table 1. Nutrient and nitrate addition to groundwater prior to re-injection

Date Week Methoda Urea Dipotassium Magnesium Sodium Purisol


(kg) phosphate sulphate nitrate 100e (T)
(kg) (kg) (36%) (T)
b
19/12/94 11 B 100 25 10 – –
21/12/94 11 B 200 50 20 – –
04/01/95 13 B 200 50 20 – –
d
06/01/95 13 B 200 50 20 – –
c
19/12/94 11 C – – – 24 –
09/01/95 13 C – – – – 5

Key
(a) Method of addition as indicated.
(b) Batch addition made on date shown.
(c) Continuous flow commencing on date shown (Purisol 100 added on alternate weeks from April 1995).
(d) On this occasion constituents added to inoculum injection wells, not reinjected groundwater.
(e) Commercial mixture consisting of urea and diammonium phosphate supplied by ICI Chance & Hunt.

final flow rate, and an increase in water levels slime was considered to have originated from rapid
at the injection wells of approximately 0.5 m build-up of microbial cells within the screen owing to
for the southern three injection wells 408, the favourable conditions for microbial activity (i.e.
409 and 410. The increase in water table lev- presence of nutrients in a relatively aerobic environ-
els in the vicinity of the northern three wells ment).
405, 406 and 407 was estimated to be of the The process was repeated during July 1995 (weeks
order of 0.8 m; 41 to 42) and subsequently at two to three month inter-
(iv) hydraulic conductivity of the aquifer was of vals.
the order of 1 m/day and total abstraction
(and re-injection) rate was of the order of 100 Nutrient and inoculum application
m3/day. Application of nutrients (as batch additions of urea,
dipotassium phosphate and magnesium sulphate)
Initial testing of the groundwater re-circulation sys- together with sodium nitrate (as oxygen source) com-
tem took place in October 1994. Groundwater abstrac- menced on 19 December 1994 following completion of
tion and re-injection commenced in December 1994 the pump tests.
and continued to be operated until August 1997 (week The purpose of the initial nutrient addition was to
148). Following completion in August 1997, periodic provide a readily available source of nitrogen, phos-
monitoring of the groundwater continued through phorus and potassium at the same time as the inoculum
1999. was added. This would primarily provide the inocu-
The groundwater re-circulation system was mostly lated bacteria with a source of nutrients as they were
run for 24 hours per day with abstraction taking place transported through the zone of contamination by the
from up to four wells at a time, although this was later re-circulated groundwater. To avoid too rapid micro-
reduced to three wells from early 1995. Groundwater bial growth (which would produce a high oxygen
abstraction was subsequently concentrated at wells demand and exacerbate pore blockage from slime for-
AW403 and AW401, with groundwater abstraction mation) the nutrients were added in four batches during
from well AW403 only, during 1997. Fouling of the weeks 11 to 13, as shown in Table 1.
re-injection wells significantly reduced their efficiency For ongoing supply of nitrogen and phosphorus,
so that the typical groundwater abstraction rate was Purisol 100, a commercial mixture of urea and ammo-
approximately 40–50m3/day over the course of the nium phosphates, supplied by ICI Chance & Hunt, was
treatment, significantly below that during the pumping added following completion of the batch additions. The
trials. Purisol 100 and the 36% sodium nitrate solution were
Due to this build-up of slime within the screen of the each injected as a continuous feed into the discharge
re-injection wells, it was necessary to shut down the pipeline using peristaltic pumps. Both these supple-
system temporarily for a period of three weeks during ments were stored in separate 1 m3 IBC containers. As
March 1995 (weeks 22 to 25) whilst the wells were from April 1995, the Purisol 100 was added every alter-
treated with concentrated hydrogen peroxide. The nate week, rather than continuously, to reduce accumu-

340
In situ bioremediation of groundwater contaminated with phenols, BTEX and PAHs using nitrate as electron acceptor

lation of slime. Later, the supply of Purisol 100 was RESULTS


terminated, once contaminant concentrations appeared
to have diminished substantially, and it was judged that Microbial populations
the groundwater was sufficiently well-charged with The total viable counts of microbial populations
nutrients. The nitrate application was continued how- (expressed as colony forming units, cfu/mL) following
incubation at 22°C are shown in Figure 3. Within the
ever, through 1995 and 1997 as it was considered that
abstraction wells there was a significant increase from
oxygen would continue to be a limiting factor.
before the pump test to the start of the remediation pro-
The inoculum used was PHENOBAC, a proprietary gramme. The effect of the pump test in drawing
mixture of naturally occurring bacteria and growth groundwater through the aquifer may have resulted in a
stimulants supplied by Microbac Ltd., Durham. The stimulation of microbial activity through disturbance
product had received previous US EPA authorisation and localised oxygenation of the groundwater.
for release into navigable waters on a case-by-case Microbial population levels then fluctuated consid-
basis. Following rehydration and filtering, a slurry of erably. The numbers following switch-off in week 169
the inoculum was added in batch form to the ground- were particularly elevated in all wells, but especially in
monitoring well BH303 (2.9 x 107 cfu/mL) and
water re-injection and inoculum injection wells. This
abstraction well AW404 (1.8 x 107 cfu/mL). By week
was performed initially during week 10 and was
199 microbial counts had also increased to >107
repeated three times during weeks 13 and 14. Addi- cfu/mL in all wells apart from AW403 and AW404
tional inoculation was performed during weeks 44 and where there was a decline to 105 cfu/mL since January.
81. However, by the final sampling during week 240 there
had been a significant decline in all wells sampled.
Monitoring The reasons for such fluctuations cannot always be
readily explained but are probably due to variations in
Samples of groundwater from the abstraction and mon-
the chemical (particularly indigenous nutrient) compo-
itoring wells were taken periodically for chemical anal-
sition of the abstracted groundwater, or in other cases
ysis. The initial sampling (week 0) took place at the localised enhancement of microbial populations
time of the initial pump tests in October 1994 (other through inoculated microorganisms, either into the
samplings being reported to the nearest week). The inoculum or groundwater, injection wells. It should be
final sampling during the re-circulation of the ground- stressed that the population levels in the groundwater
water took place in May 1997 (week 137). Following do not in themselves necessarily indicate the overall
switch-off in August 1997 (week 148), sampling was level of microbial activity. Microorganisms responsible
carried out through May 1999 (week 240). Sampling of for contaminant degradation will also be present sorbed
the abstraction wells was carried out from taps allow- onto the solid phase, and it is these, which may be
ing water to be withdrawn during the course of the responsible for the bulk of the contaminant degrada-
tion. Also, the plate count method is selective for bacte-
treatment. The remaining boreholes were sampled
ria, which can be readily cultured under laboratory
using either a Teflon bailer or an MPI pump, having
conditions and is likely to underestimate total popula-
purged each one of at least three borehole volumes to tions present. The main value of the viable count data
ensure representative samples. Each groundwater sam- was to provide a relatively rapid index to assess if there
ple was temporarily stored in a cool box refrigerated at was any gross inhibition of microbial activity which
3 to 4°C prior to despatch to the laboratory. All chemi- appears not to be the case, even on the occasions where
cal and microbiological analysis was performed by high concentrations of contaminants had been identi-
AES, Wallsend and included benzene, toluene, ethyl- fied.
benzene and xylenes by purge and trap, GC/MS, pol-
yaromatic hydrocarbons by GC/MS following Soxhlet Concentrations of ammonia and oxidised nitrogen
extraction, phenols by HPLC/electrochemical detec- Variations in concentrations of ammoniacal and oxi-
dised nitrogen are shown in Figure 3 and summarised
tion (British Gas Method) and other determinands by
in Table 2. Relatively low levels of ammoniacal, nitrite
standard ‘MEWAM’ methods or similar. Colony
and nitrate nitrogen were present prior to the pump
counts were carried out at 22°C using HMSO pub- tests in all wells. The high level of ammoniacal nitro-
lished methods (Anon 1983). More detailed speciation gen in the abstraction wells (particularly AW403) at the
of phenols was carried out using GC/MS on the final 56-week sampling may represent some localised
sampling occasion in May 1999 and undertaken by breakthrough of nutrients added to the inoculum injec-
Chemex, Cambridge. tion wells during August. Ammoniacal nitrogen con-

341
Land Contamination & Reclamation / Volume 9 / Number 4 / 2001

Table 2. Concentrations of target compounds, ammoniacal and oxidised nitrogen at the start of the remediation
programme, on termination of the recirculation system and two years afterwards

Mean concentration ± S.E.M.(a)


Prior to
Determinand Unit Two years
At start of remediation(b) termination of following
active
remediation termination

Week 0 Week 11 Week 137 Week 240


PAHs(c) µg/L 11 ± 6.5 4.0 ± 2.1 0.90 ± 0.34 0.67 ± 0.67
Target phenols(d) µg/L 88 ± 65 1100 ± 1100 12 ± 4.6 93 ± 87(e)
Phenol µg/L 6.8 ± 3.2 75 ± 75 3.8 ± 1.2 <1
Cresols µg/L <1 450 ± 450 0.83 ± 0.54 32 ± 31
Benzene µg/L 13 ± 6.1 <10 <10 0.67 ± 0.49
Toluene µg/L 14 ± 8.4 12 ± 3.8 <10 2.5 ± 2.3
Ethylbenzene µg/L 3.8 ± 3.8 <10 <10 0.83 ± 0.4
Total xylenes µg/L 27 ± 15 16 ± 16 19 ± 15 6.7 ± 5.3
BTEX µg/L 58 ± 31 28 ± 18 19 ± 15 11 ± 7.4
NH4-N mg/L 0.97 ± 0.37 – (f) 2.4 ± 0.7 0.98 ± 0.26
N02-N mg/L 0.01 ± 0.005 – 0.04 ± 0.03 0.09 ± 0.08
N03-N mg/L 0.02 ± 0.022 – 10 ± 9.0 0.97 ± 0.61

Key
(a) Mean of four abstraction wells and two monitoring wells.
(b) The week 0 data follow pump testing of abstraction wells which may have resulted in localised transient charges in ground-
water quality. Week 11 data were taken at the start of the groundwater recirculation.
(c) As sum of the 16 US EPA ‘priority pollutant’ polyaromatic hydrocarbons.
(d) As sum of phenol, cresols, dimethyl and ethyl phenols except where stated.
(e) As sum of phenol, cresols and 2,4-dimethylphenol (target compounds).
(f) – not sampled for nitrogen.

centrations in the monitoring wells however, reflect the stabilised in both the abstraction and monitoring wells.
input of Purisol 100 until this was discontinued. Concentrations of both nitrite and nitrate, whilst con-
Apart from the 56-week result for ammoniacal siderably lower than during the early phase of the
nitrogen, consistently elevated concentrations of re-injection, remained elevated in the monitoring wells
ammonia, nitrite and nitrate in the monitoring wells compared to the abstraction wells following termina-
were observed over the course of the groundwater tion.
recirculation, both compared to previous concentra- The continued presence of nitrite provided evidence
tions and to concentrations in the abstraction wells. of continuing microbial denitrification of the added
Nitrite nitrogen, an intermediate in biological nitrate nitrate.
reduction, was detected in groundwater within the
monitoring wells throughout the treatment period and Polyaromatic hydrocarbons (PAHs)
two peaks were observed at 29 and 92 weeks. Much
smaller peaks were observed in the abstraction wells at The clean-up criteria proposed for PAHs for the termi-
47 and 121 weeks, potentially representing some nation of the active remedial scheme were that the sum
breakthrough. In the case of nitrate, peaks were of the 16 US EPA Target List priority pollutant PAHs
observed in the monitoring wells at 39 and 92 weeks. In should not exceed 75 µg/L. Mean and maximum con-
the abstraction wells however, only a single peak was centrations of the sum of the 16 US EPA Target List pri-
observed at 56 weeks, following which nitrate concen- ority pollutants over the course of treatment are shown
trations remained at mostly non-detectable levels for in Figure 4 and the concentrations before and after
the remainder of the treatment and post-treatment peri- treatment are summarised in Table 1.
ods. Following termination of the recirculation system Concentrations of PAHs were somewhat lower at
concentrations of ammoniacal nitrogen appears to have the commencement of remediation than in 1993 in

342
In situ bioremediation of groundwater contaminated with phenols, BTEX and PAHs using nitrate as electron acceptor

CFU's
NH4-N
Switch off
9
10 Switch off
8 20
10 AW Wells
7 BH Wells
CFU's/ml (Geometric mean)

10
6 15
10

NH4-N (m g /l )
5
10
10
4
10
3
10 5
2 AW Wells
10 BH Wells
1 In excess of
10 these values
0
0 0 50 100 150 200 250
10 Weeks
0 50 100 150 200 250
Weeks

NO2-N NO3-N
Switch off Switch off
1.8 16
AW Wells AW Wells
1.6 BH Wells BH Wells
14

1.4
12
NO3-N (mg/l)
NO2-N (mg/l)

1.2
10
1
8
0.8
6
0.6
4
0.4

0.2 2

0 0
0 50 100 150 200 250 0 50 100 150 200 250
Weeks Weeks

Figure 3. Viable counts of microorganisms in groundwater samples (geometric means) of colony forming units (CFUs) expressed
logarithmically and concentrations of ammoniacal nitrogen, nitrite nitrogen and nitrate nitrogen (arithmetic means) in abstraction
and monitoring wells during treatment. Asterisked results are approximate and indicate CFUs in excess of indicated value.

AW401 and in AW402 (compared with the adjacent centrations were below the limits of detection. The
BH304) as illustrated in Figure 1. maximum detectable concentration of PAHs in AW403
Whilst concentrations were below the clean-up cri- had then fallen to 1.2 µg/L. However, when this well
teria, both in the abstraction and monitoring wells, the was re-sampled three months later, in week 212, none
results indicate a general decrease over the treatment of the 16 PAHs were present above their detection lim-
period, with the mean concentration falling to 0.9 µg/L its.
(maximum 2.1 µg/L) at week 92. Because of the con- At the final sampling during week 240, concentra-
centration being significantly below the criteria on tions of PAHs were below detectable concentrations in
each sampling occasion, and the consistent decrease all wells except for AW404, where a total concentration
observed, no further analyses were undertaken during of 4 µg/L of naphthalene was identified. None of the
the operation of the active scheme from week 92 to other PAHs (including the more toxic 4, 5 or 6-ringed
switch-off at week 148. compounds) were present above detection limits.
On re-sampling during week 169, an increase in
PAH concentrations was observed compared with the Phenols
previous monitoring in July 1996, with a maximum The clean-up criteria proposed for phenols for the
concentration of 5.3 µg/L. Total concentrations of the active remedial scheme were that the sum of phenol,
16 priority pollutant PAHs then subsequently cresols and xylenols on the US EPA Target List should
decreased in all wells (both abstraction and monitoring not exceed 100 µg/L; these compounds being phenol,
wells) and by week 199 were the lowest since monitor- 2-methylphenol, 4-methylphenol and 2,4-dimethylphe-
ing began. In both of the monitoring wells, PAH con- nol.

343
Land Contamination & Reclamation / Volume 9 / Number 4 / 2001

Mean Total (USEPA) PAHs Maximum (USEPA16) PAHs


START OF START OF
REMEDIATION SWITCH OFF REMEDIATION SWITCH OFF
12

10
100

µg/l (LOG SCALE)


8
µg/l

10
4

1
0
-93 0 50 100 150 200 250
0 50 100 150 200 250 300
WEEKS WEEKS

Mean Target Phenols Maximum Target Phenols


START OF START OF
REMEDIATION SWITCH OFF REMEDIATION SWITCH OFF
1200 100,000

1000
10,000
µg/l (LOG SCALE)

800
µg/l

1000

600

100
400

10
200

0 1
0 50 100 150 200 250 300 -93 0 50 100 150 200 250

WEEKS WEEKS

Mean Total BTEX Maximum Total BTEX


START OF SWITCH OFF START OF
REMEDIATION REMEDIATION SWITCH OFF
100 1,000

80
µg/l (LOG SCALE)

100
60
µg/l

40
10

20

0 1
0 50 100 150 200 250 300 -93 0 50 100 150 200 250
WEEKS WEEKS

Figure 4. Mean and maximum concentrations of key contaminants detected in abstraction and monitoring wells before and after
remediation. Maximum concentrations detected are expressed logarithmically and also show concentrations two years prior to
remediation. (Target phenols may also include ethylphenols apart from final sampling indicated by *.)

For monitoring purposes during the active remedial programme are provided in Table 1 and are depicted
scheme however, phenols were determined by the graphically in Figure 4.
‘British Gas’ (HPLC) method (HPLC being the method In summary, both the mean and maximum concen-
recommended for analysis of phenols arising from gas- trations of phenols demonstrated a substantial decrease
works sites (Department of the Environment 1987)). over the treatment period, albeit with some fluctua-
Because this method provides a quantification of phe- tions. Following switch-off there was an initial increase
nol, total cresols (methyl phenols) and dimethyl plus followed by a decrease in concentration.
ethyl phenols (as reported in these categories), other As with PAHs and BTEX, total target phenols were
phenols may have been included besides the specific also generally lower than comparative samplings in
target compounds listed above. The concentrations of 1993 (Figures 1 and 4). The mean total concentration of
total ‘target phenols’ (reported as the sum of phenol, target phenols in the groundwater being abstracted
cresols, dimethyl plus ethyl phenols) over the remedial from AW403 where the highest concentrations were

344
In situ bioremediation of groundwater contaminated with phenols, BTEX and PAHs using nitrate as electron acceptor

detected, increased to a relatively high level (6550 also the case in wells BH302 and BH303. Apart from a
µg/L) between the start of the pump tests and the start single value of 529 µg/L in AW402, concentrations in
of the groundwater recirculation in week 11. However the remaining wells were well below 100 µg/L, namely
this subsequently fell by almost an order of magnitude 24 µg/L in AW401 and 4 µg/L in AW404. As noted in
during weeks 26 and 27. Conversely, concentrations in Table 1, the ‘target phenols’ results for this final sam-
groundwater from AW402 increased from 243 µg/L in pling are not entirely comparable with the previous
week 11 to 1430 µg/L in week 26 before declining. dataset given the fact that these were performed using
Two further increases (though to a lesser degree) were GC/MS rather than the HPLC method (which includes
observed in the abstraction wells, one in week 47, the the two other xylenol isomers plus any ethylphenols
second in week 92 (the latter occurring mostly in which may be present). However, phenol itself was
AW403). Both of these were followed by decreases in below its detection limits (<1 µg/L) in all wells (Table
concentration and are probably indicative of heteroge- 1) with cresols present only in well AW402 at 189 µg/L
neities in contaminant distribution beneath the site, i.e. (Table 1). In all other wells, cresols were below
concentrations fluctuated as localised pockets of con- 10 µg/L.
tamination were drawn towards the abstraction wells.
In the case of the week 47 sample this was taken after Concentrations of BTEX
the system had been temporarily shut down for five The clean-up criteria for BTEX compounds, for the
weeks, so that the increase here could have been due to active remedial scheme were for benzene not to exceed
desorption. 20 µg/L, toluene not to exceed 50 µg/L, ethylbenzene
Loss of phenols was most pronounced in the moni- not to exceed 60 µg/L, xylene (each isomer) not to
toring wells. In BH303 concentrations reached a maxi- exceed 60 µg/L, sum of above (BTEX) not to exceed
mum of 206 µg/L in week 29 but then decreased to 100 µg/L. The reductions in concentrations of each of
below 10 µg/L. In BH302, located further down-gradi- the individual BTEX compounds are summarised in
ent from the nearest injection well than BH303, con- Table 1, whilst total BTEX concentrations are shown in
centrations were at a maximum in week 47 (64 µg/L), Figure 4.
then decreased to 21 µg/L. Since week 78, concentra- As with the other contaminants, concentrations of
tions of target phenols in this well remained below 10 benzene, toluene, ethylbenzene and xylenes at the start
µg/L. of the remediation were generally lower than in
In all wells, total concentrations of target phenols December 1993, in AW401 and also in AW402, com-
were below the clean-up criterion of 100 µg/L for the pared with the concentrations detected in adjacent
final two samplings in 1997 prior to switch-off (weeks BH304 in September and November 1993 (Figure 1).
121 and 137). Following switch-off, an increase in phe- The groundwater abstracted from AW403 and AW404
nols was observed in most of the abstraction wells was most contaminated with respect to BTEX com-
when re-sampled in week 170. In two of these, AW402 pounds. Concentrations in these, as with the other
and AW403, concentrations exceeded 100 µg/L (133 abstraction wells, fluctuated considerably with time, as
µg/L and 320 µg/L respectively). In monitoring well the groundwater was abstracted (Figure 4). By week
BH302, 15 µg/L total phenols was detected whilst in 137 concentrations of all individual BTEX compounds
BH303 concentrations had decreased to below the limit had fallen below their target concentrations in all
of detection. abstraction wells, with total BTEX below 100 µg/L
By week 199, concentrations of target phenols were (Table 1, Figure 4). On resampling during week 170
in excess of 100 µg/L only in well AW403, where a following switch-off, concentrations of total BTEX in
concentration of 764 µg/L was obtained, in the remain- AW404 were still below 100 µg/L, with only xylenes
der, concentrations were of a similar order to week 170, being detectable (56 µg/L total isomers). BTEX con-
some slightly higher, others lower. An additional sam- centrations in AW403 had increased slightly above 100
ple from this well only (not shown on Figure 4) was µg/L (105 µg/L), with benzene at 40 µg/L. Other indi-
then taken for more detailed speciation of phenols by vidual BTEX compounds remained below their respec-
GC/MS in week 212 to examine the four specific target tive targets. By the final sampling however, there had
phenols, these being phenol, 2-methylphenol, 4-meth- been subsequent decreases in both individual and total
ylphenol and 2,4-dimethylphenol. None of these target BTEX compounds (Table 1, Figure 4), none of the indi-
phenols, nor any of the other semi-volatile organics on vidual BTEX compounds being present above 20 µg/L
the US EPA Target List were present above their detec- in any abstraction well or total BTEX above 50 µg/L.
tion limits. Concentrations of each of the individual BTEX
At the final sampling in week 240, GC/MS was also compounds in the two monitoring wells BH302 and
used to speciate the listed phenols. Concentrations BH303 remained consistently less than 10 µg/L from
were again below detection limits in AW403 as was week 21 onwards, including all of the monitoring

345
Land Contamination & Reclamation / Volume 9 / Number 4 / 2001

rounds, following switch-off, through week 240 in quently declined over the following two years. Where
1999. the bounce-back occurred, this took place in the most
contaminated area: in well AW403 for example where
concentrations of phenols were 34 µg/L at termination
GENERAL DISCUSSION rising to 320 µg/L 33 weeks later, and 764 µg/L after a
further 29 weeks. Thirteen weeks later however, con-
Comparison of the concentrations of the target contam- centrations had fallen below detectable levels, which
inants one to two years before the start of the remedia- was the case after a further 28 weeks at the final sam-
tion (Figures 1 and 4) indicates that there had already pling. The phenol concentrations in AW402 were
been a degree of reduction in contamination levels therefore assumed to follow a similar cycle. Concentra-
prior to active remediation. Some of this may have tions of PAHs and BTEX also showed similar trends as
been attributable to localised source removal, and the phenols; in each case however, all such determi-
improvements in surface integrity including extending nands were below their respective target concentrations
concrete hardstanding over previously unprotected on both the penultimate and final sampling occasions.
areas and thereby minimising leaching from the Supporting indicators of biological degradation
unsaturated zone. Natural attenuation may also have were the occurrence of nitrite as an intermediate in den-
been a contributory factor. In studies at a former coal itrification during the nitrate reduction process, the
tar distillery, Lerner et al. (2000) demonstrated that depletion of nitrate and the occurrence of a high bacte-
whilst concentrations of (mostly) phenol contaminants rial count in the aqueous phase. As discussed, given the
(in excess of 1000 mg/L TOC), were inhibitory within selectivity of isolation methods and the likelihood of
the central core of a plume within the Sherwood Sand- microbial activity being concentrated on the solid
stone, natural attenuation within the more dilute areas phase the results of the microbial counts in the free
at the fringe of the plume readily took place. phase need to be interpreted with caution. However, it
Bench-scale testing had established that microbial is of interest that there is a general decline at the end of
activity was not significantly inhibited by the elevated the monitoring phase, potentially indicative of an over-
phenol concentrations, which was also supported by all decline in degradable carbonaceous material.
the plate counts (notwithstanding the limitations of this This case study therefore illustrates that in situ
technique). The addition of an inoculum to this area of bioremediation using nitrate as an electron acceptor
contamination may only have had a marginal effect on represents a viable remedial solution for groundwater
degradation and was considered appropriate in this contaminated with low molecular weight monoaromat-
example as a precautionary measure. Addition of inoc- ics, PAHs and phenols. It also demonstrates that
ula in bioremediation (bioaugmentation) has often enhanced passive remediation may be of significance
been the subject of controversy (Bewley 1996), following completion of active remediation in main-
although there have been instances of controlled condi- taining residual concentrations at acceptable levels.
tions (i.e. with or without bioaugmentation) where a
significant difference was observed, especially with the
more recalcitrant contaminants (e.g. Bewley et al.
ACKNOWLEDGEMENTS
1989).
Although definitive verification of bioremediation
full-scale is not possible, the results of the monitoring We wish to thank the owners of the site for permission
post switch-off have indicated that the treatment car- to publish this paper and acknowledge the support of
ried out has achieved its remedial objectives and that our colleagues, Mr John Alexander during detailed
the degree of microbial activity within the aquifer has design, Mr Richard Andrews for hydrogeological mod-
been sufficient to address desorption of any residual elling and Mr Mark Jones for field engineering support.
contamination present. The mean concentrations of tar- The support of the Environment Agency during the
get contaminants were all below the target concentra- implementation of this project is also appreciated. The
tions both at termination of the recirculation scheme views expressed in this publication are those of the
and after two years of switch-off. This was also the case authors and do not necessarily reflect the views of URS
for concentrations within the individual wells except Dames & Moore.
for one single concentration of total phenols within
well AW402 (529 µg/L). Where there had been some
evidence of ‘bounce-back’ in concentrations of con- REFERENCES
taminations following completion of the active recircu-
lation system (Figure 4), this appeared to be transient in Al-Bashir, B., Cseh, T., Leduc, R. and Samson, R. (1990)
nature as concentrations of all determinands subse- Effect of soil/contaminant interactions on the biodegradation

346
In situ bioremediation of groundwater contaminated with phenols, BTEX and PAHs using nitrate as electron acceptor

of naphthalene in flooded soils under denitrifying condi- Micro-organisms in the Treatment of Hazardous Materials
tions. Appl. Microbiol. Biotechnol., 34, 414-419. and Hazardous Wastes. Hazardous Materials Control
Research Institute, Silver Spring, MD.
Anon (1983) The bacteriological examination of drinking
water supplies. Reports on Public Health and Medical Sub-
Department of the Environment (1987) Problems Arising
jects, 71. HMSO, London.
from the Redevelopment of Gasworks and Similar Sites (2nd
ed.), prepared by Environmental Resources Limited. HMSO,
Battermann, G., Fried, R., Meier-Lohr, M. and Werner, P.
London.
(1993) Pilot and large-scale experiences in the in-situ biore-
mediation of a refinery site polluted with hydrocarbons, pp.
1135-1144. In F. Arendt, G. J. Annokkee, R. Bosman and W. Häner, A., Höhener, P. and Zeyer, J. (1995) Degradation of
J. van den Brink (ed.) Contaminated Soil '93. Kluwer Aca- p-xylene by a denitrifying enrichment culture. Appl. Envi-
demic Publishers, Dordrecht. ron. Microbiol., 61, 3185-3188.

Bewley, R.J.F. (1996) Field implementation of in-situ biore- Hutchins, S.R., Sewell, G.W., Kovacs, D.A. and Smith, G.A.
mediation: key physicochemical and biological factors. In
(1991) Biodegradation of aromatic hydrocarbons by aquifer
Soil Biochemistry, Volume 9, G. Stotzky and J.M. Bollag
microorganisms under denitrifying conditions. Environ. Sci.
(eds.), pp. 473-541. Marcel Dekker Inc., New York.
Technol., 25, 68-76.
Bewley, R., Ellis, B., Theile, P., Viney, I., Rees, J. (1989)
Microbial clean-up of contaminated soil. Chemistry and Krumholz, L.R., Caldwell, M.E. and Suflita, J.M. (1996)
Industry, 23, 778-783. Biodegradation of ‘BTEX’ hydrocarbons under anaerobic
conditions. In Bioremediation: Principles and Applications,
Bewley, R.J.F., Alexander, J.G. and Webb, G.H. (2001) Ex ed. R.L. Crawford and D.L. Crawford, pp. 61-99. Cambridge
situ and in situ bioremediation of former oil distribution ter- University Press, Cambridge, UK.
minals. Land Contamination and Reclamation, 9 (3),
269-277.
Lerner, D.N., Thornton, S.F., Spence, M.J., Banwart, S.A.,
Bottrell, S.H., Higgo, J.J., Mallinson, H.E.H., Pickup, R.W.
Bossert, I.D. and Young, L.Y. (1986) Anaerobic oxidation of
and Williams, G.M. (2000) Ineffective natural attenuation of
p-cresol by a denitrifying bacterium. Appl. Environ. Micro-
degradable organic compounds in a phenol-contaminated
biol., 52, 1117-1122.
aquifer. Groundwater, 38, 922-928.
Campbell, J.R., Fu, J.K. and O’Toole, R. (1989) Biodegrada-
tion of PCP-contaminated soils using in-situ subsurface Werner, P. (1985) A new way for the decontamination of
bioreclamation, pp. 17-27. In Biotreatment – The Use of polluted aquifers by biodegradation. Wat. Supply, 3, 41-47.

Apart from fair dealing for the purposes of research or private study, or criticism or review, this publication may not be reproduced, stored in a
retrieval system or transmitted in any form or by any means, electronic, mechanical, photographic or otherwise, without the prior permission
in writing of the publisher.

The views expressed in this and in all articles in the journal Land Contamination & Reclamation are those of the authors alone and do not
necessarily reflect those of the editor, editorial board or publisher, or of the authors’ employers or organizations with which they are
associated. The information in this article is intended as general guidance only; it is not comprehensive and does not constitute professional
advice. Readers are advised to verify any information obtained from this article, and to seek professional advice as appropriate. The publisher
does not endorse claims made for processes and products, and does not, to the extent permitted by law, make any warranty, express or implied,
in relation to this article, including but not limited to completeness, accuracy, quality and fitness for a particular purpose, or assume any
responsibility for damage or loss caused to persons or property as a result of the use of information in this article.

347

Вам также может понравиться